LAMPIRAN A CONTOH PERHITUNGAN Contoh perhitungan neraca massa komponen di Gathering Station, Water Cleaning Plant, Water Injection

Plant dan Disposal Well dengan data laju alir air dapat dilihat pada Tabel A.1. Tabel A.1 Data Laju Alir Air di BOB PT. BSP Pertamina Hulu, Zamrud, Siak. Water Management Description Inlet to Skim Tank Returned Water to GS (Pit Pump) Nett Total from Zamrud GS Injection to WIW Beruk Injection to WIP Zamrud Total Water Injected Injected to Non EOR Well Zamrud Injected to Beruk Disposal Well Excess Water to Emergency Pit Returned Water to GS (Pit Pump) Sumber: Morning Report GS (12 Mei 2013) BWPD 189.499 1.198 188.051 41.110 111.228 152.238 25.722 7.324 9.991 250

A-1

A. Gas Boot

Gambar A.1 Blok Diagram Alir Neraca Massa Komponen Gas Boot di BOB PT. BSP Pertamina Hulu, Zamrud, Siak Dari data pada gambar didapatkan jumlah total laju alir air pada keseluruhan proses: NMK: Finput FGB 185.384 BWPD FWashTank FWashTank = Foutput = -(FPit + FSkim) + FWashTank = -(X + 1.198 BWPD) + FWashTank = (185.384 + 1.198 + X) BWPD = (186.582 + X) BWPD

A-2

B. Wash Tank

Gambar A.2 Blok Diagram Alir Neraca Massa Komponen Wash Tank di BOB PT. BSP Pertamina Hulu, Zamrud, Siak Dari data pada gambar didapatkan jumlah total laju alir air pada keseluruhan proses: NMK: Finput FWashTank (186.582 + X) BWPD X BWPD X Sehingga, FWashTank = (186.582 + X) BWPD = 186.582 BWPD + 12.908 BWPD = 199.490 BWPD = 12.908 BWPD = Foutput = FPit + FShipping + FSkimming = (9.991 + 189.499) BWPD = -(186.582) BWPD + 199.490

A-3

C. Skimming Tank

Gambar A.3 Blok Diagram Alir Neraca Massa Komponen Skimming Tank di BOB PT. BSP Pertamina Hulu, Zamrud, Siak Dari data pada gambar didapatkan jumlah total laju alir air pada keseluruhan proses: NMK: Finput FSkimming 189.499 BWPD X X = Foutput = FPit + FGB + FFilter = (250 + 1.198 + X) BWPD = 189.499 BWPD + 1.448 BWPD = 188.051 BWPD

D. Filter

Gambar A.4 Blok Diagram Alir Neraca Massa Komponen Filter di BOB PT. BSP Pertamina Hulu, Zamrud, Siak

A-4

E. Balance Tank

Gambar A.5 Blok Diagram Alir Neraca Massa Komponen Balance Tank di BOB PT. BSP Pertamina Hulu, Zamrud, Siak Dari data pada gambar didapatkan jumlah total laju alir air pada keseluruhan proses: NMK: Finput FBalance 188.051 BWPD X X = Foutput = FPit + FWIW + FWIP = (X + 41.110 + 111.228) BWPD = 188.051 BWPD 152.338 BWPD = 35.713 BWPD

A-5

F. Emergency Pit

Gambar A.6 Blok Diagram Alir Neraca Massa Komponen Emergency Pit di BOB PT. BSP Pertamina Hulu, Zamrud, Siak Dari data pada gambar didapatkan jumlah total laju alir air pada keseluruhan proses: NMK: Finput FPit FWashTank + FBalance + FSkimming X X = Foutput = FDisposal + FGB = (X + 12.908) BWPD = (45.954 12.908) BWPD = 33.046 BWPD

(9.991 + 35.713 + 250) BWPD= X + 12.908 BWPD

A-6

G. Disposal Well

Emergency Pit

33.046 BWPD

Disposal Well

7.324 BWPD

Beruk

25.722 BWPD

Zamrud

Gambar A.7 Blok Diagram Alir Neraca Massa Komponen Disposal Well di BOB PT. BSP Pertamina Hulu, Zamrud, Siak Dari data pada gambar didapatkan jumlah total laju alir air pada keseluruhan proses: NMK: Finput FDisposal Well 33.046 BWPD 33.046 BWPD = Foutput = FZamrud + FBeruk = (25.722 + 7.324) BWPD = 33.046 BWPD

Maka, dibuktikan bahwa neraca massa komponen telah sama untuk laju alir masuk dan laju alir keluar pada tiap proses.