You are on page 1of 81

Vedanta Alumina Ltd.

SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 1 of 1
Version No 1.2

SAP R/3 IMPLEMENTATION BUSINESS BLUEPRINT Production Planning

Prepared by Aniruddha Mukherjee

Checked by Vishal Rathore

Reviewed By

Approved By

Date

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 2 of 2
Version No 1.2

TABLE OF CONTENTS
OBJECTIVE OF BUSINESS BLUEPRINT PHASE.........................................................................................................................................................................................3

SCOPE OF BPBP DOCUMENT ..................................................................................................................................................................................................................6 PRODUCTION PLANNING IN SAP - OBJECTIVE ...............................................................................................................................................................................7 SECTION I .......................................................................................................................................................................................................................................................8 SECTION II....................................................................................................................................................................................................................................................12 ORGANIZATION STRUCTURE ..............................................................................................................................................................................................................12 OTHER MAJOR CONFIGURATION ......................................................................................................................................................................................................17 SECTION III ..................................................................................................................................................................................................................................................21 SECTION IV ..................................................................................................................................................................................................................................................78
SPECIAL ORGANIZATIONAL CONSIDERATIONS:.................................................................................................................................................................................80

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 3 of 3
Version No 1.2

OBJECTIVE OF BUSINESS BLUEPRINT PHASE: This document is the outcome of the As-Is study, Discussion at Training and during the To-Be process and business process requirement analysis for the Vedanta Alumina Limited. Based on this As-Is coupled with inputs from the core team members during To-Be discussion, we arrived at the Business Processes, which are to be incorporated in the Business Blue Print. The aim of this document is to map the best business processes related to the Production Planning module in SAP ECC 5.0. This document is to be studied by core team members & process owners from Vedanta Alumina Limited. The preparation of this document is an essential precursor for prototyping and testing. The development work will start once process owners approval for this Blue Print is obtained followed by a corporate presentation to the senior management team, Vedanta Alumina Limited. This document will be used for configuring Production Planning module in SAP implementation. Document is based on discussions/presentations between representatives of VAL & PWC. In other words it contains 1. SAP Organization Model in context of existing business scenario and future requirements/issues as envisaged by VAL. 2. Mapping of business processes/issues brought forward by PwC & VAL, with SAP functionality. 3. Gaps & issues emerged during the discussion between VAL & PwC. 4. Business Process Flows mapped in SAP as per the scope defined.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 4 of 4
Version No 1.2

5. Closure of Mapping Phase and start of Piloting Phase of implementation.

A pictorial presentation of complete SAP implementation is depicted in the following page:

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 5 of 5
Version No 1.2

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 6 of 6
Version No 1.2

SCOPE OF BPBP DOCUMENT The objective of this Blue Print presented to the Project Sponsor is to document the following: a) Business Requirements of VAL that need to be translated into SAP. SAP consultants team members on the basis of As-Is document, factory visit & discussions between PwC SAP consultants and VAL core team members have prepared this. SAP Gaps as identified by PwC Team with respect to the present scope of implementation and Business Requirements of VAL. Details of SAP New Business Process description supported by Process Flow diagram with respect to Different SAP process indicating the desired To be Processes / Business Blue Print.

b) c)

In order to bring the clarity and better understanding, the document has been divided in five sections: SECTION I: Scope of SAP Production Planning and Control module for the project. SECTION II: Organization structure. SECTION III: Master Data Management, As-Is and / To-Be Business processes, and Gaps identified for business processes as per SAP. SECTION IV: Appendix-Process ( SAP) Flow Diagrams.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 7 of 7
Version No 1.2

Production Planning in SAP - Objective To provide a Production Planning, execution, control and record maintenance system fully integrated with Finance, Costing, Materials Management, Sales & Distribution and Quality Management in order to achieve superior operational efficiency, cost reduction and profitability. The module also provides better handling of all business transaction, statutory compliance, EIS, and MIS for better decision-making management Control. This is achieved through the following components:

Integration into Process Planning and Control. Shop Floor Control in the R/3 System. Special Topics of Production. An Example of PO Processing. Creating a Process Order. Important Tasks within Process Order Processing. Confirming and Settling Process Orders.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 8 of 8
Version No 1.2

SECTION I Scope of Production Planning Module in VAL

PARTICULARS Master 1.1 General Master Records 1.1.1 Material Master 1.1.2 Material BOM 1.1.3 Resource 1.1.4 Recipe 1.1.5 Batch Production Planning and Procurement Planning 1.2.1 Sales and Operations Planning 1.2.2 Demand Management 1.2.3 Long-Term Planning 1.2.4 MPS 1.2.4 MRP

Alumina

Power

X X X X

X X X X

1.2

X (MM)

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 9 of 9
Version No 1.2

PARTICULARS 1.3 Production 1.3.1 Discrete Production 1.3.2 Repetitive Manufacturing 1.3.3 Process Manufacturing 1.3.4 KANBAN 1.4 Inventory Management 1.4.1 Batch 1.4.2 Batch Search Strategy 1.4.3 Control Cycle 1.4.4 Serial Numbers Business 2.1 Production Planning and Procurement Planning 2.1.1 Market-Oriented Planning 2.1.1.1 Sales and Operations Planning 2.1.1.2 Forecast 2.1.1.3 Demand Management 2.1.1.4 Long-Term Planning 2.1.1.5 Master Production Scheduling 2.1.1.6 Material Requirements Planning

Alumina

Power

X (MM)

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 10 of 10
Version No 1.2

PARTICULARS 2.1.1.7 2.1.2 Evaluations: Logistics Information System

Alumina X X

Power

2.2

Sales Order Oriented Planning 2.1.2.1 Master Production Scheduling 2.1.2.2 Material Requirements Planning 2.1.2.3 Evaluations: Logistics Information System 2.1.3 Consumption-Driven Planning 2.1.3.1 Forecast 2.1.3.2 Material Requirements Planning 2.1.3.3 Evaluations: Logistics Information System Production 2.2.1 Process Manufacturing 2.2.1.1 Process Order Creation 2.2.1.2 Material Staging 2.2.1.3 Capacity Requirements Planning 2.2.1.4 Process Order Execution 2.2.1.5 Evaluation and Mass Processing 2.2.1.6 Evaluations: Logistics Information System 2.2.1.7 Replenishment Stock Transfer with Reservation

MM X X

MM X X

X X X X X

X X X X X

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 11 of 11
Version No 1.2

PARTICULARS 2.2.1.8 2.3

Alumina Replenishment Stock Transfer with Direct Transfer Posting X MM X X X X MM X (MM) X X X X

Power X

Inventory Management 2.3.1 Goods Movements

2.4.1.1 Reservation 2.4.1.4 Goods Receipt 2.4.1.5 Stock Transfers / Trans. Postings 2.4.1.6 Goods Issue 2.3.2 Physical Inventory & Cycle Counting 2.4.2.1 Physical Inventory Cross-Application Components 3.1 Classification System 3.1.1 Characteristics 3.1.2 Classes 3.1.3 Classification

X X X X

X X X X

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 12 of 12
Version No 1.2

Section II Organization Structure Plants The plant is an operating area or branch within a company. The plant is assigned to a single company code. A plant has its own material master data. You can maintain data at plant level for the following views on a material master record in particular: MRP, Purchasing, Storage, Work scheduling, Production resources/tools, Forecasting, Quality management, Sales, Costing. Among this, views in bold would be used in case of Vedanta Alumina Ltd. As per discussion with Finance & Materials, there will be only four Company Code (1000,2000,3000,4000) and four plants (Non-Virtual) will be created which may be as follows: PRODUCTION PLANT 1000 2000 3000 DESCRIPTION VAL Alumina Plant VAL Power Plant VAL Smelter Plant

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 13 of 13
Version No 1.2

Storage Locations Storage location is an organizational unit allowing the differentiation of material stocks within a plant. All data referring to a particular storage location is stored at storage location level. This applies mainly to storage location stocks. Several storage locations can be assigned to a plant. The logical and physical storage locations will be configured to track the inventory in the shop floor. The configuration of the storage locations will be done according to the physical or the logical movement of materials in the shop floor. The detailed discussion on storage locations will come in the plant specific documentation. Proposed Storage Locations for plant relevant for PP. Alumina Plant (1000) STORAGE LOCATIONS To Be submitted by MM DESCRIPTION

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 14 of 14
Version No 1.2

Power Plant (2000) STORAGE LOCATIONS To Be submitted by MM DESCRIPTION

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 15 of 15
Version No 1.2

Main Resources in Alumina Plant RESOURCES Calcinations Unit Hydrate Unit Process Caustic Unit DESCRIPTION Hydrate is Calcined into Alumina. Alumina as Hydrate is Obtained. Unit where Process Caustic may be captured as WIP.

Note: The Resource of caustic may not used on day-to-day basis. It may be used at the end of the month to capture WIP for Caustic and that too would be used if any other work around is not found at realization and integration testing phase. PwC s Suggestion is to manage WIP through a generalist approach.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 16 of 16
Version No 1.2

Main Resources in Power Plant RESOURCES Power DESCRIPTION Resource for power Plant.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 17 of 17
Version No 1.2

Other Major Configuration Factory Calendar Every Plant will be having a factory calendar with details of the working days and the holiday schedule. The Factory calendar will be named as Al and PO for Process and Power plants respectively. Periods and the Fiscal Year will be from April March. Holiday Calendar Every Plant will be having a holiday calendar with details of the holidays as public and other holidays, either as fixed or a moving day in a year. The Factory calendar will be named as Al and PO for Process and Power plants respectively. Periods and the Fiscal Year will be from April March. Material Groups The functional grouping of the materials for reporting and analysis. It can be used to restrict the scope of analysis and searching specifically material master record via search help. MRP Group If we are going for different process order types for Alumina (finished materials), power (raw materials for process plant) etc, and then MRP group can be created. Material type assignment has to done on one to one basis. One plant may have more than one MRP group. The number of MRP group to be finalized in the Realization phase.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 18 of 18
Version No 1.2

MRP Type For material those would be planned on the basis of manufacturing requirement would be planned through Classical MRP. For these type of material MRP type PD would be used in general. Based on this requirement planned Order would be generated in the system for finished product. Raw Materials would be planned through consumption based planning. Relevant information related to Re-order point and safety stock would be provided in the material master record. Lot-sizing Procedure Using this system should calculate the Order quantity for planned order. It is consumed from material planning. We would use Lot-for-Lot Order Quantity in general (EX). MRP Controllers It specifies the group or the number of the controller responsible for Material requirement planning in your organization (Plant or Company). The material, which is relevant for material requirement planning, should be assigned to a MRP controller

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 19 of 19
Version No 1.2

Order Types for Alumina Plant

ORDER TYPE AL HY NAOH

DESCRIPTION Order Type for Alumina. Order Type for Hydrate. Order Type for Caustic.

Note: The Order type of caustic may not used on day-to-day basis. It may be used at the end of the month to capture WIP for Caustic and that too would be used if any other work around is not found in realization phase or integration testing phase. PwC s Suggestion is to manage WIP through a generalist approach.

Order Types for Power Plant ORDER TYPE POW DESCRIPTION Order Type for Power.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 20 of 20
Version No 1.2

To-Be Processes Production Planning Processes The Business Blue Print is divided into various sections as defined by the different processes as discussed during to-be and Expectation from SAP. These processes are: Finished Product Planning. Raw Materials Planning. Consumables Planning. Production Scheduling. Capacity Evaluation. Order Execution. Goods Movement. Cost Analysis. Report Analysis.

To carry out these processes, certain Masters are required to be maintained prior to carry out the Transactions and Reports. This master is listed below with explanation text. These Masters are created before Go-Live through Mass data upload process. They are fixed or constant in nature. The system would access these master data while the user will be carrying out transaction on day-to-day basis. So from user point of view also it mandatory to understand the relevant or organization specific master data in detail so that actual business process is replicated into the system in terms of data and hence phenomenal purity.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 21 of 21
Version No 1.2

Section III Sl. No. Process Name Process PlantLogistics General Data Mode Process Description/remarks Gap (Y/N) Remarks

1.0

1.1

Batch Management

Fully system supported

The manufacturing mode of VAL is a typical case of process manufacturing scenario. Here, batch tracking is not possible physically. So production in SAP as well as in reality wont be captured through batches.

1.2

Material Classification

Fully system supported

Material Classification can be done with the standard material classification system in SAP (Class Type 001). This will allow better search.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 22 of 22
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

Characteristic is a property that describes and differentiates objects. Classification Creation/change of Class and Characteristics Fully system supported Example: length, colour, weight, etc. Class is an assembly of characteristics that can be attributed to a N product (or to several similar products). It can also be defined as a grouping of similar products according to common characteristics Example Pump class, Boiler class etc.

1.3

1.4

MRP Profile

Fully system supported

If the order types are more than one, profiles will help in maintaining some controlling data. (i.e., automatic selection of order type during manual order creation).

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 23 of 23
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

1.5

Procurement Type

This would help the system to identify the procurement type for the N particular material. We use E for produced goods, F for external procurement and X for both type of procurement.

1.6

Strategy Group

Fully system supported

For Material Produced In-House we need to maintain Strategy 11 for semi-finished product i.e., Make to stock and Gross Requirement planning.

1.7 Based on this system checks the availability. In Vedanta we would use checking rule 01 for all semi-finished and finished product. This is used for accumulating the total requirement on daily basis. N Any other availability check to be introduced can be considered at Realization stage.

Availability Check

Fully system supported

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 24 of 24
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

2.0

Process PlantProduct Data Management

2.1

Maintain Material Master

Fully system supported

Material master for Finished and Semi finished goods. Material Classifications may be used. Views such as Basic data 1, Basic Data 2, MRP 1, MRP 2, MRP 3, MRP 4 and work scheduling (as and when required basis). For example: for raw material there wont be any Work Scheduling View.

2.1.1

Create Material Master

Fully system supported Fully system supported

Create relevant views for each material and give the values of respective fields.

2.1.2

Change Material Master

Change values of settings as necessary in the material master can N be done anytime, but frequent change is not recommended.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 25 of 25
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

2.1.3

Display Material Master.

View settings without changing. This purely for read only purpose.

2.2

Maintain Bills of Material

Fully system supported

Create and change, as necessary, master data for Bills of Material. Standard BOM will be created and saved in the system. In case of N Process manufacturing scenario, this can be done along with recipe itself.

2.2.1

Create Bills of Material

Fully system supported Fully system supported

Create BOMs for all materials produced in-house. In case of Process manufacturing scenario, this can be done along with recipe itself.

2.2.2

Change Bills of Material

Change values of settings as necessary. In case of Process manufacturing scenario, this can be done along with recipe itself.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 26 of 26
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

2.2.3

Display Bills of Material

View settings without changing. This is purely Read Only view for BOM.

2.3

Maintain Resource

Fully system supported

Create and change, as necessary, master data for Resource. All Resource shall be attached to a Cost Centre. Processing Unit capacity categories may be used for a Resource. However data N related to Resource category and Capacity category may be changed at the time of realization depending on the simulation test result.

2.3.1

Create Resource

Fully system supported

Create Resource for all processing facilities in the plant with capacity categories of Processing Unit. This would capture logical N place of operation under a plant and at the same time collect the costing data generated out of activity consumption. Every resource is assigned to a cost centre.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 27 of 27
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks This process would enable the user to capture any enhanced functionality in future. It can be used to change any existing field value apart from resource category and capacity category. Any extra capacity category can be introduced by using the functionality.

Gap (Y/N)

Remarks

2.3.2

Change Resource

Fully system supported

2.3.3

Display Resource

Fully system supported

View settings without changing. This is used for viewing the master N data in Read only mode.

2.4

Recipe

Fully system supported

Create and change, as necessary, master data for Recipe. The entire standard recipe will be created in the system for all the plants and material combination. Control Key PI01 can be used up N while creating the Recipe. However, if required, separate control key can be created at time of realization phase.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 28 of 28
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks Create Recipe for all materials produced in-house. The respective operations, their phases, internal relations, material assignments are to be mentioned .The standard values for operations can also be mapped through this functionality. Control keys like PI01, and PI05 may be used depending on the business processes integrated along with the operations.

Gap (Y/N)

Remarks

2.4.1

Create Recipe.

Fully system supported

2.4.2

Change Recipe

Fully system supported

Change values of settings as necessary. Any change in the process can be mapped in future through this transaction.

2.4.3

Display Recipe.

Fully system supported

View settings without changing and in Read Only mode.

2.4.4

In-Process Inspection Fully system supported

Recipe will have In-Process Inspection Characteristics (Managed N by the QM module). This is not under the Purview of current scope of the project.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 29 of 29
Version No 1.2

Sl. No.

Process Name

Mode supported

Process Description/remarks of the project.

Gap (Y/N)

Remarks

2.5

Production Version

Fully system supported

Its a combination of BOM and Recipe. So in case of recipe it is mandatory to maintain Production version. Functionalities related to Lot size, alternative BOM etc can be captured through this. N Multiple production versions might be there for a material. It can be locked or Unlocked on as and when required basis.

2.5.1

Create Production version

Fully system supported

At the time of recipe creation system prompts to maintain Production version. Multiple production versions are only used N when more than one production line is there. Here in Vedanta only one production version would be created.

2.5.2

Change Production version

Fully system supported

Data related to production version can be changed at anytime. If New BOM is to be attached keeping the existing one in the system N with the same recipe, one production version is generated and the previous one is locked in changed mode.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 30 of 30
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

2.5.3

Display production version

Fully system supported

This is for displaying purpose read only mode.

Process Plant- Production Planning. 3.0 Process PlantProduction Planning (PP-PI) Planning cycle will start from demand management. The Production Strategy would be Make to stock. Gross Requirement Planning will be used. Planned independent requirements are used to perform Demand Management functions. A planned independent requirement contains one planned quantity and one date, or a number of planned independent requirements schedule lines, that is, one planned quantity split over time according to dates.

Demand Management

Fully system supported

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 31 of 31
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

3.1

View Demand

Fully system supported

Demand on monthly scale can be viewed from planned independent requirement. The Requirement for finished product is N fed into the system, which will be considered at the time MRP run.

3.1.1

Create PIR

Fully system supported

Create demand for standard finished product in the system based on the Rough-cut Planning idea. For Vedanta, this should not be more than the maximum production capacity since production is totally based on Utilization of Full Plant capacity. It is not driven by N sales. Down time of five days can be taken into account in PIR so that time for opportunity based maintenance or annual maintenance (Shut down type) can be taken in To account in production planning in advance.

3.1.2

Change PIR

Fully system supported

If any change is required in PIR, this process can be used .If MRP elements are not already converted, change would be directly taken into account in the stock/requirement list. For affecting the

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 32 of 32
Version No 1.2

Sl. No.

Process Name

Mode supported

Process Description/remarks taken into account in the stock/requirement list. For affecting the existing planned Order, MRP has to be run once again.

Gap (Y/N)

Remarks

3.1.3

Display PIR

Fully system supported

View the Planned independent requirement in display mode.

3.1.4

Production Strategy Fully system supported

Make to stock production-planning strategy will be used for the Process plant. This has been decided pertaining to actual philosophy of production, which is not based on sale requirement. N Basic idea is full utilization of plant capacity. Requirement type LSF and/ BSE can be used to meet such requirement.

3.1.5

Staggered period Split

Fully system supported

The requirement of PIR can be split further into smaller periods (Ex. Months into weeks or weeks into days). On the basis of the same PIR can be generated further. Hence Planned Orders can be N split automatically for smaller periods. We can use our own period splitting key to split the requirement into smaller periods.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 33 of 33
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks With the reorganization function, you can delete planned independent requirements for which there are no sales orders in the database. You can delete the planned independent requirements history.

Gap (Y/N)

Remarks

3.1.6

Reorganization of PIR

Fully system supported

4.0

Material Requirement Planning

The main function of material requirements planning is to guarantee material availability, that is, it is used to procure or produce the requirement quantities on time both for internal purposes and for sales and distribution. This process involves the monitoring of stocks and, in particular, the automatic creation of procurement proposals for purchasing and production. In doing so, MRP tries to strike the best balance possible between

Optimising the service level and Minimizing costs and capital lockup.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 34 of 34
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

4.1

Run MRP on material

Fully system supported

Activate Materials Planning for all materials at Plant to derive Gross requirements. This transfers the demand created by the PIR N for dependent planning for the BOM items.

4.2

Total Planning

Fully system supported

Total planning covers the planning of all the materials that are relevant for requirements planning and includes the BOM explosion for materials with a bill of material. You can use total planning for a single plant or you can use the scope of planning to control whether the total planning run is executed on a multi-plant level

4.3

View Stock/Requirement list

Fully system supported

View Stock /requirements list to check stock position in terms of MRP elements. All the PIR, planned order and Production Orders ( N if not delivered) would be displayed along with ATP ,safety stock( if any ) , existing Stock ( if any). User will be able to see the most

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 35 of 35
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks updated information related to Material Requirement.

Gap (Y/N)

Remarks

4.4

Stock overview

Fully system supported

View Stock overview as and when required. System enables the user to check stock available for the stock items at various areas of the organization.

4.5

MRP List

Fully system supported

Functionality relevant to MRP i.e., all MRP elements can be viewed from time to time. It will show the conditions of Stock or Requirement at time of last MRP run.

4.6

Planned Order

Fully system supported

Proposal to manufacture after MRP execution is generated troughplanned order. It can be viewed from stock/ Requirement list. Planned Orders are converted to process order before the start of N process in the shop floor.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 36 of 36
Version No 1.2

Sl. No. 5.0

Process Name Process PlantCapacity Planning

Mode

Process Description/remarks

Gap (Y/N)

Remarks

The economic use of resources is an objective for many areas of a company. The component "Capacity Planning" is available in the N System for this purpose.

5.1

Capacity Evaluation

Fully system supported

Company can use capacity evaluations to analyse capacity loads in your company. You can adjust the analyses for each user according to the planning level, planning horizon and the area of responsibility. Available capacities and capacity requirements can be selected according to various criteria and cumulated using any period split you choose. To manufacture products in the shop floor as per the Recipe and Bill of Material (Material BOM)

6.0

Process PlantProcess Execution

6.1

Process Order

Fully system supported

Process orders are used for the production of materials or for rendering of services in a specific quantity on a specific date. They N enable the planning of resources, control of process order management, and specify the rules for account assignment and order settlement.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 37 of 37
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks Actual confirmation to shop floor to go ahead with manufacturing. This can be obtained from Planned order. Other wise for any offline requirement Process Order can also be created manually.

Gap (Y/N)

Remarks

6.2

Create/ Change Process Order

Fully system supported

Creating a process order is not a stand-alone process. Process Order is created from stock/Requirement list. But system allows creation of process Order separately. It is generally done before the commencement of manufacturing. The quantity to be produced under such a process Order has to be mentioned clearly. The N scheduling of process order that has to be followed really for shop floor happens at this phase and system schedules the process order. For Vedanta forward scheduling is recommended as scheduling type.

6.3

Check Material Availability

Fully system supported

Process order consumes materials (Semi-finished / Raw). The Materials have to be issued to the Process Orders Or will have to be back flushed. Logically these materials have to be available in system before the commencement of process. System would display missing part list (if any). For Vedanta System will

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 38 of 38
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks configured in such a way that system should raise warning if the material is not available. But decision-making should be at the level of user whether the Process Order could be processed after such missing part.

Gap (Y/N)

Remarks

6.4

Release Production Order

Fully system supported

Process Order Release is carried out on verge of production initiation. In Vedanta this release procedure should be manual i.e., N user has to release the Process Order every time Production is initiated against a new Process Order.

6.5

Confirm Production Order

Fully system supported

This is for Confirming actual completion of production for an order, N either partial or final. Also actual yield, scrap, time taken, and goods movements will be confirmed.

6.6

Confirmation cancellation

Partially system supported

It is possible to cancel data previously confirmed. Every completion P confirmation entered in the system can be cancelled. Thus, if you entered three confirmations for a phase, you can also cancel three

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 39 of 39
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks confirmations and all confirmations automatically created by them.

Gap (Y/N)

Remarks

6.7

Issue Materials & Components

Fully system supported

For Posting goods issued for Production, this functionality will be used. This will ensure the total consumption for production. Movement type used for this process is 261. For any return of goods issue, movement type 262 will be used. Unplanned materials can also be issued for a process order.

6.8

By-product receipt

Fully system supported

Any by-product should also be taken as a component (-ve qty) into the BOM of in-house produced materials and that by-product will be receipt into the stock at the time of confirmation. Standard SAP movement type is 531. For Vedanta Red Mud Can be taken as by Product /Waste.

6.9

Receive Produced Materials

Fully system supported

Goods Receipt for produced goods is captured through this functionality. After Goods receive store will be updated in inventory. Generally 101 is standard SAP movement type through

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 40 of 40
Version No 1.2

Sl. No.

Process Name

Mode supported

Process Description/remarks inventory. Generally 101 is standard SAP movement type through which goods receipt against production is captured.

Gap (Y/N)

Remarks

6.10

View Cost

Fully system supported

The Planned vs. actual costs can be viewed after all issues and activities are completed in the process Order change mode/display mode.

Technical Closure (TECO) Once the process order is confirmed fully i.e., desired yield is confirmed in terms of Goods movement and activity confirmation is also done along with, it has to be declared Technically complete. N The entire reservation list pending (if any) for the Process Order is deleted after this activity by the system itself.

6.11

Fully system supported

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 41 of 41
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

7.0

Reports

Reports are generated in the SAP system based on the information fed on day-to-day basis. This enables the user to take decision related to business.

7.1

Stock Overview

Fully system supported

It can be used to view Stocks for different material taking Plant and N storage location as additional selection criteria.

7.2

Extend material views

Fully system supported

It shows the historical data related to material extension at different N point of time.

7.3

List of material Storage location assignment.

Fully system supported

Shows the exhaustive list for material- storage location assignment.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 42 of 42
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

7.4

Material List

Shows Detail of a material on basis of selection criteria like plant, material, material type, material group and created by.

7.5

Material list with price and inventory values

Fully system supported

Gives the detail of standard price, Per unit price, Currency Key etc.

7.6

Resource List

Fully system supported

Gives detail of resources.

7.7

Cost Centre assignment.

Fully system supported

Shows the details assignment of cost centres to Resources.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 43 of 43
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

7.8

Resources Capacity

Shows the capacity records (Master) for different resources list wise.

7.9

Where used listResource

Fully system supported

Lists the different recipes where resources are used.

7.10

Where Used List Material

Fully system supported

Lists of material Used into different BOM.

7.11

Stock/Requirement list-collective display

Fully System supported

Gives the stock /requirement scenario for a MRP area or plant

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 44 of 44
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

7.12

Multi level Order Report

Gives multilevel order report for Process Order with different information.

7.13

Missing Part InfoSystem

Fully System supported

Gives the list of missing parts on plant. Material and different selection criteria for plant.

7.14

Stock/Requirement list

Fully system supported Fully System supported

Shows the detail scenario of stock or requirement scenario.

7.15

Collective Display of Planned Order.

Can display the planned orders collectively on the basis of MRP controller, Material and production version.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 45 of 45
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks Functionality relevant to MRP i.e., all MRP elements can be viewed from time to time. It will show the conditions of Stock or Requirement at time of last MRP run. This is of static type.

Gap (Y/N)

Remarks

MRP List 7.16

Fully System supported

7.17

MRP List Collective Display

Fully System supported

Same as previous, only it can be displayed MRP area wise.

7.18

Process Order Information System

Fully System supported

Gives the detail of the information regarding process Order management.

7.19

Process Order Individual list display.

Fully System supported

Gives the detail of the information regarding process Order management object wise.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 46 of 46
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

7.20

Resource analysis

Gives plant wise analysis of resources.

7.21

Operation analysis

Fully System supported

Gives the shop floor information operation wise.

7.22

Material Analysis

Fully System supported

Shop floor material analysis information.

7.23

Process Order Analysis

Fully System supported

Shop floor analysis for Process Order.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 47 of 47
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

7.24

Product Cost Analysis

Shop floor Product cost analysis.

7.25

Exception analysis

Fully System supported

N Exception analysis at material, plant and Process Order Level.

7.26

Capacity Planning

Fully System supported

Resource Load Analysis.

7.27

Capacity Planning

Fully System supported

Process Order Level.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 48 of 48
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

7.28

Capacity Planning

Resource Overload Analysis.

Resource View 7.29

Fully System supported

N Enhanced capacity evaluation-resource wise.

7.30

Order View

Fully System supported

Enhanced capacity evaluation-Order wise.

7.31

Material Consumption

Fully System supported

N Material Consumption analysis.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 49 of 49
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

7.32

Capacity Planning Table

Capacity Planning table- Process Order View.

7.33

Material to be costed.

Fully System supported

Display of material to be costed.

7.34

Result of Costing run.

Fully System supported

Analyse or compare material cost estimates.

7.35

Price Vs. Cost Estimate.

Fully System supported

Analyse or compare Material Cost Estimates.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 50 of 50
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

7.40

Costed Multi level BOM

Multi level BOM: Value /Amount/Status

7.41

Cost components

Fully System supported

Analyse cost component split for planned cost: cost component

8.0

Power PlantLogistics General Data

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 51 of 51
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

8.2

Batch Management

Fully system supported

The manufacturing mode of VAL is a typical case of process manufacturing scenario. Here, batch tracking is not possible N physically, neither it is required. So production in SAP as well as in reality wont be captured through batches in case of power plant. Material Classification can be done with the standard material classification system in SAP (Class Type 001). This will allow better search.

8.3

Material Classification

Fully system supported

Characteristic is a property that describes and differentiates objects. Classification Creation/change of Class and Characteristics Fully system supported Example: length, colour, weight, etc. Class is an assembly of characteristics that can be attributed to a N product (or to several similar products). It can also be defined as a grouping of similar products according to common characteristics Example Pump class, Boiler class etc.

8.4

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 52 of 52
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks If the order types are more than one, profiles will help in maintaining some controlling data. (i.e., automatic selection of order type during manual order creation).

Gap (Y/N)

Remarks

8.5

MRP Profile

Fully system supported Fully system supported

8.6

Procurement Type

This would help the system to identify the procurement type for the particular material. We use E for produced goods, F for external N procurement and X for both type of procurement.

8.7

Availability Check

Fully system supported

Based on this system checks the availability. In Vedanta we would use checking rule 01 for all semi-finished and finished product. This is used for accumulating the total requirement on daily basis. Any other availability check to be introduced can be considered at N Realization stage.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 53 of 53
Version No 1.2

Sl. No. 9.0

Process Name Product Data Management

Mode

Process Description/remarks

Gap (Y/N)

Remarks

9.1

Maintain Material Master

Fully system supported

Material master for Finished and Semi finished goods. Material Classifications may be used. Views such as Basic data 1, Basic Data 2, MRP 1, MRP 2, MRP 3, MRP 4 and work scheduling ( as and when required basis ). For example: For raw material there wont be any Work Scheduling View.

9.1.1

Create Material Master

Fully system supported Fully system supported

Create relevant views for each material and give the values of respective fields.

9.1.2

Change Material Master

Change values of settings as necessary in the material master can N be done anytime, but frequent change is not recommended.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 54 of 54
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

9.1.3

Display Material Master.

View settings without changing. This purely for read only purpose.

9.2

Maintain Bills of Material

Fully system supported

Create and change, as necessary, master data for Bills of Material. Standard BOM will be created and saved in the system. In case of N Process manufacturing scenario, this can be done along with recipe itself.

9.2.1

Create Bills of Material

Fully system supported Fully system supported

Create BOMs for all materials produced in-house. In case of Process manufacturing scenario, this can be done along with recipe itself.

9.2.2

Change Bills of Material

Change values of settings as necessary. In case of Process manufacturing scenario, this can be done along with recipe itself.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 55 of 55
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

9.2.3

Display Bills of Material

View settings without changing. This is purely Read Only view for BOM.

9.3

Maintain Resource

Fully system supported

Create and change, as necessary, master data for Resource. All Resource shall be attached to a Cost Centre. Processing Unit capacity categories may be used for a Resource. However data N related to Resource category and Capacity category may be changed at the time of realization depending on the simulation test result. Create Resource for all processing facilities in the plant with capacity categories of Processing Unit. This would capture logical place of operation under a plant and at the same time collect the costing data generated out of activity consumption.

9.3.1

Create Resource

Fully system supported

9.3.2

Change Resource

Fully system supported

This process would enable the user to capture any enhanced functionality in future. It can be used to change any existing field value apart from resource category and capacity category. Any

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 56 of 56
Version No 1.2

Sl. No.

Process Name

Mode supported

Process Description/remarks value apart from resource category and capacity category. Any extra capacity category can be introduced by using the functionality.

Gap (Y/N)

Remarks

9.3.3

Display Resource

Fully system supported

View settings without changing. This is used for viewing the master N data in Read _only mode.

9.4

Maintain Recipe

Fully system supported

Create and change, as necessary, master data for Recipe. The entire standard recipe will be created in the system for all the plants and material combination. PI01 can be used up while creating the Recipe.

9.4.1

Create Recipe.

Fully system supported

Create Recipe for all materials produced in-house. The respective operations, their phases, internal relations, material assignments are to be mentioned .The standard values for operations can also be mapped through this functionality. Control keys like PI01, PI22

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 57 of 57
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks and PI05 may be used depending on the business processes integrated along with the operations.

Gap (Y/N)

Remarks

9.4.2

Change Recipe

Fully system supported

Change values of settings as necessary. Any change in the process can be mapped in future through this transaction.

9.4.3

Display Recipe.

Fully system supported

View settings without changing and in Read Only mode.

9.5

Production Version

Fully system supported

Its a combination of BOM and Recipe. So in case of recipe it is mandatory to maintain Production version. Functionalities related to Lot size, alternative BOM etc. Multiple production version might be there for a material. It can be locked or Unlocked on as and when required basis.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 58 of 58
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

9.5.1

Create Production version

Fully system supported

At the time of recipe creation system prompts to maintain Production version. Multiple production versions are only used N when more than one production line is there. Here in Vedanta only one production version would be created.

9.5.2

Change Production version

Fully system supported

Data related to production version can be changed at anytime. If New BOM is to be attached keeping the existing one in the system N with the same recipe , one production version is generated and the previous one is locked in changed mode.

This is for displaying purpose read only mode. 9.5.3 Display production version Fully system supported N

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 59 of 59
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

Process Plant- Production Planning. 10.0 Production Planning (PP-PI) Make to stock production-planning strategy will be used for the Process plant. This has been decided pertaining to actual philosophy of production, which is not based on requirement. Basic idea is full utilization of plant capacity. Requirement type LSF and/ N BSE can be used to meet such requirement. For Power plant this functionality is used if and only if long term planning is done.

10.1

Production Strategy Fully system supported

11.0

Material Requirement Planning

The main function of material requirements planning is to guarantee material availability, that is, it is used to procure or produce the requirement quantities on time both for internal purposes and for sales and distribution. This process involves the monitoring of stocks and, in particular, the automatic creation of procurement proposals for purchasing and production.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 60 of 60
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks In doing so, MRP tries to strike the best balance possible between

Gap (Y/N)

Remarks

Optimising the service level and Minimizing costs and capital lockup.

For power plant planning would be done either through Consumption based planning (MM) or Long term Planning. But for Refinery Classical MRP (Deterministic) PP and consumption based (MM), both can be used. For power plant planning would be done either through Consumption based planning or Long term Planning. But for Refinery Classical MRP (Deterministic) PP and consumption based (MM), both can be used.

11.1

Run MRP on material

Fully system supported

11.2

Total Planning

Fully system supported

Total planning covers the planning of all the materials that are relevant for requirements planning and includes the BOM explosion for materials with a bill of material.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 61 of 61
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks You can use total planning for a single plant or you can use the scope of planning to control whether the total planning run is executed on a multi-plant level. For power plant planning would be done either through Consumption based planning ( MM ) or Long term Planning. But for Refinery Classical MRP (Deterministic) PP and consumption based (MM), both can be used.

Gap (Y/N)

Remarks

11.3

View Stock/Requirement list

Fully system supported

View Stock /requirements list to check stock position in terms of MRP elements. All the PIR, planned order and Production Orders ( if not delivered) would be displayed along with ATP ,safety stock( if any ) , existing Stock ( if any). User will be able to see the most updated information related to Stock/Requirement list. For power N plant planning would be done either through Consumption based planning (MM) or Long term Planning. But for Refinery Classical MRP (Deterministic) PP and consumption based (MM), both can be used.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 62 of 62
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks View Stock overview as and when required. System enables the user to check stock available for the stock items at various areas of the organization.

Gap (Y/N)

Remarks

11.4

Stock overview

11.5

MRP List

Fully system supported

Functionality relevant to MRP i.e., all MRP elements can be viewed from time to time. It will show the conditions of Stock or Requirement at time of last MRP run. For power plant planning would be done either through Consumption based planning (MM) or Long term Planning. But for Refinery Classical MRP (Deterministic) PP and consumption based (MM), both can be used.

11.6

Planned Order

Fully system supported

Proposal to manufacture after MRP execution is generated troughplanned order. It can be viewed from stock/ Requirement list. Planned Orders are converted to process order before the start of N process in the shop floor. For power plant planning would be done either through Consumption based planning (MM) or Long term Planning. But for Refinery Classical MRP (Deterministic) PP and

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 63 of 63
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks consumption based (MM), both can be used.

Gap (Y/N)

Remarks

12.0

Capacity Planning

The economic use of resources is an objective for many areas of a company. The component "Capacity Planning" is available in the N System for this purpose.

12.1

Capacity Evaluation

Fully system supported

Company can use capacity evaluations to analyse capacity loads in your company. You can adjust the analyses for each user according to the planning level, planning horizon and the area of responsibility. Available capacities and capacity requirements can be selected according to various criteria and cumulated using any period split you choose. To manufacture products in the shop floor as per the Recipe and Bill of Material (Material BOM)

13.0

Process Execution

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 64 of 64
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

13.1

Process Order

Fully system supported

Process orders are used for the production of materials or for rendering of services in a specific quantity on a specific date. They enable the planning of resources, control of process order management, and specify the rules for account assignment and N order settlement. Actual confirmation to shop floor to go ahead with manufacturing. This can be obtained from Planned order. Other wise for any offline requirement Process Order can also be created manually.

13.2

Create/ Change Process Order

Fully system supported

Creating a process order is not a stand-alone process. It is generally done before the commencement of manufacturing. The quantity to be produced under such a process Order has to be mentioned clearly. The scheduling of process order that has to be followed really for floor happens at this phase and system schedules the process order. For Vedanta forward scheduling is recommended as scheduling type.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 65 of 65
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks Process order consumes materials (Semi-finished / Raw). The Materials have to be issued to the Process Orders Or will have to be back flushed. Logically these materials have to be available in system before the commencement of process. System would display missing part list (if any). For Vedanta System will configured in such a way that system should raise warning if the material is not available. But decision-making should be at the level of user whether the Process Order could be processed after such missing part.

Gap (Y/N)

Remarks

13.3

Check Material Availability

Fully system supported

13.4

Release Production Order

Fully system supported

Process Order Release is carried out on verge of production initiation. In Vedanta this release procedure should be manual i.e., N user has to release the Process Order every time Production is initiated against a new Process Order.

13.5

Confirm Production Order

Fully system supported

This is for Confirming actual completion of production for an order, N either partial or final. Also actual yield, scrap, time taken, and goods movements will be confirmed.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 66 of 66
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

13.6

Confirmation cancellation

Partially system supported

It is possible to cancel data previously confirmed. Every completion confirmation entered in the system can be cancelled. Thus, if you P entered three confirmations for a phase, you can also cancel three confirmations and all confirmations automatically created by them.

13.7

Issue Materials & Components

Fully system supported

For Posting goods issued for Production, this functionality will be used. This will ensure the total consumption for production. Movement type used for this process is 261. For any return of goods issue, movement type 262 will be used. Unplanned materials can also be issued for a process order.

13.8

By-product receipt

Fully system supported

Any by-product should also be taken as a component (-ve qty) into the BOM of in-house produced materials and that by-product will be receipt into the stock at the time of confirmation. Standard

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 67 of 67
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks movement type is 531.For reversal 532 may be used.

Gap (Y/N)

Remarks

13.9

Receive Produced Materials

Fully system supported

Goods Receipt for produced goods is captured through this functionality. After Goods receive store will be updated in inventory. Standard movement type 101. For reversal 102 may be used.

13.10

View Cost

Fully system supported

The Planned vs. actual costs can be viewed after all issues and activities are completed in the process Order change mode/display mode.

13.11

Technical Closure (TECO)

Fully system supported

Once the process order is confirmed fully i.e., desired yield is confirmed in terms of Goods movement and activity confirmation is also done along with, it has to be declared Technically complete. N The entire reservation list pending (if any) for the Process Order is deleted after this activity by the system itself.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 68 of 68
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks

Gap (Y/N)

Remarks

14.0 Reports Fully system supported Reports are generated in the SAP system based on the information fed on day-to-day basis. This enables the user to take decision related to business.

14.0

Reports

14.1

Stock Overview

Fully system supported

It can be used to view Stocks for different material taking Plant and N storage location as additional selection criteria.

14.2

Extend material views

Fully system supported

It shows the historical data related to material extension at different N point of time.

14.3

List of material Storage location assignment.

Fully system supported

Shows the exhaustive list for material- storage location assignment.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 69 of 69
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

14.4

Material List

Shows Detail of a material on basis of selection criteria like plant, material, material type, material group and created by.

14.5

Material list with price and inventory values

Fully system supported

Gives the detail of standard price, Per unit price, Currency Key etc.

14.6

Resource List

Fully system supported

Gives detail of resources.

14.7

Cost Centre assignment.

Fully system supported

Shows the details assignment of cost centres to Resources.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 70 of 70
Version No 1.2

Sl. No.

Process Name

Mode Fully system supported

Process Description/remarks

Gap (Y/N)

Remarks

14.8

Resources Capacity

Shows the capacity records ( Master) for different resources list wise.

14.9

Where used listResource

Fully system supported

Lists the different recipes where resources are used.

14.10

Where Used List Material

Fully system supported

Lists of material Used into different BOM.

14.11

Stock/Requirement list-collective display

Fully System supported

Gives the stock /requirement scenario for a MRP area or plant

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 71 of 71
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

14.12

Multi level Order Report

Gives multilevel order report for Process Order with different information.

14.13

Missing Part InfoSystem

Fully System supported

Gives the list of missing parts on plant. Material and different selection criteria for plant.

14.14

Stock/Requirement list

Fully system supported Fully System supported

Shows the detail scenario of stock or requirement scenario.

14.15

Collective Display of Planned Order.

Can display the planned orders collectively on the basis of MRP controller, Material and production version.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 72 of 72
Version No 1.2

Sl. No.

Process Name

Mode

Process Description/remarks Functionality relevant to MRP i.e., all MRP elements can be viewed from time to time. It will show the conditions of Stock or Requirement at time of last MRP run. This is of static type.

Gap (Y/N)

Remarks

MRP List 14.16

Fully System supported

14.17

MRP List Collective Display

Fully System supported

Same as previous, only it can be displayed MRP area wise.

14.18

Process Order Information System

Fully System supported

Gives the detail of the information regarding process Order management.

14.19

Process Order Individual list display.

Fully System supported

Gives the detail of the information regarding process Order management object wise.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 73 of 73
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

14.20

Resource analysis

Gives plant wise analysis of resources.

14.21

Operation analysis

Fully System supported

Gives the shop floor information operation wise.

14.22

Material Analysis

Fully System supported

Shop floor material analysis information.

14.23

Process Order Analysis

Fully System supported

Shop floor analysis for Process Order.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 74 of 74
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

14.24

Product Cost Analysis

Shop floor Product cost analysis.

14.25

Exception analysis

Fully System supported

N Exception analysis at material, plant and Process Order Level.

14.26

Capacity Planning

Fully System supported

Resource Load Analysis.

14.27

Capacity Planning

Fully System supported

Process Order Level.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 75 of 75
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

14.28

Capacity Planning

Resource Overload Analysis.

Resource View 14.29

Fully System supported

N Enhanced capacity evaluation-resource wise.

14.30

Order View

Fully System supported

Enhanced capacity evaluation-Order wise.

14.31

Material Consumption

Fully System supported

N Material Consumption analysis.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 76 of 76
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

14.32

Capacity Planning Table

Capacity Planning table- Process Order View.

14.33

Display Material to be costed.

Fully System supported

Display of material to be costed.

14.34

Result of Costing run.

Fully System supported

Analyse or compare material cost estimates.

14.35

Price Vs. Cost Estimate.

Fully System supported

Analyse or compare Material Cost Estimates.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 77 of 77
Version No 1.2

Sl. No.

Process Name

Mode Fully System supported

Process Description/remarks

Gap (Y/N)

Remarks

14.40

Costed Multi level BOM

Multi level BOM: Value /Amount/Status

14.41

Cost components

Fully System supported

Analyse cost component split for planned cost: cost component

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 78 of 78
Version No 1.2

SECTION IV
Process Plant: (SAP Flow Diagram) Purchase Requisition Create Demand Integration with MM Convert Planned Order to Process Order/Process Order Creation Integration With PM Integration with MM

Raise PIR

Run MRP

Planned Order

Scheduling

Capacity Availability Check

Material Availability Check

Ready For Delivery (SD Integration

Usage Decision (QM Integration) Technical Completion of Order

Goods Received

Process Order Confirmation

Goods Issue against Process Order. Accounting Document, Material Document and Controlling document Generated.

Calculation of Planned cost at the time of saving

Release

Closing

Integration With FI-CO and MM

Integration with FI-CO

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION Power Plant:

Production Planning
Business Process Blueprint

Page 79 of 79
Version No 1.2

Integration With PM Process Order Creation Scheduling

Integration with MM Material Availability Check

Capacity Availability Check

Closing

Technical Completion of Order

Goods Received

Process Order Confirmation Integration With FI-CO and MM

Goods Issue against Process Accounting Document, Material Document and Controlling document Generated.

Calculation of Planned cost at the time of saving

Release

Integration with FI-CO

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 80 of 80
Version No 1.2

Special Organizational Considerations: Different Grades of Bauxites and coal would be treated as single material. Neither it would be batch managed nor separate material code would be maintained for that. It will be managed through Moving Average price. In Refinery only three Resources might be there. There will be no In Process Inspection. Red Mud should be treated as Waste. Process Order would be created for a month for refinery. At the end of every month Process Order would be reconciled. Demand for Alumina should be generated on monthly scale. Confirmation of process Order of refinery will be done shift wise/Daily basis. In power plant consumption would be posted based on the actual Production. Reading of meters at the end of power plant may be taken into account.

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Vedanta Alumina Ltd.


SAP ECC 5.0 IMPLEMENTATION

Production Planning
Business Process Blueprint

Page 81 of 81
Version No 1.2

Only one saleable item is there Alumina. Hydrate wont be sold. For power plant DM water would be considered as activity and would be directly booked to cost centre on a certain frequency. For power plant process order should be created on daily basis. Plant shall have only one resource. Process Order confirmation in power plant would be done on daily basis.
For power & steam one PO will be generated on daily basis. Distribution rule of power & steam will be posted on daily basis per process

order (manually). All the raw materials will be planned by consumption based planning and that will be taken care by MM.

------ End ------