Professional Documents
Culture Documents
and an area of 620 square miles. The LAS comprises 70 ambulance stations, 700
patient transfer vehicles) and over 3,000 people (670 paramedics, 300 control
staff). On average, the Service responds to more than 2,000 emergency calls
per day. The demand for emergency services has increased steadily over the
subsidiary of British Telecom) was scrapped just before implementation due to problems relating
to ‘load test performance criteria’ (Page et al., 1993) at a cost of £7.5million (approximately 10.8
million dollars).
The next Computer Aided Dispatch system went live on Monday, October 26, 1992.
Beynon-Davies (1995) reports that on that night "a flood of 999 calls apparently swamped
operators’ screens… and that many recorded calls were wiped… causing a mass of automatic
alerts to be generated, indicating that calls to ambulances had not been acknowledged”. The
operators were unable to deal with the messages that the system was producing and unable to
clear the queues that developed. These queues slowed the system and when ambulances
completed a job they were not cleared. Thus the system had fewer and fewer resources to
allocate.
The result was chaos in the emergency service. Multiple vehicles appear to have been
sent to some incidents and for others the closest vehicle was not dispatched. One ambulance
arrived to find the patient dead and taken away by undertakers, another ambulance answered a
made their own way to hospital (Finkelstein and Dowell, 1996). Crews reported ambulances
from far afield passing them on the way to a call for which they were better placed. The crews
became very frustrated by the delays in arriving at the scene and the angry reaction from the
public. Crew frustration also led to an increase in radio traffic with crews querying the
allocations or requesting further information. This caused radio bottlenecks and further delay of
ambulance mobilizations.
The system staggered on over the long hours of October 26 and on into the 27th, but was
clearly not viable. Finally at 2 p.m. on the 27th the LAS reverted to a semi-manual method of
operation. Calls continued to be taken on the system (including use of gazetteer1) but the incident
details were printed out and allocation of ambulances was done manually. The mobilization of
ambulances continued to be done via the system. This, together with an increase in the number
Unfortunately, this semi-manual system did not last long. On November 4, 1992 the
system failed to print out calls and shortly after this the LAS reverted to a fully manual, paper
based system, with voice or telephone ambulance mobilization. Luckily no serious ramifications
were reported as this occurred in the early hours of the morning, nevertheless it was a further
blow to the beleaguered LAS. The London Times of November 5,1992, reported a 25 minute
delay in dispatching an ambulance and that senior management were forced to “concede that the
system could not cope with its task”. The Computer Aided Dispatch system was abandoned.
1
A gazetteer pinpoints the location of an emergency call on a map.
AFTER THE CRASH
John Wilby, the CEO of the LAS who had championed the 1992 system, resigned on
October 28, when it became clear that the system was not working. Martin Gorham, deputy
chief executive of South West Thames Regional Health Authority, was appointed in his place on
a temporary basis. Gorham was a career National Heath Services (NHS) manager, and had been
in the NHS for about 25 years, mainly in hospital management and he had been director of
corporate planning for a large health authority. However, he had no direct experience with
ambulance services but was recognized as someone with strong management and change skills.
As Gorham describes it, “I remember somebody saying to me on day two, what do you know
about ambulance services? I said nothing, but I don’t need to, I’ve got 2,500 experts here. You
tell me. I know about management and leadership. And that was my bargain with the Service.
You tell me the whats and I’ll tell you the hows. And if the whats don’t make sense, I’ll ask you
questions until we clarify what the whats really are. I didn’t pretend to have their expertise.
One of the things Gorham had to do immediately was to talk to the union representatives
and try and establish some kind of relationship and dialogue. He saw their role as crucial and
needed them to be, if not completely supportive, at least not too antagonistic. He set out his stall
by saying “I’m not really here for a battle with the trade unions. I’m here to ensure the future of
the LAS and I’m sure that’s what you’re here for too and we’ll achieve it a lot quicker, and a lot
better, working together rather than continuing this highly public confrontation”. Although at the
time this seemed a vain hope, given the previous history of conflict. There had been a very
damaging pay dispute before the current CAD problems and the ramifications were still evident.
Although the dispute had eventually been resolved at a national level the London area had voted
against the settlement. Although, according to Gorham, he felt working together was not
impossible because the unions were apparently quite shocked at the turn of events, particularly
the resignation of Wilby. They had seen him as the problem and now found themselves having
‘won’ that battle but not quite knowing where to go next. In a sense they now needed Gorham as
much as some other people needed him, otherwise they had no frame of reference, which
Nevertheless it could have gone either way. Very early on the union representatives came
into Gorham’s office and demanded that the computer system be switched off completely. At the
time the semi-manual system was in operation. Gorham admits he did not really know what to
do. He had the unions on one side saying it must be shut down and what was left of his
management team telling him that to shut down would be the final abdication. He says “there I
was sat in the middle and didn’t actually understand what they were talking about anyway”. In
fact he managed to buy some time by going to the unions London regional officer to get the staff
Gorham set about making sure minimum management arrangements were in place that
would hold things together. He then tried very rapidly to learn the service by getting out and
meeting people and stressing the basic messages. He was keen to establish a period of stability
and retrenchment. He clearly stated that he was not going to be rushed into changing things, that
he recognised that the Service had been through a period of enormous, very uncontrolled change.
He calculated that people needed a break as they were totally shell-shocked, the last thing he
wanted to do was to be rushed into another ill-thought out scheme. He spent quite some time in
the central control room, because that is where it had happened and describes the staff as being
“in an awful state. They’d all worked very, very hard to make the thing work, and it had just sort
of blown up in their hands. It was like after a bomb, really”. He also spent time with the
ambulance crews and went out with them on calls, a learning process for him and quite a shock
On a longer-term basis Gorham decided to restructure the organization. “The simple fact
was that the current structure was a complete obstacle to making progress. We didn’t have the
level of management resources that we needed. I think that’s one of the reasons why my
predecessor wasn’t able to deliver what he set out to deliver. He just never had the number, the
amount of high level management resource you need to turn around a big high-profile complex
organization which had drifted 10-15 years behind the time.” Gorham adopted a four divisional
structure and created a sort of executive board, which consisted of a Chief Executive, Finance
Director, Director of Personnel, an Operating Director, the four divisional directors, and a deputy
who also managed the Control Room. According to Gorham, “My view was that given the state
of development and the need for effective management of the crews – it was a large fleet,
dispersed throughout 70 stations – we just had to have a much, much stronger management lead
at the operational level. That’s why I went with this very heavy divisional structure”. A planning
function was established and an IT Director, Ian Tighe, was appointed from the West Midlands
Police.
The Page Report (Page et al., 1993), which examined the circumstances leading to the
1992 crash,provided Gorham and his team with some insights into problems with the system.
The 1992 CAD system was the primary means by which the LAS planned to meet new
government efficiency improvement guidelines for the National Health Service (Beynon-Davies,
1995). It was introduced into an atmosphere of mistrust by staff, with no real feeling of
ownership by the majority of users. There was little user involvement in the development of the
system. The system, which would completely change the way calls were taken and dispatched,
continued to be modified practically until the day of implementation. There were serious flaws
in the Computer Aided Dispatch system itself. A significant problem identified in the Page report
was that the 1992 CAD system was developed by an inexperienced, unstable consortium of
organizations, with no one willing to take on a leadership role. (No one consulting company
bidding on the project had both the hardware and software experience called for in the Request
for Proposals; therefore smaller consulting firms joined together for this project. None of the
low bidders had experience developing emergency systems.) The hardware/software platform –
essentially a PC architecture – selected for the 1992 system was unfamiliar and untested in this
environment, and proved to be insufficient for the task. Visual Basic was not a suitable
programming language for a system that had to support huge transaction volumes. Although
management had been warned of delays in readying the control staff, control room, and system
itself for implementation, the scheduled implementation date was viewed as a hard deadline that
In the wider perspective Gorham saw two big themes that needed to be addressed “The
first is cultural change, which is about getting the staff motivated to do the job right. The second
is putting the things in place which allow people to do the job right, some of these are technical
and some are training and recruiting the right people and so on. Essentially, in a nutshell, that’s
what is always required together with the resources to do it”. The Service had been suffering
from under-investment for many years and required substantial investment. “Half the fleet was
off the road at any one time. There were vehicles on the road that were ten years old, they were
falling apart. You just can’t run an Ambulance Service on half a fleet”. In addition the electrical
supply was discovered to be unsafe, the switchboard was dying on its feet, the existing Control
Room was a mess to the extent that it couldn’t simply be refurbished but needed completely
rebuilding.
The morale of the people in the organization was at rock bottom. The situation had been
bad for some time with a lack of confidence in the management, a damaging pay dispute, and
then the 1992 crash. Some of the war stories were frightening; this was nasty stuff, according to
Gorham. “There was a very deep underlying cultural problem that had to be changed. My
assessment was that this was an organization that didn't respect individuals and this was the core
problem”.
In June 1994 the LAS was again “blown off course” by the tragic case of Nasima Begum,
an 11 year old girl, who died after “being denied an ambulance” (Collins, 1997). Nasima Begum
had a liver condition for which she was receiving regular treatment but on this day her condition
required urgent attention. Unfortunately despite four calls she had to wait 53 minutes for the
ambulance only to die of renal failure. The tragedy was compounded by the fact that she lived
only two minutes from a hospital and that the only available ambulance was sent elsewhere, to
someone that did not really require emergency service. Again, and unsurprisingly, very bad
publicity resulted and resulted in another review of the Service, this time by William Wells,
South West Thames RHA Chairman, on behalf of the Secretary of State. The outcome of the
review and the Nasima Begum case helped show people that although some improvements had
been made and working methods changed it was not enough and that the manual approach was
not really a long-term solution. However, the barriers to introducing and gaining acceptance of a
new computer system, seen by many as the villain of the piece, were formidable.