SIEMENS (TYPE-GMSG)

VACUUM CIRCUIT BREAKER

RACKING THE SIEMENS GMSG


1. Close the circuit breaker compartment door and secure all latches. 2. Insert the racking crank on the racking screw on the front of the circuit breaker cell, and push in. This action operates the racking interlock latch. 3. Rotate the racking crank counterclockwise until the circuit breaker is in the DISCONNECT position.

RACKING THE SIEMENS GMSG


4. Open the circuit breaker compartment door and insert the two extension rails into the fixed rails. Be sure the extension rails are properly secured in place. 5. Depress and hold down the circuit breaker Racking Latch Release Handle and pull the circuit breaker out from the DISCONNECT position. The circuit breaker can now be removed from the cubicle and rolled out on to the two extension rails.

RACKING THE SIEMENS GMSG


6. Remove the circuit breaker from the two extension rails using the approved Siemens circuit breaker lifting device or a Siemens lifting sling and a Suitable crane. 7. Lift the two extension rails and withdraw them from the switchgear. 8. Close the circuit breaker compartment door and secure all latches.

MANUAL CHARGING OF CLOSING SPRINGS

SPLIT JUMPER
CONNECTED AT THE BREAKER

SPLIT JUMPER
CONNECTED AT THE SWITCHGEAR

MAIN STABS AND VACUUM INTERRUPTERS

SIEMENS (SION)
VACUUM CIRCUIT BREAKER