PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"


DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
01.01.00 OBRAS PRELIMINARES
01.01.01 LIMPIEZA DE TERRENO (MANUAL) M2 104.73
01.01.02 TRAZO Y REPLANTEO M2 104.73
01.02.00 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS Y ZAPATAS M3 38.48
01.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO M2 108.41
01.02.03 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 5.83
01.02.04 ELIMINACION DE MATERIAL EXCEDENTE M3 41.51
01.02.05 AFIRMADO COMPACTADO E=4" EN PISOS Y VEREDAS M2 108.41
01.03.00 OBRAS DE CONCRETO SIMPLE
01.03.01 SOLADO PARA ZAPATAS Y VIGA DE CIMIENTO 4" 1:12 M2 50.49
01.03.02 CIMIENTOS CORRIDOS MEZCLA 1:10 + 30% P.G. M3 25.45
01.03.03 CONCRETO EN FALSO PISO MEZCLA CEMENTO 1:8 HORMIGON E=4" M2 66.80
01.03.04 VEREDAS - CONCRETO Fc=140 Kg/CM2 FROTACHADO Y BRUADO M2 41.62
01.04.00 CONCRETO ARMADO
01.04.01 ZAPATAS
01.04.01.01 CONCRETO EN ZAPATAS Fc = 210 KG/CM2 M3 9.60
01.04.01.02 ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS KG 225.44
01.04.02 VIGA DE CIMENTACION
01.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 M3 1.80
01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 14.40
01.04.02.03 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS DE CIMENTACION KG 310.78
01.04.03 SOBRECIMIENTO REFORZADO
01.04.03.01 CONCRETO EN SOBRECIMIENTOS REFORZADOS Fc = 210 KG/CM2 M3 2.14
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 32.59
01.04.03.03 ACERO ESTRUCTURAL TRABAJADO PARA SOBRECIMIENTOS REFORZADOS KG 644.04
01.04.04 COLUMNAS
01.04.02.01 CONCRETO EN COLUMNAS Fc = 210 KG/CM2 M3 3.68
01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 21.00
01.04.02.03 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS KG 1,417.67
01.04.05 VIGAS
01.04.05.02 CONCRETO EN VIGAS Fc = 175 KG/CM2 M3 7.15
01.04.05.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS M2 57.20
01.04.05.04 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS KG 865.35
01.04.06 LOSAS ALIGERADAS
01.04.06.01 CONCRETO EN LOSAS ALIGERADAS Fc = 210 KG/CM2 M3 5.28
01.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS M2 30.16
01.04.06.03 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS ALIGERADAS. KG 290.57
01.04.06.04 LADRILLO HUECO/ARCILLA 15 X 30 X 30 /TECHO ALIGERADO. UND 502.47
02.00.00 ARQUITECTURA
02.01.00 ALBAILERIA
02.01.01 MUROS DE SOGA DE LADRILLO KK DE ARCILLA C/M 1:4 X 1.5 CM. M2 127.58
02.01.02 MUROS DE CANTO DE LADRILLO KK DE ARCILLA C/M 1:4 X 1.5 CM. M2 48.80
02.02.00 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.01 TARRAJEO DE INTERIORES M2 127.58
02.02.02 TARRAJEO EN EXTERIORES M2 159.68
02.02.03 TARRAJEO DE COLUMNAS M2 34.80
02.02.04 TARRAJEO DE SUPERF. EN VIGAS PERALTADAS M2 188.10
02.02.07 VESTIDURAS DE DERRAMES M 67.20
02.03.00 CIELORRASO
02.03.01 TARRAJEO EN CIELO RASO M2 60.32
02.04.00 PISOS Y PAVIMENTOS
02.04.01 PISO CERAMICO DE 0.30 X 0.30 M M2 66.80
02.04.02 VEREDA DE CONCRETO Fc=140 Kg/CM2 FROTACHADO Y BRUADO M2 42.24
02.04.03 JUNTAS DE DILATACION EN VEREDAS ML 13.49
02.05.00 CONTRAZOCALO
02.05.01 CONTRAZOCALO DE CEMENTO S/COLOREAR H=30 CM M 57.80
02.06.00 CARPINTERIA DE MADERA
02.06.01 PUERTA DE MADERA DE CEDRO, MARCO 2" X 4" (1.90 X 2.10 M) UND 2.00
02.06.02 PUERTA CONTRAPLACADA DE 0.60X2.00M. UND 11.00
02.06.06 VENTANA DE MADERA C/MARC DE CEDRO (0.60 X 0.60M)INCL. COLOC. UND 16.00
DESCRI PCI ON
HOJ A DE METRADOS
I TEM UNI D MET
2
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
DESCRI PCI ON
HOJ A DE METRADOS
I TEM UNI D MET
02.07.00 CERRAJ ERIA
02.07.01 CERRADURA PTA. INTERIOR 2 GOLPES UND 2.00
02.07.02 BISAGRA CAPUCHINA DE 31/2" X 31/2" PZA 18.00
02.08.00 VIDRIOS CRISTALES Y SIMILARES
02.08.01 VIDRIO SEMIDOBLE. EN VENTANAS MADERA SUM. Y COLOCACION PIE2 136.99
02.09.00 PINTURA
02.09.01 PINTURA LATEX EN INTERIORES, COLUMNAS Y DERRAMES M2 385.28
02.09.02 PINTURA LATEX EN EXTERIORES M2 159.68
02.09.03 PINTURA LATEX EN CIELO RASO Y VIGAS M2 248.42
02.09.04 BARNIZ EN CARPINTERIA DE MADERA M2 19.08
03.00.00 INSTALACIONES ELECTRICAS
03.01.00 CABLES Y/O CONDUCTOS
03.01.01 ROTURA Y RESANE DE PARED PARA COLOCAR CAJA DE PASE ML 11.25
03.01.02 TUBERIA PVC - P 20MM M 45.29
03.01.03 TUBERIA PVC - P 25MM M 14.20
03.01.04 TUBERIA PVC - P 50 MM M 50.00
03.02.00 TABLEROS Y SUBTABLEROS
03.02.01 TABLEROS Y SUBTABLEROS UND 1.00
03.02.02 T.G. 1-3x100,3-3x40,1-1x30 UND 1.00
03.03.00 SALIDA DE ALUMBRADO Y TOMACORRIENTE
03.03.01 SALIDA DE TECHO PTO 6.00
03.03.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/PUESTA A TIERRA PTO 2.00
03.04.00 CIRCUITOS DE INTERRUPTORES Y TOMACORRIENTES
03.04.01 INTERRUPTORES SIMPLES TICINO PTO 2.00
03.05.00 ARTEFACTOS DE ILUMINACION
03.05.01 FLUORESCENTE JOSEL 2x40 W UND 6.00
03.06.00 POZO PUESTA A TIERRA
06.01.00 POZO CONEXIN A PUESTA A TIERRA UND 1.00
04.00.00 INSTALACIONES SANITARIAS
04.01.00 SISTEMA DE AGUA FRIA
04.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 20.00
04.01.02 RED DE DISTRIBUCION TUBERIA 1/2" PVC-SAP ML 8.00
04.01.03 RED DE DISTRIBUCION TUBERIA 3/4" PVC-SAP ML 60.00
04.01.04 VALVULA COMPUERTA DE BRONCE DE 1/2" PZA 8.00
04.02.00 SISTEMA DE DESAGUE
04.02.01 SALIDAS DE PVC SAL PARA DESAGE DE 2" PTO 15.00
04.02.02 SALIDAS DE PVC SAL PARA DESAGE DE 4" PTO 7.00
04.02.03 SALIDAS DE PVC SAL PARA VENTILACIN DE 2" PTO 16.00
04.02.04 TUBERIA PVC SAL DE 2" ML 31.00
04.02.05 TUBERIA PVC SAL DE 4" ML 104.25
04.02.06 CAJA DE REGISTRO DE DESAGE DE 12X24 PZA 6.00
04.02.07 SUMIDERO DE 2" PZA 2.00
04.02.07 SALIDA P/REGISTRO DE 4'' PZA 8.00
04.03.00 APARATOS Y ACCESORIOS SANITARIOS
04.03.01 LAVATORIO DE PARED BLANCO DE 1 LLAVE PZA 8.00
04.03.02 INODOROS TANQUE BAJO BLANCO PZA 7.00
04.03.03 TANQUE ELAVADO DE 1000 LTS INCLUIDOS ACCESORIOS GLB 1.00
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
LARGO ANCHO PROF.
01.00.01 OBRAS PRELIMINARES
01.01.01 LIMPIEZA DE TERRENO (MANUAL) 104.73 M
1.00 12.22 8.57 104.73
01.01.02 TRAZO Y REPLANTEO 104.73 M
1.00 12.22 8.57 104.73
01.02.00 MOVIMIENTO DE TIERRAS
01.02.01 38.48 M3
CIMIENTOS 16.69
EJ ES HORIZONTALES
EJE A-A
ENTRE 1 - 2 1.00 1.65 0.50 0.90 0.74
ENTRE 2- 3 1.00 2.12 0.50 0.90 0.95
ENTRE 3- 4 1.00 3.40 0.50 0.90 1.53
EJE A'-A'
ENTRE 2- 3 1.00 2.25 0.40 0.90 0.81
EJE C'-C'
ENTRE 1'- 3 1.00 2.25 0.50 0.90 1.01
ENTRE 3- 4 1.00 3.40 0.50 0.90 1.53
EJE D-D
ENTRE 1 - 1' 1.00 1.53 0.50 0.90 0.69
ENTRE 1' - 3 1.00 2.25 0.50 0.90 1.01
EJ ES VERTICALES
EJE 1-1
ENTRE A-B 2.00 2.48 0.50 0.85 2.10
ENTRE B-C 2.00 2.48 0.50 0.85 2.10
ENTRE C-D 2.00 2.48 0.50 0.85 2.10
EJE E-E ENTRE 1'-2' 2.00 2.48 0.50 0.85 2.10
16.69
4.44
EJ ES HORIZONTALES
2.00 0.50 0.40 0.85 0.34
1.00 0.65 0.40 0.85 0.22
3.00 0.65 0.20 0.40 0.16
1.00 0.90 0.40 0.85 0.31
3.00 3.00 0.25 0.40 0.90
EJ ES VERTICALES
2.00 0.60 0.40 0.85 0.41
1.00 0.63 0.20 0.40 0.05
3.00 0.50 0.20 0.40 0.12
EJ ES HORIZONTALES
2.00 0.50 0.40 0.85 0.34
2.00 0.93 0.40 0.85 0.63
1.00 0.65 0.40 0.85 0.22
2.00 0.65 0.20 0.40 0.10
1.00 0.30 0.40 0.85 0.10
EJ ES VERTICALES
2.00 0.60 0.40 0.85 0.41
2.00 0.50 0.20 0.40 0.08
1.00 0.65 0.20 0.40 0.05
4.44
ZAPATAS 17.35
Z-1 2.00 1.00 1.00 0.90 1.80
Z-2 12.00 1.20 1.20 0.90 15.55
17.35
01.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO 108.41 M2
66.80
SSHH 2 1.00 11.30 3.00 33.40
33.40
41.62
VEREDAS 1 2.00 1.20 3.10 7.33
1.00 1.20 4.00 4.73
2.00 2.00 2.00 7.88
1.00 21.67
41.62
01.02.03 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 5.83 M3
CIMIENTOS 2.78
EJ ES HORIZONTALES
EJE 1'-1' ENTRE A - E 2.00 10.77 0.35 0.15 1.13
EJE 2'-2' ENTRE A - B 2.00 10.77 0.35 0.15 1.13
EJ ES VERTICALES
EJE A-A ENTRE 1'-2' 2.00 2.48 0.35 0.15 0.26
EJE E-E ENTRE 1'-2' 2.00 2.48 0.35 0.15 0.26
2.78
0.53
EJ ES HORIZONTALES
2.00 0.50 0.30 0.15 0.05
1.00 0.65 0.30 0.15 0.03
INTERIOR SSHH DAMAS
UNI D
1
INTERIOR SSHH DAMAS
HOJ A DE METRADOS
MEDI DAS
PARC TOTAL DESCRI PCI ON I TEM CANT
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
1
1
EXCAVACION DE ZANJAS PARA CIMIENTOS Y ZAPATAS
INTERIOR SSHH VARONES
22.00
1
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
LARGO ANCHO PROF.
UNI D
HOJ A DE METRADOS
MEDI DAS
PARC TOTAL DESCRI PCI ON I TEM CANT
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
1.00 0.90 0.30 0.15 0.04
3.00 3.00 0.25 0.05 0.11
EJ ES VERTICALES -
2.00 0.60 0.30 0.15 0.05
1.00 0.63 0.20 0.05 0.01
3.00 0.50 0.20 0.05 0.02
-
EJ ES HORIZONTALES 2.00 0.50 0.30 0.15 0.05
2.00 0.93 0.30 0.15 0.08
1.00 0.65 0.30 0.15 0.03
1.00 0.30 0.30 0.15 0.01
EJ ES VERTICALES
2.00 0.60 0.30 0.15 0.05
0.53
ZAPATAS 2.52
Z-1 2.00 0.50 1.20 0.30 0.36
Z-2 12.00 0.50 1.20 0.30 2.16
2.52
INTERIOR SSHH VARONES
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
LARGO ANCHO PROF.
UNI D
HOJ A DE METRADOS
MEDI DAS
PARC TOTAL DESCRI PCI ON I TEM CANT
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
01.02.04 ELIMINACION DE MATERIAL EXCEDENTE 41.51 M3
17.80
4.90
18.81
01.02.05 AFIRMADO COMPACTADO E=4" EN PISOS Y VEREDAS 108.41 M2
66.80
SSHH 2 1.00 11.30 3.00 33.40
33.40
41.62
VEREDAS 1 2.00 1.20 3.10 7.33
1.00 1.20 4.00 4.73
2.00 2.00 2.00 7.88
1.00 21.67
41.62
01.03.00 OBRAS DE CONCRETO SIMPLE
01.03.01 SOLADO PARA ZAPATAS Y VIGA DE CIMIENTO 4" 1:12 50.49 M2
CIMIENTOS 26.49
EJ ES HORIZONTALES
EJE 1'-1' ENTRE A - E 2.00 10.77 0.50 10.77
EJE 2'-2' ENTRE A - B 2.00 10.77 0.50 10.77
EJ ES VERTICALES
EJE A-A ENTRE 1'-2' 2.00 2.48 0.50 2.48
EJE E-E ENTRE 1'-2' 2.00 2.48 0.50 2.48
26.49
ZAPATAS 24.00
Z-1 20.00 1.00 1.20 24.00
24.00
01.03.02 CIMIENTOS CORRIDOS MEZCLA 1:10 +30% P.G. 25.45 M3
CIMIENTOS 21.19
EJ ES HORIZONTALES
EJE 1'-1' ENTRE A - E 2.00 10.77 0.50 0.80 8.62
EJE 2'-2' ENTRE A - B 2.00 10.77 0.50 0.80 8.62
EJ ES VERTICALES
EJE A-A ENTRE 1'-2' 2.00 2.48 0.50 0.80 1.98
EJE E-E ENTRE 1'-2' 2.00 2.48 0.50 0.80 1.98
21.19
4.26
EJ ES HORIZONTALES
2.00 0.50 0.40 0.80 0.32
1.00 0.65 0.40 0.80 0.21
3.00 0.65 0.20 0.40 0.16
1.00 0.90 0.40 0.80 0.29
3.00 3.00 0.25 0.40 0.90
EJ ES VERTICALES
2.00 0.60 0.40 0.80 0.38
1.00 0.63 0.20 0.40 0.05
3.00 0.50 0.20 0.40 0.12
EJ ES HORIZONTALES
2.00 0.50 0.40 0.80 0.32
2.00 0.93 0.40 0.80 0.59
1.00 0.65 0.40 0.80 0.21
2.00 0.65 0.20 0.40 0.10
1.00 0.30 0.40 0.80 0.10
EJ ES VERTICALES
2.00 0.60 0.40 0.80 0.38
2.00 0.50 0.20 0.40 0.08
1.00 0.65 0.20 0.40 0.05
4.26
01.03.03 CONCRETO EN FALSO PISO MEZCLA CEMENTO 1:8 HORMIGON E=4" 66.80 M2
66.80
SSHH 2 1.00 11.30 3.00 33.40
33.40
01.03.04 VEREDAS - CONCRETO Fc=140 Kg/CM2 FROTACHADO Y BRUADO 41.62 M2
41.62
VEREDAS 1 2.00 1.20 3.10 7.33
1.00 1.20 4.00 4.73
2.00 2.00 2.00 7.88
1.00 21.67
41.62
CIMIENTOS
1
INTERIOR SSHH DAMAS 1
1
1
1
SSHH
INTERIOR SSHH VARONES
22.00
22.00
1
ZAPATAS
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
ENCOFRADO
TOTAL PARC. TOTAL
LARGO ANCHO ALTO m3 m2
01.04.00 CONCRETO ARMADO
01.04.01 ZAPATAS 9.60 -
Z-1 20.00 1.20 1.00 0.40 9.60
9.60 -
01.04.02 VIGA DE CIMENTACION 1.80 14.40
6.00 3.00 0.25 0.40 1.80 14.40
1.80
01.04.03 SOBRECIMIENTO REFORZADO 2.14 32.59
4.00 2.30 0.15 0.40 0.55 7.36
4.00 2.63 0.15 0.40 0.63 8.40
2.00 3.00 0.15 0.40 0.36 4.80
2.00 2.10 0.10 0.40 0.17 3.36
SSHH DAMAS -
2.00 1.00 0.10 0.40 0.08 1.60
2.00 1.13 0.10 0.40 0.09 1.81
2.00 0.30 0.10 0.40 0.02 0.48
SSHH VARONES -
2.00 1.00 0.10 0.40 0.08 1.60
3.00 1.13 0.10 0.40 0.14 2.70
2.00 0.30 0.10 0.40 0.02 0.48
2.14 32.59
01.04.04 COLUMNAS 3.68 21.00
1 3.68
20.00 3.50 0.35 0.15 3.68 21.00
01.04.05 VIGAS 7.15 57.20
1.00 7.15
4.00 11.30 0.25 0.50 5.65 45.20
4.00 3.00 0.25 0.50 1.50 12.00
7.15 57.20
01.04.06 LOSAS ALIGERADAS 5.28 30.16
SSHH 2.00 60.32
2.00 2.50 2.90 14.50
2.00 2.70 2.90 15.66
30.16 30.16
Vol Tot / m = .05+0.25hl
hl = Alt del Lad 0.15
Entonces Vol Tot / m 0.09 TOTAL M DE L. ALIG. : 60.32
PARC TOTAL
Cantidad de ladrillo Huecos und
Arcilla de 0.3m x0.3m.
8.33 / m 502.47
CONCRETO Fc=210Kg/cm2
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
SSHH
HOJ A DE METRADOS
MEDI DAS
PARC.
ELEMENTO
I TEM
CANT. DESCRI PCI ON
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5NIVELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
TOTAL
CANT/ELEM 3/4'' 5/8'' 1/2'' 3/8'' PARC KG CANT/ELEM 3/8" 1/4" PARC KG KG
2.240 1.552 0.994 0.560
01.04.01 ZAPATAS 225.44
Z-1 20.00 8.00 1.35 226.80 225.44
225.44 225.44
01.04.02 VIGA DE CIMENTACION 310.78
1.00 130.98 130.19 180.59
6.00 6.00 3.30 124.74 130.19 20.00 1.60 201.60 50.40 180.59
124.74
01.04.03 SOBRECIMIENTO REFORZADO 644.04
1.00 273.62 259.03 385.01
4.00 6.00 2.60 62.40 62.03 21.00 1.05 92.61 23.15 85.18
4.00 6.00 2.93 70.20 69.78 21.00 1.05 370.44 92.61 162.39
2.00 6.00 3.30 39.60 39.36 21.00 1.05 185.22 46.31 85.67
2.00 6.00 2.40 28.80 28.63 21.00 1.05 92.61 23.15 51.78
SSHH DAMAS
2.00 10.00 0.55 11.00 10.93
2.00 11.30 0.55 12.43 12.36
2.00 3.00 0.55 3.30 3.28
SSHH VARONES
2.00 10.00 0.55 11.00 10.93
3.00 11.25 0.55 18.56 18.45
2.00 3.00 0.55 3.30 3.28
260.59
01.04.04 COLUMNAS 1,417.67
1.00 654.89 650.96 766.72
20.00 6.00 4.95 623.70 650.96 21.00 1.05 463.05 115.76 766.72
623.70
01.04.05 VIGAS 865.35
SSHH 2.00
VP100 (0.25 X 0.50) 2.00 4.00 11.60 194.88 193.71 73.00 1.70 521.22 291.88 549.05
2.00 4.45 37.38 37.16
2.00 3.15 26.46 26.30
VP 101 (0.25 X 0.50) 2.00 4.00 3.30 55.44 86.04 20.00 1.70 142.80 79.97 316.30
2.00 4.45 37.38 20.93
2.00 3.15 3.15 83.35 129.36
HOJ A DE METRADOS
I TEM ELEMENTO CANTI DAD
ACERO Fy=4200Kg/cm
ESTRI BOS
DISTRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
ACERO LONGI TUDI NAL
ADMINISTRACIN
ADMINISTRACIN
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5NIVELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
TOTAL
CANT/ELEM 3/4'' 5/8'' 1/2'' 3/8'' PARC KG CANT/ELEM 3/8" 1/4" PARC KG KG
2.240 1.552 0.994 0.560
HOJ A DE METRADOS
I TEM ELEMENTO CANTI DAD
ACERO Fy=4200Kg/cm
ESTRI BOS
DISTRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
ACERO LONGI TUDI NAL
01.04.06 LOSAS ALIGERADAS 1.00 290.57
2.00
2.00 12.00 2.90 146.16 145.28 145.28
2.00 12.00 2.90 146.16 145.28 145.28
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
LARGO ANCHO ALTO
02.00.00 ALBAILERIA
02.01.01 MUROS DE LADRILLO KK DE ARCILLA DE SOGA
C/M 1:4 X 1.5 CM. 127.58 M2
SSHH
2.00 3.00 2.90 17.40
2.00 2.10 2.90 12.18
4.00 2.30 2.90 26.68
4.00 2.60 2.90 30.16
4.00 2.30 2.10 19.32
4.00 2.60 2.10 21.84
#REF! MUROS DE LADRILLO KK DE ARCILLA DE SOGA
C/M 1:4 X 1.5 CM. 48.80 M2
SSHH DAMAS 1.00
4.00 1.15 2.00 9.20
2.00 0.20 2.00 0.80
SSHH VARONES
4.00 1.15 2.00 36.80
2.00 0.25 2.00 2.00
02.02.00 REVOQUES ENLUCIDOS Y MOLDURAS
02.02.01 TARRAJEO DE INTERIORES 127.58 M2
INTERIOR 1.00
2.00 3.00 2.90 17.40
2.00 2.10 2.90 12.18
4.00 2.30 2.90 26.68
4.00 2.60 2.90 30.16
4.00 2.30 2.10 19.32
4.00 2.60 2.10 21.84
02.02.02 TARRAJEO EN EXTERIORES 159.68 M2
EXTERIOR 1.00
2.00 3.30 3.20 21.12
2.00 2.40 3.20 15.36
4.00 2.60 3.20 33.28
4.00 2.90 3.20 37.12
4.00 2.60 2.40 24.96
4.00 2.90 2.40 27.84
02.02.03 TARRAJEO DE COLUMNAS 34.80 M2
COLUMNAS F'C=210 KG/CM2 1.00
20.00 2.90 0.60 34.80
02.04.00 TARRAJEO DE SUPERF. EN VIGAS PERALTADAS 188.10 M2
1.00
SSHH 2.00
VP100 (0.25 X 0.50) 2.00 4.00 1.10 11.30 99.44 -
2.00 1.10 4.15 18.26 -
2.00 1.10 2.85 12.54 -
VP 101 (0.25 X 0.50) 2.00 4.00 1.10 3.00 26.40 -
2.00 1.10 3.00 13.20 -
2.00 1.10 4.15 18.26 -
02.07.00 VESTIDURAS DE DERRAMES
67.20 M
P - 1 2.00 0.90 4.20 18.60
P - 2 4.00 3.60 28.80
V - 1 16.00 2.40 38.40
02.03.00
02.03.01 TARRAJEO EN CIELO RASO
60.32 M2
2.00 60.32
2.00 2.50 2.90 14.50
2.00 2.70 2.90 15.66
30.16
CIELORRASO
HOJ A DE METRADOS
MEDI DAS
PARC TOTAL DESCRI PCI ON I TEM CANTI DAD
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
UNI D
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
LARGO ANCHO ALTO
HOJ A DE METRADOS
MEDI DAS
PARC TOTAL DESCRI PCI ON I TEM CANTI DAD
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
UNI D
02.04.00 PISOS Y PAVIMENTOS
02.04.01 PISO CERAMICO DE 0.30 X 0.30 M 66.80 M2
SSHH 2.00 1.00 11.30 3.00 66.80
02.04.02 VEREDA DE CONCRETO Fc=140 Kg/CM2 FROTACHADO Y BRUADO 42.24 M2
2.00 1.20 3.10 7.44
1.00 1.20 4.00 4.80
2.00 2.00 2.00 8.00
1.00 22.00
#REF! VEREDA DE CONCRETO Fc=140 Kg/CM2 FROTACHADO Y BRUADO 72.90 M2
VEREDA 1.00
1.00 24.80 2.10 52.08
2.00 5.55 0.60 6.66
1.00 23.60 0.60 14.16
02.04.03 JUNTAS DE DILATACION EN VEREDAS 13.49 M
VEREDA 1.00
02.05.00 CONTRAZOCALO
02.05.01 CONTRAZOCALO DE CEMENTO S/COLOREAR H=30 CM 57.80 M
2.00 28.90 57.80
02.06.00 CARPINTERIA DE MADERA
02.06.01 PUERTA DE MADERA DE CEDRO, MARCO 2" X 4" (1.90 X 2.10 M) 2.00 UND
02.06.02 PUERTA CONTRAPLACADA DE 0.60X2.00M. 4.00 UND
02.06.06 VENTANA DE MADERA C/MARC DE CEDRO (0.60 X 0.60M)INCL. COLOC. 16.00 UND
02.07.00 CERRAJ ERIA
02.07.01 CERRADURA PTA. INTERIOR 2 GOLPES 6.00 #REF!
02.07.02 BISAGRA CAPUCHINA DE 31/2" X 31/2" 18.00 PZA
02.08.00 VIDRIOS CRISTALES Y SIMILARES 136.99 PIE2
16.00 2.40 38.40 136.99
02.09.00 PINTURA
02.09.01 PINTURA LATEX EN INTERIORES, COLUMNAS Y DERRAMES 385.28 M2
INTERIOR 1.00
2.00 3.00 2.90 17.40
2.00 2.10 2.90 12.18
4.00 2.30 2.90 26.68
4.00 2.60 2.90 30.16
4.00 2.30 2.10 19.32
4.00 2.60 2.10 21.84
COLUMNAS F'C=210 KG/CM2 1.00
20.00 2.90 0.30 69.60
SSHH 2.00 4.00 1.10 11.30 99.44
VP100 (0.25 X 0.50) 2.00 1.10 4.15 18.26
2.00 1.10 2.85 12.54
2.00 4.00 1.10 3.00 26.40
VP 101 (0.25 X 0.50) 2.00 1.10 3.00 13.20
2.00 1.10 4.15 18.26
02.09.02 PINTURA LATEX EN EXTERIORES 159.68 M2
21.12
15.36
33.28
37.12
24.96
27.84
02.09.03 PINTURA LATEX EN CIELO RASO Y VIGAS 248.42 M2
CIELO RRASO 60.32
VIGAS 188.10
02.09.04 BARNIZ EN CARPINTERIA DE MADERA 19.08 M2
PUERTAS
P - 1 2.00 0.90 4.20 7.56
P - 2 4.00 - 3.60 0.00
V - 1 16.00 2.40 - 11.52
22.00
VENTANA DE MADERA C/MARC DE CEDRO (0.60 X 0.60M)INCL. COLOC.
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
SOLICITA :
RESPONSABLE : FECHA : OCTUBRE-2014
LARGO ANCHO ALTO
03.00.00 CABLES Y/O CONDUCTOS
03.01.00 CABLES Y/O CONDUCTOS
03.01.01 ROTURA Y RESANE DE PARED PARA COLOCAR CAJA DE PASE 11.25 ML
1.00 6.00
03.01.04 TUBERIA PVC - P 20MM 45.29 M
1.00 45.29
1.00 45.29
03.01.05 TUBERIA PVC - P 25MM 14.20 M
1.00 14.20
1.00 14.20
03.01.06 TUBERIA PVC - P 50 MM 1.00 50.00 50.00 M
1.00 50.00
03.02.00 TABLEROS Y SUBTABLEROS
03.02.01 TABLEROS Y SUBTABLEROS 1.00 UND
1.00 1.00
1.00
02.02.00 T.G. 1-3x100,3-3x40,1-1x30 1.00 UND
03.03.00 SALIDA DE ALUMBRADO Y TOMACORRIENTE
03.03.01 SALIDA DE TECHO 6.00 PTO
2.00 6.00
3.00
03.03.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/PUESTA A TIERRA 2.00 PTO
0 1.00 2.00
2.00
03.04.00 CIRCUITOS DE INTERRUPTORES Y TOMACORRIENTES
03.04.01 INTERRUPTORES SIMPLES TICINO 2.00 2.00 2.00 PTO
03.05.00 ARTEFACTOS DE ILUMINACION
03.05.01 FLUORESCENTE JOSEL 2x40 W 6.00 6.00 6.00 PTO
03.06.00 POZO PUESTA A TIERRA
03.06.01 POZO CONEXIN A PUESTA A TIERRA 1.00 1.00 1.00 PTO
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
HOJ A DE METRADOS
I TEM DESCRI PCI ON CANTI DAD
MEDI DAS
PARC TOTAL UNI D
0
PROYECTO : " CONSTRUCCI ON DE MULTI FAMI LI AR - 5 NI VELES"
SOLICITA :
RESPONSABLE: FECHA : OCTUBRE-2014
LARGO ANCHO ALTO
04.00.00
04.01.00 SISTEMA DE AGUA FRIA
04.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" 20.00 PTO
20.00
04.01.02 RED DE DISTRIBUCION TUBERIA 1/2" PVC-SAP 8.00 ML
1.00 8.00 8.00
04.01.03 RED DE DISTRIBUCION TUBERIA 3/4" PVC-SAP 60.00 ML
1.00 60.00 60.00
04.01.04 VALVULA COMPUERTA DE BRONCE DE 1/2" 8.00 PZA
1.00
8.00 8.00
04.02.00 SISTEMA DE DESAGUE
04.02.01 SALIDAS DE PVC SAL PARA DESAGE DE 2" 1.00 15.00 PTO
15.00
04.02.02 SALIDAS DE PVC SAL PARA DESAGE DE 4" 1.00 7.00 PTO
7.00
04.02.03 SALIDAS DE PVC SAL PARA VENTILACIN DE 2" 1.00 16.00 PTO
16.00
04.02.04 TUBERIA PVC SAL DE 4" 1.00 31.00 ML
31.00
04.02.05 CAJA DE REGISTRO DE DESAGE DE 12X24 1.00 6.00 PZA
6.00
04.02.06 SALIDA P/REGISTRO DE 4'' 1.00 2.00 PZA
2.00
04.03.00 APARATOS Y ACCESORIOS SANITARIOS
04.03.01 LAVATORIO DE PARED BLANCO DE 1 LLAVE 1.00 8.00 PZA
8.00
04.03.02 INODOROS TANQUE BAJO BLANCO 1.00 7.00 PZA
7.00
04.03.03 TANQUE ELAVADO DE 1000 LTS INCLUIDOS ACCESORIOS 1.00 1.00 GLB
I NSTALACI ONES SANI TARI AS
HOJ A DE METRADOS
DI STRI TO DE NUEVO CHI MBOTE - SANTA - ANCASH"
I TEM DESCRI PCI ON CANTI DAD
MEDI DAS
PARC TOTAL UNI D