HOPE REPORT/RECOMMENDATION TO COUNCIL
3500 LDP 41/18
DATE: November 26, 2018 FIL
SUBMITTED BY: Jas Gill- Director of Community Development
Cs oa ne arose
Peon eta etre 7.04
CMe WNT)
PURPOS!
To obtain Couneits approval o prepare a Development Permit with Variance in order forthe
applicant to proceed witha hotelestaurantconference centre development
RECOMMENDATIOI
Resolution #1
THAT a Rail & Highway Service Conidor Development Permit be prepared fr the property
legally described as That Part of Distict Lot 60 Lying South of the Southern Limit of the
Hope-Princeton Highway as shown on Plan H4 and West ofthe West Boundary of Section
11 Township 5 Range 28 West ofthe 6 Meridian, Yale Division Yale Distict Except Plan
39120, PID 014-767-945, 960 Old Hope Princeton Way to enable the owmerideveloper to
proceed with the development of a hotel/testauranticonference centre; and
FURTHER THAT the Director of Community Development be authorized to approve minor
changes tothe Development Permit, and
FURTHER THAT for purposes of the Development Permit vay period, the conditions of
the Development Permit shall expte on November 28, 2020; and
FURTHER THAT for purposes of any associated building permit, thatthe “substantial stat
of any construction” shall mean the completion of any foundation for any of the proposed
structures; and
FURTHER THAT the site preparation and tree removal area be restricted to the
development of ahoteltestaurant/conference centre only and not the overall site; and
FURTHER THAT the Director of Community Development be authorized to endorse the
Development Permit and associated documents
Resolution #2
THAT Council approve the preparation of a Development Variance Permit to vary the
Highway Commercial (C-2) maximum building height provision for a principal building or
structure in Zoning Bylaw 1324, 2012 from 15 metres (49.5 feet) to 18.6 metres (61 feet) in
trder to construct hotel, restaurant and conference centre on the property legally
Pi91Page
described as That Part of District Lot 80 Lying South of the Southem Limit of the Hope-
Princeton Highway as shown on Plan H84 and West of the West Boundary of Section 11
Township 5 Range 26 West of the 6" Meridian, Yale Division Yale District Except Plan
‘39120, PID 014-767-945, 950 Old Hope Princeton Way; and
FURTHER THAT in accordance with the District of Hope Procedures Bylaw 19/93, the Local
Government Act and the Community Charter authorize staff to issue a notice of intent to
consider the approval of the Development Variance Permit fo the neighbouring property
‘owners including the Ministy of Transportation and Infrastructure.
ANALYSIS:
A. Rationale:
Proposal - The developer would lke to reiniiate the project to develop a
hotelrestauranticonference centre on the property. In an effort to manage expectation, the
drawings presented indicate the corporate franchise Best Western; however, there is a
possibilty that this franchise could change as this project progresses. The developer has
‘an overall development plan for the site; however, its important to note that this application
is specific to the development currently being proposed (hotel/estaurant/convention centre)
and should not be misconstrued as an application for the developer's overall development
plan for the entire site,
Background ~ The developer is well known to District staff as they were the developer's
who brought Tim Hortons to the District and also tried to introduce a
hotelrestauranticonvention centre at 150 Old Hope Princeton Way. Unfortunately, the
developer's efforts came to an end at 150 Old Hope Princeton Way. In 2015, the developer
relocated his hotel/restaurant/convention centre proposal to 950 Old Hope Princeton Way
with new partnerships,
(On February 23, 2015, Council approved a form and character Development Permit (DP) for
the subject site; however, that approval has now expired. Section 504 of the Local
Government Act states "subjoct fo the torms of the pormit, i the holder of a fand use permit
does not substantially start any construction with respect fo which the permit was issued
wihin 2 years alter the date itis issued, the permit lapses.”
On February 27, 2017, the expired 2018 Development Permit with a Variance project was
reintroduced to Counci Council did approve the application; however, the proposal being
introduced today has changed too significantly for it to be considered a minor amendment to
the former application. This "new" application requires the necessary approvals including
Counci’s confirmation or acceptance of conditions. on bondingivoluntary contributions
previously approved in the former applications.
“The overall size ofthe propery is approximately 18.40 acres and the proposed development
(building and parking lot) is to occupy approximately 3.5 acres. The property is zoned
Highway Commercial (C-2) which permits a hoteVtestaurant/conference centre.
Development Permit (DP) Form & Character ~ The development meets the expectations
of the Rail & Highway Service Corridor DP for form character. The spit level building can
be broken into four main decorative components, ‘The first is the “heathered moss" green
color hardie plank siding that makes up the predominant wall faces excluding the windows
P192Pages
‘of doorways. The secondary wall faces that are tucked away under roof overhangs have
sandstone beige hardie plank siding. Secondly, the siding Is contrasted with exposed
stained wood fascia boards that follow the predominant rooflines or are structural
components (beam and post). The windows are accented with white tim, Thirdly, the
building has a decorative stone veneer base that follows the ground floor. Finally, any
peaked portions of roof that contain wall face, all have a cedar shakes accented with
exposed stained wood fascia board, Signage elements wil maintain their corporate theme
to retain brand recognition,
Overall, staf feels thatthe proposal is complementary to the area and should be sulficient to
‘atioty the applicable DP guidolincs.
Development Variance Permit (DVP) ~ Typically in the C-2 zone, the maximum building
height is 15 metres. The applicant requires 18,6 metres for their development. The building
height increase is due to a combination of things. Many hotel franchises (like Best Western)
have a standard of nine-foot celings for all guest rooms, Requesting such a variance will
also provide flexibility when it comes to construction type and material (prefabricated
‘modular verses stick frame). The substantial change to the hotel isthe spli-level approach
Which technically increases the building height. In accordance with the definition of Building
Height in our Zoning Bylaw:
“means the vertical distance from the average finished grade at the perimeter of a building
or structure fo:
(a) the mid-point between the elevation of the highest eaves and the highest ridge in a
pitched roof building (AM#1343)
‘The majority of the proposed building footprint occupies a lower contour at the sloped site
which increases the depth of the average finished grade and in turn increases the building
height.
Voluntary Contributions and Council Confirmation ~ Staff felt it was important to give
Council some background as to how the voluntary contribution tem came about:
At the February 23, 2015 Council meeting, Council had the following questions:
‘+ "Will the previous Voluntary Contributions continue to apply from the application at
10 Old Hope Princeton Way?”
‘+ "Can we obtain a Performance Security should the developer abandon the project?”
‘The answer to the first question is "no", There Is no obligation or connection with the
Voluntary Contributions to the new property. The covenant registered on the property ttle at
150 Old Hope Princeton Way is tied to the former development proposal on that site.
Furthermore, these types of agreements are not best practices
To answer the second question, itis possible that a Performance Bond or Letter of Credit
‘could be carefully worded to accomplish this, but the problem is that finances are tied up in
securities that could affect the cash flow required to do the project. The developer indicated
that funds would be more available once the project is complete, but this does not provide
any protection that the project will just be dropped half way through construction. Tying
anything to the property tile is not an option as it does not tle the developer to any
commitments,