GAMBARAN UMUM PROYEK PENGURUGAN

JALAN TOLL PEJAGAN - PEMALANG


OWNER

: BAKRIE BROTHERS

MAIN KONTRAKTOR

: PT. SMR (PT. SEMESTA MARGA RAYA)


PT. TRI MANUNGGAL

PEMBAYARAN

: PER 500.000 M3. (SKBDN / BANK GARANSI)

VOLUME KONTRAK :

5.000.000

M3.

ATAU

HARGA KONTRAK

: Rp.

250,000 DUMP
72,000.00 / M3. PADAT VIBRO

RENCANA ANGGARAN PELAKSANAAN ( PER M3. )


BIAYA RITASI DT & QUARRY :
1. SEWA DUMP TRUCK
2. BIAYA BBM DT
3. BIAYA SUPIR DT
4. DEPOSIT TANAH
5. SEWA EXCAVATOR
6. BIAYA BBM ALAT
7. BIAYA OPERATOR ALAT
BIAYA PEMADATAN :
1. SEWA VIBRO & BULDOZER
2. BIAYA BBM ALAT
3. BIAYA OPERATOR ALAT
BIAYA UMUM & ADMIN. :
1. PEMOTONGAN OLEH MAIN KONTRAKTOR
( UNTUK BIAYA PAJAK & ADMINISTRASI )
2. BIAYA PERSIAPAN/PENDAHULUAN
JUMLAH
PROFIT
JUMLAH
CATATAN : PROFIT

Rp

30,665 /M3.

= Rp.
= Rp.
= Rp.
= Rp.
= Rp.
= Rp.
= Rp.

8,910
6,000
2,255
6,250
935
802
167

= Rp.
= Rp.
= Rp.

1,007
807
203

= Rp.
= Rp.
= Rp.
= Rp.

12,000
2,000
41,336
30,665

= Rp.

72,000

BELUM TERMASUK UNTUK FEE SUKSES PHK MEDIASI

ASUMSI - ASUMSI :
WAKTU PELAKSANAAN :
VOLUME KONTRAK
1. EXCAVATOR (BEKO)
KEMAMPUAN ALAT (EXCAVATOR)
GALI/MUAT PER HARI = 10 JAM
JML PEMAKAIAN ALAT
GALI/MUAT PER HARI = 10 JAM
JML WAKTU PELAKSANAAN
2. DUMP TRUCK :
Kapasitas Dump truk
Frequensi Dump Truk
Jumlah armada
Frequensi tiap 1 DT

5,000,000 M3.
50
500
10
5,000

M3./JAM
M3.
UNIT
M3.

1,000 HARI
33 BULAN
20
250
8
33

m3/DT
trip/hari
DT
trip

1.2
50
10
500
10

M3.
M3.
Jam
M3.
Unit

WAKTU SIKLUS ALAT/DT :


1. EXCAVATOR (BEKO)
Kapasitas Bucket
Kapasitas Produksi Per Jam
Jumlah Jam Kerja
Jumlah Produksi/Alat
Jumlah Pemakaian Alat

GAMBARAN UMUM PROYEK PENGURUGAN


JALAN TOLL PEJAGAN - PEMALANG
OWNER

: BAKRIE BROTHERS

MAIN KONTRAKTOR

: PT. SMR (PT. SEMESTA MARGA RAYA)


PT. TRI MANUNGGAL

PEMBAYARAN
: PER 500.000 M3. (SKBDN / BANK GARANSI)
Jumlah Produksi Per Hari

5,000 M3.

GAMBARAN UMUM PROYEK PENGURUGAN


JALAN TOLL PEJAGAN - PEMALANG
OWNER

: BAKRIE BROTHERS

MAIN KONTRAKTOR

: PT. SMR (PT. SEMESTA MARGA RAYA)


PT. TRI MANUNGGAL

PEMBAYARAN
: PER 500.000 M3. (SKBDN / BANK GARANSI)
2. DUMP TRUCK :
Jarak Tempuh
Waktu muat dan manouver
Kecepatan (dgn muatan)
Waktu tempuh (dgn muatan)
Waktu bongkar dan manouver
Kecepatan (tanpa muatan)
Waktu tempuh (tanpa muatan)
Jml Waktu Bongkar/Muat/Perjalanan
Jumlah trip tiap jam
Jam kerja per hari
Total trip per hari (real time)
Total daya angkut per hari/DT
Target Volume Angkut per hari
Jumlah Dump Truk yg diperlukan

2
6
20
6
2
30
4
18
3.33
0.30
10
33

km
menit
km/jam
menit
menit
km/jam
menit
menit/trip
trip/jam
jam/trip
jam/hari
trip/hari

667 m3 /hr/DT
5,000 m3
8 Unit DT

PREDIKSI PELAKSANAAN PEKERJAAN PENGURUGAN :


1

PEKERJAAN PERSIAPAN :
-

DIREKSI KEET / SITE OFFICE


MOBILISASI DAN DEMOBILISASI PERLATAN & PERSONIL
PENGUKURAN LEVELING TANAH DASAR
PEMBUATAN JALAN AKSES DARI QUARRY KE JALAN UMUM

PEKERJAAN PEMATANGAN LAHAN SEPANJANG DAERAH TIMBUNAN TANAH :


-

PEMBONGKARAN TERHADAP PENGHALANG YANG MUNGKIN ADA


MEMINDAHKAN DAN MENANGANI AIR YANG ADA AGAR TIDAK TERHENTI
MEMBUANG DAN MENANGANI LOKASI TIMBUNAN TANAH YANG BERLUMPUR
MENGHENTIKAN / MENYUMBAT SUMBER AIR TANAH YANG TIMBUL APABILA ADA

PEKERJAAN PEMADATAN TANAH DASAR SEPANJANG LOKASI KERJA

PEKERJAAN PENIMBUNAN TANAH DAN PEMADATAN


- SETIAP PENGHAMPARAN 30 CM. ATAU SESUAI KETENTUAN YANG ADA DALAM
SPESIFIKASI YANG DIKELUARKAN PIHAK OWNER DAN ATAU STANDAR PT. JASA MARGA

PEKERJAAN COMMISIONING TEST PEMADATAN DENGAN MENGGUNAKAN PERALATAN


SAND CONE DAN ATAU SHEEP FOOT ROLLER SAMPAI DENGAN MEMENUHI TINGKAT
KEPADATAN DAN DAYA DUKUNG YANG DITETAPKAN SESUAI PERATURAN UNTUK
JALAN TOLL.
PERALATAN YANG DIGUNAKAN :

1
2
3
4

EXCAVATOR
DUMP TRUCK
BULDOZER
COMPACTOR / VIBRO ROLLER

CILEGON, 12 DESEMBER 2009


S E & O

5
6
7
8

MOTOR GRADER
SHEEP FOOT ROLLER
TRUCK TANGKI AIR
PERALATAN PENDUKUNG LAINNYA

GAMBARAN UMUM PROYEK PENGURUGAN


JALAN TOLL PEJAGAN - PEMALANG
OWNER

: BAKRIE BROTHERS

MAIN KONTRAKTOR

: PT. SMR (PT. SEMESTA MARGA RAYA)


PT. TRI MANUNGGAL

PEMBAYARAN
JAUHARY

: PER 500.000 M3. (SKBDN / BANK GARANSI)

RENCANA ANGGARAN PENDAPATAN DAN BIAYA OPERASIONAL


PROYEK PENGURUGAN JALAN TOLL PEJAGAN - PEMALANG
I.

PENDAPATAN :
NILAI KONTRAK PENGURUGAN TANAH MERAH : 5.000.000 M3. x Rp. 72.000,-

II.

= Rp.

360,000,000,000

= Rp.

85,822,500,000

= Rp.

9,519,000,000

BIAYA OPERASIONAL (PENGELUARAN PROYEK) :

A.

BIAYA RITASE DUMP TRUCK DAN QUARRY :


1

DUMP TRUCK :
SEWA
: 135 UNIT x Rp. 30.000.000,- x 11 BULAN
BBM
: 20 LTR/TRIP x 250.000 TRIP x Rp. 6.000,SUPIR
: Rp. 250.000,-/HARI x 334 HARI x 135 UNIT

44,550,000,000
30,000,000,000
11,272,500,000

EXCAVATOR :
SEWA
BBM
OPERATOR

= Rp.
= Rp.
= Rp.

: 10 UNIT x 3.340 JAM x Rp. 140.000,- / JAM


: 20 LTR x 3.340 JAM x 10 UNIT x Rp. 6.000,: Rp. 250.000,-/HARI x 334 HARI x 10 UNIT

PEMBELIAN TANAH MERAH :


:

= Rp.
= Rp.
= Rp.

4,676,000,000
4,008,000,000
835,000,000

250.000 DUMP (RIT) x Rp. 125.000,-/DUMP

JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY :


B.

BULDOZER D6
COMPACTOR/VIBRO R.
MOTOR GRADER
SHEEP FOOT ROLLER
TRUK TANGKI AIR

BBM ALAT :
- BULDOZER D6
- COMPACTOR/VIBRO R.
- MOTOR GRADER
- SHEEP FOOT ROLLER
- TRUK TANGKI AIR

126,591,500,000

:
:
:
:
:

:
:
:
:
:

6 UNIT
3 UNIT
3 UNIT
1 UNIT
2 UNIT

20 LTR
15 LTR
15 LTR
15 LTR
80 LTR

x
x
x
x
x

x
x
x
x
x

3.340 JAM x Rp. 135.000,-/JAM


2.338 JAM x Rp. 130.000,-/JAM
2.338 JAM x Rp. 130.000,-/JAM
500 JAM x Rp. 135.000,-/JAM
Rp. 20.000.000,- x 11 BULAN

3.340 JAM x 6 UNIT x Rp. 6.000,2.338 JAM x 3 UNIT x Rp. 6.000,2.338 JAM x 3 UNIT x Rp. 6.000,500 JAM x 1 UNIT x Rp. 6.000,334 HARI x 2 UNIT x Rp. 6.000,-

=
=
=
=
=

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

= Rp.

5,036,540,000

Rp.
Rp.
Rp.
Rp.
Rp.

= Rp.

4,032,960,000

2,705,400,000
911,820,000
911,820,000
67,500,000
440,000,000

2,404,800,000
631,260,000
631,260,000
45,000,000
320,640,000

OPERATOR ALAT :
-

BULDOZER D6
COMPACTOR/VIBRO R.
MOTOR GRADER
SHEEP FOOT ROLLER
TRUK TANGKI AIR

:
:
:
:
:

Rp. 250.000,-/HARI
Rp. 250.000,-/HARI
Rp. 250.000,-/HARI
Rp. 250.000,-/HARI
Rp. 250.000,-/HARI

x
x
x
x
x

334
224
224
50
334

HARI
HARI
HARI
HARI
HARI

x
x
x
x
x

6 UNIT
3 UNIT
3 UNIT
1 UNIT
2 UNIT

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

501,000,000
168,000,000
168,000,000
12,500,000
167,000,000

JUMLAH BIAYA PEMADATAN :

= Rp.

1,016,500,000

= Rp.

10,086,000,000

= Rp.

60,000,000,000

BIAYA PEMOTONGAN DARI MAIN KONTRAKTOR :


UNTUK BIAYA PPH PAJAK KONSTRUKSI DAN BIAYA ADMINISTRASI : 5.000.000 M3. x Rp. 12.000,-/M3.

D.

31,250,000,000

= Rp.

BIAYA PEMADATAN :
1 SEWA ALAT :
-

C.

= Rp.

BIAYA PERSIAPAN / PENDAHULUAN PROYEK :


1
2
3
4
5
6

BIAYA
BIAYA
BIAYA
BIAYA
BIAYA
BIAYA

BIKIN DIREKSI KIT / SITE OFFICE


MOBILISASI DAN DEMOBILISASI PERALATAN & PERSONIL
PENGUKURAN LEVELING TANAH DASAR
BIKIN JALAN AKSES DARI QUARRY KE JALAN UMUM
PEMATANGAN LAHAN SEPANJANG LOKASI KERJA
OVERHEAD PROYEK, BIAYA COMMISIONING TEST PEMADATAN DAN BIAYA TAK TERDUGA LAINNYA

JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK :

REKAPITULASI :
PENDAPATAN :

= Rp.

360,000,000,000

=
=
=
=

Rp.
Rp.
Rp.
Rp.

126,591,500,000
10,086,000,000
60,000,000,000
10,000,000,000

= Rp.

206,677,500,000

= Rp.

153,322,500,000

BIAYA OPERASIONAL (PENGELUARAN PROYEK) :


A.
B.
C.
D.

JUMLAH
JUMLAH
JUMLAH
JUMLAH

BIAYA RITASE DUMP TRUCK DAN QUARRY


BIAYA PEMADATAN
PEMOTONGAN OLEH MAIN KONTRAKTOR
BIAYA PERSIAPAN / PENDAHULUAN PROYEK

KEUNTUNGAN KOTOR PROYEK :

NOTE : BELUM TERMASUK FEE SUKSES UNTUK PIHAK MEDIASI.-

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

75,000,000
230,000,000
100,000,000
3,500,000,000
2,750,000,000
3,345,000,000

= Rp.

10,000,000,000

CILEGON, 12 DESEMBER 2009.