This PRINCE2 template was kindly produced for OGC by PROJECT in a box.

This Crown copyright material


is reproduced with the permission of the Controller of HMSO and the Queen's Printer for Scotland.

Project Issue

Project Name:
Date:
Author:

Release:

Draft/Final

Owner:
Client:
Document Number:
Note: This document is only valid on the day it was printed
The source of this document will be found in the Project file

Revision History
Date of next revision:
Revision Date

Previous
Revision Date

Summary of Changes

Changes
Marked

Approvals
This document requires the following approvals. A signed copy should be placed in the project files.
Name
Signature
Title
Date of Issue

Version

Distribution
This document has been distributed to:
Name

259140084.doc

Title

Date of Issue

Version

page 1 of 2

Project Issue

insert project name

date:

Overview
Purpose

A generic term for any matter that has to be brought to the attention of the
project team and requires an answer. After receiving a unique reference
number, Project Issues are evaluated in terms of impact on the product, effort
and cost, risks, Project Plan and Business Case. The PM may make a decision
on what action to take or the Project Issue may be referred to the Project
Board. A Project Issue may have a negative impact on the project. Project
Issues include:
Requests for change
Off specification
Questions
Statements of concern

Contents

The Project Issue should cover the following topics


Description of the Project Issue..........................................................................................................2
Priority.................................................................................................................................................2
Impact Analysis...................................................................................................................................2
Decision..............................................................................................................................................2

Advice

Anyone may submit a Project Issue. Typical sources are users and specialists
working on the project. Capturing Project Issues (CS3) deals with collating
Project Issues. They are often examined during Examining Project Issues
(CS4).
Ensure that the Project Issue has been correctly logged, that the
problem/requirement/opportunity is clear and that the implications have been
thought through.

Author:

Date:

Issue no:

Description of the Project Issue

Priority

Impact Analysis

Decision

Decision Maker: (signature)

259140084.doc

Decision Date:

page 2 of 2