You are on page 1of 57

Maharashtra State Power Generation Co. Ltd.

Thermal Power Station, Parli – V


Testing Stage - II

Report on
Parli Unit No. 4 Modification in
Generator Protection Scheme
Prepared by : P. A. Amilkanthwar

Modifications using Alstom make Generator Protection Relay Micom


P343
Importance Of Generator Protection
Scheme
Generator is a having vital importance in the generating stations. It is
one of the expensive equipments installed in thermal power plant.
Hence it is worth to have reliable and accurate protective system for
the generator. Though the protective relays cannot prevent the faults to
occur but the correct protection system can definitely avoid or minimize
the secondary damage to the generator under fault condition or
running under abnormal working conditions this includes external
faults, working beyond capability, etc.

Previous Generator Protection Scheme


Previously ABB Make Static conventional Generator protection Scheme was
installed at Parli Unit No. 4 during first commissioning of the unit.
During every annual over haul of the unit the protective relays are
being tested and the results of relay testing shows the generator
protection relays are loosing its accuracy and reliability, it was
observed since few years. Some of the relays getting mal operated
hence the reliability of operation was decreased. This might be due to
aging.

Most of the relays used were basically designed for 110Vdc and by
using voltage dropping resistances, those were used with 220 vdc
hence internal heating caused damage to the relays.

Also the relays were of old technology and the setting ranges were
limited. Hence it was difficult to set the relays accurately, according to
the generator capabilities.

The event logging and disturbance recording was not available with old
relays. Hence it was difficult to analyze the fault / events occurred and
the tripping analysis was based on imagination only.

The on-line healthiness checking was not available with old relays. This
was always creating doubt in the mind about the availability of
protection.

Considering the above it was necessary to change the generator


protection scheme.

Availability of Suitable Relay in the Market:


PAGE 1 OF 58
ALSTOM introduced microprocessor based integrated generator
protection relay Type P343

• Salient Features of the relay P343:


Following Protections of generator are covered in the relay

1. Generator Differential Protection: - Phase segregated differential


protection operating on a biased or high impedance principle.
Provides high speed, discriminative protection for all fault types.
{P343 only}

OR

Generator Interturn protection: suitable for use with split phase


generator and CBCT with facility of DT function.

2. Phase fault over current protection: - Two stage non-directional


back up protection.

3. Neutral voltage displacement protection: - Two stage element


providing protection against earth fault on high impedance earthed
system.

4. 100% Stator earth fault protection: - Provides protection against


earth faults close to the generator start point.

5. Under/over voltage protection: - Two stage under voltage and two


stage over voltage protection.

6. Under/over frequency protection: - Four stage under frequency and


two stage over frequency protection.

7. Reverse power: - Protection against loss of prime mover.

8. Low forward power: - Provides an interlock for non-urgent tripping.

9. Field failure: - Two stage element for protection against loss of


excitation.

10. Negative phase sequence protection: - Provides protection against


unbalanced loading, which can cause overheating of the generator
rotor.

11. Over fluxing: - Provides protection for the generator/transformer


against unusual voltage or frequency conditions.

12. Unintentional energisation at standstill (dead machine) protection: -


Protection against inadvertent closing of the generator circuit
breaker when machine is not running.

PAGE 2 OF 58
Other non-protective features of the relay:

1. Voltage transformer supervision: - To prevent mal-operation


of voltage dependent protection elements upon loss of a VT
input signal.

2. Measurements: - Various measurement of value for display


on the relay or accessed from the serial communications
e.g. Currents, voltages, Power etc.

3. Fault / event / disturbance records: - Available from the


serial communication or on the relay display (fault and event
records only on relay display.

4. Four setting groups: - Independent setting groups to cater


for alternative arrangements or user specific application.

5. Continuous self monitoring: - Power on diagnostics and self


checking routine to provide maximum relay reliability and
availability.

6. Circuit breaker state monitoring: - Provides indication of


discrepancy between circuit breaker auxiliary contacts.

PAGE 3 OF 58
PAGE 4 OF 58
Scheme Design:
100% Redundancy:
Considering the vital importance of generator protection scheme Two
number of P343 relays are used. One used as a Main and other as a
redundant. Both the relays will be all the time in service and functions
independently. CT/PT circuits, tripping circuits and alarm / interlocking
circuits are made independent to achieve 100% redundancy.

Removal of old protective relays


Following old Generator Protection relays completely removed along
with the associated components

 Generator Diff. Protection


 Gen. Inter-turn Protection
 Gen. Negative Sequence Protection
 Gen. Loss of excitation Protection
 Gen Back up impedance Protection
 Gen. 95% Stator Earth Fault protection
 Gen Over voltage protection
 Gen over fluxing Protection
 Gen over current Protection
 Gen. Low forward power protection
 Gen Under / Over Frequency Protection
 Gen under voltage protection.
Retention of old conventional relays with the modified
Generator Protection Scheme
Following conventional relays retained in the scheme.

 GT overall differential Protection (RADSB).

 Gen. Reverse Power Protection (WCD)

 GT Restricted Earth Fault Protection.

 GT HV Back-Up Over Current Protection (HBB Make)

 Local Breaker Back-Up Protection (RAICA)

 UAT differential Protection (RADSB).

PAGE 5 OF 58
 UAT HV Back-Up Over Current Protection (CDG61)

 UAT LV Neutral displacement Relay

 Gen. PT fuse monitoring Scheme.

 Gen. Check Synchronization Relay (SKE11).

 Gen. Breaker Trip Circuit Supervision Relay.

 Gen. Protection Master Trip Relay for Class A Protection. (86G,


86GT, 86T, 86TT, 86B)

 Gen. Rotor Earth-Fault Protection Scheme .

 GT & UAT Winding temp, Oil Temp, Buccholz Protection Scheme.

PAGE 6 OF 58
Preparation and Homework
 Procurement of Relays: Two numbers of ALSTOM make
microprocessor based generator protection relay type P343
procured for this modification

 Preparation of scheme and schematic drawings:


The scheme is design to accommodate the above changes and to
ensure adequate protection to the generator, the protection scheme
drawings prepared before the shut down.

The modified drawings prepared in three sections

1. Single line Diagrams: This covers the allotment of generator


CT & PT for different protection relays. Also it shows the over
view of the generator protection scheme.

2. CT/PT CIRCUITS: This covers the CT/PT Secondary


connection details.

3. Generator Protection control DC circuit: This covers the


different trip commands, alarm and interlocking circuitry up to
the final elements of execution.

The complete “Generator Protection Scheme” drawings are


enclosed in Annexure B.

PAGE 7 OF 58
Execution of work:
• Above listed old conventional relays removed along with associated wiring
and components from the panel.
• Two number of P343 relays mounted on RA1 Panel
• Wiring of relays and scheme is done as per approved drawings.

Checking and Testing


• Wiring checking: After completion of installation and wiring work. Wiring
is thoroughly checked before charging the scheme with control supply.
• Charging of control supply: 220 v dc control supply charged and
voltage measurements at all the relays checked for correct polarity and
magnitude.
• Interlocking checking: all interlocking circuitry checked thoroughly by
operating respective contacts/ Relays manually the correctness is
checked and confirmed as per drawings.
• Secondary injection testing : all the relays tested completely by
secondary injection method for correctly functioning.

PAGE 8 OF 58
 Calculation of settings for P343
1. Gen differential protection
Previous setting = 20mA, 100V
Setting for P343
Function- high impedance
Is1=250mA (min available setting)
Stabilizing resistance value
Rst = Vs/Is1= (1.5*If(Rct+2RL))/Is1
If – maximum through fault current that can flow through the generator
From previous SCC results
To circulate 9000A stator currents, excitation current required 1920A as
there is limit for maximum excitation that is 3200A therefore maximum short
circuit stator current corresponding to maximum excitation will be
Isc max=(3200*9000)/1920 A
= 15000 A (C.T. secondary 7.5 A)
Rct+2RL=3.2ohm (measured)
Rst=1.5*7.5*3.2/0.25
= 144 ohm
Actual set at 400 ohms , to get 100 V differential voltage.
2. Gen power protection
Operating mode generator
a) Reverse power protection
-P>1 = -20 watts (5.72 MW) minimum setting available on relay
selected
PSL time settings
Electrical RPP = 10 sec
Mechanical RPP = 1 sec (interlocked with turbine trip)
b) Generator low forward power protection
P>2 = 20 watts (5.72 MW) minimum setting available on relay
selected
Delay = 2 sec
PSL interlocked with turbine trip

PAGE 9 OF 58
3. Gen field failure protection

Previous settings
Xa1 = 2 ohm
Xa1 +Xb1 = 42.5 ohm
Hence Xb1 = 40.5 ohm delay 2
sec
Setting criteria
Xa1 = 0.5*Xd*CTR/PTR
Xd = 30.5% = 0.305 pu …………sub-transient reactance of generator
Xa1 = 0.5*Xd*(10000/5)*(110/15750)
Xd in ohms = Xd (pu)*kv*kv/MVA
= 0.305*15.75*15.75/247
=0.306311993 ohm
Xa1 = 2.139 ohm
Nearest settable value is 2.099 ohms
Xb1 = Xd * CTR/PTR
Xd (ohmic) = Xd(pu)*kv*kv/MVA
Xb1 = 2.22*(15.75*15.75/247)*(10000/5)*(110/15750)
= 31.14 ohm
Nearest settable value is 31.2 ohms
Time delay = 2 sec for trip
Field fail alarm angle = 25 degrees
Alarm delay = 1 sec

4. Negative phase sequence protection


Original setting
Start time capability
I22 *t = 8
I2 start = 7.5%
Continuous rated I2 = 5% of rated current

PAGE 10 OF 58
tmax = 300 sec
New settings
Alarm
I2>1 alarm enabled
I2>1 current setting
Alarm for 5% of Im
I2> 1 current set = I2 continuous rating (pu)*( Ifull load /Ip)*In
Ifull load = rated full load current in primary = 9050 A
Ip = Rated C.T. primary current = 10000 A
In = Rated C.T. secondary current = 5 A
I2>1 (set) = 0.05*9050*5/10000 = 0.226 A
Nearest available setting = 200 mA
Alarm delay = 2 sec
I2>2 trip enabled
I2 >2 start = 6%
I2>2 set = I2 start (pu)*( Ifull load /Ip)*In
= 0.06*9050*5/10000 = 0.271 A
Nearest settable value = 250 mA
K setting calculations
Generator capability for I2 is I22*t = 8
To operate the relay earlier than the capability of generator relay
characteristic selected I22*t = 7
in standard format kg = I22*t hence kg = 7
K = kg*(Ifull load/Ip)2
K = 7*(9050/10000)2 = 5.733
Nearest available setting of K = 5.7

Kreset
Kept same as K that is 5.7
I2>2 tmax
This is the maximum operating time for negative phase sequence
thermal characteristic

I2>2 tmax set at 500 sec (minimum setting available)

PAGE 11 OF 58
I2>2 tmin
This is the minimum operating time and set at 250 msec

5. Gen backup impedance protection

Original setting Z = 1.5 ohms (per phase)


Function under impedance
Z (G.T.) = 12.5%
Ohmic value of Z (G.T.) = Z(pu)*KV2/MVA
= 0.125*15.752/250
= 0.124 ohm
Impedance protection to be covered up to 220 KV bus bar that is Z
= Z(G.T.)
Z at C.T.,P.T. secondary level = Z*(CTR/PTR)
= 0.124*(10000/5)*(110/15750)
= 1.73 ohm
For three phase impedance 1.73*sqrt(3) = 2.996 ohm
Z<2 set = 3 Ohm (nearest setting available)
Time setting = 2.5 sec (considering the line under impedance time
setting that is to allow the line protections to clear the fault before
tripping of generator)

Z<1 setting (for P343 main only)


Setting criteria: for long faults and sustained overloading the setting
of this stage should be kept to operate at 30% overloading i.e. it
should be set at 70% impedance of the full load parameters of the
generator.

Zfull load at C.T., P.T. level = rated volts (phase to phase)/ Ifull load
= 110/4.525
= 24.3 ohms
Z 70% = Zfull load*0.7 = 24.3*0.7 = 17.01 ohms
Hence Z<1 setting = 17 ohms (nearest available value)
Z<1 delay = 5 sec

PAGE 12 OF 58
1. Gen thermal overload protection
BHEL supplied the following capability for the generator
Current in % Time in
KA Overload minute
9.95 1.1 60
10.41 1.15 15
10.86 1.2 6
11.31 1.25 5
11.76 1.3 4
12.22 1.35 3
12.67 1.4 2
13.57 1.5 1

As per BHEL generator is capable of continuous over load of 10% hence


Ithermal set at 1.12 pu
1.12*9050*5/10000 = 5.068 A
nearest available setting is 5.05 A
T constant is selected as 7 minutes
With above setting & allowable over loads the compatibility
checked.

As per relay manual


t = T*ln((Ieq2-Ip2) / ( Ieq2-Iset2))

After calculations following are the results

Current in KA % Time in Relay time in minute


Overload minute
With I2=0% With I2=5%
9.95 1.1 60
10.41 1.15 15 10.88 10.315
10.86 1.2 6 6.04 5.88
11.31 1.25 5 4.21 4.138
11.76 1.3 4 3.21 3.1759
12.22 1.35 3 2.59 2.56

PAGE 13 OF 58
12.67 1.4 2 2.155 2.1
13.57 1.5 1 1.5 1.582213

Above characteristics shows relay setting is ok except current above 1.35


times overload to protect this part of overload definite time over current
protection
2. Gen over current protection
Iset > 1.35*(9050*5/10000) = 6.108 A
Iset > 6.1 A (nearest available setting)
Fixed delay 40sec
3. Residual over voltage of NVD (Generator stator 95% E/F protection )
Original setting 5.75V
5% of 125 = 6.25V
Vn>1 function DT
Vn>1 voltage set = 6V (nearest available setting)
Time delay = 1 sec
4. 100% stator E/F
It is based on third harmonic under voltage measurement principle
hence after observing the third harmonic component during
different loading conditions the setting for 100% stator E/F will be
decided presently it kept disable.

5. GT over fluxing protection (V/Hz protection)


Original setting V/Hz = 2.53
New setting
Alarm V/Hz alarm = 2.35 V/Hz
Alarm delay = 3.5 sec
Trip function IDMT
V/Hz set = 2.4 V/Hz, TMS = 4
Trip time t = 0.8+0.18*TMS/(M-1)2

M = V/Hz actual/V/Hz set


6. Gen voltage protection
a) Generator under voltage protection

PAGE 14 OF 58
only alarm is given for generator under voltage and set at 80% of
the rated voltage
V<1 voltage set = 88 V, with delay 1 sec
b) Generator over voltage protection stage-I
V>1 voltage set at 121 V (10% over voltage)
V>1 time delay 5 sec
c) Generator over voltage protection stage-II
V>2 voltage set at 127 V (15% over voltage)
V>2 time delay 500 msec
7. Gen frequency protection
a) Generator under frequency alarm
F<1 set = 48 Hz
F<1 time delay = 1 sec
b) Generator under frequency trip
F<2 set = 47 Hz
F<2 time delay = 500 msec
c) Generator over frequency alarm
F>1 set = 51.5 Hz
F>1 time delay = 1 sec
d) Generator over frequency trip
F>2 set = 52.5 Hz
F>2 time delay = 1 sec
Actual settings done and final PSL attached in Annexure C

PAGE 15 OF 58
Conventional Relay Settings and Testing Report
(Not Included in P343)
1. Check synchronization relay
Model No. : SKE11BF550 3B(M)
Sr. No. : M837347
Rated Voltage: 63.5/110 Vac, 50Hz
<α: +/- 200
Aux Supply: 220 Vdc
▲v setting: 5%
t- Set: 0.5Sec
Relay Testing
▲v Checking:
a. Applied V1 Voltage (5 & 7) = 110V (fixed)
Variable Voltage applied V2 (8 & 10)
Relay Picks up at 104 V
Relay Drops Out at 102 V
b. Applied V2 Voltage (8 & 10) = 110V (fixed)
Variable Voltage applied V2 (5 & 7)
Relay Picks up at 106 V
Relay Drops Out at 104 V
<α Checking
V1 and V2 applied voltage = 110 V
Phase difference between V1 & V2 Varied and observed
Relay operates from -200 to +200
2. Reverse Power Protection Relay
Relay Type WCD12BF2026A5
Sr. No. 115084J
Testing Procedure:
 Apply 3 Phase balanced Currents 180 degree to 3 phase applied
balanced voltage
 Voltage Applied = 63.5 V (Phase to Neutral)
 Go on increasing current till relay operates
 Relay operated at 11 mA, Drop out 9mA

PAGE 16 OF 58
 Electrical Reverse Power delay 10.399 Sec ( set 10 Sec)
 Mechanical Reverse Power delay 2.037 Sec ( set 2 Sec)
3. UAT Diff Protection (87UAT)
Relay Type: RADSB
RA3:D1:101
101:RXTP18, 107: RXTUG 2H, 113:RTQTB60 In= 1A, 119:RTQTB61 In=1A,
125:RXDSB-4, 137:RXMS-1, 337:RXSGA-1
Setting Range:
3Id /I > Isr = (0.2,---------,0.5) In
3 Id >> Isu = (8, 13, 20) In
Adopted Setting:
3Id /I > Isr = 0.2* In = 0.2 A
3 Id >> Isu = 8* In = 8 A
Relay Testing Report
Operational Test
Phase Current Injected Pick Up Expected
Between (A)
R 3 – 12 0.207 0.2
phase
Y phase 4 - 13 0.21 0.2
B phase 5 - 14 0.205 0.2
3 Phase 0.284 0.34

Through Current Restrain Checking


Phase Current Injected at Ia Ib Id % Bais
R Ia = 3, Ib = 6, Id = 0. 0.53 0.26 39.34
phase
12 8 7 3
R Ia = 3, Ib = 6, Id = 1. 0.69 0.31 36.68
phase
12 0
Y phase Ia = 4, Ib = 7, Id = 0. 0.54 0.26
13 8 0 0 38.80597
Y phase Ia = 4, Ib = 7, Id = 1. 0.68 0.31
13 0 9 1 36.82652
B phase Ia = 5, Ib = 8, Id = 0. 0.54 0.25
14 8 6 4 37.74146
B phase Ia = 5, Ib = 8, Id = 1. 0.69 0.30
14 0 8 2 35.57126
3phase 1. 0.61 0.38 47.37168

PAGE 17 OF 58
0 7 3
% Bais = 100*Id/(Ib + 0.5*Id)
4. UAT 95% Earth Fault Protection.(64UAT)
RA3:D1:101
101:RTXP18, 107: RXIG 28, 307:Filter Unit, 119:RXKB1, 319:RXSF-1
Setting Range: (1,-------,3)*5 V
Time Setting Range: (00—99)* 10 msec
Adopted Setting: 6V, 1 Sec Delay
Relay Testing Report
Voltage Applied Between: 9 & 10
Pick Up Value: 6.1 V
Drop Out Value: 6.0 V

5. UAT HV Over Current Protection (50/51 UAT)


Relay Type: CDG61 EG 111ZMCH
Sr. No.: 130534770409002
In: 5A
Setting Range:
PS: (2.5, 3.75, 5, 6.25, 7.5, 8.75, 10) A
Inst: LK1 (50* K), LK2 (25*K), LK3 (12.5* K): K: (1.2 -----2)
Setting Adopted:
PS: 5 Amp, TMS: 1
Inst: LK2(25), K= 1.6, = 40A
Relay Testing Report
Instantanious Element Test
Phas Settin Actual Expected Value
e g Value
R 40 A 40 A 40 A
Y 40 A 40.5 A 40 A
B 40 A 40 A 40 A

Induction Pick Up Test


Phas Settin Pick Drop Expected
e g Up Out
R 5A 5.0 A 4.98 A 5A
Y 5A 5A 4.99 A 5A

PAGE 18 OF 58
B 5A 5.03 A 4.98 A 5A

Charectristic Checking
Phas Settin Current Expected trip Actual Trip Time
e g Injected time
R 5A 10 A 3.85 Sec 3.92 Sec
Y 5A 10 A 3.85 Sec 3.95 Sec
B 5A 10 A 3.85 Sec 3.77ec

6. Voltage Balance Scheme (60G)


RA3:D25:101
101:RTXP18 Test switch
107, 119, 131: RXEG21 Metering PT
307, 319, 331: RXEG21 AVR PT
507, 519, 531: RXEG21 Protection PT
Setting Range: (1-------3)*40 V
Relay Pick Drop Out
up
Metering 48.8 V 47.8 V
R
Metering Y 48.0 V 46.9 V
Metering B 48.5 V 47.6 V
AVR R 43.6 V 42.7 V
AVR Y 42.9 V 42.10 V
AVR B 42.6 V 41.6 V
PROT R 45.5 V 44.5 V
RROT Y 44.5 V 43.7 V
PROT B 45.7 V 44.7V

7. Over all Diff Protection (87GT)


Relay Type: RADSB
RA3:D1:101
101:RXTP18, 107: RXTUG 2H, 113:RTQTB60 In= 5A, 119:RTQTB61 In=5A,
125:RXDSB-4, 137:RXMS-1, 337:RXSGA-1
Setting Range:

PAGE 19 OF 58
3Id /I > Isr = (0.2,---------,0.5) In
3 Id >> Isu = (8, 13, 20) In

Adopted Setting:
3Id /I > Isr = 0.2* In = 1.0 A
3 Id >> Isu = 8* In = 40 A
Relay Testing Report
Operational Test
Phase Current Injected Pick Up Expected
Between (A)
R 3 – 12 1.02 1.0
phase
Y phase 4 – 13 0.99 1.0
B phase 5 – 14 1.014 1.0
3 Phase 1.406 1.7

Through Current Restrain Checking


Phase Current Injected at I Ib Id % Bais
a
R Ia = 3, Ib = 6, Id = 5 3.4 1.5
phase
12 1 9 37.81213
R Ia = 3, Ib = 6, Id = 4 2.6 1.3
phase
12 9 1 39.16293
Y phase Ia = 4, Ib = 7, Id = 5 3.5 1.4
13 2 8 34.74178
Y phase Ia = 4, Ib = 7, Id = 4 2.7 1.2
13 9 1 35.64065
B phase Ia = 5, Ib = 8, Id = 5 3.5 1.4
14 3 7 34.46659
B phase Ia = 5, Ib = 8, Id = 4 2.7 1.2
14 6 4 36.68639
3phase 5 3 2 50
% Bais = 100*Id/(Ib + 0.5*Id)
8. GT Restricted Earth Fault Protection(64GT)
Relay Type RADHD
RA4:D5:101
101:RTXP18, 107:RXTLA1, 113:RXTCA1, 307:RXID1, 313:RXSF1
Setting: 97 V fixed

PAGE 20 OF 58
Relay Testing Report
Voltage Applied Between: 3&4
Pick Up Value: 93.5 V; (17.9 mAmp)
Drop Out Value: 70.2 V; (13.3 mAmp)

PAGE 21 OF 58
GEN PROTECTION TESTING REPORT DURING ANNUAL OVERHOUL OF UNIT-
4 Dec -2007

Relay testing report


Gen Protection Relay P343 Main

Relay Sr. No 072605C


Current Injected at RA1: TTB1 FOR R,Y,B & N respectively except for
diff. protection
Voltage Injected at out terminals of PT fuses for the relay
1. Generator Differential Protection

Phas Setting Operating Value


e Adopted
R 250 mA 250 mA
250 mA 250 mA
250 mA 250 mA

2. Generator Reverse Power Protection.

Setting Operating Value Remark


Adopted
-P>1 Pick-Up Drop -Out 3 Phase Nominal
-5.72 MW -5.76 MW -5.35 MW Voltage Injected (63.5 V)
(20 Watt) (0.106A) (0.099 A)

Time Delay Checking


Set Actual Value Remark
Delay
10 Sec 10.0463 Without 86TT
Sec
1 Sec 1.048 With 86TT

3. Generator Low Forward Power Protection.

Setting Adopted Operating Value Remark


P>2 • Relay Tested with 86TT operated
5.72 MW 5.657 MW Actual delay 2.048 Sec (set 2 Sec)
• 3 Phase Nominal Voltage Injected
(63.5 V)

Field Failure Protection.


4.
 Alarm Checking

Setting Adopted Operating Value Remark


25 Degree 25.09 Degree Checked in both generating and
(Lead) (lead) Motoring mode

PAGE 22 OF 58
 FF1 settings
Xa1 = 2.1 ohm
Xb1 = 30.2 ohm

 OB = Xa1 + Xb1 = 2.1 + 30.2 = 32.23 ohm


 OA = Xa1 = 2.1 ohm
 Test Procedure:
Checking of Point “B”
1. Apply 3 Phase balanced Currents 90 degree leading to 3 phase
applied balanced voltage
2. Voltage Applied = 63.5 V (Phase to Neutral)
3. Go on increasing current till relay operates
4. Relay operated at 1.98 A
5. Actual X =63.5 /1.98 = 32.075 ohm
Checking of Point “A”
6. Apply 3 Phase balanced Currents 90 degree leading to 3 phase
applied balanced voltage
7. Currents Applied = 5.3 A
8. Go on increasing Voltage till relay operates
9. Relay operated at 11.15 V (Phase to Neutral)
10. Actual X =11.15 / 5.3 = 2.10 ohm
11. Delay Checked actual delay 2.0248 sec (Set at 2 Sec)

5. Gen Negative Phase Sequence Protection

 Settings Adopted:
I2 > 1 Alarm
I2 > 1 Current Set = 200 mA
I2 > 1 Time Delay = 2 Sec.
I2 > 2 Trip
I2 > 2 Current Set = 250 mA.
I2 > 2 K Setting = 6.5 Sec.
I2 > 2 K Reset = 6.5 Sec

 Alarm Checking

PAGE 23 OF 58
Single Phase Current injection
Iinj = I2/ 0.577
Expected Iinj = 200/0.577 = 346.6 mA

Phase Setting Adopted Expected Value Operating Value Desk Meter


R-Y 200 mA 346.6 mA 350 mA(I2 403.1A) 4.4%
Y-B 200 mA 346.6 mA 350 mA(I2 403.4A) 4.4%
B-R 200 mA 346.6 mA 350 mA(I2 402.5A) 4.4%

 Trip Time Checking


T = - K (ln (1-((I2 Set)*( I2 Set)/(I2*I2))
I2 Set* I2 Set

T= time in sec.
K = K set = 5.7 Sec
I2 = Actual I2 in P.U.
I2 Set = I2 st in p.U. = 0.06
Trip Timing for 20% I2
T= -(5.7/0.06*0.06)ln(1-(0.06*0.06/0.2*0.2))
T = - (1583.34)ln(1-(0.09))
T = 149.3 Sec.
Current Injected for 20% I2 = 5*0.2/0.577
= 1.73A

Actual Time = 148.18 Sec.


6. Under Impedance Protection:
 Settings Adopted:
Z < 1 set = 17 ohm
Z < 2 set = 3 ohm

 Test Procedure for Z1:


1. Apply 3 Phase balanced Currents & 3 phase applied balanced
voltage

PAGE 24 OF 58
2. Voltage Applied = 63.5 V (Phase to Neutral)
3. Go on increasing current till relay operates
4. Relay operated at 6.5 A
5. Actual X = 63.5*1.73 / 6.5 = 16.92 ohm
6. Delay actul 5.0242 Sec (Set at 5 Sec)
 Test Procedure for Z2:
7. Apply 3 Phase balanced Currents & 3 phase applied balanced
voltage
8. Current injected Applied = 5A
9. Go on decreasing voltage till relay operates
10. Relay operated at 8.6 V
11. Actual X = 8.6*1.73 / 5 = 2.98 ohm
12. Delay actul 2.5429 Sec (Set at 2.5 Sec)
7. Thermal Over load:
 Settings Adopted:
Thermal I> 5.05
Thermal Alarm = 90%
T Heating = 7 min
T cooling = 7 Min
M factor = 3
Ieq = SQR(I1*I1 + 3 *I2*I2)
 Testing Procedure:
Single phase injection
Current injected Between R & B Phases
I1 = 0.577 Iinj.
I2 = 0.577 Iinj.
Ieq = 1.154 Iinj
t = T ln(((Ieq*Ieq)-(Ip*Ip))/(( Ieq*Ieq)- (th Set* Ith Set)))
t = 7 ln(((1.154Iinj*1.154Iinj)-(0)/(( 1.154Iinj*1.154Iinj)-(5.05*5.05)))
For Iinj = 5 A
t = 609.96 sec
Actual time = 609.6262 Sec

8. GT over fluxing Protection:


 Setting adopted:
V/Hz Alarm = 2.352
V/Hz Trip Function IDMT
V/Hz Trip Set = 2.4
TMS = 4

 V/Hz Trip Alarm Checking


Apply 3 Phase Balanced Voltage = 63.5 V (Phase to Neutral)
Go on reducing frequency till relay operates
Actual Value = 46.76 Hz
Actual V/Hz = 63.5*1.73/46.76 = 2.35212
 Trip time Characteristic Checking
t = 0.8 + 0.18*TMS/(M-1)*(M-1)
M = V/Hz (actual)
V/Hz (set)

PAGE 25 OF 58
V (phase to phase) Hz Expected time Actual Time
135V 45 12.32 Sec 12.35 Sec
138.56V 40 4.46 Sec 4.54 Sec

9. Voltage Protection:
 Over Voltage Protection Stage 1
Settings Adopted
V>1 set = 121 V
Actual Value: Pick up = 121.07 V, Drop out = 118.57 V
Actual delay 5.045 Sec (Set at 5.0 Sec)
 Over Voltage Protection Stage 2
Settings Adopted
V>2 set = 127 V
Actual Value: Pick up = 127.01 V, Drop out = 124.24 V
Actual delay m Sec (Set at 500 m Sec)

10. Frequency Protection:


 Under Frequency Alarm
Settings Adopted
F<1 set = 48 Hz
Actual Value = 48 HZ
Drop out = 48.03 Hz
Actual delay 1.178 Sec (Set at 1.0 Sec)
 Under Frequency Trip
Settings Adopted
F<2 set = 47 Hz
Actual Value = 47 HZ
Drop out = 47.03 Hz
Actual delay 717 mSec (Set at 500 mSec)
 Over Frequency Alarm
Settings Adopted
F>1 set = 51.5 Hz
Actual Value = 51.5 HZ
Drop out = 51.47 Hz
Actual delay 1.1544 Sec (Set at 1.0 Sec)
 Over Frequency Trip
Settings Adopted
F>2 set = 52.5 Hz
Actual Value = 52.51 HZ
Drop out = 52.47 Hz
Actual delay 1.21 Sec (Set at 1.0 Sec)
11. Gen Over Current Trip
Settings Adopted
I>1 set = 6.1 Amp
Actual Value = 6.1 Amp
Drop out = 5.77 Amp
Actual delay 40.05 Sec (Set at 40Sec)
12. 95% Stator Earth Fault Protection
Settings Adopted

PAGE 26 OF 58
Vn>1 set = 6.0 Volt
Actual Value = 6.02 Volt
Drop out = 5.71 volt
Actual delay 1.05 Sec (Set at 1Sec)

PAGE 27 OF 58
Gen Protection Relay P343 Redundant

Relay sr. No. 130504130351001


Current Injected at RA1 TTB 4 FOR R,Y,B & N respectively except for
Inter turn protection
Voltage Injected at Out terminals of PT fuses for the relay

13. Generator Inter Turn Protection

Phase Setting Operating Drop Out Delay


Adopted Value
250 mA 253 mA 241 mA 1.01 Sec (set at 1 Sec)
(253 A) (241A)
250 mA 253 mA 241 mA 1.04 Sec (set at 1 Sec)
(253 A) (241A)
250 mA 253 mA 241 mA 1.04 Sec (set at 1 Sec)
(253 A) (241A)

14. Gen Over Current Trip


Settings Adopted
I>1 set = 6.1 Amp
Actual Value = 6.1 Amp
Drop out = 5.79 Amp
Actual delay 40.053
Sec (Set at 40Sec)

15. Generator Reverse Power Protection.

Setting Operating Value Remark


Adopted
-P>1 Pick-Up Drop -Out 3 Phase Nominal
-5.72 MW -5.73 MW -5.32MW Voltage Injected (63.5 V)
(20 Watt) (0.105A) (0.098)

Time Delay Checking


Set Actual Value Remark
Delay
10 Sec 10.0143 Without 86TT
Sec
1 Sec 1.047 With 86TT

16. Generator Low Forward Power Protection.

Setting Adopted Operating Value Remark


P>2 Relay Tested with 86TT operated
5.72 MW 5.625 Actual delay 2.041 Sec (set 2 Sec)
MW( 0.103
mA)

PAGE 28 OF 58
17. Field Failure Protection.
 Alarm Checking

Setting Adopted Operating Value delay


25 Degree 25.07 Degree Actual delay 1.05 Sec (set at 1
(Lead) (lead) Sec)

 FF1 settings
Xa1 = 2.1 ohm
Xb1 = 30.2 ohm

 OB = Xa1 + Xb1 = 2.1 + 30.2 = 32.23 ohm


 OA = Xa1 = 2.1 ohm
 Test Procedure:
Checking of Point “B”
1. Apply 3 Phase balanced Currents 90 degree leading to 3 phase
applied balanced voltage
2. Voltage Applied = 63.5 V (Phase to Neutral)
3. Go on increasing current till relay operates
4. Relay operated at 1.972 A
5. Actual X =63.5 /1.972 = 32.2 ohm
Checking of Point “A”
6. Apply 3 Phase balanced Currents 90 degree leading to 3 phase
applied balanced voltage
7. Currents Applied = 5.3 A
8. Go on increasing Voltage till relay operates
9. Relay operated at 11.15 V (Phase to Neutral)
10. Actual X =11.143 / 5.3 = 2.10 ohm
11. Delay Checked actual delay 2.06 sec (Set at 2 Sec)

18. Gen Negative Phase Sequence Protection

 Settings Adopted:
I2 > 1 Alarm :

PAGE 29 OF 58
I2 > 1 Current Set = 200 mA
I2 > 1 Time Delay = 2 Sec.
I2 > 2 Trip:
I2 > 2 Current Set = 250 mA.
I2 > 2 K Setting = 6.5 Sec.
I2 > 2 K Reset = 6.5 Sec

 Alarm Checking

Single Phase Current injection


Iinj = I2/ 0.577
Expected Iinj = 200/0.577 = 346.6 mA

Phase Setting Adopted Expected Value Operating Value Remark


R-Y 200 mA 346.6 mA 349 mA(I2 402.5A)
Y-B 200 mA 346.6 mA 349 mA(I2 402.5A)
B-R 200 mA 346.6 mA 349 mA(I2 402.5A)

 Trip Time Checking


T = - K (ln (1-((I2 Set)*( I2 Set)/(I2*I2))
I2 Set* I2 Set

T= time in sec.
K = K set = 5.7 Sec
I2 = Actual I2 in P.U.
I2 Set = I2 st in p.U. = 0.06
Trip Timing for 20% I2
T= -(5.7/0.06*0.06)ln(1-(0.06*0.06/0.2*0.2))
T = - (1583.34)ln(1-(0.09))
T = 149.3 Sec.
Current Injected for 20 I2 = 5*0.2/0.577
= 1.73A

Actual Time = 148.24 Sec.


19. Under Impedance Protection:
 Settings Adopted:
Z < 1 set = 17 ohm
Z < 2 set = 3 ohm

PAGE 30 OF 58
 Test Procedure for Z1:
1. Apply 3 Phase balanced Currents & 3 phase applied balanced
voltage
2. Voltage Applied = 63.509 V (Phase to Neutral)
3. Go on increasing current till relay operates
4. Relay operated at 6.48 A
5. Actual X = 63.509*1.73 / 6.48 = 16.97 ohm
6. Delay actul 5.035 Sec (Set at 5 Sec)
 Test Procedure for Z2:
7. Apply 3 Phase balanced Currents & 3 phase applied balanced
voltage
8. Current injected Applied = 5A
9. Go on decreasing voltage till relay operates
10. Relay operated at 8.66 V
11. Actual X = 8.66*1.73 / 5 = 2.99 ohm
12. Delay actul 2.53 Sec (Set at 2.5 Sec)

20. GT over fluxing Protection:


 Setting adopted:
V/Hz Alarm = 2.352
V/Hz Trip Function IDMT
V/Hz Trip Set = 2.4
TMS = 4

 V/Hz Trip Alarm Checking


Apply 3 Phase Balanced Voltage = 63.509 V (Phase to Neutral)
Go on reducing frequency till relay operates
Actual Value = 46.78 Hz
Actual V/Hz = 63.509*1.73/46.78 = 2.3514
Delay 3.75 sec (set at 3.5sec)
 Trip time Characteristic Checking
t = 0.8 + 0.18*TMS/(M-1)*(M-1)
M = V/Hz (actual)

PAGE 31 OF 58
V/Hz (set)

V (phase to phase) Hz Expected time Actual Time


135V 45 12.32 Sec 12.41 Sec
138.56V 40 4.46 Sec 4.55Sec

21. Voltage Protection:


 Over Voltage Protection Stage 1
Settings Adopted
V>1 set = 121 V
Actual Value: Pick up = 121.01 V, Drop out = 118.59 V
Actual delay 5.1 Sec (Set at 5.0 Sec)
 Over Voltage Protection Stage 2
Settings Adopted
V>2 set = 127 V
Actual Value: Pick up = 127.02 V, Drop out = 124.46 V
Actual delay 552 m Sec (Set at 500 m Sec)

22. Frequency Protection:


 Under Frequency Alarm
Settings Adopted
F<1 set = 48 Hz
Actual Value = 47.99 HZ
Drop out = 48.04 Hz
Actual delay 1.178 Sec (Set at 1.0 Sec)
 Under Frequency Trip
Settings Adopted
F<2 set = 47 Hz
Actual Value = 47 HZ
Drop out = 47.03 Hz
Actual delay 740 mSec (Set at 500 mSec)
 Over Frequency Alarm
Settings Adopted
F>1 set = 51.5 Hz
Actual Value = 51.5 HZ
Drop out = 51.47 Hz
Actual delay 1.1544 Sec (Set at 1.0 Sec)
 Over Frequency Trip
Settings Adopted
F>2 set = 52.5 Hz
Actual Value = 52.51 HZ
Drop out = 52.47 Hz
Actual delay 1.21 Sec (Set at 1.0 Sec)
23. Thermal Over load:
 Settings Adopted:
Thermal I> 5.05
Thermal Alarm = 90%
T Heating = 7 min
T cooling = 7 Min

PAGE 32 OF 58
M factor = 3
Ieq = SQR(I1*I1 + 3 *I2*I2)
 Testing Procedure:
Single phase injection
Current injected Between R & B Phases
I1 = 0.577 Iinj.
I2 = 0.577 Iinj.
Ieq = 1.154 Iinj
t = T ln(((Ieq*Ieq)-(Ip*Ip))/(( Ieq*Ieq)- (th Set* Ith Set)))
t = 7 ln(((1.154Iinj*1.154Iinj)-(0)/(( 1.154Iinj*1.154Iinj)-(5.05*5.05)))
For Iinj = 5 A
t = 609.96 sec
Actual time = 609.942 Sec

24. 95% Stator Earth Fault Protection


Settings Adopted
Vn>1 set = 6.0 Volt
Actual Value = 6.02 Volt
Drop out = 5.71 volt
Actual delay 1.05 Sec (Set at 1Sec)

PAGE 33 OF 58
Alarm and trip protection trial protocol:
Date

Annunciation and Protection Tripping Trials


After completion of generator protection panel wiring work following
annunciation and protection trials taken in presence of operation staff

1. Gen protection DC fail


P343M/M11-M12 OK
P343R/ M11-M12 OK
+B Failed (Remove fuse) OK
+T Failed (Remove fuse) OK
+GT Failed (Remove fuse) OK
+G Failed (Remove fuse) OK
+TT Failed (Remove fuse) OK
2. Gen Differential Trip
P343M/K3-K4 OK
3. Gen. Interturn Protection Trip
P343R/ K3-K4 OK
4. Gen Stator E/F Trip
P343M/J9 – J10 OK
P343R/ J9 – J10 OK
5. Gen Over Voltage Protection Trip
P343M/J7 – J8 OK
P343M/J7 – J8 OK
6. Gen NPS Trip
P343M/L11-L12 OK
P343R/H15-H14 OK
7. GT Over Fluxing Trip
P343M/H1 – H2 OK
P343R/ H1 – H2 OK
8. Gen Backup Impedance Protection Trip
P343M/J15 –J14 OK
P343R/ J15 –J14 OK
9. Gen Loss of Excitation Trip
P343M/K1-K2 OK
P343R/K1-K2 OK
10. Gen RPP Trip
P343M/K5-K6 OK
P343R/ K5-K6 OK
WCD /1-2 OK
Observe Master trip operation 86GT OK
WCD/11-12+86TT operated OK
Observe Master trip operation 86GT OK
11. Gen Frequency Trip (U/F or O/F)
P343M/K7-K8 OK
P343R/ K7-K8 OK

PAGE 34 OF 58
12. Gen Thermal O/L or O/C Trip
P343M/K9-K10 OK
P343R/ K9-K10 OK
13. Gen LPF Trip
P343M/H5 – H6 OK
P343R/ H5 – H6 OK
14. Gen Over Current Alarm
P343M/K14-K15 OK
P343R/K14-K15 OK
15. Gen RPP Plain
P343M/K17-K18 OK
P343R/K17-K18 OK
16. Gen NPS Alarm
P343M/J1-J2 OK
P343R/J1-J2 OK
17. Gen Over Voltage Alarm
P343M/J3 – J4 OK
P343R/J3 – J4 OK
18. Gen Under Frequency Alarm
P343M/J5-J6 OK
P343R/J5-J6 OK
19. Gen Over Frequency Alarm
P343M/J11-J12 OK
P343R/ J11-J12 OK
20. Gen Over Fluxing Alarm
P343M/H3 – H4 OK
P343R/H3 – H4 OK
21. Gen Under Excitation Alarm / Under Voltage Alarm
P343M/H7 – H8 OK
P343R/H7 – H8 OK
22. Gen CT/ VT Fail
P343M/H9 – H10 OK
P343R/H9 – H10 OK
23. P343M/L1-L2 (R1 Class A Trip)
Master trip operation 86G OK
Alarm OK
24. P343R/L1 – L2 (R1 Class A Trip)
Master trip operation 86T OK
Alarm OK
25. P343M/L3-L4 (R2 Class B Trip)
Master trip operation 86B OK
Alarm OK
26. P343R/ L3-L4 (R2 Class B Trip)
Master trip operation 86B OK
Alarm OK
27. Gen Rotor E/F AC Fail
Make AC supply off(SF96) OK
28. Gen Rotor E/F
Short ( RA2/X4/101 -104) and observe
Rotor E/F Stage II Operated OK

PAGE 35 OF 58
Rotor E/F Stage II Operated OK
Master Trip Relay 86GT Operated OK
29. Gen Rotor E/F Protection Out
Put the switch on +/- to Earth OK
30. UAT Oil Temp Alarm
Short RA3/X4/114 -115 OK
31. UAT Oil Temp Trip
Short RA3/X4/116 -117 OK
Master Trip Relay 86GT Operated OK
32. UAT Winding Temp Alarm
Short RA3/X4/112-113 OK
33. UAT Winding Temp Trip
Short RA3/X4/110 -111 OK
Master Trip Relay 86GT Operated OK
34. UAT Differential Trip
Short RA3:D1:101:125:421 -425
Master trip operation 86GT OK
Alarm OK
35. Excitation Class A Trip
Short RA3/X4/105 -106
No alarm only operation of 86GT OK
36. UAT Buccholz Alarm
Short RA3/X4/108-109 OK
37. UAT Buccholz Trip
Short RA3/X4/108 -107 OK
Master Trip Relay 86GT Operated OK
38. UAT Over Current Trip OK
Master trip operation 86GT OK
39. Serious Turbine Faults
Short RA3/X4/118 – 119
No alarm only operation of 86GT OK
40. GT R/E/F Trip
For Alarm 307:17 - 18 OK
For Trip 307:15 -25Master trip operation 86GT OK
41. GT Buccholz Alarm
Short RA4/X4/101-103 OK
42. GT Buccholz Trip
Short RA4/X4/102 -104 OK
Master Trip Relay 86GT Operated OK
43. GT HV Back Up Over Current Trip OK
44. GT Winding Temp Alarm
Short RA4/X4/105-109 OK
45. GT Winding Temp Trip
Short RA4/X4/106 -110 OK
Master Trip Relay 86GT Operated OK
46. GT Oil Temp Alarm
Short RA4/X4/107 -111 OK
47. GT Oil Temp Trip
Short RA4/X4/108 -112 OK
Master Trip Relay 86GT Operated OK

PAGE 36 OF 58
48. GT PRV Operated Trip
Short RA4/X4/116 -117 OK
Master Trip Relay 86GT Operated OK
49. GT Overall Differential Trip OK
Short RA3:D1:101:125:421 -425
Master trip operation 86GT OK
Alarm OK
50. Gen LBB Operated
Short 331:23 -24 OK
51. 220 KV Bus Bar Protection Operated
Operate 96L manually and observe
Alarm OK
Master trip operation 86T OK
52. Excitation Class B Trip
Short RA3/X4/131 -132
No alarm only operation of 86B OK
53. Stator Water Conductivity Very High
Short RA3/X4/133 -134
No alarm only operation of 86B OK
54. UAT 95% E/F protection
Short 107:118 -117 only Alarm OK
55. Stator Water Flow very low
Short RA5/X4/191 -192 (delayed)
No alarm only operation of 86B OK
56. Oil Level in damper tank very low
Short RA5/X4/194 -193 (delayed)
No alarm only operation of 86B OK
57. Metering PT fuse Fail
Short 307:117 – 118 OK
58. AVR PT fuse Fail
Short 507:117 – 118 OK
59. Protection PT fuse Fail
Short 107:227 – 228 OK
60. Operation of 86TT
Short RA3/X4/165 -166
Alarm OK
Gen 220 KV Breaker Protection and ON/OFF Trials

1. Breaker Local ON-OFF trial taken stood OK


2. Breaker remote ON-OFF trial taken OK
3. Synchronization circuit interlocking checked OK
4. Breaker closed and tripped on
generator differential protection through P343M relay.(86G) OK
Gen. Interturn Protn through P343R relay. (86T) OK
Gen. RPP by shorting WCD /1 – 2 (86GT) OK

Sd/- Sd/-

Gen. Desk Operator JE (Testing II)

PAGE 37 OF 58

220 KV Back Charging Activity for Synchronizing


circuit checking for unit 4
Date: 08/01/2008

• GT HV Links removed

• 220 KV isolators 29AL, 29DL Closed

• Gen 220 KV breaker closed.

• Synchroscope showing 12 o clock Position Ok

• Delta V showing 4%

• Check Synchro lamp showing clearance Ok

• PT Voltages measured at SKE relay

Termina Voltage
l

5–7 105

8 - 10 108

Breaker tripped on 86T master trip operation through P343R

AE(Test – II) Operation Unit 4

PAGE 38 OF 58
GT local panel annunciation trials
Unit #4
Date 12/01/2008
Sr Operation Remark
n
o
1 GT Buccholz alarm Ok
(By shorting 1T 35 – 1T 36 in marshaling box )
2 GT Buccholz trip Ok
(By shorting 1T 34 – 1T 33 in marshaling box )
3 GT HV winding temp high alarm Ok.
By operating WTI 94o C
4 GT HV winding temp high trip Ok.
By operating WTI 106o C
5 GT LV winding temp high alarm Ok.
By operating WTI 94o C
6 GT LV winding temp high trip Ok.
By operating WTI 106o C
7 GT oil temp high alarm Ok
By operating OTI 84o C
8 GT oil temp very high trip Ok
By operating OTI 95o C
9 GT PRV operated Ok.
(By shorting 1T 29 – 1T 30 in marshaling box )
(By shorting 1T 31 – 1T 32 in marshaling box )
1 GT conservator oil level low Ok
2 (By shorting 1T 37 – 1T 38 in marshaling box )
1 A) Pumps start and stop from local when Ok
3 selection is on local
Ok
B) Pumps start and stop from MCC when
selection is on MCC

C) Pumps selected on remote Ok


I) Pump selected on manual mode Ok
a) Pump A Start and Stop
b) Pump B Start and Stop
c) Pump A RUN and Pump B STANDBY selected
Pump A
get started on wdg temp 54 degree
d) Pump B RUN and Pump A STANDBY selected
Pump B Ok
get started on wdg temp 54 degree
Ok
II) Pump selected on auto mode
a) Both Pumps pickup along with pump ON Ok
annunciation at Ok
HV wdg temp 85 o C and dropout at 78o
C
b) Both Pumps pickup along with pump ON
annunciation at
LV wdg temp 85 o C and dropout at 78o
C
c) Stand by Pump pickup when selected
pump dropout
d) Select Pump gets ON when FB ON
contact simulated

PAGE 39 OF 58
PAGE 40 OF 58
UAT local panel annunciation trial
Unit #4
Date Jan 12, 2008

Sr Operation Remark
n
o
1 Power supply trial Ok
Both main & standby supply made ON from
turbine board
a) Main supply switch made OFF (in Marshaling
box)
Found supply changeover to standby after 20
sec. b) Main supply made ON
Found supply changeover to main after 20 sec.

2 Control Supply trial


Normal supply fed from CCT-I (415/240 V) Ok
a) Remove CCT I fuse (in Marshaling box) and
observe supply change over to CCT-II
b) Put CCT I fuse (in Marshaling box) and
observe supply change over to CCT-I

3 Manual mode cooling fan trial Ok


Fan No. 3, 5 and 6 stars directly irrespective of
selection as it is having only MCB

4 Auto mode Fan trial by operating HV WTI Ok.


manually
Selector switch kept on auto
Fans 1, 2 & 4 get started at 58 degrees
Fans 1, 2 & 4 get stopped at 48 degrees
5 UAT Buccholz alarm Ok.
( short TB T2 – T3 in Marshaling box )
6 UAT Buccholz trip Ok
( short TB T2 – T1 in Marshaling box )
7 UAT LV winding temp high alarm Ok
By operating WTI 95o C
( T11- T12 )
8 UAT LV winding temp very high trip Ok.
By operating WTI 105o C
( T13- T14 )
9 UAT oil temp-high alarm Ok
By operating OTI 84o C
( T5- T6 )
1 UAT Oil temp very high trip Ok
0 By operating OTI 90o C
( T7- T8 )
1 UAT Conservator oil level low Ok
1 ( short TB T15 – T16 in Marshaling box )

PAGE 41 OF 58
Generator Testing
1. Generator winding resistance measurement
Phase R-N Y-N B-N R-Y Y-B B-R

Resistance in 1.773 1.776 1.743 3.42 3.39 3.394


milliohm 2 9 2 6 1

2. Generator HV Testing:
Taken by M/S Mahale, Pune

a. IR Test before HV test:

IR Value measured by Evershed Megger with 1KV

Phas IR15 IR60 IR600 PI


e

R 2000 5000 19000 3.8


Mohm Mohm Mohm

Y 1800 4900 17000 3.46


Mohm Mohm Mohm

B 1900 4900 18000 3.67


Mohm Mohm Mohm

b. HV test with 16KV for 1min. Temp during test- 330

Phase R Y B

Leakage Current in milli 114 113 1120


amp 8 2

c. IR Test after HV test:

IR Value measured by Evershed Megger with 1KV

Phas IR15 IR60


e

R 1800 5000 Mohm


Mohm

Y 1700 5000 Mohm

PAGE 42 OF 58
Mohm

B 2000 5100 Mohm


Mohm

PAGE 43 OF 58
3. Rotor Impedance Test
Voltage Current Impedance (Z)
(Vac) (Iac)

26 10.8 2.407

49 19.3 2.538

74 26.5 2.792

100 32.9 3.0395

126 38.4 3.281

151 42.4 3.561

175 46.8 3.739

200 50.1 3.992

225 54 4.166

303 65.5 4.625

326 68.8 4.738

348 71.8 4.846

4. Rotor Resistance Test


Rotor Resistance = 93.89 milliohm at 300

Measured with motwane make micro-ohm meter

5. Transformer Testing:
After completion of maintenance works Gen. Transformer, UAT, Excitation Transformer tested for
confirming healthyness the test results are enclosed in annexture D

PAGE 44 OF 58
Dynamic testing
Modifications for dynamic testing
Following Modification done for Slow Built up / Dynamic Testing of Unit
No. 4 Generator

Excitation System:

1. HV Supply to Excitation Transformer: Removed the HV


Power connections of excitation transformer from 15.75 KV
bus bar and extended 6.6KV Power supply to excitation
transformer from unit bus.
2. Manual Pot Modification (To facilitate the excitation to
start from O V)

Spare digital reference unit UN8001 prepared with R1005 =


3.32 K (Original value 4.7 K) R1004 = 4.7K (Original value
3.32K)
This will facilitate manual UST at minimum position to –1V to
–2V
Rest of resistances and links kept as it is i.e. links
1006 – Closed 1007 – closed
& Resistances R1002 – Open R1003 – 53 K ohm
Replace existing man pot with above
3. AFR Unit Supply: 230Vac is separately extended to
19TY(n), 20TY from 10TY(n) & 11TY(p) respectively.
(Original wires coming from 275R &276R kept removed)
4. AR104 removed
To inhibit FFB closing & bypass the FF disturb protection.
5. Thyrister Fan Supply: Thyrister fan supply is extended
separately from EB through FF fuses. Remove outgoing
wires of FS107, FS108 & FS109. Remove internal wires of
34FF, 35FF &36FF. Extend 3 phase supply from FS107,
FS108 & FS109 to 34FF, 35FF &36FF respectively.
6. Tier fan supply: (To extend Station Supply to Tier Fans)4of
MCB6 is disconnected (wire No.) supply extended to 4 of
MCB6 from 4 of MCB3 T4 supply.
7. 17R and 18R looped to bypass GCB ON contact. (To
Extend Class B Tripping)
8. FB closing interlock ( To Extend 6.6 KV breaker ON
Interlock for FB closing)
Remove loop between FB36 & FB32 and connect wires
from 6.6KV breaker (Aux Contact ) 3A17 & 3A18 to FB36 &
FB32 respectively.
Rest of the FB closing interlocks are retained i.e. ULR reset,
Auto/Man pot at homming position.

PAGE 45 OF 58
9. 6.6KV Breaker protection to FB Tripping: (contact of
51R, Y, B , 86, 6.6KV breaker off, PB in FB cubical are
connected in parallel brought to 52FB, 53FB for FB tripping
Rest of the trippings kept as it is i.e. ULR, Remote PB,
Tripping on AR36.

10. 6.6KV breaker tripping: Spare contacts of AR35 relay


(AR3, AR4 ) extended to 6.6KV breaker tripping.

11. 6.6 KV Breaker closing:

12. UN2007 MCB mode OFF


13. Auto channel UN1001 racked out.
14. Thyrister fan supply fuse unit F25 isolated.
15. Cable schedule

PAGE 46 OF 58
PAGE 47 OF 58
After Slow built up modifications following trials / Tests Carried out
1. Man Ust Measurement
At Pot Position Min Ust = -1.71 V
At Pot Position Max. Ust = 2.093 V
2. Thyrister fan trials: All Thyrister Fan started and direction trials taken
stood OK.
3. Tier fan trial: Regulation supply made on and confirmed tier fan is
running.
4. 6.6 kv settings: CTR 100/5 inst set = 12.5 Amp, PSM = , TMS =
5. Excitation Transformer IR value Measurement
LV to Earth = 10 Mohm.
HV to Earth = 200 Mohm
Megger Voltage = 500V
6. FB & 6.6 KV feeder protection / Interlock / ON – OFF Trials taken and
found OK
7. Excitation transformer charged from 6.6 KV & Following
measurements taken
• Phase Sequence checked at trunking Cubical found OK
• Voltage measured at trunking cubical
VRY = 236 Vac
VYB = 235 Vac
VBR = 236 Vac
• Voltage measured at Regulation cubical
• Voltage measured at Manual Filter
1-2 = 155 Vac
2-3 = 154 Vac
3-1 = 154 Vac
• Voltage measured at VR1
2-3 = 155 Vac
3-4 = 154 Vac
4-2 = 155 Vac

• Voltage measured at tier Panel


RU08/ 74-75 = 158 Vac
75-76 = 158Vac
76-74 = 158 Vac
• Voltage measured at tier Panel
RU08/ 43-44 = 157 Vac
44-45 = 157 Vac
45-43 = 158 Vac

• Voltage measured at Final stage


Terminal TY TY TY TY4
RU12 1 2 3
10-11 160 160 160 160
11-12 159 159 159 159
12-10 160 160 160 160

PAGE 48 OF 58
8. Manual Channel DC Supplies Measurement
RU 08/ +15V = 15 Vdc
- 15V = - 14.8 Vdc
5V = 4.8 Vdc
UL = 18.8 Vdc
Ust = -1.71 Vdc
9. Final Stage DC Supplies Checking

Terminal TY1 TY2 TY3 TY4


RU12 30-7 5V 5.18 V 5.02 V 5.22 V
-8 15 V 15.03 vdc 15.06 V 14.65 V
-9 -15.13 V -15.15 V -15.25 V -15.4 V
-10 24.9 V 25.2 V 25.3v 25.3v

10. Dummy Load Testing of Excitation system taken as follows

Sr MAN Firing TY-I TY-II Y-III TY-IV Common


UST angle
degree Vdc Idc Vdc Idc Vdc Idc Vdc Idc Vdc Idc
-1.71 223.2 0V 50mA 5V 0.10 A 5V 0.10A 5V 0.06A
(min)
-1.33 208.8 13 V 0.26 14.75 0.26 A 14.75 0.26 A 15.2 V 0.275 11 V 0.22A
V A V V A
-0.93 201.6 22 V 0.4 A 22 V 0.4 A 22.6 0.4 A 22.6 V 0.4 A 19 V .35A
V V
-0.56 190.8 28.73 0.513 29.9 V 0.52 A 30 V 0.52 A 29.8 V .65 A 8V 0.71A
V A
0.00 V 180 38.1 0.625 47 V 0.88 A 47 V 0.88 A 48 V 0.89 A 47 V 0.88A
V A
+0.97 158.4 117.1 1.95 115.85 1.9 A 115.1 1.9 A 108 V 2.0 A 13 V .11A
V A V V
1.35 147.6 158.1 2.78 158.15 2.78 A 158 V 2.78 A 151 V 2.7 A 85 V 3.45A
5V A V
1.71 136.8 198.9 3.6 A 196.8 3.6 A 197 V 3.6 A 187 V 3.6 A 243 V 4.54A
V V
2.09 122.4 245 V 4.6 A 242 V 4.5 A 245 V 4.5 A 243 V 4.6 A 253 V 5.78A
(max)

Dynamic Testing of Generator:


Dynamic testing procedure is newly developed and ipmlemented in unit 4. The
detailed procedure is enclosed in Annexture E

TA set rolled and dynamic testing performed the detailed result of dynamic testing is
enclosed herewith in annexure E

PAGE 49 OF 58
Normalization and Synchronization:
• Normalized the modifications for dynamic testing.

• Protection trials and interlock trials of FB / excitation System is taken


satisfactory.

• Rolled the TA set to 3000 rpm and synchronized the unit No. 4 to the grid at
12.50 Hrs. on 05/02/2008.

On Load Measurements of Generator Parameters


After synchronization on load measurements are done. Print outs of the same are
enclosed in annexure E

Setting of 100% Stator Earth Fault:


Following table shows the measurement of 3rd Harmonic component of Gen.
Neutral voltage

Sr. Description 3rd Harmonic Remark


No. Voltage

1. Single Phase to Earth 10.25 v During Dynamic Testing


Fault

2. At 5 KV Gen Voltage 50.51 V During Open Circuit Test

3. At 7 KV Gen Voltage 69.46 V During Open Circuit Test

4. At 10 KV Gen Voltage 98.93 V During Open Circuit Test

5. At 15 KV Gen Voltage 124.2 V During Open Circuit Test

6. At 15.75 KV Gen Voltage 187.1 V During Open Circuit Test

7. At 7.812 MW 187.9 V After Synchronization

8. At 192 MW 526 V After Synchronization

PAGE 50 OF 58
According to above observations, 3rd Harmonic Under Voltage setting should be less than
50 V (in secondary term 350 mV)

Setting Adopted = 300 mV (Nearest Available Setting)

With delay = 5 Sec

PAGE 51 OF 58
ANNEXTURE “A”

TEST – II
OFFICE – NOTE

Date: 15/05/2006
Sub: Approval for Modification of Generator Protection Scheme with
microprocessor based Integrated Generator Protection Relay.

Generator is a having vital importance in the generating stations. It is


one of the expensive equipments installed in thermal power plant. Hence it
is worth to have reliable and accurate protective system for the generator.
Though the protective relays cannot prevent the faults to occur but the
correct protection system can definitely avoid or minimize the secondary
damage to the generator under fault condition or running under abnormal
working conditions this includes external faults, working beyond capability,
etc.

Nowadays it is utmost to know the exact picture of occurrences


happened in the system. The occurrence may be happened due to internal
(Gen) fault or it may be due to external (Grid) reason, the analysis of
occurrence is very much important. Exact analysis can save lot of downtime
and ultimately money.

Presently ABB Make Electromagnetic Generator protection Scheme is


in service at Parli Unit No. 4 since commissioning of the unit.

The relays are of old technology and the setting ranges are limited.
Hence it is difficult to set the relays accurately, according to the generator
capabilities.

The event logging and disturbance recording is not available with


existing relays. Hence it is difficult to analyze the fault / events occurred and
the tripping analysis is based on imagination only.

PAGE 52 OF 58
The on-line healthiness checking is not available with existing relays.
This is always creating doubt in the mind about the availability of protection.

The existing relays are deteriorating due to ageing and heating of


relays (the voltage dropping resistances are provided inside the relays and
relays gets heated up). The deterioration is like hardening of internal control
wire, dry soldering of PCBs and cases of mal operations also noticed.

Similar modification has been done in unit No. 3 and working


satisfactory since oct. 2005. during this period it proved the imporatance of
disturbance recording during AC failuere and during the different disturbances
occurred. Also these relays are used in unit no. 2 during rehabilitation after
fire. The same relays are also being used in new parli.

Considering the above it is necessary to change the generator


protection scheme by Microprocessor based integrated Generator protection
relays.

Considering the vital importance of generator protection scheme two


numbers of relays are proposed (One as main and other as Redundant).

The relays proposed to procure vide G. O. – 2 / CS 93 clause No. 6

Total estimated amount for 2 relays is Rs 2200000/-

Budget provision is already made in 2006-07.

Submitted for approval please.


Sd/-

Executive Engineer

TIC, St-II

Sd/-

Superintendent Engineer

Op. St-II

Sd/-

General Manager

TPS, Parli-V. Sd/-

PAGE 53 OF 58
Chief General Manager
TPS, Parli-V.

ANNEXTURE B

TESTING – STAGE II

OFFICE NOTE

Date: 02/06/2007

Sub: - Approval for the Modifications / Modified Generator Protection


Scheme Drawings With Microprocessor Based Gen Protection Relays
Micom P343. For unit No. 4 Generator During proposed shut Down.

Presently ABB make protection relays system is used for Unit 4


Generator. The protection relays are of old version (ABB make static relays) and
the accuracy and reliability have deteriorated due to aging. Hence it was decided
to replace the relays with microprocessor based integrated relays. In line with this,
P343 Areva make generator protection relays (2 Nos) are under procurement.

Following major works involves in the modifications.

I. Following conventional relays to be removed along with associated


wiring.
2. Generator Diff. Protection
3. Generator Inter Turn Protection
4. Gen. Negative Sequence Protection
5. Gen. Loss of excitation Protection
6. Gen Back up impedance Protection
7. Gen. 95% Stator Earth Fault protection
8. Gen Over voltage protection
9. Gen over fluxing Protection
10. Gen over current Protection
11. Gen. Low forward power protection
12. Gen Under / Over Frequency Protection
13. Gen under voltage protection.
14. Gen Reverse Power Protection

II. Two number micom P343 relay commissioning (One as Main and other
as redundant).

PAGE 54 OF 58
III. Following conventional relays are to be retained in the scheme.
1. GT overall differential Protection (RADSE).
2. Gen. Reverse Power Protection (WCD) to be installed as a
back up protection
3. GT Restricted Earth Fault Protection.
4. GT HV Back-Up Over Current Protection (P111) in place of
old relay HBB make
5. Local Breaker Back-Up Protection
6. UAT differential Protection (RADSE).
7. UAT HV Back-Up Over Current Protection (P111) in place of
old relay HBB make
8. UAT LV Neutral displacement Relay.
9. Gen. PT fuse monitoring Scheme
10. Gen. Check Synchronization Relay (SKE11).
11. Gen. Breaker Trip Circuit Supervision Relay.
12. Gen. Protection Master Trip Relay for Class A Protection.
13. Gen. Rotor Earth-Fault Protection Scheme (VAEM33
&CAEM33). to replace old relay ABB Make
14. GT & UAT Winding temp, Oil Temp, Bucchoz Protection
Scheme.
For accommodation of above changes and to ensure adequate protection
to the generator, the protection scheme drawings have been modified /
prepared.

The modified proposed drawings are prepared in three sections

• Single line Diagrams: This covers the allotment of generator CT & PT for different
protection relays. Also it shows the over view of the generator protection scheme.
• CT/PT CIRCUITS: This covers the CT/PT Secondary connection details.
• Generator Protection control DC circuit : This covers the different trip commands,
alarm and interlocking circuitry up to the final elements of execution.
The Proposed Modification Drawings are submitted herewith for kind
perusal & approval please

Sd/-
Sd/- Executive Engineer (Gen)
Superintending Engineer (Gen)
ELECTRICAL STAGE – II T,I&C STAGE-II

Sd/-
General Manager (Gen)
TPS Parli-V

PAGE 55 OF 58
Sd/-
Chief General Manager (Gen.)
TPS Parli-V

PAGE 56 OF 58

You might also like