Post Tender Valuations & Budget Control

Better Financial Control for your Projects using Candy Valuations

Course Notes

Evelio De Abreu - November 2010

Post Tender Valuations & Budget Control

Post Tender Valuations & Budget Control

Contents

Chapter 1. Starting Up ....................................................................................................................... 1 1.1 Starting Candy ..................................................................................................................................................... 1 1.2 Company Manager ............................................................................................................................................ 1 1.3 Create a New Company ................................................................................................................................... 2 1.4 Job Manager ........................................................................................................................................................ 3 1.5 Create a new Job ................................................................................................................................................ 4 1.6 Recover the CCS Demo Job ........................................................................................................................... 5 Chapter 2. Candy User Interface ....................................................................................................... 7 2.1 Candy Navigation............................................................................................................................................... 7 2.2 Document Navigation ...................................................................................................................................... 8 2.3 Right click menu functions ............................................................................................................................. 9 2.4 Keystrokes, Icons and Mouse Functions.................................................................................................. 11 Chapter 3. Post Tender Checks ....................................................................................................... 13 3.1 Job Information................................................................................................................................................. 14 3.2 Confidence Check ............................................................................................................................................ 16 3.3 Selling Rate ......................................................................................................................................................... 17 3.4 Copy the final quantity from the bill quantity ....................................................................................... 21 3.5 Check and review reports ............................................................................................................................. 23 3.6 Value Analysis .................................................................................................................................................... 27 3.7 Resource Checks............................................................................................................................................... 29 Chapter 4. Pricing using Worksheets ............................................................................................. 35 4.1 Price Code ........................................................................................................................................................... 35 4.2 Price Plug and Split Rate items using Worksheets .............................................................................. 35 Chapter 5. Value Engineering (or Re-modelling) .......................................................................... 43 5.1 Job Remodelling ............................................................................................................................................... 43 5.2 Explode Macros................................................................................................................................................. 45 Chapter 6. Coding using Cost and Group codes ........................................................................... 49 6.1 Cost codes & Group codes .......................................................................................................................... 49 6.2 Defining the Cost codes ................................................................................................................................ 50 6.3 Allocating the Cost & Group codes to Simple resources ................................................................. 52 6.4 Resource Analysis Reports ............................................................................................................................ 54 Chapter 7. Controlling Labour and Plant using Task Codes ........................................................ 61 7.1 Defining the Task codes ................................................................................................................................ 62 7.2 Task code allocation........................................................................................................................................ 63 7.3 Task code analysis............................................................................................................................................ 67 7.4 Task code reports ............................................................................................................................................. 69 Chapter 8. Variation Pricing and VO codes ................................................................................... 75 8.1 Variation pricing ............................................................................................................................................... 75 8.2 VO Codes ............................................................................................................................................................ 77 8.3 Variation Order documents.......................................................................................................................... 77 Chapter 9. Valuation No.1 using Calcsheets .................................................................................. 79 9.1 Valuation Setup ................................................................................................................................................ 79 9.2 Primary Valuation Quantities ....................................................................................................................... 81 9.3 Measuring Final qtys using Quantity Calcsheets ................................................................................ 83 9.4 Entering Valuation quantities ...................................................................................................................... 86

Post Tender Valuations & Budget Control

Contents

Chapter 10. Valuation No. 1 using Area Bills ................................................................................ 89 10.1 Area manager .................................................................................................................................................... 89 10.2 Importing the bill items in the area bills ................................................................................................. 90 10.3 Apply area code ................................................................................................................................................ 92 10.4 Measure Area Actual Quantities ................................................................................................................. 95 10.5 Update Valuation Actual qtys using Areas ............................................................................................ 96 Chapter 11. Valuation Report Manager ......................................................................................... 97 11.1 Interim Payment Claim report ..................................................................................................................... 97 11.2 Valuation Listings report ............................................................................................................................... 98 11.3 Valuation Resource Analysis report ....................................................................................................... 100 11.4 Project Codes Resource Analysis report ............................................................................................... 101 11.5 Valuation Trade Total Display................................................................................................................... 103 Chapter 12. Costs & Allowables ....................................................................................................105 12.1 Analyse Allowable to-date ......................................................................................................................... 106 12.2 Cost & allowable columns ......................................................................................................................... 107 12.3 Import To-Date costs ................................................................................................................................... 107 12.4 Check import file ........................................................................................................................................... 109 12.5 Cost Adjustments .......................................................................................................................................... 111 12.6 Release costs ................................................................................................................................................... 111 12.7 Analyse Allowables to date vs. Costs to Date..................................................................................... 112 12.8 Cost to complete using cost rates .......................................................................................................... 113 12.9 Cost & Allowables at Completion ........................................................................................................... 117 12.10 Cost & Allowables using Task and Cost Codes ................................................................................. 118 Chapter 13. Set up Next Valuation ...............................................................................................119 13.1 Setup Next Valuation ................................................................................................................................... 119 Chapter 14. Subcontract Manager................................................................................................123 14.1 Create a new Subcontract .......................................................................................................................... 123 14.2 Creating Subcontract Bill using the Main Bill ..................................................................................... 125 14.3 Creating the Subcontract Bill using S/C Adjudicator ....................................................................... 130 14.4 Subcontractor Details .................................................................................................................................. 133 14.5 Subcontract Progress Measure ................................................................................................................ 135 14.6 Extras .................................................................................................................................................................. 140 14.7 Charges ............................................................................................................................................................. 142 14.8 S/C MOS ........................................................................................................................................................... 143 14.9 S/C Summary .................................................................................................................................................. 144 14.10 S/C Liability ...................................................................................................................................................... 147 Chapter 15. Valuation No. 2 Using Subcontract Manager .........................................................149 Appendix A- System Registration ................................................................................................153 Appendix B System Settings ......................................................................................................155

Post Tender Valuations & Budget Control

Company & Job Manager

Chapter 1. Starting Up
1.1 Starting Candy

Start the System from the windows desktop by double clicking on the Candy shortcut. Complete the user Login with your User Name, Initials and Company name.

1.2 Company Manager


This is the top level menu in the system where a maximum of 24 companies may be created.

For example, if you are tendering in a joint venture with another firm, you can create a brand new company for that bid. To select a company, position the cursor on the required company and use Enter or Double click.

Post Tender Valuations & Budget Control

Company & Job Manager

1.3 Create a New Company


Do this Click the Company > New > Company menu.

Edit the company name to read CCS Training Company, click

Note: You may enter a Company Code and a Password for your company

Post Tender Valuations & Budget Control The company CCS Training Company has now been created.

Company & Job Manager

1.4 Job Manager


Double click on the CCS Training Company to access the Jobs in the company.

The job manager generates a new header and new job automatically. You may create up to 99 jobs within a company that may be copied, renamed, deleted and backed up using the Job menu or using the Right-click Menu.

Post Tender Valuations & Budget Control

Company & Job Manager

1.5 Create a new Job


Do This Click the Job > New Job menu.

Edit the job name to read Waste Water Treatment Works and then click

Note: You may designate a Job Code and Password for your job

Open the job by double clicking on the job or by clicking

Post Tender Valuations & Budget Control

Company & Job Manager

1.6 Recover the CCS Demo Job


From the Job Manager click Job > Backup/recover job > Recover into a NEW job > from file

Recover the Ventshaft and Substation Contract using the following directory on the Candy Installation CD <CD Drive>/FSCOMMAND/Demo Jobs/Ventshaft and Substation Contract

Post Tender Valuations & Budget Control

Company & Job Manager

Click

to confirm

Click on

to access the Ventshaft & Substation Contract

Post Tender Valuations & Budget Control

User Interface

Chapter 2. Candy User Interface

Candy Button

System Toolbar

Title Bar

Application Tab

Candy Version

General Toolbar

Application Menu

Application Toolbar

General Menu

Customise Toolbar

The Candy user interface consists of four main sections namely: Title bar, Application Tabs, Application Menus & Toolbars.

2.1 Candy Navigation

Candy button System toolbar Title Bar Candy version Application tabs Application menu General menu

To select the job manager, system settings and to exit the software Job manager and system settings toolbar buttons Displays the company and job you are working in Displays the software version installed on the computer and displays the system information To select the Various Candy applications Displays the menus of the application selected Menu for Utilities & Help including telephone list, daily dairies, card games, help files, licence registration, support information & a website link to Update the Candy version Displays general tool buttons for use on all applications Displays shortcuts specific to the application selected. This tool bar changes when a different application tab is selected To select the toolbar buttons displayed on the different toolbars

General toolbar Application toolbar

Customise Toolbar

Post Tender Valuations & Budget Control

User Interface

2.2 Document Navigation


Do this To add the Standard Bill of Quantities Document to the Document Manager click on Documents>Estimating Documents then click and confirm then click and Select 1.1 Standard Bill of Quantities to open the document.
Document Menu Document Toolbar Split Screen Buttons

Document Title

Escape

Column Selector

Select all records

Record Selector

Page Navigation Buttons

Function Buttons

Document Title Split screen buttons Escape Document menu Document toolbar Select all records Function Buttons

The name of the document Resizes the document to the top or bottom half of the screen. Go back to the previous menu. The menus available for this document Tool buttons for larger or smaller screen fonts, line deletion, find & replace, export to Excel and print screen. Selects all records in the Bill of Quantities. These buttons relate to the function keys on the keyboard. Namely; Calculate (F12), Worksheet (F11) and Go to Page (F10). NB: If the rates and heading totals require re-calculation, click the red calculate button. Selects the entire record. Right click to display the record menu Selects the entire column. Right click to display the column menu Scrolls between different pages namely; first page, previous page, next page and last page of the bill. 8

Record selector Column Selector Page Navigation Buttons

Post Tender Valuations & Budget Control

User Interface

2.3 Right click menu functions


The menu functions in Candy are context sensitive; therefore, specific tasks can be performed directly on the documents cell, record, or column by right clicking for additional options. In a cell:

Right Click

In a record selector:

Right Click

Post Tender Valuations & Budget Control

User Interface

In a selected column:

Right Click

10

Post Tender Valuations & Budget Control

User Interface

2.4 Keystrokes, Icons and Mouse Functions


Mouse Functions Note: This table assumes that the mouse buttons are configured for a right-handed user. Mouse action Left-click Function On an Active Document - moves the cursor line to and positions the editing cursor at the mouse pointer. On an Inactive Document - Turns the document Active and acts as above. On an Active Document calls up the context menu. Fetch another document, i.e.: Double Click on a Net Rate calls up the Worksheet. Select a line of data for Dragging and Dropping. Marks the Start and End of a Range of records for Dragging and Dropping. Set an Alternate document.

Right-click Double Click Row Record +Left-click Row Record Shift+Left-click Alt+Left-click

Keystrokes This is a list of the Editing and Cursor Movement Keystrokes, with a brief explanation of the function, and the equivalent Icon if available. Note: Normal Windows shortcut keys can be used e.g. Ctrl C Copy, Ctrl V Paste etc.

Shift+Esc(ape) Esc(ape) Ctrl+Tab Ctrl+Insert Ctrl+Del Tab Home End Ctrl + > Ctrl + <

Returns to the job selector Returns to the previous menu Moves the document currently on top to behind all other documents. Inserts a new line at the cursor position Deletes the current line at the cursor Moves the cursor forward to the next Field. Shift+Tab moves the cursor backwards. Moves the cursor to beginning of the field Moves the cursor to the end of the field Move to the next page Move to the previous page

11

Post Tender Valuations & Budget Control

User Interface

Ctrl+Page Up Ctrl+Page Down Ctrl+Enter Backspace Ctrl+Backspace Ctrl+Left-arrow Ctrl+Right-arrow Ctrl+Up-arrow Ctrl+Down-arrow Shift+Ctrl+Downarrow Shift+Ctrl+Uparrow Ctrl+Space Bar Shift+Ctrl+Space Bar Ctrl+R Shift+Ctrl+R (Ctrl+D) Ctrl+U Ctrl+L Ctrl+T Ctrl+K Ctrl+J Alt+Del Shift+Alt+Del Ctrl+Z

Takes you to the first line of the first page of a document Takes you to the first line of the last page of a document Split the line at the cursor position Deletes one character at a time Deletes one word at a time Bubble Up - move the current line up Bubble Down - move the current line down Collapse level headings (to hide all text under headings) Expand level headings (to show all text under headings) Opens all sub headings within the cursor position heading Closes all sub headings within the cursor position heading Open all headings completely Close all headings completely Pick Up the current Line Drop (insert) Lines picked up using Ctrl+R at the current line Turn current line to UPPERCASE letters Turn current line to lowercase letters Turn current word to Sentence case Copy the Field above Copy the Field above and moves cursor down one line Close the active Document. Close All Documents. Undo. Note: As soon as the cursor is moved off the line, the line is stored and the undo button will not function

12

Post Tender Valuations & Budget Control

Post Tender Checks

Chapter 3. Post Tender Checks


Explanation The estimate created by the tender department in Candy Estimating can now be used by the Site Team. It is essential to do some post tender check to prepare the Tender for Post Tender use.

Recover the estimate and do the following Checks. It is good practice to copy the job before Remodelling the job for Post Tender Valuations. Eventually the Q.S will have and electronic copy for the Job at Estimate Stage and a copy for the Remodelled Job for use at Post Tender Valuations stage.

Do This Go to the Job Manager Duplicate the Ventshaft & Substation Contract, rename the job to Ventshaft & Substation Contract- Remodelled.

13

Post Tender Valuations & Budget Control

Post Tender Checks

3.1 Job Information


Certain useful information like the Contract Value and Job Size can be analysed.

Trade Totals Display


Do this: Choose the Valuations application tab.

The job total by trade can be displayed by clicking the

(Trade Totals) icon.

Initial Valuation setup


The Initial Valuation setup dialog appears when accessing the Valuations Application for the first time. The valuation setup dialog is used for entering details for the first Valuation. Enter the Valuation Date, Number and header.

Cost and Allowable options


Cost and Allowables options allows for inclusion or exclusion of Variation orders in Cost and allowable documents. Variation orders and Cost and Allowables will be covered in detail later.

Choose the Cost and Allowable options. Note: These options may be changed later if required. 14

Post Tender Valuations & Budget Control

Post Tender Checks

Select the Bill Quantity Select Net rates

The Net Trade Summary is shown.

The Gross Trade Total and Selling Trade Total can be displayed using the same selecting the appropriate rate.

icon and

15

Post Tender Valuations & Budget Control

Post Tender Checks

3.2 Confidence Check


Checks the entire estimate and reports problems found. Unpriced or plug/split pricing codes, provisional items and resources, data copied from the master, markup and selling rates are checked and recorded.

Do this: In the Trade Totals Display click Select Perform full error check with report

16

Post Tender Valuations & Budget Control

Post Tender Checks

Job Size Display


Gives an overall listing of the job and is an important indicator for the time factor allocated to the job. Do this: Click Check & Review > Job Size Display

3.3 Selling Rate


At Tender Stage the: Net Rate + Applied Mark Up = Gross Rate. The gross rate is calculated based on the net and mark up applied therefore any changes made on the net or applied mark up will change the gross rate. This is ideal at tender stage but not ideal for the post tender stage of the contract. At the Post tender stage, a Selling Rate is available in Candy. The selling rate is used as the contractual rate for printing the Interim Payment Claim to the client. Adjusting the net or Applied Mark Up will not affect the selling rates. Therefore, for Post Tender Stage the: Net Rate + Calculated Mark Up = Selling Rate The selling is a fixed contractual rate by adjusting the Net (job remodelling) the Calculated Mark Up will change. One of the essential checks at post tender is to ensure that the job contains a selling rate. The confidence check shows items that do not have a selling rate therefore, the selling rate must be entered or we can copy the Selling rate from Gross rate. 17

Post Tender Valuations & Budget Control Do this:

Post Tender Checks

Open the Document Manager by choosing Documents > Valuation Document Manager.

Now open document 1.1 Gross to Sell Bill

Note the selling rate column on the right side of the document. At Tender Stage the job was priced and the Mark up was applied, the selling rates can now be established by copying the Gross rate. Right-click in the selling rate column header, select Copy > Copy Selling rates from Gross. 18

Post Tender Valuations & Budget Control

Post Tender Checks

Right Click

Check the option to lock selling rates after copy and Copy zero gross rates click OK and confirm the message.

Note the selling rates are displayed next to each bill item. NB: Check the selling amount balances back to the signed contract document. If the totals do not balance then go back to the problem bill page and check the selling rate of each bill item on that page.

19

Post Tender Valuations & Budget Control Now open this document 1.2 Selling Bill of Quantities

Post Tender Checks

Unlock & Lock the Selling Rate


The indicator in the selling rate column indicates that the rate is locked. To fix the rate we must first unlock it. Right click on the selling rate and select Lock/Unlock > Unlock selling rate.

20

Post Tender Valuations & Budget Control

Post Tender Checks

3.4 Copy the final quantity from the bill quantity


Something to consider........ The bill quantity will normally be used for the first Final Value projection and as a starting point can be copied to the Final Quantity column.

NOTE: Its best to do this before entering any valuation quantities. Do this: Open the document 2.2 Primary Valuation Entry Right-click on the Final Quantity column header and choose > Copy from selected quantity.

Then select the Bill Quantity as the source and confirm.

Click YES

21

Post Tender Valuations & Budget Control And then OK the quantities copied. See that the Bill qty have been copied to the Final Qty

Post Tender Checks

Note: Later in the course the final qty will be re-measured using the quantity calc sheet.

22

Post Tender Valuations & Budget Control

Post Tender Checks

3.5 Check and review reports


Explanation Now Candy can generate a number of reports to help you check for any possible problems on the tender.

To do a Pricing Check Report


Do this: Go to Check & Review > Pricing Check

Select all price codes on Direct Cost bill pages and select priced in plug and priced in split.

Note: unused Priced codes should be deleted before printing this report.

23

Post Tender Valuations & Budget Control

Post Tender Checks

To delete unused price codes


Explanation The Price code list may contain price codes not used in the bill. You should consider deleting unused price codes which will result in having a less confusing job. The job will therefore only contain price codes used in the bill.

To delete unused price codes go to the document 1.1 Price Code Listing ( and click Tools > Delete unused Price codes

and choose YES to confirm the Price Code deletion

Note: 12 unused price codes deleted. and OK

24

Post Tender Valuations & Budget Control

Post Tender Checks

Similarly unused resource can also be deleted directly from the resource list.
Do This Go to the document 1.1.Resource List ( ), click Tools > Delete ALL unused resources > Delete Key resources as well

And click YES to confirm deleting ALL unused resources The list shows what unused resources were deleted.

25

Post Tender Valuations & Budget Control

Post Tender Checks

Worksheet calc line check


Explanation Checks for mistakes on worksheet calculation lines. If there is a space between +5%waste then the wastage report would be incorrect. If *CONC] is used instead of *[CONC] the first occurrence would be seen as a comment and not a variable if 1.O9 is used instead of 1.09 then 1.00 instead of 1.09 will be used on the calculation line. Ensure accuracy at all times.

Check & Review > Worksheet calc line check

Click OK. How many errors were detected? If errors are detected a report will be generated.

Provisional Listings: Worksheets


Explanation At tender stage the estimator may mark worksheets, resources and bill items as provisional. Locate the provisional worksheets, resources and bill items. Check & Review > Provisional Listing Choose Worksheets In this example the check shows that no Provisional Worksheets were found. If errors are detected, a report will be generated. 26

Post Tender Valuations & Budget Control

Post Tender Checks

3.6 Value Analysis


Explanation 80/20 rule of thumb, identify which items contain the value and which items should be concentrated on at pre and post tender stage. Open the Valuation Reports by choosing Reports > Valuation Reports Manager. Print the Value Analysis (68) report

and choose Final Quantity.

27

Post Tender Valuations & Budget Control

Post Tender Checks

Select 80% Percentage of total to be printed.

28

Post Tender Valuations & Budget Control

Post Tender Checks

3.7 Resource Checks


Resources can be checked for potential problems like provisional rates or out-dated rates.

Resource List with Date


Here we will alter a standard document to make a new Resource List with Date document and customise it. Do this Open the Resource Document Manager by choosing VALUATIONS >Documents > Valuation document Manager.

Select the Resources tab to display the available resource documents.

Click the New Document button to open the list of template documents and choose 1. Estimating layouts > 1.1 Resource List Now right click on new 1.1 Resource List and rename it to 1.1a Resource list with Date.

To change the columns shown, click Customise 29

Post Tender Valuations & Budget Control

Post Tender Checks

Explanation This is the column layout selector. To include column data into your document, you can move available columns (left hand side) to the right with the green arrow; to remove them use the red arrow.

Add the column 4.2 Date of resource rate change and confirm.

Now open your new document 1.1a Resource list with Date. Look for resources that have old dates and check the rates.

30

Post Tender Valuations & Budget Control Sorting the resources by the date The resources can be sorted by the date in ascending order. To do this, right-click in the Final rate changed column, select Sort > Ascending

Post Tender Checks

When you are finished you can clear the sort with

31

Post Tender Valuations & Budget Control

Post Tender Checks

Provisional resources
If you move the pointer over the red dots on the Final rate, you will notice that these are marked as provisional, like this:

Alternatively, a fixed filter can be used to find resources that where marked as provisional.

Select the document menu View > Filter > Provisional Resources

Note: Filter toolbar 6 indicating 6 filtered provisional resources. You can now show just the resources you want with

On the filter toolbar, click 32

Post Tender Valuations & Budget Control

Post Tender Checks

Resource percentage report


Value Analysis can be performed on resources to identify which resources contain the value and which resources should be concentrated on at pre and post tender stage. Open the Valuation Reports by choosing VALUATIONS >Reports > Valuation Reports Manager. Click Select 8. Resource Analysis Reports > 8.5 Resource percentage (74)

Select Primary sort by Resource type

Select Final Quantity

33

Post Tender Valuations & Budget Control

Post Tender Checks

34

Post Tender Valuations & Budget Control

Pricing using Worksheets

Chapter 4. Pricing using Worksheets


Plug rates and split rates must also be converted to Worksheets to generate the required resource budget.

4.1 Price Code


Price codes and how they work The Price codes function is to deal with the unit price of a bill item. To rate a bill item, a Price Code is entered against it and the bill item adopts the rate from the Price Code (regardless of whether it was generated by plug rate, split rates or worksheet). The Price code can be up to 8 alpha-numeric characters in length. The first character of the Price Code must start with a Trade Code letter and the rest of the code is entirely up to you. Note that the Price code has its own Description. The description of the bill item is totally independent of the Price code description. Therefore, one Price Code may be used for multiple Bill Items effectively speeding up the pricing process.

4.2 Price Plug and Split Rate items using Worksheets


The pricing check report printed earlier listed Price code E1133 as a Plug rate and Price code E42111 as Split rate. To control your allowable the plug rate and split rate must be priced using worksheets.

The list of price codes for the job can be displayed by clicking on the

35

Post Tender Valuations & Budget Control

Pricing using Worksheets

Do this Go to document 1.1 Price code listing

Note: Price code document lists all the Price codes available in the job in Alpha numeric order.

Price Code E1133 using a Worksheet Price Code E1133 Site clearance is plugged. Right click in the rate and select Display worksheet.

to show the Price codes worksheet.

36

Post Tender Valuations & Budget Control About Worksheets

Pricing using Worksheets

315 Calculation lines are available to calculate the net rate for the price code. The worksheet header displays Price code, Pricing description and pricing qty of 8250m2. The worksheet header also display where the price code is used in the bill Page 4 item A and Page 1 item A. Therefore the change in rate for the price code will change the rate on the items where the price code is used. Note: A calculation must start in the beginning of the line using a resource code. Beginning with a space will only create a comment line.

Do This To add the required resources to the worksheet from the Resource List, type resource codes 32511 3171 2211 at the beginning of calculation lines 2, 3 & 4. The worksheet fetches the resources from the Resource List.

Now multiply each resource by the required number. Type in the multipliers: 32511 JD 410 Digger loader 3171 2211 6m3 Tipper Labourer *1off *2off *4off

37

Post Tender Valuations & Budget Control

Pricing using Worksheets

Start an applied factor using# on calculation line 1. End the applied factor using a = followed by the calculation *0.5day/710m2.

Note: The Enter key or moving off the line will automatically calculate the result and the words APPLIED FACTOR will appear.

Use the shifted function on the Store & next w/s function button to change the store mode from Store & Next worksheet to Store & return to document.

Click Store Worksheet This message will offer to change it from Plug Rate mode to Worksheet mode. 38

Post Tender Valuations & Budget Control

Pricing using Worksheets

Click YES to change to worksheet mode and OK to store the worksheet.

Price Code E42111 using a Worksheet The Price Code E42111 Exc fnd; ne 2m is Split. Right click in the rate and select Display worksheet

Note The worksheet header displays the total pricing qty of 1725m3, 600m3 on Page 4/Item C, and 1125m3 on Page 1/Item C.

Typing the resource code requires knowing the correct code. If you dont know the code you can add a resource by right-clicking on the calculation line and choosing Resource list.

39

Post Tender Valuations & Budget Control Select the resource 32511 JD 410 Digger Loader W&O

Pricing using Worksheets

and

to add the resource to the w/s calculation line.

Place the cursor on the next calculation line and add 2211 Labourer

Multiply each resource by the required number.

32511 JD 410 Digger loader 2211 Labourer

*1off *2off

Price worksheet using the applied factor applying a production of 85m3/day and adding 10% for battering. 40

Post Tender Valuations & Budget Control

Pricing using Worksheets

The net rate is calculated to 34.74

Click Store worksheet

Click YES and store the worksheet.

41

Post Tender Valuations & Budget Control

Pricing using Worksheets

42

Post Tender Valuations & Budget Control

Value Engineering

Chapter 5. Value Engineering (or Re-modelling)


Purpose of Value Engineering The site team can now re-visit each of the worksheets and adjust the productions to what they will achieve on site. Better buying, better S/C rates are taken into account, the site team agrees on the productions in the worksheets and relooks at the construction methods used. By doing this, the site team takes ownership of the tender and any losses cannot be blamed on the estimating department. By remodelling, the site team could have more financial gain with productivity and innovation making a profit from better buying and alternative construction methods. Macro price codes must also be exploded so that progress quantities may be entered.

5.1 Job Remodelling


Lets assume the site team will purchase diesel for 6/ Litre instead of 6.3/ Litre. Resource List Open resource document 1.4 Utilisation and value bill quantity

43

Post Tender Valuations & Budget Control Adjust the diesel rate accordingly and click Calculate

Value Engineering

Note that the Diesel allowable decreases from 280 155.37 to 266 814.64 representing a buying saving of 13 340.73.

Trade Totals Display

Do a Trade Totals Display on Selling at 6.3/Ltr of Diesel.

The tender rate for Diesel at 6.3/Ltr calculates Material Net Amount of 2 583 388.80 and a Markup of 757 249.87 Do a Trade Totals Display on Selling at 6.00/Ltr of Diesel.

44

Post Tender Valuations & Budget Control

Value Engineering

The Diesel at 6/Ltr calculates Material Net Amount 2 570 048.08 and a markup is now higher at 770590.59. An increase in markup of 13 340.72 Now return to page one of the Bill of Quantities Do this: Open document 1.1 Gross to Sell Bill

Notice that the Net and Gross rates have changed as these items use the cheaper diesel in their make-up. The Selling rates remained fixed and the calculated mark-up has increased in relation to the Selling.

5.2 Explode Macros


Macro Price codes are ideal for the estimator to price but are not suitable for the site team to progress against. For example progressing 50% of the Manhole will generate 50% allowable for Excavations, Concrete, Brickwork etc. The solution to this problem is to explode Macro Price codes so that Excavations, Concrete, Brickwork may be progressed against. Do this: Access document 3.1 Variation Pricing This document is ideal for variation pricing.

45

Post Tender Valuations & Budget Control

Value Engineering

Right click on the price code column header and select Explode Macro Price codes > Explode Macros without recoding

Click Yes

46

Post Tender Valuations & Budget Control

Value Engineering

Note: The additional Internal Items were added below Item F. Internal Items only have a net rate and no Selling rate. Internal items are marked with an I in the attributes column and therefore will not be printed on the Interim Payment claim to the client. Item F is the external item and therefore only has a selling and no Net rate.

Copy Bill to Final Qty


Note the Internal items do not have final qtys, they can be copied from the bill qty. Do this Do a filter for internal Items. Right click in the attributes column header, select filter > Internal items.

16 Internal Items are filtered

47

Post Tender Valuations & Budget Control

Value Engineering

Right click in the Final Qty Column header, Select filtered records

Copy from selected quantity

Select Bill Quantity

Yes to confirm

16 Quantities copied to final

48

Post Tender Valuations & Budget Control

Cost and Group Codes

Chapter 6. Summarising Resources using Cost & Group codes


Cost codes together with Task codes provide a summary of the allowable. The matrix below illustrates the various the codes available and where to define and allocate them. For example all the Task codes are defined in the Definitions & Settings (Blue hammer) and are allocated to the price codes using either the price code document or Bill document. The Cost code is defined in the Definitions and Settings (Blue hammer) and allocated to simple resources using a resource document.

6.1 Cost codes & Group codes


At Post Tender Stage the Allowable to date in Candy can be reconciled to the Costs to Date in Accounts. It is therefore important to have the cost code in Candy matching the accounting ledger code. The Cost Code is used to summarise the resources into Cost codes. Similarly the Group code is used to summarise resources into suppliers. Resource Document 1.6 Resource Group and Cost code allocation displays both group and cost code columns. Do this: Open the document manager and select the resources Tab

Resource document 1.6 Resource Group and Cost code allocation is available as a template document. Add a new template document by clicking on New Document 49

Post Tender Valuations & Budget Control

Cost and Group Codes

Select 1.6 Resource Group and Cost code allocation Open resource document

6.2 Defining the Cost codes


The Cost and Group must be defined before allocating them to the resources. Do this: Click on the to access the definitions and Enter and check the following Cost and Group Codes. Choose 4.1 Cost codes (Ledger code)

50

Post Tender Valuations & Budget Control

Cost and Group Codes

Choose 4.2 Group codes

Click OK to close the Definitions

51

Post Tender Valuations & Budget Control

Cost and Group Codes

6.3 Allocating the Cost & Group codes to Simple resources


Cost Code
Check that all the simple resources have a cost code and that the correct Cost code has been allocated to the simple resources. The money is summarised into the cost codes for Cost & Allowable control. Return to the resource list and allocate the Cost and Group codes to the various resources. Cost and Group codes should only be applied to Simple resources, those resources that are bought and are defined with a letter in the resource type column i.e. M for Material, P for Plant.

Complex resource
Complex resource is a combination of simples and complexes. A complex resource is identified by using a number in the Type column. The number represents the level of the complex from level 9 being the most basic to 1 being the most complex. Applying a cost code to a complex resource such as JD 410 Digger Loader W&O would be incorrect because the complex includes a combination of Plant, Fuel and Labour.

Filter Simple Resources


To make it easier to allocate cost to simple resources only use the filter facility shown below. The same filter can be used to check if all simple resources have cost codes. Do this: Go to View > Filter > Blank codes> Cost codes (simples only)

Click

to view only the simple resources with blank cost codes.

52

Post Tender Valuations & Budget Control

Cost and Group Codes

Allocate codes using double click


Double click in the Cost code column for resource code 60329 High Tensile Steel

Select 506 Reinforcing and confirm.

Click Abandon

Allocate Group code


Similarly allocate the group code ABC to all the stone and sand resources.

53

Post Tender Valuations & Budget Control

Cost and Group Codes

6.4 Resource Analysis Reports


Resource analysis reports can now be printed showing the resource Utilisation and Amount including a Cost code or Group code summary. Do this: Open the Valuation Reports by choosing Reports > Valuation Reports Manager

Select report Valuation Resource Analysis (70) Click Customise

54

Post Tender Valuations & Budget Control

Cost and Group Codes

Select Cost Codes as the Summary Click OK, select Bill Quantity and confirm, select Allowable rates and Print Report Now print the report and preview the report. Page 1 reflects all the complex resources

55

Post Tender Valuations & Budget Control Page 2 reflects all the root complexes

Cost and Group Codes

Page 3 reflects all the simple resources. Note that all simple resources should have a Cost Code allocated.

and Page 4 is the Cost Summary

56

Post Tender Valuations & Budget Control

Cost and Group Codes

Cost and Group Code Audit Reports Analysis by Cost code report This report will list those resources that contribute to a particular cost code. Do this: From the report manager select report Analysis by Group/Cost (72). Customise the report and select Sort by Cost Code.

Entering a cost code in the sieve will print out only those resources that contribute to that particular cost code. By leaving the sieve blank will analyse all the cost codes.

57

Post Tender Valuations & Budget Control

Cost and Group Codes

Tracer report The Tracer report will list all the bill items that contribute to a particular cost code. The tracer report is available under the Check and Review Reports heading. Print the Tracer report and select Cost Codes in the tracer selector.

58

Post Tender Valuations & Budget Control

Cost and Group Codes

Type in the cost code 400 and click OK.

Analysis by Group code report This report will list those resources that contribute to a particular Group Code. Do this: From the report manager select report Analysis by Group/Cost (72). Customise the report and select Sort by Group Code.

59

Post Tender Valuations & Budget Control

Cost and Group Codes

Click OK

60

Post Tender Valuations & Budget Control

Task Codes

Chapter 7. Controlling Labour and Plant using Task Codes


The Cost Code provides resource-based control for managing fixed resources such as Materials. The Cost Code will provide limited control to productive resources such as Plant and Labour but is not ideal. The engineering site staff will require the Labour and Plant allowable in more detail typically the allowable per Task completed on site. CCS provides a simple method of summarising the Bill items into Tasks. The allowable for each bill item is broken down into the various Resource Types, so immediately there is the Labour and Plant allowable for each Task, the exact information required to control the productive resources. The Task Code is used to implement Functional Control on the Job. The Task Code summarises bill items into categories of Function or Activity. The key is to summarise items with similar production, e.g. bulk earthworks items would be summarised separately to hand excavation. Machines for bulk earthworks and labour for hand excavation would be used. By summarising items with like production and are summarising items with like resources and, therefore, like cost sensitivity. If the machine is not being used effectively, it is costing a lot more than if labour is not being productive. There would be different controls on plant versus labour.

61

Post Tender Valuations & Budget Control

Task Codes

7.1 Defining the Task codes


The task codes must be defined before allocating them to the Bill items or Price codes. Do this: Open the Definitions and enter the following Task codes.

Task codes may be summarised into Task code headings. The level column represents the heading level from level 9 to level 1. Therefore, the Earthworks Tasks of Clear site and Excavation may be summarised into the level 1 heading Earthworks. Note the m2 quantity of Clear site must be factorised by 0.10 to calculate the m2 to m3. The task code accumulates the amount of money and quantity; therefore, each task code should have a unit.

62

Post Tender Valuations & Budget Control

Task Codes

7.2 Task code allocation


Add an additional document containing the Task code columns
Do this: Open the Valuations Document Manager , select Valuation Bills Tab.

Click on New document to add a new template document 2.6 Task coding (Controlling labour & plant)

63

Post Tender Valuations & Budget Control

Task Codes

Customise the document and add columns 26.8 Task code description and 26.9 Task code unit.

Allocate the Task Codes


Do this: Open document 2.6 Task coding (Controlling labour & plant) and check to see if all the bill items have Task code. To filter for Bill items without Task codes Right click in the Task code column select Filter > Filter for blanks.

Click

64

Post Tender Valuations & Budget Control

Task Codes

Explanation of the Task code factor


The Task Code accumulates the amount of Money and Quantity, the Task Factor column is used to determine the quantity to be added together for each Task code. If the unit of the Bill item is the same as the Task code then a factor of one is used. There may be instances where the unit of measure of the bill item may be different to the unit of measure of the Task Code. For example, there may be a bill item measured in linear metres of formwork, yet the bill item has a Task Code with a unit of measurement of m2 so a Task factor to factorise the Lm to m2 is applied. By using a Task factor of 0, the money will be included but not the quantity, for example, the cost of wood float finish could be added to Task Code Concrete in Ground Slabs but only the quantity of the Concrete in Ground Slabs is required and not the quantity of the wood float finish. Allocate Task codes and factors to each of the bill items. Allocate the Task codes

65

Post Tender Valuations & Budget Control

Task Codes

66

Post Tender Valuations & Budget Control

Task Codes

7.3 Task code analysis


Price Plug rate to a least a Split rate
Note: to calculate the Task Code summary no plug rate items may exist in the job. Do this: Do an on-screen task analysis, click Finalisation > Job analysis > Job analysis by Task code.

Select document 00 JOB: PROJECT ANALYSIS CODES

Update the values by clicking on Update Codes

Click Yes

Click OK

67

Post Tender Valuations & Budget Control

Task Codes

Note that the Total Quantity, Amount and derived rate is calculated for each Task Code. When finalising a tender, if the derived rate is much lower or higher compared to previous tenders, then relevant items can be investigated for possible errors in the pricing worksheets. The total allowable for Labour is calculated for each Task Code, i.e. The Labour allowable for placing concrete in Foundations is 1,352,959. Once progress quantities have been entered for each bill item, the total Labour allowable amount for each Task code is calculated and should be reconciled back to the total Labour cost for each Task code. Clicking the Split Rates or Split Amounts toggles between displaying split rates and split amounts for each of the Task Codes.

Note the derived Labour rate to place 1m3 of concrete in Foundations is 80.16 per m3, if the concrete team on site has poured 10m3 then you should not have spent more than 10 x 80.16 = 801.60 on the Labour team. Daily costing should be done against the relevant Task Codes which should be reconciled to the Labour allowable based on the work that has been completed on site. A similar approach should be followed to control Plant. 68

Post Tender Valuations & Budget Control

Task Codes

Totals for Task code headings may be displayed by placing the cursor on the heading and pressing Ctrl-Up and Down Arrow.

7.4 Task code reports


Various Task code reports are available in the Report Manager under the report heading Project Code Reports.

Project Codes Report


The project codes report will list the bill items in Task Code order with a total for each Task Code. Print the Project Codes (78) report.

69

Post Tender Valuations & Budget Control

Task Codes

Select Task code as Primary and none as the secondary and click OK.

Select Final Qty Select Summary only, net, Spreadsheet and click OK

Report includes the Task code summary

70

Post Tender Valuations & Budget Control

Task Codes

Project Codes Quantity Summary


The Project Codes Quantity Summary report lists the total quantity for each task. The project code quantity summary report is available in the template reports. Do this: From the report manager click New report and select report 9.6 Project Codes Quantity Summary (83).

Print the report. Select Final Quantity Select Task code as Primary and none as the secondary and click OK.

71

Post Tender Valuations & Budget Control

Task Codes

The Task code summary report displays the total Quantity per Task. Note for this job consists of a total of 27745m3 of excavations.

Project Codes Resource analysis


A complete resource analysis for each Task code may be printed with totals for each Cost code per Task code. Do this: Print the Project Codes Resource Analysis. Select Analyse complexes to level 9, Print codes separately and Summary by Cost Code.

72

Post Tender Valuations & Budget Control

Task Codes

Select Final quantity then Allowable rates. Select Task code as Primary and none as the secondary and click OK.

Page 1 - 50: Lists the resource analysis per Task and the Cost code summary per Task

73

Post Tender Valuations & Budget Control

Task Codes

74

Post Tender Valuations & Budget Control

Variation Pricing

Chapter 8. Variation Pricing and VO codes


8.1 Variation pricing
Recap on pricing and the function of the Price code
The Price Codes function is to deal with the unit price of a bill item. To rate a bill item, a Price Code is entered against it and the bill item adopts the rate from the Price Code regardless if it was generated, by plug rate, split rates or worksheet).

Variation pricing document


The variation pricing document includes the ideal columns for V.O. pricing. Do This Go to Valuation bills in the Document manager and open document 3.1 Variation pricing

Variation orders can be entered between existing bill items or entered on new page of the bill. The practical method would be to add and price all the VOS in a new page in the bill. Heading levels can be used to group each VO in to headings. To create a new page Click on the Select New page and

Note: The new bill page 7 has been added.

75

Post Tender Valuations & Budget Control

Variation Pricing

Do This Type in the New heading, Sub headings & Variation item including final qty. Headings should coincide with existing heading structure, Create the level 2 heading called Variation orders and level 3 heading for variation order # 1.

Price V.O. # 1 Clear site North Boundary using Price code E1133.

Note: The bill item Clear site North boundary adopts the Price codes Net and Selling rates effectively speeding up the pricing process. The Price Code E1133 has a red indicator block indicating that it is used on multiple bill items. If the rate is changed then the changed rate will apply to all the bill items. Therefore if different rate is required the bill item will require a different Price code.

Apply the Task code to the variation items.


Do This Open document 2.6 Task coding (Controlling labour & plant)

Note: The bill item already has a Task code 0100. The task code is allocated to the price code therefore by allocating the same price code the bill item will adopt its Task code.

76

Post Tender Valuations & Budget Control

Variation Pricing

8.2 VO Codes
Define VO Code in the definitions and settings

Open document 2.5a My Variation pricing and Allocate VO Code 1 and mark it approved.

Double click in the VO Status column and mark it approved.

8.3 Variation Order documents


Variation Orders with BOQ allocations
This document groups the bill item by VO code Do This Go to Valuation bills in the Document manager with BOQ allocations and select document 3.2 Variation Orders

77

Post Tender Valuations & Budget Control

Variation Pricing

Variation Orders Financial Summary


This document is used to analyse the Valuation amounts per Variation Order. Go to Valuation bills in the Document manager Financial Summary and select document 3.3 Variation Orders-

Variation Order Bill


This document displays all the bill items on 1 Page per VO. This is mainly used for when the VOs were entered between existing bill items.

78

Post Tender Valuations & Budget Control

Valuations

Chapter 9. Valuation No.1 using Calcsheets

The Candy Valuations is used for the post tender stage of a project. The Bill of Quantities created in Candy Estimating is available in Candy Valuations, the difference between Estimating and Valuations is the extra Valuation quantity columns, Valuation layouts and the Valuation reports.

9.1 Valuation Setup


The initial Valuation and every Valuation thereafter commences at the Valuation Setup process listed below: Step 1: Duplicate & Rename the Job Step 2: Setup Next Valuation

Step 1: Duplicate and rename the job.


It is good practice to copy the job before entering the new monthly valuation quantities. Eventually the Q.S will have and electronic copy for each Valuation in Candy, and if required, can back track to previous valuations. Do this: Go to the Job manager , select Ventshaft & Substation Contract - Remodelled, click on Job in the menu and select Duplicate job then rename it to Ventshaft & Substation Contract Valuation NO. 1

79

Post Tender Valuations & Budget Control

Valuations

Step 2: Step next Valuation


Setup next valuation is not required for Valuation No.1 because the initial valuation setup has already been done on chapter 4. Therefore Setup next Valuation is only required for all Valuations that follow. In Valuations click on the Main menu, select Valuation setup and click on Setup next valuation.

Please Note: Setup next valuation will copy all to date Quantities to previous. Therefore this step must be done before entering any new quantities for all Valuations that follow.

80

Post Tender Valuations & Budget Control

Valuations

9.2 Primary Valuation Quantities


This document contains the three primary progress quantities available in the system. Actual Quantity - Actual cumulative quantity to-date for a bill item. Used for internal reporting, it measures the actual amount of work done. Claimed Quantity - This quantity is used to record how much you are claiming to date in an application for payment. Think of it as an External quantity. Paid Quantity- This quantity is used to record how much the client has paid you to date. Final Quantity- This is the anticipated ultimate quantity of the bill item.

Valuation Documents
Do this: Click on Manager or Open the Valuation Document Manager Documents > Valuation Document

Duplicate document 2.2 Primary Valuation Entry & rename it to 2.2a Favourite Valuation Entry

81

Post Tender Valuations & Budget Control Select document 2.2a Favourite Valuation Entry Click on in the Valuation document

Valuations to select the columns required

Select the required columns as per the above layout and click

Link the valuation tool button Right click on document 2.2a Favourite Valuation Entry > Link/unlink toolbutton > Link document to the VALUATION BILl toolbutton.

Note: The valuation toolbutton

will now open your Favourite valuation entry. 82

Post Tender Valuations & Budget Control

Valuations

9.3 Measuring Final qtys using Quantity Calcsheets


The quantities can be entered manually against a bill item. Alternatively, double-clicking on the quantity displays a "calc-sheet" where detailed measurements can be recorded to calculate the quantity. If there is a calc-sheet, a green dot is displayed in the quantity field and the letter is displayed in the quantity calcsheet indicator column. Calcsheets are available for Bill, Actual, Claimed and Final Quantities.

Note: Item 1/A Clear and strip site has a calcsheet for the bill qty therefore indicating a green indicator block on the Bill Quantity and a B in the Qty Calcsheet indicator column.

Do this: Using Document 2.2a Favourite Valuation Entry double click on the Final Qty for Clear and Strip site to open a calcsheet.

Measurements from other calcsheets and bill items can be copied using

Copy the Bill qty calcsheet into the Final Qty calcsheet. Select the Bill qty as the source selection and type in Page 1 Item A.

83

Post Tender Valuations & Budget Control

Valuations

Click

to confirm.

On line 4 add the following calculation 20*20 and remarks Area 4 DRW # 110 Rev1.

Click

Select Update after rounding on 4/5 rule and 84

Post Tender Valuations & Budget Control

Valuations

Note: The quantity calc sheet indicator now contains a B and F

85

Post Tender Valuations & Budget Control

Valuations

9.4 Entering Valuation quantities


Entering the Actual quantity will automatically reflect the claimed and paid quantity columns. Do this: Progress all Earthworks, Formwork, Reinforcing, Concrete and Joints in the ventilation shaft as 100% complete by typing in 100% in Actual % Final column. On Page1

On Page 2

86

Post Tender Valuations & Budget Control On Page 3

Valuations

On Page 7

87

Post Tender Valuations & Budget Control

Area Bills

88

Post Tender Valuations & Budget Control

Area Bills

Chapter 10. Valuation No. 1 using Area Bills


Areas are used to isolate sections or areas of a contract for measurement and control purposes. Areas provide a location based control within a construction project. Each area has an area bill that must contain main bill items. The measurement from the area bills can be used to update the main bill. Section 3 Substation and yard on page 4 consists of two substations. Areas II will be used to isolate the control the measurements for each substation.

10.1 Area manager


The area manager is used to create, delete, copy, rename and backup the area bills Do this: Click on Areas > Area II definitions to access area bills.

Click

to create new areas for Substations A & B.

89

Post Tender Valuations & Budget Control

Area Bills

10.2 Importing the bill items in the area bills


Do This Select Sub A Substation A

Document manager holds all the required documents for areas. Select document 1.1 Area bill

90

Post Tender Valuations & Budget Control

Area Bills

Click Tools > Import bill items > Import bill items by page & trade

Importing may be done using a page range. Uncheck Select all pages and Select trades. Select page range from page 4 to 6.

Message appears confirming 34 items imported. Click OK to confirm.

91

Post Tender Valuations & Budget Control

Area Bills

10.3 Apply area code


The area bill can also be linked to the main bill by allocating the area code to main bill. Do this In the Area manager Select Sub B - Substation B

Select document 2.1 Valuation bill Area allocation

92

Post Tender Valuations & Budget Control

Area Bills

Note: The area code Sub A has already been allocated to the bill items. Filter for area code Sub A. Right click in the Area Code column > Filter > Start a new filter.

Type Sub A

Filter Toolbar indicates 34 Items Filtered.

Click

to select the filtered items.

93

Post Tender Valuations & Budget Control

Area Bills

Right click on the selection > Code allocation > Areas > Allocate to Area

Select Substation B and

to confirm.

94

Post Tender Valuations & Budget Control Message appears confirming 34 allocated. Click OK to confirm.

Area Bills

10.4 Measure Area Actual Quantities

95

Post Tender Valuations & Budget Control

Area Bills

10.5 Update Valuation Actual qtys using Areas

96

Post Tender Valuations & Budget Control

Valuation Reports

Chapter 11. Valuation Report Manager


Print the following Valuation reports from the Valuation Report Manager

11.1 Interim Payment Claim report


The Interim Payment Claim is always based on Claimed Quantity and can only be based on the Gross and Selling rate. Do this: Click on to access the Valuations Job Manager , double click on Valuation Bills and select . Interim Payment Claim, click

Select the following options then click

97

Post Tender Valuations & Budget Control

Valuation Reports

11.2 Valuation Listings report


The Valuation Listings report can be based on any Valuation Quantity and can be based on the Net, Gross or Selling rate. Do this: Return to the Valuation Document Manager and select Valuation Listings Report then select and

Select the following options and click

98

Post Tender Valuations & Budget Control

Valuation Reports

Select Actual Quantity

99

Post Tender Valuations & Budget Control

Valuation Reports

11.3 Valuation Resource Analysis report


The Valuation Resource Analysis can be based on any Valuation quantity. Printing this report on Actual Quantity will list the resource and cost allowable to date. Do this: Return to the Valuation Document Manager and double click on Resource Analysis Reports and select Valuation Resource Analysis report then select Select the following options and click and

and select Actual Quantity

100

Post Tender Valuations & Budget Control

Valuation Reports

11.4 Project Codes Resource Analysis report


This report prints the Resource Analysis split into the Task codes. Printing this report on Actual Quantity will list the resource and cost allowable to date per Task code. Do this: Return to the Valuation Document Manager and double click on Project Codes Reports and click on Project Codes Analysis report then select Select the following options and

and choose Actual Quantity

101

Post Tender Valuations & Budget Control

Valuation Reports

Choose Task code as the Primary code and None as Secondary.

Click

102

Post Tender Valuations & Budget Control

Valuation Reports

11.5 Valuation Trade Total Display


Trade summary can be based on any Valuation Quantity and Rate. Do this: Click on the tool button select Actual Quantity and select Net rate.

103

Post Tender Valuations & Budget Control

Cost & Allowables

104

Post Tender Valuations & Budget Control

Cost & Allowables

Chapter 12. Costs & Allowables


Cost & Allowables is used to monitor the financial performance of a project. The comparison of the To-Date allowable generated in Candy with the To-Date costs captured in the accounting system like BuildSmart is monitored within Candy. Additionally the Remaining and At completion allowables and costs is also monitored in Candy. Cost & Allowables is used to analyse the following: To Date Allowable vs. To Date Costs Remaining Allowable vs. Remaining Cost At Completion Allowable vs. At Completion Costs.

The Cost & Allowables documents are available in the Valuation document manager.

105

Post Tender Valuations & Budget Control

Cost & Allowables

12.1 Analyse Allowable to-date


Go to Costs & Allowables Tab in the Valuations Document manager use doc 2.1 Cost Allowables by Period

The above document shows the To-date, Remaining and At completion for the current Valuation period. Note: The Task code column is included by default in this document. The BuildSmart accounting system has both the Task code (Activity code) and Cost code (Ledger code) for more comprehensive cost control. However some other accounting systems only make use of Cost codes for their cost control.

Summarise by Cost codes only


In this course we will import a text file from another accounting system that only use Cost codes. To do the comparison we need to change our Cost & Allowable documents to work with only the Cost code. Do This From the document menu select View > Column layout. Remove the Task code column and confirm. The document is automatically re-calculated and displays only the Cost code information.

106

Post Tender Valuations & Budget Control

Cost & Allowables

12.2 Cost & allowable columns


The following is the definitions for the terminology used in Cost & Allowable: Allowable to date Cost to date Variance to date Allowable remaining Cost remaining Variance remaining Allowable at completion Cost at completion Variance at completion Actual quantity x Net rate. Imported cost to date from the accounting system Allowable to date less Cost to date Remaining quantity x Net rate Remaining quantity x Cost rate in Candy Remaining allowable less Remaining cost Final quantity x Net rate Cost to date + Remaining cost Allowable at completion less Cost at completion

Note: To do a meaningful comparison with the costs from accounts it is essential to measure the actual quantity on the day of cost close (e.g. 25th of the month). Additionally Job remodelling is essential to price Plug rate and split rate with worksheets (Refer to Chapter 4).

12.3 Import To-Date costs


The To-date costs can be imported as follows: 1. Imported via a text file (MS Excel) from an accounting software package. 2. Imported from Candys Material received module. 3. Import BuildSmarts cost and accruals.

Do This Select the Cost & Allowable tab on the Valuation document manager. Open the document 4.1 Cost import. Select Tools > Import and overwrite Cost to date > Import cost from a file. Use explorer to find the text (Excel) file and import the file.

Column Identification is used to select column headings that match the imported information. Identify columns for the Cost code and Real cost to date.

107

Post Tender Valuations & Budget Control

Cost & Allowables

Click Continue

108

Post Tender Valuations & Budget Control

Cost & Allowables

12.4 Check import file


When the import is complete, the imported information needs to be checked against the Candy formation for differences. The check is used to verify if all the imported cost codes exist in the Candy Job. Select Check import file and select the codes for checking. If the imported file contains data with costs codes that do not exist in the job a message will be displayed listing which line/lines are not compatible. These lines will also be filtered out and displayed. Most likely it would be column headings in the import document that have not been defined as cost codes in Candy. Use CTRL+DELETE to remove this unwanted information. Click Check Import file and select Cost Codes.

109

Post Tender Valuations & Budget Control

Cost & Allowables

If the imported file is not fully compatible with Candys information a message will be displayed advising which line/lines are not compatible. These lines will also be filtered out and displayed. Most likely it would be column headings in the import document that have not been defined as cost codes in Candy. Use CTRL+DELETE to remove this unwanted information.

Re-check the file and you should get a Validation successful message.

110

Post Tender Valuations & Budget Control

Cost & Allowables

12.5 Cost Adjustments


After the real cost have been imported, further adjustments can be made by the site team to reflect the site situation. Do This Use the cost import document to make some reallocations and additional cost provisions as per the screen below.

Note: Reallocation total must always add up to zero.

12.6 Release costs


Having made the adjustments as required, the adjusted costs can now be released for comparison with the allowable. Do This Click Tools > Release costs for Costs & Allowables

111

Post Tender Valuations & Budget Control Something to consider........ The cost import document should form part of your Cost reporting pack.

Cost & Allowables

12.7 Analyse Allowables to date vs. Costs to Date


The variance between the To-date Allowable and To-date Cost can now the analysed using Doc. 2.1 Costs & Allowables by period Do This Open doc 2.1 Cost Allowables by Period and Click Calculate to view

112

Post Tender Valuations & Budget Control

Cost & Allowables

12.8 Cost to complete using cost rates


Thus far the comparison was only used to monitor the To-Date performance of the project. The Tocompletion performance of the project can now also be monitored by the use of the remaining Allowable and remaining Costs. The remaining costs are derived by the use of a resource cost rate and the use of the cost worksheets.

Cost to complete using resource cost rate


Do this Use doc 7.2 Resource cost rates to completion

In the Cost rate column change the simple resources cost rate to the following resources. 4914 Diesel rate change cost rate from 6.00/Ltr to 6.20/Ltr. 53111 Stock Bricks rate change cost rate from 750.75/Thou to 800/Thou. 53411 Face Bricks rate change cost rate from 915.92 to 980/Thou.

113

Post Tender Valuations & Budget Control

Cost & Allowables

Re-calculate the document 2.1 Cost & Allowables by period to see the changes in the Remaining Cost column.

Cost to complete using cost worksheets


Production outputs, wastages and could even go as far changing construction methods will affect the remaining costs. These adjustments can be done using the cost worksheet. Do this: Open the document 6.2 Bill with cost rates for cost w/s adjustment.

Open the worksheet for item 5/A One brick wall in foundations.

Select View > Flip to cost worksheet. 114

Post Tender Valuations & Budget Control

Cost & Allowables

Adjust the output formulae from 600 bricks per shift /day down to 500 bricks per shift and change the wastage from 10%waste to 15%waste.

Store worksheet

Note: Indicators on the Cost rate will indicate cost rates that use Net rate, Use Net w/s with resource cost rate and Use Cost worksheet. 115

Post Tender Valuations & Budget Control

Cost & Allowables

Re-calculate the document 2.1 Cost & Allowables by period to see the additional changes in the Remaining Cost column.

116

Post Tender Valuations & Budget Control

Cost & Allowables

12.9 Cost & Allowables at Completion


Allowable at completion is calculated using the Final quantity x Net rate and the Cost at completion is the sum of the Cost to date and Remaining costs. This information is used to determine the at Completion performance of the project. Do this: Open document 2.1 Cost & Allowables by period and Calculate

117

Post Tender Valuations & Budget Control

Cost & Allowables

12.10

Cost & Allowables using Task and Cost Codes

The Cost Code provides resource-based control for managing fixed resources such as Materials. The Cost Code will provide limited control to productive resources such as Plant and Labour but is not ideal. The engineering site staff will require the Labour and Plant allowable in more detail typically the allowable per Task completed on site. Cost Code 201 General Labour is a typical problem, we know we losing money on labour but now we need to know what Task is the cause of the losses. The example below illustrates a loss for labour on Vertical formwork and a gain on Excavation.

118

Post Tender Valuations & Budget Control

Set up Next Valuation

Chapter 13. Set up Next Valuation


In Valuations we can track Previous, Months and To Date Qtys. Setup next valuation will copy all the To- Date quantities into the previous quantities. Therefore Setup next valuation is required before entering any new valuation quantities. Open 2.1 Valuation Input Actuals. Note the Previous Actual qty is empty because this was the first Valuation.

13.1 Setup Next Valuation


Step 1 Backup or Copy the job.
It is good practice to backup each valuation job before entering the next monthly valuation quantities. Eventually the Q.S will have and electronic copy for each Valuation in Candy and if required can back track to previous valuations. For this course we are going to just copy and rename the job. Do This Go to the Job manager , copy Ventshaft & Substation Contract Valuation No. 1 and rename it to Ventshaft & Substation Contract Valuation No. 2

119

Post Tender Valuations & Budget Control

Set up Next Valuation

Step 2 Setup next valuation


Select Main > Valuation setup > Setup next valuation.

Set the date and entre the Valuation Header. Note the option to Archive previous quantities is also Checked

Note: The option to Archive previous qty is checked. This will archive all previous quantities. The archived quantities can be viewed using valuation document 4.3 Archive Valuation Quantities.

120

Post Tender Valuations & Budget Control The Bill is now ready for Valuation 2.

Set up Next Valuation

121

Post Tender Valuations & Budget Control

Subcontract Manager

122

Post Tender Valuations & Budget Control

Subcontract Manager

Chapter 14. Subcontract Manager


The Subcontract Manager is used at post-tender to handle the projects subcontractors. Subcontract manager contains Subcontract bills which are created using items from the main BOQ. Multiple Subcontractors can work on one Main BOQ Item. Each subcontract is awarded to a subcontractor, and his rates and 'awarded' quantities are entered in the subcontract bill. Progress is recorded in the subcontract bill and is used to create a Subcontractors payment certificate and may also be used to update the Quantities in the main BOQs. Extras, contras and inter-subcontract charges can be recorded for each subcontractor and included in the Subcontractors payment certificate.

14.1 Create a new Subcontract


The S/C manager is used to create and manage various subcontracts. These subcontracts are bills that define the work to be carried out by a certain Subcontractor. Do this In Valuations select Subcontract > Subcontract manager

Click New

123

Post Tender Valuations & Budget Control

Subcontract Manager

Explanation A new Subcontract can be added using the following options: Manually: This option is used for when we need to create a new subcontract from scratch. Selecting a s/c package code: This option is used to select pre-defined subcontracts. Selecting a subcontract from the adjudicator: This option is used to select subcontracts from the Subcontract adjudicator.

124

Post Tender Valuations & Budget Control

Subcontract Manager

14.2 Creating Subcontract Bill using the Main Bill


The Subcontract Bill This bill must be populated with items from the main BOQ together with the relevant quantities. When a subcontractor is appointed he is attached to this subcontract and his rates are entered into the subcontract bill. Do This Open the Painting subcontract by double-clicking on the subcontract, or by pressing the Select softkey or Enter.

Any item on the BOQ (or a selection of items) can be dragged, copied or imported into a subcontract bill - the code for that subcontract will be displayed against the BOQ item. Alternatively, entering a subcontract code against a Main BOQ item will insert that item into the subcontract bill. Many subcontract codes can be entered against a BOQ item - in other words, many subcontracts can refer to the same BOQ item. Do This Import the bill items by page & trade Click on Tools> Import bill items > Import bill items by page & trade

125

Post Tender Valuations & Budget Control

Subcontract Manager

Importing may be done using a page range or trade. At the tender stage trades have been and therefore check the option Select Trades to import by trade.

Select the trade V Painting Note: 6 Items imported

126

Post Tender Valuations & Budget Control Subcontractor Awarded Rates and Quantities

Subcontract Manager

The subcontractor's rate for each item in his bill must be entered - called the Subcontract Rate. The contract quantity must also be entered - called the Awarded Quantity. Do This Right click in the Awarded Quantity column, select Copy from selected Bill quantity

Select Final Quantity

Check Overwrite existing items and click Yes

127

Post Tender Valuations & Budget Control

Subcontract Manager

To import the bill rates into the subcontract bill, right click on the Subcontract rate column and select Import Bill rates.

128

Post Tender Valuations & Budget Control

Subcontract Manager

Select Net Rate by resource type

Select S Subcontract

129

Post Tender Valuations & Budget Control

Subcontract Manager

14.3 Creating the Subcontract Bill using S/C Adjudicator


The S/C Adjudicator may have been used at the tender stage. The subcontract adjudicator contains quotes from various Subcontractors on various S/C Packages. One of the S/C quotes can be used to price the main bill item. The S/C quote in the S/C Adjudicator can then be used to create the Subcontract in Subcontract manager. Do this On the S/C Manager click New and choose the option Select a subcontract from the Subcontract Adjudicator

Choose Drainaway Limited and Import Subcontractor rate

130

Post Tender Valuations & Budget Control

Subcontract Manager

Click OK

Click Select to open the Plumbing Subcontract.

131

Post Tender Valuations & Budget Control

Subcontract Manager

Note: The S/C Bill Items have been imported using the rates quoted by Drainaway limited in the S/C Adjudicator

132

Post Tender Valuations & Budget Control

Subcontract Manager

14.4 Subcontractor Details


The Subcontracts for Painting and Plumbing can now be awarded to the subcontractors. Seagreen Painters will do the Paintwork and Drainaway Limited will do the Plumbing. Do This For the Painting subcontract entre the code SEAGREEN and Name Seagreen Painters

Click Allocate a subcontractor to this subcontract Entre all the required Subcontractor details

For the Plumbing subcontract entre the code DRAIN010 and Name Drainaway Ltd. Then entre the subcontractor details.

133

Post Tender Valuations & Budget Control

Subcontract Manager

Note: Subcontractors code could be the code used for the subcontractor in your companys accounts system. If the subcontractor is already in your Subcontractor database, the drop down list can be used to copy the details.

134

Post Tender Valuations & Budget Control

Subcontract Manager

14.5 Subcontract Progress Measure


Progress Quantities As the Subcontractor contract progresses, the following quantities must be entered: Invoiced quantity - quantity claimed by the subcontractor. Due quantity quantity measured by the main contractor. Pay quantity - quantity used to pay the subcontractor. Note: the terms Claim, Actual and Paid are avoided to prevent confusion with the main contractor's progress quantities.

Progress Painting subcontract


Do this Choose the Painting contract

To access the s/c document manager click Tools > Document manager

Select 2.2 Subcontract Bill with progress update

135

Post Tender Valuations & Budget Control

Subcontract Manager

Note: the Subcontract Bill with progress update includes Due and Pay quantities.

Do the Progress measure as per the screen below.

Progress the Plumbing contract


Choose the Plumbing contract

136

Post Tender Valuations & Budget Control

Subcontract Manager

Click tools > Document Manager

Select 2.2 Subcontract Bill with progress update

Do the Progress measure as per the screen below.

137

Post Tender Valuations & Budget Control

Subcontract Manager

Customising the document


Click View > Column layout

And add the pay amount column

138

Post Tender Valuations & Budget Control

Subcontract Manager

139

Post Tender Valuations & Budget Control

Subcontract Manager

14.6 Extras
Any additional work done by the subcontractor outside his contract can be added as an extra cost. VOS between the main contractor and the subcontractor are extras. VOS that need to be claimed to the client will not be an extra. Client VOS must be entered as a Main bill Item and then imported into the Subcontract bill. Repairs charged to others will be additional work done that must be contra charged to another subcontractor. Do This Seagreen Painters damaged an eaves gutter during painting. The damaged gutter must repaired by the Plumber and contra charged to the Painter. In the Plumbing subcontract select the Extras Tab and click New in the Repair charged to others section

Entre the required information as per the next screen picture.

140

Post Tender Valuations & Budget Control

Subcontract Manager

Note: Repair charged to other must have a charged to Subcontract

141

Post Tender Valuations & Budget Control

Subcontract Manager

14.7 Charges
Any items that incurred by the subcontractor will be a charge. Charges from Main Contractor will be some additional items supplied to the subcontractor like safety equipment. Do This In the Painting subcontract select the Charges tab

Note the charge from the Plumbing subcontractor automatically appears as a Charge from other Subcontractor.

142

Post Tender Valuations & Budget Control

Subcontract Manager

14.8 S/C MOS


Materials on Site claimed by the subcontractor. Only the entries for the current period are regarded for this periods certificate - in other words, any lines that are displayed in grey text are ignored in determining the current month's MOS. When the next certificate is made, the previous certificate's entries will be displayed in grey text but cannot be changed.

Do This Add MOS for the Plumbing Subcontractor as per the illustrated below. Select the MOS Tab then Click New and add the rainwater pipe.

Click OK

143

Post Tender Valuations & Budget Control

Subcontract Manager

14.9 S/C Summary


Certificate record
All previous and the current certificate are recorded. All the information shown on this screen can be edited to reflect the progress of the payment to the subcontractor. However, the Certificate Number cannot be changed as it reflects the sequence of certificates and is in cemented automatically when the next certificate is setup. Do this Click Edit

and Entre the certificate details.

Click Ok

144

Post Tender Valuations & Budget Control

Subcontract Manager

Note: The next certificate button is used to setup next S/C certificate. When used, the to-date values will be copied to previous. Therefore this must be done before entering the next certificate value. The next certificate button will only apply to the current Subcontractor and must be done for each individual subcontractor.

Lookup values
This is the accumulation of all the Subcontractor data and is used to create the subcontractors certificate. The export button will send the data in this list to your Excel template, the information can be mapped to your Excel Template by row and column.

145

Post Tender Valuations & Budget Control

Subcontract Manager

146

Post Tender Valuations & Budget Control

Subcontract Manager

14.10

S/C Liability

A summary of all the subcontractors can be viewed in the S/C Liability document. The liability document displays all the subcontractors bill values.

Do This Click Subcontract liability

Note: The Subcontract liability amount is calculated using Total due less Total Pay Amount

147

Post Tender Valuations & Budget Control

Valuation using Subcontract Manager

148

Post Tender Valuations & Budget Control

Valuation using Subcontract Manager

Chapter 15. Valuation No. 2 Using Subcontract Manager


The Valuation S/C Due Quantities accumulate to the S/C total due Quantity (column 28.13) in the main bill which can be copied into the main bills actual qty. Do This Open the valuation document Manager

Customise document 8.2 Bill with Subcontract update to add column 28.13 Subcontract total due quantity

149

Post Tender Valuations & Budget Control

Valuation using Subcontract Manager

Click Ok and open the document Right click on the Actual Quantity and select Update from Subcontract Due quantity

Note 11 Quantities copied

150

Post Tender Valuations & Budget Control

Valuation using Subcontract Manager

151

Post Tender Valuations & Budget Control

System Registration

152

Post Tender Valuations & Budget Control

System Registration

Appendix A- System Registration


To use Candy, the system must be registered with CCS. If your system has not been registered, the system registration dialogue box will be displayed as a broken key.

If the system has been registered the job selector will be displayed. Please contact the nearest CCS office:

153

Post Tender Valuations & Budget Control

System Registration

154

Post Tender Valuations & Budget Control

System Settings

Appendix B System Settings


The Candy desktop may be configured individually to your requirements. To open and configure the system settings use the Candy button > System settings . Alternatively use the (brown hammer) icon.

Fonts
Change the font, style and size for various areas of the system. You may find that the view is limited in a document, for example the Bill of Quantities, and may need to adjust your fonts later.

Desktop

Set desktop images and/or calendars to display in the desktop

155

Post Tender Valuations & Budget Control Documents

System Settings

Colours can be selected for cursors and input fields on documents and level headings.

Tool buttons Frequently used shortcuts keys can be activated here by applying ticks or removing ticks Do this:

Select utilities tool buttons to activate the system tools

156

Post Tender Valuations & Budget Control

System Settings

Folders and Paths


This sheet holds various folder paths used by Candy. The paths may be entered manually or located by using the Browse button.

The Candy system can be configured on the network by setting up the folders and paths. The following paths can be set as below:Common backups to set the path to the Common folder used by all the users wishing to backup data on the organisations network. (The backed up data can be recovered by other users) Archived backups - to set the path to the Archived folder for the individual user wishing to backup data on the organisations network. (The backed up data can only be recovered by the individual user) Candy network masters To set the path for a master network company enabling users to access the master library job centrally Microsoft Excel - the path pointing to Excel for exporting Candy data directly to Excel. Tool buttons Job start-up Folders and paths Number format Keyboard Languages Macro keys Toolbar keys Set tool buttons to display in each toolbar button Set the start tool button document to open immediately when a job is selected. Set the folders and network path for backups and network masters. If Excel is installed on the computer, the executable command can be located here for exporting document information direct into Excel. Set number styles to use Set text input and Enter key direction Set the langue file to use (other than English) Set keyboard shortcuts to activate recorded keystrokes in sequence Set keyboard short cut commands to activate tool button functions

157