THE GREATEST
RETROFITTING, REVISIONS, STRENGTHENING, REANALYSIS, REDESIGN OF RC EARTHQUAKE RESISTANCE BUILDING IN INDONESIA
EXISTING CONDITION
2ND AFC INTERNATIONAL CONFERENCE, BALI
East & West Tower: apartments changes direction from N-S to EW direction
PROBLEMS (1)
REASSESMENT OF THE AS BUILT DRAWINGS WITH AS BUILT STRUCTURES :
BUILDING LAY-OUT & FOOT PRINT STRUCTURAL MEMBER STRENGTH & SECTION PROPERTIES (REBARS) DEWATERING WELL (REPAIR & CHECKS + CLEANING)
CUTTING & DEMOLISHED THE 800 MM THICK OF CONCRETE WALL WITH GRADE OF 50 MPa !! (EARLIER STAGE, PREPARE SERIES OF CORES AND MANUAL HAMMERING CONCRETE VERY SLOW PROGRESS & EXPENSIVE COSTS (PROJECT DELAY) CHANGES METHOD
20-21 NOV. 2 CORES AT CERTAIN DISTANCE, INSERT THE WIRES, 2ND AFC INTERNATIONAL PREPARE2006 CONFERENCE, BALI ROTATE WITH PRESSURE, WORKS AS JIG-SAW 6
REQUIRE EXTRA CARES AND WELL PLAN COORDINATION FOR UPPER HEAVY QUIPMENT MOBILIZATION INTERNATIONAL FLOORS 20-21 NOV. 2006 2ND AFC AND LOWER CONFERENCE, BALI CONSTRUCTION ACTIVITIES !!!
SPACE LIMITATION AT EXISTING LOWER & BASEMENT FLOORS REQUIRE MANUAL DEMOLITION !!!
20-21 NOV. 2006 2ND AFC INTERNATIONAL CONFERENCE, BALI 8
EXTENDED MAT FOUNDATION EXCAVATION & ADDITIONAL 2ND AFC INTERNATIONAL BORED PILE FOUNDATION CONFERENCE, BALI
PROBLEMS (2)
BORED PILE INSTALLATION
PREOPENING DRILLING & INSTALLATION
R C D S Y S T E M
theodolit (survey); lalu di buat lubang tiap-tiap lantai, diameternya lebih besar dari diameter bored pile, pada Basement 4 di buat sampai tembus ke tanah.
Existing Soil
Existing Soil
3.Pengeboran dimulai dengan alat bor RCD, selama pengeboran lumpur dan tanah akan disedot melalui pipa dan dimasukkan ke dalam tangki yang telah disediakan dimana pengeboran sampai batas kedalaman yang ditentukan.
4.Memasukkan pembesian yang telah dirakit, oleh alat Rafter Crane sampai batas kedalaman yang ditentukan.
Existing Soil
11 8
Study Time
Add subtitle here
12
13
14
6. Pengecoran dimulai dengan menggunakan Concrete Pump sampai batas COL atau level yang ditentukan.
R C D S Y S T E M
7.Pencabutan casing. 8.Pekerjaan Bored Pile selesai
15 9
16
PROBLEMS (3)
RETROFITTING & STRENGTHENING
COLUMNS SHEARWALLS EXTENDED MAT SLABS; PILE CAPS (CHEMICAL ANCHORS)
17
CHEMICAL ANCHORS, INTERFACE PREPARATION FOR EXISTING CONCRETE SURFACES (SAND BLAST, CHIPPINGS), EXISTING REBAR OBSTRUCTIONS, ADDITIONAL REBARS, SPECIAL NON-SHRINK CONCRETE PLACEMENT
18
MANUAL EXCAVATIONS
CHEMICAL ANCHORS
19
EXTENDED MAT SLABS: EXISTING REBAR OBSTRUCTIONS FOR CHEMICAL ANCHORS (LIMITED IN SPACINGS AND DRILLING LENGTH),, 20-21 NOV. 2006 2ND AFC INTERNATIONAL PROOF TESTS (CYCLIC), APPLIES SHEAR RESISTANT JOINT CONCEPT CONFERENCE, BALI (INSTEAD OF MOMENT RESISTANT) !!
20
21
22
EARLIER STAGES DESIGN CONCEPT (SIMPLIFED THE STRUCTURAL ANALYSIS AND COMPEXITY)
23
ELIMINATE THE SEISMIC JOINT 3D-FULL STRUCTURAL DESIGN & ANALYSIS FOR THE WHOLE BUILDING
25
LOADING COMBINATIONS
26
COL
COM
LOADING COMBINATIONS (34 LOAD CASES) : SPECIFICALLY CHECK THE ADDITIONAL INDUCED SHEARS DUE TO LATERAL TORSION APPLIES PAULAYS CONCEPT ON THE UPPER-BOUND LIMIT 15% ADDITIONAL SHEAR INDUCED BY LATERAL TORSION (FOR REGULAR 20-21 NOV. 2006 2ND AFC INTERNATIONAL 27 BUILDING)
CONFERENCE, BALI
28
CONCLUSION
MANY UNPREDICTABLE PROBLEMS APPEAR DURING THE REASSESMENT & REDISGN OF EX ASBUILT STRUCTURE FULL DAY TO DAY COOPERATION WORK BETWEEN CLIENT, CONTRACTOR, ARCHITECT STRUCTURAL ENGINEERS & COST CONSULTANTS
20-21 NOV. 2006 2ND AFC INTERNATIONAL CONFERENCE, BALI 29
ACKNOWLEDGEMENTS
PT PACIFIC PLACE (THE CLIENT) PT ACSET (MAIN CONTRACTOR) FICHER INC. (CHEMICAL ANCHOR SUPPLIER & SUB CONTRACTOR) HAERTE CONSULTING ENGINEERS (STRUCTURAL ENGINEERS)
WITHOUT THEIR INGENEOUS CONTRIBUTION, THIS WORK WOULD NOT BE ACCOMPLISED
20-21 NOV. 2006 2ND AFC INTERNATIONAL CONFERENCE, BALI 30