Professional Documents
Culture Documents
Field Investigation
3.1Overview
This section addresses subsurface investigation that includes drilling and excavation
of test pits as part of a geotechnical field investigation. It is organized by activities
andpolicies involved prior to, during, and after exploration.
4. Make sure that the project office has asked for (preferably obtained)
anarcheological assessment of the site to determine if there is potential
toencounter Native American or other artifacts.
5. Coordinate with the project office to make sure any right-of-entrys needed are
obtained for the proposed drilling.
6. Coordinate with the project office to make sure the necessary permits are obtained
(especially with regard to wetlands and other environmentally sensitive areas).
7. Coordinate with the Field Exploration Supervisor (FES) who will beassigned
tothe project, and the project office, to conduct a joint field review
toevaluate access and other issues related to setting up and finalizing the field
explorationprogram.
8. Act as the liaison between the Field Exploration Manager (FEM) and the project
office to make sure the FEM knows when all the tasks have been completed
and to inform the FEM of the results so that the exploration program can
beproperlyestimated.
WSDOT Geotechnical Design Manual M 46-03.10
August 2014
Page 3-1
Field Investigation
Chapter 3
Note that to obtain permits and right-of-entry, a preliminary field exploration plan
willlikely be needed by the region (or WSF) before the final exploration plan
iscompleted and turned in. Therefore, the development of the field exploration plan
may require a somewhat iterative process. Once enough field exploration plan details
have been developed, the geotechnical designer should request that those who will
bedirectly negotiating with local owners to obtain right-of entry (if needed) invite
the FEM or FES to assist in those negotiations. This generally makes the negotiations
gomuch smoother.
If the geotechnical designer recognizes, either through an environmental assessment
or through general knowledge of the previous site use, that there is a potential
toencounter hazardous materials during the geotechnical field exploration,
itisimportant that the geotechnical designer make the FEM aware of this as soon
as possible in the development of the exploration plan. The potential to encounter
hazardous subsurfacematerials can completely change the approach, cost, and
scheduling for the site exploration activities.
A preliminary field exploration plan is also needed for use as the basis for
conducting the joint field review mentioned above. This field review should
beusedtodeterminehow each individual exploration site will be accessed, the
type ofdrill equipment best suited for the site, areas for utility locates, required
traffic control, and to identify any permit, right-of-entry, and environmental issues.
Adjustments to the specific locations of exploration points can be made as needed
during the field review to address the aboveissues.
During the field review, the FES will stake the borings if they have not already been
located and if right-of-entry (if needed) has been obtained. The FES should also
assessthe traffic control needs for the exploration work at this time. The FES will
coordinate directly with the Maintenance Office for traffic control. After staking
borings, the FES is responsible for calling all utility locates a minimum of 48 hours
prior to the start of explorations.
Once the final field exploration plan has been completed, the FEM will provide
acost estimate to the geotechnical designer to complete the field exploration plan.
Once the expenditure for the field exploration has been authorized, the geotechnical
designer must then notify the FEM to commence with the field exploration. Once
the exploration plan has been executed, any subsequent requests to modify the plan
shouldbe provided in writing by the geotechnical designer to the FES. The FES will
respond with an updated estimate and schedule for requested plan change.
If the geotechnical design is to be conducted by a geotechnical consultant, the
WSDOTgeotechnical designer who is overseeing the consultant task assignment
or agreement is responsible to make sure that the consultant accomplishes the tasks
described above and to assist in the coordination between the consultant and the
FEM. If the consultant needs changes to the field exploration plan, the geotechnical
designer is responsible to provide input to the FES or FEM as to the acceptability
of the changes. The FES or FEM is not to act on the requested changes to the field
exploration plan without input from the geotechnical designer.
Page 3-2
Chapter 3
Field Investigation
Page 3-3
Field Investigation
Chapter 3
Page 3-4
Chapter 3
Field Investigation
SPT Correlation
Clay
# PP blows/4
Silt
# PP blows/3
Sand/Gravel
# PP blows/2
Page 3-5
Field Investigation
Chapter 3
The excavation of test pits can provide valuable subsurface information not
determinable or well characterized by test borings. Extreme care should be exercised
around open excavations, and access within them should adhere toWashington
Administrative Code (WAC) sections 296-155-655 and296-155-657.Prior to demobilizing, the drill inspector should ensure location information (e.g., station,
offset, elevation and/or state plane coordinates) of all the explorations are recorded
onthe field logs. If exact location information is unavailable upon completion of field
activities, a sketch of each exploration location should be made indicating relationship
to observable features (i.e., bridge/structure, mile post, etc.). This information should
be provided with the field logs to the geotechnical designer. In addition to providing
field logs for all explorations, required documentation for test pits should include a
scale drawing of the excavation and photographs of the excavated faces. Sampling
methods and in situ measurement devices such as pocket penetrometers should also be
documented. Detailed requirements for boring logs are provided in Chapter 4.
3.6References
Mayne, P. W., Christopher, B.R., and DeJong, J., 2002, Subsurface Investigations
Geotechnical Site Characterization, Publication No. FHWA NHI-01-031, National
Highway Institute, Federal Highway Administration, Washington, DC, 300 pp.
Page 3-6
Appendix 3-A
CS
Date
Project
Project No.
Drill
Drill No.
Structure
Hole No
Line
Size
Landslide
Angle
From
Item
Piezo Pipe
Materials Source
Soil
Hours
To
Rock
Total
Item
Hours
Cement
Bentonite
Additives
Other
Support Equipment
No.
Job
Yard
O Serv.
Remarks
Reg.
OT
Comp
Total
Inspector
Driller
Helper
Shift Start
Shift Finish
Service Codes
Page 3-A-1
Page 3-A-2
Appendix 3-A
Appendix 3-B
Background
The WSDOT portable penetrometer (PP) is a field test used in highway and small
foundation design. The test may be used in both cohesive (clay) and cohesionless
(sands & gravels) soils. The test values (i.e., blow count per foot of penetration) are
dependent upon the effective overburden pressure of granular soils and shear strength
of cohesionless soils. However, since all equations and correlations related to use
of blow count values are approximate, sound engineering judgment is necessary for
accurate interpretation of the test results.
The PP test is a derivative of the Standard Penetration Test (SPT), the most widely
used method for determining soil conditions in the world. The SPT is both a dynamic
penetration test and a method of obtaining disturbed samples. For the SPT test, a splitspoon sampler attached to drill steel is driven downward by the impact of a falling
weight on the steel. In the SPT test, a 140 lb. weight falls a distance of 30inches
per blow. In the PP test method, a 35 lb weight falls an approximate distance of
25.5 inches. In the SPT test, as a split-spoon sampler is driven downward, it fills
with disturbed soil. In the PP test, no sample is obtained as a solid, cone-shaped tip
isdrivendownward by a falling weight. However, the PP method requires excavation
of a test hole, and samples should be obtained with each change in soil strata.
Equipment
Performance of portable penetrometer testing requires two groups of equipment.
The first group is associated with preparation of a drilled borehole, backhoe test pit,
orhand-excavated test hole. This group includes the tools used to dig the hole, with
a hand auger employed most frequently in a PP test application. A list of equipment
usedfor excavation of a test hole with a hand auger follows:
Shovel with pointed end for breaking up turf and vegetation at the surface.
Posthole digger for assistance in establishing the test hole excavated using the
handauger.
Hand auger to include: auger, pipe extensions (3feet lengths), and handle.
Steel bar to loosen up hard pack soil and assist in the removal of rock or gravel
from the test hole.
Tarp for collecting representative samples of soil strata.
Field notebook and pencil for recording location of test holes, numbers and
descriptions of distinct soil layers encountered, and other information relative
toareview of site characteristics and
conditions.
Sample bags with ties for preservation of samples of material encountered with
changes of soil strata.
Marker for writing on sample bags or tags to delineate test hole and depth
ofsample collection.
Pocket or rag tape to be used to locate the test hole relative to some reference point,
grid, or proposed alignment and for measurement of depth below surface of distinct
soil strata and depth of exploration.
WSDOT Geotechnical Design Manual M 46-03.10
August 2014
Page 3-B-1
Appendix 3-B
The PP device and accessories form the second group of equipment required for
geotechnical investigation of proposed highway or small foundation designs. A list
ofthe equipment necessary for this group follows:
Portable penetrometer to include cone-shaped tip; drill rod sections (A-rod 1.75 in. pipe OD & 22.5 in. lengths); falling weight section (length ofbar for
sliding weight up and down); the 35-lb weight; and the coupling devices used for
connecting the tip drill rod sections falling weightsection falling weight stop.
Pipe wrenches (2) used to loosen connections when breaking down
theportablepenetrometer.
Lathe or another straight-edge useful for establishing a surface
referenceelevation.
Construction crayon or marker used for marking three 6 inch intervals on the
penetrometer in order to clearly delineate displacement as the penetrometer
isdriven into the ground.
Rags to wipe down equipment, removing moisture and dirt, prior to packing
awayequipment.
Test Procedure
1. Using a shovel or other hand tool, strip away sod or surface vegetation and set
aside for future restoration of the location. Using a posthole digger or a6 in
diameter or greater hand auger, dig down approximately 2feet, noting the depth
oftopsoil, subsoil, and other changes in soil strata. Describe soil conditions such
as color, texture, and moisture content of the soils encountered in the bore log.
Collectsamples for lab soil classification, grain size determination, or Atterberg
limits determination.
2. Assemble the PP device for evaluation of soils near the surface. Use threaded
coupling devices to connect the cone-shaped tip, drill rod sections, and falling
weight slide section.
3. Measure the distance from the bottom of the test hole to the surface and record.
From the tip of the penetrometer, measure this distance on the body of the testing
device and annotate a reference line on the body of the device. From this line
measure and mark three intervals, each 6 inches inlength.
4. Lift up the PP device and place the tip at the bottom of the test hole. Insure that
the bottom or base line mark lines up with the approximate ground surface.
Place a lathe or other straight edge on the ground surface so that any downward
displacement of the PP device may be measured accurately.
5. Lift the 35 lb weight up and lower it down on to the upper, slide portion of the
testing device. Screw on the threaded stop at the upper end of the slidesection.
Page 3-B-2
Appendix 3-B
Page 3-B-3
Appendix 3-B
Figures 3-C-1 through 3-C-8 illustrate the equipment and procedures used for
conducting the Portable Penetrometer test.
a field reconnaissance
of the site of of
thethe
geotechnical
Insure
that the
Figure Perform
3C-1. Perform
a field reconnaissance
site of theinvestigation.
geotechnical
investigation.
Figure
Perform
of the site
of the
geotechnical
investigation.
proposed
designaisfield
tied
toreconnaissance
anisestablished
system,
datum,
or
permanent
monument.
Insure3C-1.
that
the
proposed
design
tied to ancoordinate
established
coordinate
system,
datum,
or permanent
Insure
that
the
proposed
design
is
tied
to
an
established
coordinate
system,
datum,
or permanent
Figure
3-C-1
monument.
monument.
in conjunction
with the PP test.
Figure Hand
3C-2.augers
Handused
augers
used in conjunction
with the PP test.
Figure 3-C-2
Figure
3C-2.
Hand augers
usedManual
in conjunction with the PP test.
WSDOT
Geotechnical
Design
June 2006
Page 3-C-4
WSDOT Geotechnical Design Manual
2006
Page 3-B-4
WSDOT Geotechnical Design Manual June
M 46-03.10
Page 3-C-4
August 2014
Appendix 3-B
equipment.
Clockwise from
the top left:
tape
tips coneFigurePorta-Pen
3C-3. Porta-Pen
equipment.
Clockwise
from
themeasure
top left:above
tapecone-shaped
measure above
(2);22.5-inch lengths (9); threaded coupling devices used to connect PP components
shaped(10);threaded
tips (2); 22.5-inch
lengths (9);
threaded
coupling devices
used
to connect
PP components
coupler used to
stop weightfrom
(1); falling-weight
slide
section
above pipe
Figure 3C-3.
Porta-Pen
equipment.
Clockwise
thefrom
top left:
tape
measure
above
Figure
3C-3.
Porta-Pen
equipment.
Clockwise
the
top
left:
tape
measure
above cone(10);
threaded
coupler
used
to
stop
weight
(1);
falling-weight
slide
section
above
pipe conewrenches
wrenches (2); 35 lb. weight; and threaded coupling devices used with small cone tips
shaped tips
(2);
22.5-inch
lengths
(9);
threaded
coupling
devices
used
to
connect
PP
components
shaped
tips
(2); 22.5-inch
lengths
(9); devices
threaded
coupling
devices
to connect
(2);
35(notshown).
lb.
weight;
and threaded
coupling
used
with small
cone used
tips (not
shown). PP components
(10); threaded
coupler used
to stop
falling-weight
slide section
wrenches
(10); threaded
coupler
usedweight
to stop(1);
weight
(1);3-C-3
falling-weight
slide above
sectionpipe
above
pipe wrenches
Figure
(2); 35 lb.
weight;
and
threaded
coupling
devices
used
with
small
cone
tips
(not
shown).
(2); 35 lb. weight; and threaded coupling devices used with small cone tips (not shown).
Figure 3C-4. The vicinity of the test hole is cleared of vegetation using a shovel or posthole
digger. Left photo shows using the auger to advance the hole to the desired depth . Right photo
shows placing soil on the tarp prior to sampling.
The
vicinity
of theoftest
cleared
vegetation
using a shovel
or posthole
digger.
Left
Figure 3C-4.
The
vicinity
thehole
test
is of
cleared
vegetation
using
a shovel
posthole
Figure
3C-4.
The
vicinity
ofis hole
the
test
hole
is of
cleared
of vegetation
using
aorshovel
or posthole
photo shows using the auger to advance the hole to the desired depth. Right photo shows
digger. digger.
Left photo
shows
using
the
auger
to
advance
the
hole
to
the
desired
depth
.
Right
photo
Left
photo
shows
using
the
auger
to
advance
the
hole
to
the
desired
depth
. Right photo
placing soil on the tarp prior to sampling.
shows placing
soil
on
the
tarp
prior
to
sampling.
shows placing soil on the tarp prior to sampling.
Figure 3-C-4
Page 3-C-5
WSDOTWSDOT
Geotechnical
Design Manual
Geotechnical
Design Manual
Page 3-C-5
Page 3-C-5
WSDOT Geotechnical Design Manual M 46-03.10
August 2014
June 2006
June 2006
June 2006
Page 3-B-5
Appendix 3-B
PP device
in the
process
of being
assembled.
threaded coupling
devices on
the
Figure Photo
3C-5.ofPhoto
of PP
device
in the
process
of beingThe
assembled.
The threaded
coupling
left side of the box are used to connect the cone-shaped tip to lengths forming the body of the
devices
on the
left of
side
the box
to connect
theassembled.
cone-shapedThe
tip to
lengths coupling
forming the
Figure
3C-5.
Photo
PPofdevice
inare
theused
process
of being
threaded
penetrometer. The lengths forming the body of the penetrometer are then connected to the
bodyon
ofsection
the left
penetrometer.
The
forming
the body
of the penetrometer
are thenforming
connected
devices
the
ofthe
theweight
boxlengths
are
used
to connect
the cone-shaped
tip to lengths
the
onside
which
slides.
toof
thethe
section
on which the
slides.
body
penetrometer.
Theweight
lengths
forming the body of the penetrometer are then connected
Figure 3-C-5
Figure 3C-6. Marking a base line on the body of the penetrometer. This will line up with the
top of the test hole. In addition, also mark three 6 inch intervals, measured from this base line, to
a base line on the body
of thethe
penetrometer.
This will
line up with the top of the test
track3C-6.
theMarking
downward
when
falling
is applied.
Figure
Markingdisplacement
a base line on
the body
of theweight
penetrometer.
This will line up with the
hole. In addition, also mark three 6 inch intervals, measured from this base line, to track the
Page 3-C-6
June 2006
Appendix 3-B
PP testing in progress. Lathe is used to mark the surface of the test hole excavation. In this
Figure 3C-7.
PP testing in progress. Lathe is used to mark the surface of the test hole
instance, one person is steadying the equipment, another is lifting and dropping the 35 lb
excavation.
In
instance,
one person
is steadying
equipment,
another
lifting
Figure
3C-7.
PP
testing
Lathe
isdisplacement
used tothe
mark
the
surface
of theistest
holeand
weight,this
and
a thirdinis progress.
observing
downward
and
counting
blows.
dropping theIn35
lb instance,
weight, and
third isisobserving
downward
displacement
and
counting
excavation.
this
oneaperson
steadying
the equipment,
another is
lifting
and blows.
Figure 3-C-7
dropping the 35 lb weight, and a third is observing downward displacement and counting blows.
Figure 3C-8. This PP testing can be tiring. Photo shows another person providing relief for the
This PP
testing
can be tiring.
Photo
showsPhoto
another
personanother
providingperson
relief forproviding
the falling relief for the
falling 3C-8.
weight
task.
Figure
This
PP testing
can be
tiring.
shows
weighttask.
falling weight task.
Figure 3-C-8
Page 3-C-7
Page 3-C-7
June 2006
June 2006
Page 3-B-7
Page 3-B-8
Appendix 3-B
Appendix 3-C
Page 3-C-1
Field Investigation Best Management Practices for Erosion and Spill Prevention
Appendix 3-C
The drill crew will have a copy of the Hydraulic Project Approval (HPA), issued bythe
Washington State Department of Fish and Wildlife (WDFW) on-site for all work
adjacent to or over water. The Supervisor will discuss the requirements of this permit
with the crew prior to each project. All of the provisions in each HPA will bestrictly
followed until the completion of said project. The previously defined erosion/
sedimentcontrol philosophy and BMPs will be implemented in these conditions
The approach to protecting surface and ground water is focused on prevention.
The drill shaft will be filled with bentonite clay to prevent mixing of aquifers and
eliminating the route for surface contaminants. In addition, the following Spill
Prevention Control & Countermeasures (SPCC) BMPs will be used when applicable:
Minimize Risk:
Visually inspect equipment for leaks or worn hoses on a daily basis
Fix equipment leaks as soon as possible to minimize cleanup
Use proper equipment to transfer materials
Reduce the overall volume of fuel and chemicals on site
Remove as many sources of spills as possible from the site when not working
(evenings/weekends)
Use environmentally-friendly chemicals whenever possible
Store all chemicals with lids closed and keep containers under cover
Have secondary containment devices underneath potential spill sources when
applicable (e.g. 5 gallon bucket)
Maximize Response:
Each drilling operation will have at least one emergency spill response kit on site
atall times
Know who to call in case of emergency spill
If an incidental spill (less than 1 gallon/small equipment leak) occurs, immediately
collect contaminated soil and store it in label storage drum. Do not mix soils with
different contaminants together. Report spill to your supervisor, as they are aware
ofreporting requirements.
If a major spill (more than 1 gallon) to water occurs, control the source of the leak
ifpossible and contact the Washington State Emergency Management Division
(800-258-5990) and the National Response Center (800-424-8802). If a major spill
to soil occurs and there is immediate risk to human health and/or the environment,
control the source of the leak if possible and contact the Washington State Department
ofEcology (800-407-7170). Then contact your supervisor, as they are aware
ofreportingrequirements.
Page 3-C-2
Department of Natural Resources
Memorandum of Understanding: Drilling
Appendix 3-D Operations State Owned Aquatic Lands
Page 3-D-1
Appendix 3-D
Page 3-D-2
Appendix 3-D
Page 3-D-3
Appendix 3-D
Page 3-D-4
Appendix 3-D
Page 3-D-5
Appendix 3-D
Page 3-D-6
Appendix 3-E
Page 3-E-1
Appendix 3-E
INTRODUCTION
This document has been produced as a guide for Washington State Department of Transportation
(WSDOT) personnel involved in geotechnical exploration drilling where potential environmental
contamination may be encountered. This guide provides simple procedures to support WSDOT personnel
in planning for, storing, and disposing of potentially contaminated material generated during drilling
activities. Information in this document will be incorporated into WSDOT manuals, such as the Design
Manual (M 21-02), Geotechnical Design Manual (M 46-03), and the Environmental Manual (31-11) as
appropriate.
A decision tree included below as Figure 1, illustrates a simplified step by step process to follow in
preparing for and dealing with geotechnical drilling waste. The following sections will provide further
explanation of the decisions associated with each step in the process.
SUSPECTED CONTAMINATION
As described in the WSDOT Geotechnical Design Manual (GDM), a geotechnical field exploration plan and
an environmental assessment (per GDM, Chapter 3) is done prior to drilling activities. As part of this
environmental assessment the WSDOT project engineer (PE) assigned to the project will:
Review NEPA/SEPA environmental documentation prepared for the project, such as the
Hazardous Materials Analysis, Technical Memorandums, or NEPA/SEPA checklists (i.e.,
Environmental Classification Summary). For more information regarding these reports, read
Chapter 447 of the Environmental Manual and/or contact the Regional Environmental Office.
If environmental documentation does not yet exist, the project PE shall coordinate with the
WSDOT Regional Environmental Office to review environmental information on the Department of
Ecologys (Ecology) Facility Site Atlas Database and conduct a field reconnaissance of the drilling
site to identify recognized environmental conditions (as defined in ASTM E-1527).
Identify known or suspected contamination on the geotechnical drilling crews soil investigation
checklist drilling work order request. Information will include a briefly describe the location and
the type (e.g., petroleum, metals, or solvents) and concentrations (if known) of contaminates that
may be encountered.
If the drilling activity is suspected to generate contaminated material, notify owners, operators, and
facility managers of the site. Also, coordinate waste characterization sampling with a WSDOT Hazardous
Material Specialist or an environmental consultant.
Encountering contamination is more likely when drilling at sites historically used for commercial or
industrial purposes, however an environmental assessment can better evaluate the potential risks and
determine if suspect contamination is on site and warrants special handling and disposal. If there is no
reason to suspect contamination on the site, field screening during drilling activities is appropriate.
Page 3-E-2
Page 1 of 5
Appendix 3-E
All waste generated at a facility operating under a RCRA ID# 1 Dangerous Waste permit must be
left on-site pending lab results. Arrangements must be coordinated with the RCRA site facility
manager for specific storage and disposal requirements.
Potentially contaminated drilling material generated at a secure/safe location (i.e., fixed facility
under the control of WSDOT) will remain on-site where the drilling activities occur.
Potentially contaminated drill cuttings generated from areas that are not under the control of
WSDOT (i.e., left in unsecure or unsafe areas) may be transported to a temporary secured
location for analysis and disposal within 90 days.
The preferred location for accumulating containers of potentially contaminated material is on-site where
the drilling activities occur, but it may not always be safe or practical to do so. In these instances the
containers may be transported to a nearby WSDOT maintenance facility with prior approval of the
maintenance superintendent. It is the WSDOT Geotechnical Divisions responsibility to ensure containers
are in good condition, properly labeled, with lids tightly closed, stored in a safe orderly manner and
disposed within 90 days,
1A
RCRA ID number is issued by Ecology for facilities that generate, transport, transfer, recycle, treat, store, or dispose of certain quantities of
dangerous waste, as defined in the Dangerous Waste Regulation WAC 173-303. The PE should ascertain from the property owner or facility
manager if the proposed geotechnical drilling site has a RCRA ID#.
Page 2 of 5
Page 3-E-3
Appendix 3-E
CONTAMINATION CHARACTERIZATION
The type and concentration of contamination must be identified through representative sampling
methods to determine a proper disposal method.
If contamination is observed during drilling activities, or if the site has known contaminants a WSDOT
Hazardous Materials Specialist or environmental consultant must sample waste material prior to
disposal. The following WSDOT Hazardous Material Specialists who retain the necessary training, and are
qualified to collect samples include:
Labeling waste containers at the time of drilling is extremely important to manage sampling costs.
Proper labeling, knowledge of the site history and the methods used to generate the waste can allow for a
targeted sampling strategy with specific laboratory analysis. For example, proper labeling and a site
boring plan can help determine whether to sample all containers or a select group of containers. It can
also help determine whether to have the samples tested for one specific analysis (i.e., metals) rather than
a complete list which significantly increase costs. Although the disposal facility dictates the lab analysis
required prior to acceptance, often demonstrating knowledge of the site, previous lab data (if any) and
the process that generated the waste can provide enough justification where the disposal facility will
allow for limited sampling work (which is documented in a waste profile sheet required prior to disposal
acceptance).
Clean Soil
If contamination is not suspected and field screening did not indicate the presence of contamination or if
laboratory testing results are below regulatory cleanup levels, the material may be considered clean soil.
This designation may allow for disposal at the site of origin, or an appropriate WSDOT facility, in
accordance the jurisdictional health departments solid waste regulations. If material will be placed at
another location other than the site of origin, then approval shall be obtained from the site manager prior
to delivery.
Page 3-E-4
Page 3 of 5
Appendix 3-E
Solid Waste
If laboratory analysis indicates that concentrations of any contaminants of concern are greater than the
appropriate regulatory cleanup level, but the laboratory results do not designate the material as
dangerous waste per WAC 173-303, the material is considered Solid Waste. Solid waste which is not a
liquid or sludge-like, may legally be disposed of in a permitted landfill or with one of the many permitted
businesses that accept such waste. Regional offices are responsible for identifying and determining the
acceptability of solid waste for disposal in their region.
and
The
Department
of
Ecology
(http://www.ecy.wa.gov/programs/swfa/facilities/
http://www.ecy.wa.gov/programs/swfa/solidwastedata/) can provide updated information on permitted
businesses, their location, fees, and restrictions.
Dangerous Waste
It is highly unlikely that geotechnical drilling waste would ever designate as dangerous waster (per
WAC173-303). However, if laboratory analysis indicates that waste designates as dangerous waste,
disposal will be coordinated through a contractor that is licensed and permitted to handle, transport and
dispose of dangerous waste. With the assistance of a WSDOT hazardous material specialist, regional
offices must obtain a RCRA Site Identification Number using the Ecology Dangerous Waste Site
Identification Form before offering dangerous waste for transport. A few exceptions are permitted for
small quantity generators, as described in WAC 173-303-070(8). A separate identification number is
necessary for each site from which dangerous waste is shipped. Because Ecology requires annual reports,
limiting the number of storage sites for potentially dangerous sampling waste will reduce documentation
required.
It is best to legally dispose contaminated drilling waste as soon as possible, but it must be disposed
within 90 days. For Solid Waste and Dangerous Waste, copies of the following disposal documentation
shall be retained by the generating facility for a minimum of 5 years:
1. waste profile sheets, and associated sampling reports,
2. waste authorization or other type of permit documenting a disposal facilitys pre-approval for
acceptance of material (if a facility requires such),
3.
shipping manifest or bill of lading indicating the amount of material hauled to disposal, and
bearing the disposal site operators confirmation for receipt of the material.
Page 4 of 5
Page 3-E-5
Appendix 3-E
Figure 1
Decision Tree
Page 3-E-6
Page 5 of 5
Appendix 3-E
Is contamination suspected
in the area where drilling
activities will occur?
yes
no
Have contaminants
been characterized?
yes
no
no
Dangerous waste
Clean soil
Page 3-E-7
Appendix 3-E