You are on page 1of 10

DATE: 01.03.2014 K/ATTN.: MR.

SAKTHI VEL
TO: L&T LTD. HOSUR KRISHNAGIRI PROJECT
Sl No Item Description
Type of Poles
Nos or
SETS or
mtr
Supply Unit
Price
10M OCTAGONAL POLE 501
DOUBLE ARM BRKT 2M 501
10M OCTAGONAL POLE 362
SINGLE ARM BRKT 1 M 362
9M OCTAGONAL POLE 276
SINGLE ARM BRKT 1 M 276
OCTAGONAL POLES TOTAL 1139
250 W SV SL - ITIN0148 1364 10,550.00
SP MCB in JB 1640 188.00
HAYLEM WITH TB 1139 625.00
2C X 1.50 SQ MM WIRE 19130 82.00
FP-I/C :- Fuse units 3,
Contactor 63 A - 1, Timer 1,
63 A MCB, terminals
61 37,500.00
PANEL EARTHING 61
3 1/2 C X 25 SQ MM UG
ARMOURED AL CABLE
40495 142.00
3 1/2 C X 50 SQ MM UG
ARMOURED AL CABLE
2185 207.00
250 W SV SL -
SSN1125IH/FG
276 2,950.00
70 W MH LOW BAY-
LMHA1107IH
32 1,584.00
250 W MH FLOOD LIGHT -
FADT1125IH09
20 3,508.00
MOUNTING BRACKET 52 1,000.00
DISTRIBUTION BOARD 13 5,625.00
PANEL BOARD 13 18,125.00
PANEL EARTHING 13
2x400 W SV FLD -
FHD1624 + CG12240S(CA)
24 9,500.00
FEEDER PILLAR WITH TIMER 2 37,500.00
L E D AVIATION - GLN 704 2 6,000.00
16,050.00
21,475.00
20,475.00
2
LIGHT
FIXTU
RES &
LAMPS
along
with
Cables
&
Panels
Quotation from M/s. Crompton Greaves ( Without Sales Tax & Service Tax )
1
OCTAGONAL
LIGHT POLES
WITH
DECORATIVE
CURVED
BRACKETS WITH
10/15 DEGREE
TILT
25M HIGHMAST -HM1225-
360 degree
1
25M HM ACCES.-360
DEGREES
1
25M HIGHMAST -HM1225-
180 degree
1
25M HM ACCES.-180
degrees
1
16A PLUG & SOCKET 4 700.00
IPFC1124EB 66 1,850.00
MOUNT BRKT 66 900.00
PANEL WITH TIMER 66 8,125.00
2 C X 10 SQ MM UG ARMRD
AL CABLE
2310 107.00
PANEL EARTHING 66
250W SV OSRAM LAMP 1640 900.00
70W MH DE LAMP 32 500.00
250W MHL T LAMP 20 600.00
36W FTL 132 35.00
400 W SV T LAMP 48 400.00
CASTING OF FOUNDATION
FOR POLES
1139
ERECTION OF POLE WITH
TERMINATION OF CABLE
1139
EARTH WORK FOR LAYING
OF 31/2 C X 50 SQ MM
CABLE
2185
EARTH WORK FOR LAYING
OF 31/2 C X 25 SQ MM
CABLE
40495
EARTHING OF POLE FOR
EVERY 5 NOS
456 4625
6 25 Mtr HM As per TDS 2
265,000.00
335,000.00
4 FEEDER PILLARS
FEEDER PILLARS TOTAL
37500
2
LIGHT
FIXTU
RES &
LAMPS
along
with
Cables
&
Panels
LIGHT FIXTURES & LAMPS & CABLES
TOTAL
ERECTION WORK
5
EARTHING
MATERIALS
EARTHING MATERIALS TOTAL
ERECTION &
CIVIL WORK
I/C :- Fuse units 3, Timer
1, 80 A MCCB, terminals
2
7 Transportation Lumpsum without any tax
TERMS AND CONDITIONS:
PRICES: QUOTED PRICES ARE UPTO THE NEAREST TRANSPORTERS GODOWN FOR THE SUPPLY.
TAXES : TN VAT AND SERVICE TAX AS APPLICABLE WILL BE EXTRA. AT PRESENT IT IS 14.50% AND 12.36% RESPECTIVELY
DELIVERY : WITHIN 16 WEEKS FROM THE DATE OF RECEIPT OF MANUFACTURING CLEARANCE
ERECTION: WITHIN 12 WEEKS FROM THE DATE OF CLEARANCE OF SITE AFTER THE SUPPLY OF MATERIALS GETS COMPLETED
PAYMENT : 20% ADVANCE ALONG WITH THE ORDER AND BALANCE AGAINST THE SUPPLY OF MATERIALS. FOR ERECTION 20% ADVANCE AND BALANCE AGAINST THE COMMISSIONING ON PRO-RATA BASIS.
VALIDITY : UPTO 31.03.2014 SUBJECT TO OUR CONFIRMATION THEREAFTER.
Note:
The Supply tax applicable for the light fittings , poles are 14.5 % as per prevailing as on date.
The erection service considered for cable laying, erection of poles as 12.36 % as per prevailing as on date.
CABLE QTY QUOTED ARE TENTATIVE. HENCE, ACTUAL QTY MAY PLEASE CONSIDERED AT THE TIME OF EXECUTION
SUPPLY PO NEEDS TO BE SEPARATE AND WORK ORDER NEEDS TO BE SEPARATE.
ADVANCE FOR ERECTION & SUPPLY IS MUST FOR EXECUTION. PAYMENT ON PRO-RATA/RUNNING BILLS FOR SUPPLY AND ERECTION
ANY CHANGE IN SALES TAX WILL BE EXTRA AT THE TIME OF DESPATCH
regards,
For CROMPTON GREAVES LIMITED,
TOTAL
K/ATTN.: MR. SAKTHI VEL
HOSUR KRISHNAGIRI PROJECT
Total Supply Price
Erection Unit
Price
Total Erection Price Total Price
0
0
0
22,600,725.00 0 22,600,725
14,390,200.00 14,390,200
308,320.00 308,320
711,875.00 711,875
1,568,660.00 1,568,660
2,287,500.00 2,750 167,750 2,455,250
6,375 388,875 388,875
5,750,290.00 5,750,290
452,295.00 452,295
814,200.00 814,200
50,688.00 50,688
70,160.00 70,160
52,000.00 52,000
73,125.00 73,125
235,625.00 2,750 35,750 271,375
4,625 60,125 60,125
228,000.00 228,000
75,000.00 2,750 5,500 80,500
12,000.00 12,000
4,429,800.00 4,429,800
10,758,975.00
7,411,950.00 7,411,950
10,758,975
Quotation from M/s. Crompton Greaves ( Without Sales Tax & Service Tax )
265,000
2,800.00 2,800
122,100.00 122,100
59,400.00 59,400
536,250.00 2,750 181,500 717,750
247,170.00 245 565,950 813,120
6,375 420,750 420,750
1,476,000.00 1,476,000
16,000.00 16,000
12,000.00 12,000
4,620.00 4,620
19,200.00 19,200
30,175,478.00 1,826,200.00 32,001,678
7,250 8,257,750 8,257,750
4,000 4,556,000 4,556,000
245 535,325 535,325
245 9,921,275 9,921,275
23,270,350 23,270,350
75,000 0 75,000
2,109,000 2,750 1,254,000 3,363,000
2,109,000 1,254,000 3,363,000
0 121,250 242,500 242,500
335,000.00
265,000.00
335,000
0 0 75,000 75,000
265,000.00
52,855,828 26,593,050 79,713,878
PRICES: QUOTED PRICES ARE UPTO THE NEAREST TRANSPORTERS GODOWN FOR THE SUPPLY.
TAXES : TN VAT AND SERVICE TAX AS APPLICABLE WILL BE EXTRA. AT PRESENT IT IS 14.50% AND 12.36% RESPECTIVELY
DELIVERY : WITHIN 16 WEEKS FROM THE DATE OF RECEIPT OF MANUFACTURING CLEARANCE
ERECTION: WITHIN 12 WEEKS FROM THE DATE OF CLEARANCE OF SITE AFTER THE SUPPLY OF MATERIALS GETS COMPLETED
PAYMENT : 20% ADVANCE ALONG WITH THE ORDER AND BALANCE AGAINST THE SUPPLY OF MATERIALS. FOR ERECTION 20% ADVANCE AND BALANCE AGAINST THE COMMISSIONING ON PRO-RATA BASIS.
The Supply tax applicable for the light fittings , poles are 14.5 % as per prevailing as on date.
The erection service considered for cable laying, erection of poles as 12.36 % as per prevailing as on date.
CABLE QTY QUOTED ARE TENTATIVE. HENCE, ACTUAL QTY MAY PLEASE CONSIDERED AT THE TIME OF EXECUTION
SUPPLY PO NEEDS TO BE SEPARATE AND WORK ORDER NEEDS TO BE SEPARATE.
ADVANCE FOR ERECTION & SUPPLY IS MUST FOR EXECUTION. PAYMENT ON PRO-RATA/RUNNING BILLS FOR SUPPLY AND ERECTION
ANY CHANGE IN SERVICE TAX AT THE TIME OF ERECTION WILL BE EXTRA
wattage calculations
384,648.00
48,300.00
2,656.00
21,216.00
21,216.00
478,036.00
PAYMENT : 20% ADVANCE ALONG WITH THE ORDER AND BALANCE AGAINST THE SUPPLY OF MATERIALS. FOR ERECTION 20% ADVANCE AND BALANCE AGAINST THE COMMISSIONING ON PRO-RATA BASIS.
DATE: 01.03.2014
SUMMARY: HOSUR KRISHNAGIRI
SL.NO. AREA-LOCATION CG CAT REF. QTY WATTTAGE SOURCE
1 VEHICULAR UNDERPASS FADT1125IH09 20 250 MH
2 PUBLIC UNDER PASS LMHA1107IHMH 32 70 MH
3 BUS SHELTERS -387 IPFC1124EB 66 36 FTL
4 SERVICE ROAD SSGN1125IH/FG 276
4A 9MPOLES FOR ABOVE HM-1209 276
4B SA BRACKET SA BRACKET 1M 276
5 SERVICE ROAD ITIN0148 362
5A 10MPOLES FOR ABOVE HM-1210 362
5B SA BRACKET SA BRACKET 1M 362
6 MAIN CARRIAGE WAY ITIN0148 1002 250 HPSV
6A 10MPOLES FOR ABOVE HM-1210 501
6B DA BRACKET DA BRACKET 2M 501
7 REST AREA LAYOUT-HM HM-1225 2 2X400 HPSV
6A 2X400W SV LUM FHD1624 24
6B 2X400W SV CG CG12240S(CA) 24
6C 400W SV T LAMP SV400T 48
SUPPLY PORTION OF ERECTION SCOPE:
SL.NO. AREA-LOCATION QTY
A VEHICULAR & PUBLIC UNDERPASS:
1 MOUNTING BRACKET 52
2 DISTRIBUTION BOARD 13
3 2C X 1.50 SQ MMWIRE 100
4 PANEL BOARD 13
5
3 1/2 C X 25 SQ MMUG
ARMRD AL CABLE 520
B BUS SHELTERS:
6 MOUNT BRKT 66
9 2C X 1.50 SQ MMWIRE 990
10 PANEL WITH TIMER 66
11
2 C X 10 SQ MMUG
ARMRD AL CABLE
2310
C M C W with 10M octagonal pole
15 SP MCB in JB 1002
16 HAYLEMWITH TB 501
18 2C X 1.50 SQ MMWIRE 11022
19 FP 38
20
3 1/2 C X 25 SQ MMUG
ARMRD AL CABLE
17535
21
3 1/2 C X 50 SQ MMUG
ARMRD AL CABLE
1330
D SERVICE ROAD with 9 & 10M octagonal pole
28 SP MCB in JB 638
29 HAYLEMWITH TB 638
31 2C X 1.50 SQ MMWIRE 7018
32 FP 23
33
3 1/2 C X 25 SQ MMUG
ARMRD AL CABLE
22330
34
3 1/2 C X 50 SQ MMUG
ARMRD AL CABLE
855
E 25M HIGHMAST FOR 12 NOS 2X400W SV - REST AREA
35 FEEDER PILLAR WITH TIMER 2
36
3 1/2 C X 25 SQ MMUG
ARMRD AL CABLE
110
ERECTION PORTION OF ERECTION CONTRACTOR'S SCOPE:
SL.NO. AREA-LOCATION CG CAT REF. QTY WATTTAGE SOURCE
A VEHICULAR & PUBLIC UNDERPASS:
1
CLAMPING OF CABLE ON
THE WALL
325
2
EARTHING OF PANEL
WITH TERMINATION OF
CABLE
13
3 GROUTING OF PANEL 13
4 ERECTION OF PANEL 13
5
EARTH WORK FOR
LAYING OF 31/2 C X 25
SQ MMCABLE
520
6
LAYING OF 31/2 C X 25
SQ MMCABLE
520
B BUS SHELTERS:
6
FIXING OF THE 2X36W
FTL LUMINAIRE
66
7
EARTHING OF PANEL
WITH TERMINATION OF
CABLE
66
8 GROUTING OF PANEL 66
9 ERECTION OF PANEL 66
C M C W with 10M octagonal pole
10
CASTING OF
FOUNDATION FOR
POLES
501
11
ERECTION OF POLE
WITH TERMINATION OF
CABLE
501
12
EARTHING OF POLE FOR
EVERY 5 NOS
102
13
PANEL BOARD
EARTHING
38
14 GROUTING OF PANEL 38
15 ERECTION OF PANEL 38
16
EARTH WORK FOR 31/2
C X 50 SQ MMCABLE
1330
LAYING OF 31/2 C X 50
SQ MMCABLE
1330
17
EARTH WORK FOR 31/2
C X 25 SQ MMCABLE
17535
LAYING OF 31/2 C X 25
SQ MMCABLE
17535
D SERVICE ROAD with 9 & 10M octagonal pole
18
CASTING OF
FOUNDATION FOR
POLES
638
19
ERECTION OF POLE
WITH TERMINATION OF
CABLE
638
20
EARTHING OF POLE FOR
EVERY 5 NOS
130
21
PANEL BOARD
EARTHING
23
22 GROUTING OF PANEL 23
23 ERECTION OF PANEL 23
24
EARTH WORK FOR 31/2
C X 50 SQ MMCABLE
855
LAYING OF 31/2 C X 50
SQ MMCABLE
855
25
EARTH WORK FOR 31/2
C X 25 SQ MMCABLE
22330
LAYING OF 31/2 C X 25
SQ MMCABLE
22330
E 25M HIGHMAST FOR 12 NOS 2X400W SV - REST AREA
26 CIVIL PORTION 2
27
ERECTION &
COMMISSION INCL.
CRANE
2
ERECTION TOTAL
250 HPSV
250 HPSV

You might also like