1 Total construction period 30 days Fri 8/22/14 Sat 9/20/14


2 Mobilization work 1 day Fri 8/22/14 Fri 8/22/14
3 Fabrication work in our work shop 4 days Thu 8/21/14 Sun 8/24/14
4 Removing of roof sheet,glass wool, rafters,
columns, purlin, cladding & girtz
12 days Fri 9/12/14 Tue 9/23/14
5 Erection of Rafters, Columns ,Purlin, Tie
beam & girts
9 days Sat 9/20/14 Sun 9/28/14
6 Fixing of roof sheets 6 days Tue 9/23/14 Sun 9/28/14
7 Fixing of cladding 10 days Fri 9/26/14 Sun 10/5/14
8 Fixing of Aluminium louvers 8 days Sun 9/28/14 Sun 10/5/14
9 Fixing of Gutter & Down pipes 5 days Fri 9/26/14 Tue 9/30/14
10 Fixing of curve roof canopy frame 4 days Sun 9/28/14 Wed 10/1/14
11 Fixing of curve sheets 4 days Wed 10/1/14 Sat 10/4/14
12 Monitor roof - roof sheet & glass wool
removing
2 days Mon 9/29/14 Tue 9/30/14
13 Monitor roof sheet laying 3 days Wed 10/1/14 Fri 10/3/14
14 Site clearing & Hand over 2 days Sun 10/5/14 Mon 10/6/14
8/31 9/7 9/14 9/21 9/28 10/5
Aug 31, '14 Sep 7, '14 Sep 14, '14 Sep 21, '14 Sep 28, '14 Oct 5, '14
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
PROPOSED RECTIFICATION WORK TO WASHING PLANT SMART SHIRTS LANKA LIMITED AT EPZ,
KATUNAYAKE
Page 1