OBP004607

From: (b) (6)


To: (b) (6)

Cc: (b) (6)


Subject: EL PASO P-70 Daily REPORT 8-14-2007.xls
Date: Wednesday, August 15, 2007 12:32:12 AM
Attachments: (b) (6)

Daily PF-70 report attached for review.

Snapshot for the Blackberry users.

All,

40 total panels were installed today for a total of 365 linear feet. Agents also fabricated 21 out of the
31 panels made today. A surplus of over 100 sections of fence is in the fabrication yard ready staging
and installation. We are definitely staying ahead of the install crew.

Evening shift Agents on site fabricating panels and supports as this report is being sent. Their work will
be added on tomorrow’s report.

No panels installed on the evening shift today. Staging of panels at the fence site will continue on
evening shift.

Agents have fabricated 113 panels (1,032 Lin. Ft) in three and a half days and have assisted installing
approximately 457 Lin. Ft. on the fence.

Thank you

(b) (6)
Supervisory Border Patrol Agent
Deming Station
Station (b) (6)
Office (b) (6)