As production manager, you have developed the following value chart: Operation Receiving materials Storing materials Handling materials Cutting/measuring materials Assembling materials Building boxes Attaching hinges Inspection Average Number of Days 1 3 4 7 5 9 2 1
Required: a. Determine the value-added activities and their total time. b. Determine the non-value-added activities and their total time. c. Calculate the manufacturing cycle efficiency.