Perhitungan pile cap

(Dimensi 170 cm X 235 cm X 350 cm)


Volume pile cap :
1,7 m X 2,35 m X 3,5 m= 13,98 m3
D16 = 1,58 kg/m
Lebar = 235 cm (selimut beton)
= 235 cm 8 cm
= 227 cm = 2,27 m

Jumlah tulangan

Tinggi = 350 cm / 20 cm ( spasi antar tulangan)


= 17,5 = 18 tulangan
Jadi total berat tulangan:

2,27 m X 18 X 1,58 kg/m = 64,56 kg


2,27 m X 18 X 1,58 kg/m = 64,56 kg
0,18 m X 2 X 1,58 kg/m = 0,57 kg
0,34 m X 2 X 1,58 kg/m = 1,07 kg +
130,76 kg

D25 = 3,85 kg/m


Tinggi = 350 cm
Jumlah tulangan = 15 tulangan
Jadi total berat tulangan:
3,5 m X 15 X 3,85 kg/m = 202,13 kg
0,2 m X 15 X 3,85 kg/m = 11,55 kg +
213,68 kg

D13 = 1,004 kg/m