You are on page 1of 82

Dust Abatement Handbook

Air Quality Department

March 2010
Dust Abatement Handbook-Introductory Information

Table of Contents
Introductory Information . ....................................................................................................................................v
Introduction...............................................................................................................................................................vi
PM-10 Nonattainment Area ...............................................................................................................................vii
Coverage of Rule 310.............................................................................................................................................vii
About this Handbook . .......................................................................................................................................viii
Acknowledgements................................................................................................................................................ix
Document Conventions........................................................................................................................................ix
Acronyms.....................................................................................................................................................................x

Section 1 - Before Starting Work


Getting Started......................................................................................................................................................1-1
Why Rule 310?...................................................................................................................................................1-1
Coverage of Rule 310......................................................................................................................................1-1
What’s Not Covered.........................................................................................................................................1-1
Does Rule 310 Apply?.....................................................................................................................................1-1
Is a Permit Required?......................................................................................................................................1-1
A Few Essentials....................................................................................................................................................1-2
Before Starting Work.......................................................................................................................................1-2
While Your Permit is Active...........................................................................................................................1-3
As Your Project Nears Completion.............................................................................................................1-3
What Activities Are Covered by Rule 310?...................................................................................................1-4
What is Considered a Dust-Generating Activity?.................................................................................1-4
What Is Required Before Commencing Work at a Project Site?............................................................1-5
Understand Your Obligations......................................................................................................................1-5

Section 2 - Dust Control Permit


The Dust Control Permit and Dust Control Plan........................................................................................2-1
Applying for a Permit......................................................................................................................................2-1
The Dust Control Plan.....................................................................................................................................2-1
Fees.......................................................................................................................................................................2-1
Receiving Your Permit....................................................................................................................................2-1
What to Do When Your Permit is about to Expire.................................................................................2-1
The Dust Control Plan (310 §402)...................................................................................................................2-2
Updating the Dust Control Plan ................................................................................................................2-2
Changes Made at the Initiative of the Permit Holder ......................................................................2-2

i March 2010
Dust Abatement Handbook-Introductory Information

Table of Contents
Changes Required by the Department . ...............................................................................................2-2
How is the Approved Dust Control Plan Used? (310 §402)...................................................................2-3
Section 3 - Approved Training
Dust Training (310 §309 and §310).................................................................................................................3-1
What Training is Required?...........................................................................................................................3-1
Who Can Provide Training?...........................................................................................................................3-1
Certifications......................................................................................................................................................3-1
Authority to Direct Activities to Comply with Rule 310.....................................................................3-2

Section 4 - Permit Signage and Recordkeeping


Project Information Signs (310 §308)............................................................................................................4-1
Information to Include...................................................................................................................................4-1
When to Update the Sign..............................................................................................................................4-1
Where to Post the Sign...................................................................................................................................4-1
Recordkeeping (310 §502)................................................................................................................................4-2
What Records are Required?........................................................................................................................4-2
Document Retention......................................................................................................................................4-2

Section 5 - Accessible Areas


Areas that are Accessible to the Public.........................................................................................................5-1

Section 6 - Subcontractor and Block Permits


Subcontractors......................................................................................................................................................6-1
Subcontractor Registration..........................................................................................................................6-1
Subcontractors are Subject to Enforcement..........................................................................................6-1
Block Permits and Utility Responsibilities (310 §404) . ......................................................................6-3
Activity Occurring at Locations Not in the Block Permit.................................................................6-3
Enforcement....................................................................................................................................................6-3

Section 7 -Trackout
Trackout Rule (310 §306)....................................................................................................................................7-1
Trackout Clean-up Requirements..............................................................................................................7-1
The Difference between Trackout and Staining...................................................................................7-1
Trackout Controls.............................................................................................................................................7-4
Controlling and Changing Exits during Construction Phases.......................................................7-5

ii March 2010
Dust Abatement Handbook-Introductory Information

Table of Contents
Section 8 - Stabilizing Your Site
Control and Stabilization (310 §304 and §305).........................................................................................8-1
Pre-disturbance................................................................................................................................................8-1
Work Phases.......................................................................................................................................................8-1
Operations..........................................................................................................................................................8-1
Control Measures on Disturbed Areas (no activity for 30 Days or Longer).................................8-2
Trespass...............................................................................................................................................................8-2

Section 9 - Visible Emissions
Visible Emissions (310 §303).............................................................................................................................9-1
On-site Visible Emission Opacity Limits....................................................................................................9-1
Visible Emissions Beyond the Property Line...........................................................................................9-1
High Wind Conditions and Visible Emissions (310 §303.2)....................................................................9-3
Site Operations During High Winds...........................................................................................................9-3
Visible Emissions Originating from Adjacent Lands.............................................................................9-3

Section 10 - Onsite Operations


Unpaved Parking Lots (310 §304.1)............................................................................................................ 10-1
Unpaved Haul and Access Roads (310 §304.2 and §305.7) ............................................................... 10-2
Unpaved Roads(310 §304.2 and §305.7)................................................................................................... 10-3
Trackout Control Devices (310 §306.1)...................................................................................................... 10-4
Hauling Bulk Marterials (310 §305.1-3)...................................................................................................... 10-5
Moving Bulk Materials . .............................................................................................................................. 10-5
Storage Piles, Bulk Material Stacking, Loading and Unloading (310 §304.5 and 305.5) ......... 10-6
Open Storage Piles....................................................................................................................................... 10-6
Managing Open Storage Piles (during active use)............................................................................ 10-6
Managing Open Storage Piles (inactive).............................................................................................. 10-6
Weed Abatement (310§305.8)...................................................................................................................... 10-7

Section 11-Permit Administration
When is an Activity Completed? What Do I Need to
Do to Close Out a Permit? (310§402.c).................................................................................................... 11-1
Changes in Ownership of Property............................................................................................................. 11-2
Transferring a Permit ....................................................................................................................................... 11-3
Changing an Address or an Element of the Dust Control Plan ........................................................ 11-3
Permit Acreage Increase ................................................................................................................................ 11-4
Permit Renewal ................................................................................................................................................. 11-4

iii March 2010


Dust Abatement Handbook-Introductory Information

Table of Contents
Section 12 - Inspections
Compliance Warning Signs....................................................................................................................... 12-1
Specific Warning Signs................................................................................................................................ 12-1
Inspection Rights............................................................................................................................................... 12-2
Once an Inspection Begins, What Do Inspectors Look For?............................................................... 12-3
A Permit............................................................................................................................................................ 12-3
Completed Records . ................................................................................................................................... 12-3
The Approved Dust Control Plan............................................................................................................. 12-3
Whether a Dust Control Coordinator is on Site.................................................................................. 12-3
Water ................................................................................................................................................................ 12-3
Impacts on Sensitive Groups.................................................................................................................... 12-3
Subcontractors ............................................................................................................................................. 12-3
Site Conditions . ............................................................................................................................................ 12-3
Courtesy Inspections........................................................................................................................................ 12-4
Inspection Initiative ......................................................................................................................................... 12-4

Section 13 - Enforcement
Enforcement ....................................................................................................................................................... 13-1
Ombudsman Review........................................................................................................................................ 13-2
Administrative Hearings.................................................................................................................................. 13-2
Public Records Act Requests.......................................................................................................................... 13-3

Section 14 - Test Methods


Test Methods (Visible Emissions)................................................................................................................. 14-1
Determining the Presence of Visible Emissions Crossing a Property Line............................... 14-1
Determining Opacity of Fugitive Emissions........................................................................................ 14-1
Test Methods (Soil Stability)........................................................................................................................... 14-2
Soil Crust Determination (The Drop Ball Test).................................................................................... 14-2
Standard Test Methods for Laboratory Determination
of Water (Moisture) Content of Soil and Rock by Mass (ASTM D2216 - 05) .......................... 14-3
Determining Silt Content Using ASTM Method C136-06............................................................... 14-3
Determining Silt Loading........................................................................................................................... 14-3
Threshold Friction Velocity........................................................................................................................ 14-3
Threshold Friction Velocity with Rock Test Method......................................................................... 14-3

Section 15 - More Helpful Hints


More Helpful Hints............................................................................................................................................ 15-1

Section 16 - Resources
Resources.............................................................................................................................................................. 16-1

iv March 2010
Dust Abatement Handbook-Introductory Information

Table of Contents
Appendices

A. Rule 310 Fugitive Dust from Dust-Generating Operations (revised 1-27-2010)


B Draft Guidance Document for Issuing Notices of Violation Directly to
Subcontractors or to other Non-Permitted Entities Observed Violating
Rule 310 (April 18, 2006)
C. Notice to Comply Interim Policy
D Frequently Asked Questions
E Dust Compliance Fact Sheet (Fall 2008)
F Permit Signage Fact Sheet
G Gravel Pads Fact Sheet
H Dust Control Permit Application Package
I Permit Acreage Increase Request Form
J Permit Cancellation Request Form
K Permit Name Change Request Form
L Dust Control Plan Change Form
M Parcel Change Notification Form
N Dust Control Recordkeeping Forms
Self Inspection and Control Measure Application
Employee List of Training Certifications
Subcontractor Registration List
O Application for Subcontractor Registration
P Subcontractor Registration Renewal Application
Q Subcontractor Registration Change Request Form

Most of the above documents are directly linked in this pdf


version so you can readily access the document online.
Only those documents not accessible online are included in the
Appendices

v March 2010
Dust Abatement Handbook-Introductory Information

Introduction
If there is a scene that epitomizes the West in early
movies and song, it is that of the dusty trail. Cattle
drives and wagon trains are accompanied by
prevalent, pervasive dust. If there is anything that
can be readily created in the West, it is dust.

Today, dust (also known as particulate matter)


is an unwelcome and unhealthy feature of poor
stewardship of our lands. While dust from disturbed
lands is predictable, it is also preventable.
The Maricopa County Air Quality Department’s
(department) Rule 310—Fugitive Dust from Dust-
Generating Operations is a comprehensive set of
regulations that, when properly implemented, will
dramatically reduce dust emissions and improve
air quality. The need for improved air quality for
particulates is urgently important in Maricopa
County.
While air quality is often good to excellent, the
number of days that do not meet or approach the
particulate air quality standard established by the
United States Environmental Protection Agency
(EPA) are far too many and leave the region in non-
attainment. The result of unhealthful air quality
on far too many days is the imposition of stringent
controls designed to curtail and control emissions.
Rule 310 is a critical element in Maricopa County’s
strategy to achieve improved air quality, and broad
compliance with the Rule’s provisions is essential.
The department has instituted an aggressive
program to monitor compliance with the Rule,
and strict enforcement is leading to reduced dust
emissions.
Every approach to improving air quality comes with
a learning curve. Rule 310 imposes requirements
and opportunities for interpretation under a
variety of scenarios. In developing this handbook,
the department has reached out to those most
affected and asked for and received their input. The
intent of this handbook is to craft a practical guide
offering a comprehensive overview of how the Rule
310 is interpreted that will be useful and used—a
document that will become dog-eared and tattered
through frequent reference.

vi March 2010
Dust Abatement Handbook-Introductory Information

PM-10 Nonattainment Area


The PM-10 nonattainment area includes a ordinances (such as residential wood-burning) as the
substantial portion of Maricopa County that area of applicability for those respective regulations.
includes most of the metropolitan Phoenix area.
This area has been deemed a “nonattainment” Coverage of Rule 310
area for air quality by the EPA and the Arizona
Department of Environmental Quality (ADEQ). Although Indian communities are found within the
borders of Maricopa County, the department has no
The PM-10 nonattainment area exceeds the jurisdiction over them, because they are considered
acceptable national standard for PM-10 pollution sovereign nations.
levels. PM-10 (particulate matter 10 microns, or
smaller, in diameter) includes dust, soot, and other This handbook does not apply to developments in Pinal
tiny bits of solid material that are released into County.
and move around in the air. PM-10 is produced by Additionally, normal agricultural practices are under
many sources, including exhaust from cars, trucks, the jurisdiction of ADEQ, not Maricopa County.
buses, and planes; industrial sources like power Construction activities on agricultural land are subject
plants; fugitive dust sources like construction, to Rule 310.
mining, and agricultural activities; as well as fuel
combustion like the operation of fireplaces and Rule 310 applies to all of Maricopa County regardless
wood stoves. of whether a site is located in the PM-10 nonattainment
area or Area A (two related but distinct designations).
Area A differs from the PM-10 nonattainment area.
Within Area A, clean-burning gasoline measures
(emissions testing; summer and winter fuel
formulations) are applicable. The boundary has
been used by many other state statues, rules, and

PM-10 Nonattainment Area Map showing Area A

vii March 2010


Dust Abatement Handbook-Introductory Information

About this Handbook


The purpose of this handbook is to provide a practical
guide offering a comprehensive overview of the
department’s policies and interpretations of Rule 310.
The intent is that this guide will be useful and used.
The handbook is organized to respond to topical
questions and it is structured to provide answers to the
most commonly encountered compliance challenges.
The department has also produced the Dust Abatement
Field Guide for the Construction Industry, a pocket-sized,
quick reference designed to provide information about
how to comply with Rule 310 in the field. While not
as comprehensive as this handbook, the Field Guide
is a durable, reliable, and brief summary of the most
important points that designated site representatives
and workers in the field should know about Rule 310.

Disclaimer
This Dust Abatement Handbook and the related Field
Guide are provided to assist in better understanding
the provisions of Maricopa County Air Quality
Department’s Rule 310—Fugitive Dust From Dust-
Generating Operations. The contents of this handbook
and the Field Guide should not be viewed as the
definitive statement of the Rule and how to achieve
compliance. Where the clear language of Rule 310 and
any formally issued policy related to Rule 310 conflicts
with this handbook or the Field Guide, Rule 310 and the
policy will prevail.
The user of this handbook should clearly understand
that the discussion contained in this document is not
binding. The Rule itself should be relied upon for a final
determination of compliance. This handbook is not
intended to serve as an alternative to Rule 310 which
is, by itself, the definitive statement of dust-control
requirements.

Updates
This document is expected to be updated from time to
time. If you identify any area that requires clarification,
please let us know. Send your comments to
dickersond@mail.maricopa.gov. You may wish to check
the website from time to time to see if any revisions are
posted.

Where to Find the Full Text of Rule


310
Rule 310 is available online at http://www.maricopa.
gov/aq/divisions/planning_analysis/rules/docs/310.
pdf. Rule 310 is also an appendix to this document.

viii March 2010


Dust Abatement Handbook-Introductory Information

Acknowledgements
This handbook and the related field guide were developed in 2009 in a collaborative effort between the regulated community
and the Maricopa County Air Quality Department. The basic document was developed by an internal working group within the
Department and review and comment was provided by an external working group. The external working group was comprised
of members of the regulated community who will rely on the contents of this handbook and field guide to improve compliance
with Rule 310. Additional support was provided by Logan Simpson Design, Inc., working under contract with the department.

External Working Group Internal Working Group


Alisa Schroder, Director of Compliance Dennis Dickerson, Ombudsman
Meritage Homes Ken Hooker, Supervisor
Adam Lebrecht, Environmental Manager Monica Perrin, Inspector
DL Withers Construction, LC
Aaron Jensen, Inspector
Amanda McGinnis, Senior Vice President
Associated General Contractors Logan Simpson Design Inc.
Brian Kasitz, Project Environmental Coordinator Wayne Colebank, RLA, Principal
Kiewit
Kevin Boesch, CPESC IT, Senior Permitting Specialist
Cameron Flower, Senior Environmental Manager
Trace Baker, Technical Publications/Document
Kitchell
Development Specialist
Katea Ravega, Attorney at Law
Brian Nething, Graphics Specialist
Quarles and Brady
Nathan White, Environmental Manager
Beazer Homes
Paul Haggerty, Vice President
Lennar
Roger Ferland, Attorney at Law
Quarles and Brady
Spencer Kamps, Vice President of Legislative Affairs
Home Builders Association of Central Arizona

Document Conventions
When a reference to a period of days is mentioned, it
will mean calendar days unless otherwise specified.
It is recommended that this document be printed in
color to allow all graphical features to be seen.
The reference to the Control Officer in the document
refers to the Director of the Air Quality Department.

ix March 2010
Dust Abatement Handbook-Introductory Information

Acronyms
Commonly Used Rule 310-Related Acronyms
ABC Aggregate Base Course
ASTM American Society for Testing and Materials
ATI At the Time of the Inspection
CCM Contingency Control Measure
DCC Dust Control Coordinator
DCP Dust Control Plan
DG Decomposed Granite
HPA High Pollution Advisory
HPV High Priority Violation
HT Haul Truck
NOV Notice of Violation
NTC Notice to Comply
OAC Order of Abatement by Consent
PAAP Paved Area Accessible to the Public
PCR Permit Cancellation Request
PCM Primary Control Measures
PM Particulate Matter
PM-10 Particulate matter whose size is 10 micrometers or smaller (One micrometer is equivalent to 3.93700787 × 10-5 inches)
TOCD Trackout Control Device
TFV Threshold Friction Velocity
TO Trackout
VE Visible Emissions
VEE Visible Emissions Evaluation

x March 2010
Section 1 - Before Starting Work
Dust Abatement Handbook-Section 1 Before Starting Work

Getting Started
Why Rule 310? and access roads, disturbing surface
areas associated with a project site
Construction activities that
take place on agricultural lands
Because air quality in the greater and installing initial landscaping are subject to Rule 310. For
metropolitan Phoenix area does not or landscape maintenance using example, construction of a new
meet air quality standards for PM-10, it mechanized equipment. food processing warehouse
is necessary to a have a comprehensive Rule 316 - Nonmetallic Mineral on farmland would be covered
program to control PM-10 air pollution. Processing is another rule that and a permit required if the
Maricopa County’s Rule 310 - Fugitive applies a separate set of dust control surface area disturbed met
Dust from Dust-Generating Operations, requirements on specific activities. or exceeded 0.1 acre. Also,
was developed to provide part of this Although many features are similar, trackout originating from
comprehensive program. there are distinct differences.
agricultural lands is covered
Coverage of Rule 310 What’s Not Covered? under Rule 310 and is subject
to enforcement.
Rule 310 is a county-wide rule and Although tribal communities are found
can be enforced in any portion of within the borders of Maricopa County,
Maricopa County. Rule 310 also applies the department has no jurisdiction
regardless of whether a site is located over them because they are legally Does Rule 310 Apply?
in the PM-10 Nonattainment Area considered sovereign nations. Note:
or Area A (two related but distinct check with tribal governments as If you are engaged in a dust-generating
designations). some have their own dust control activity covered by Rule 310, the rule
requirements. requirements apply at all times (24/7).
Rule 310 applies to any construction
Even if you do not need to have a permit,
activity that results in soil disturbance. This handbook does not apply to the dust control provisions of Rule 310
While a few activities are exempt, developments in Pinal County. still apply to your project.
a good rule of thumb is to assume Additionally, normal agricultural
that the activity you are planning is
covered by Rule 310 until you confirm
practices are under the jurisdiction
of the Arizona Department of
Is a Permit Required?
otherwise. Environmental Quality (ADEQ), not The threshold for a permit is based on
The following activities are definitely Maricopa County. the amount of surface area disturbed
covered: Land clearing using by a project. If the area disturbed will
mechanized equipment, earthmoving, meet or exceed 0.1 acre (4,356 square
weed abatement by discing or blading, A tenth of an acre is a relatively feet) then a permit is required.
excavation, construction, demolition, small amount of land. Most
bulk material handling, storage custom home residential
and or transporation operations,
projects will easily fall under
operating outdoor equipment, using
staging areas, parking areas, haul
the criteria to have a permit. Helpful Hint
If in doubt, ask us. Department
staff are available to answer your
questions and a good place to
start is to contact the Desk Duty
Supervisor at (602) 506-6734.

The opacity of dust emissions


from dust-generating
operations, as pictured at left,
cannot exceed 20%.

1-1 March 2010


Dust Abatement Handbook-Section 1 Before Starting Work

A Few Essentials
What do you need to do to ensure is deemed complete. Also, factor in The department has up to
that a project is in compliance? time for postal delivery of the permit. 14 days to review a paid,
The following list of important Do’s technically complete permit
33 As part of the permit application
and Don’ts are intended to provide application package.
a snapshot of some of the most process, you will be required to fill
out an application which includes This timetable does not include
significant provisions of Rule 310. This
the Dust Control Plan. The approved postal delivery. Line up a Dust
handbook provides more expansive
permit and the plan must be on site Control Coordinator, hydrants,
discussions on each of these provisions
in later sections. before you start work. and control equipment to
be used at your site prior to
Before Starting Work 33 Read and understand your
approved Dust Control Plan. During
submitting the application
package. Consider municipal
33 Understand your project— preconstruction meetings inform all requirements, such as backflow
boundaries, type of work, areas project workers of Dust Control Plan prevention devices and
where soil will be disturbed, locations requirements and ensure a successful obtaining hydrant meters.
of exits and entrances, storage project start-up.
areas, equipment paths—consider 33 Request a courtesy inspection by an
everything that could potentially air quality inspector or their presence
create dust. at the preconstruction meeting to Helpful Hint
33 Don’t start a project that disturbs answer questions. One courtesy Ideally, the Dust Control Plan
greater than or equal to 0.1 acre inspection is allowed for each should be filled out by someone
until you have obtained a dust project phase (generally, these are familiar with controlling dust
control permit. Include paths, foot demolition, land development, and emissions.
traffic areas, and all other areas vertical construction).
that are anticipated to result in soil 33 Familiarize yourself with Rule 310 and size, your application must identify
disturbance, in your calculations to this handbook. The Rule contains the soil texture found at the site. The
determine the size of the project. important details and requirements soil texture is generally found in a
33 Plan ahead to ensure you receive your that may not be addressed in the soils report prepared for the project
dust control permit before you start handbook. Develop a working site (alternatively, Appendix F of the
work—start the application process knowledge of the dust control department’s rules and regulations
early. The department may require 14 requirements and related challenges. contains a map of soil descriptions).
days for review once an application 33 If your project is 1 acre or larger in 33 While trackout is prohibited for any

Installing a Gravel Pad

1-2 March 2010


Dust Abatement Handbook-Section 1 Before Starting Work

A Few Essentials cont’d.


size project, if the project site is 2
acres or larger or you will be moving
100 yd3 of material per day, establish a
controlled exit with a trackout control
device.
33 If your project disturbs an area greater
than one acre, the site superintendant
must have completed the Basic Dust
Control Training Class within the past
three years
33 If your project disturbs an area five
acres or larger, an on-site Dust Control
Coordinator is required. Make sure
you have lined up a certified Dust
Control Coordinator with a valid
certification before starting work.
33 Ensure that you are prepared to
control dust prior to starting a project. While Your Permit is Active As Your Project Nears
(for example, secure a water source
and be ready to apply water prior to 33 Make sure subcontractors have a Completion
initiating soil disturbance). current registration number.
33 Know when your permit expires and
33 Post required project information 33 Never allow on-site emissions to place the expiration date on your
signs when the permit area is five exceed 20% opacity. calendar along with the date by
acres or greater. 33 Actively monitor trackout during the which the permit renewal application
course of the workday. must be submitted (be sure to
allow enough time for processing
33 Do not allow any visible dust to cross
and postal delivery). Note: the
Helpful Hint your property line.
33 Apply water to control emissions
department has up to 14 days to
process your complete application.
Once you understand the project before, during, and after earthmoving If the application is not complete or
and the obligations of your Dust operations (Note: additional control errors are present, additional time will
Control Plan, factor dust-control options are available). be required to resolve any problems.
costs into your project bid and
budget. Include the cost of 33 If the primary dust control measure is 33 Apply for permit cancellation when
signage, training, dust-control ineffective, immediately implement work is completed and ensure that
staff, trackout control devices, and the contingency measure from your disturbed areas within the permit area
all other personnel and materials approved Dust Control Plan. While are stabilized and meet stabilization
used to control dust. the contingenecy measure can be standards.
applied along with the primary
Provide a Dust Control Plan with control measure, use of both,
bid materials to subcontractors so concurrently, is not required.
they understand what is required
and can submit accurate bids. 33 Document the use of the contingency
measure in your daily log.
33 If dust emissions cannot be
controlled, stop work.
33 Understand and meet stabilization
standards.

1-3 March 2010


Dust Abatement Handbook-Section 1 Before Starting Work

What Activities Are Covered by Rule 310?


Rule 310 regulates dust emissions Examples of activities that can disturb Remember:
associated with construction activities. 0.1 acre include:
Disturbed surfaces do not have
Generally, if the surface of the ground
33 parking five pickup trucks next to to be contiguous (connected
is disturbed in some manner, or if bulk
materials are moved from one location each other on open dirt. to or adjacent to each other)!
to another or stockpiled, the potential 33 staging 10 yd³ of aggregate base.
exists for fugitive dust emissions.
33 driving 360 feet onto undisturbed material hauling and/or transporting,
Rule 310 applies to all activities that
may result in fugitive dust emissions land. bulk material stacking, loading, and
and a permit is required if the area to unloading operations).
be disturbed is 0.1 acre or more. What is Considered a 33 storage and/or transporting
Maricopa County defines “disturbance”
as “a portion of the earth’s surface or
Dust-Generating Activity? operations (e.g., open storage
piles, bulk material hauling and/or
material placed on the earth’s surface A primary dust-generating activity is transporting, bulk material stacking,
that has been physically moved, any operation capable of generating loading, and unloading operations).
uncovered, destabilized, or otherwise fugitive dust, including but not limited
modified from its undisturbed native to, the following: 33 operation of any outdoor equipment.
condition if the potential for the 33 operation of motorized machinery.
33 land clearing, maintenance, and
emission of fugitive dust is increased
by the movement, destabilization, or land cleanup using mechanized 33 establishing and/or using staging
modification.” equipment. areas, parking areas, material storage
If you are engaged in dust-generating 33 earthmoving. areas, or access routes to and from a
operations, no matter how small, site.
33 weed abatement by discing or
you must control those emissions blading. 33 establishing and/or using unpaved
and comply with Rule 310. If you are haul/access roads to, from, and within
disturbing 0.1 (one-tenth) acre or more, 33 excavating.
a site.
you must comply with Rule 310 and 33 construction.
obtain a dust-control permit. One-tenth 33 disturbed surface areas associated
of an acre is just 4,356 ft². 33 demolition. with a site.
33 bulk material handling (e.g., bulk 33 installing or maintaining landscaping
while using mechanized equipment.

Bulk Material Pile

1-4 March 2010


Dust Abatement Handbook-Section 1 Before Starting Work

What Is Required Before Commencing Work at a Project Site?


Be safe—get a permit before doing 33 If the site is one acre or greater,
anything that will disturb the land. a description of the site-specific Become familiar with Rule 310
33 Apply for and receive a permit before soil designations must be and its requirements.
doing anything that will disturb as prepared. (See Appendix F of the Rule 310 is available through
little as 0.1 acre of land. Maricopa county Air Pollution the department’s website at
Control Rules and Regulations). www.maricopa.gov/aq/
33 Prepare a Dust Control Plan and divisions/planning_analysis/
submit it to the department as part Still need a permit even though rules/docs/310-1001.pdf.
of your permit application. your existing permit may soon
expire?
33 Remember: year or until the permit is closed out
RR permit coverage is required for 33Apply for a new permit at least 14 by the department).
only those areas in your permit calendar days prior to expiration.
The permit holder is ultimately
that will be disturbed, including Keep in mind:
responsible for ensuring the
the working area, prep areas, and 33 A new Dust Control Plan must be permitted site is in compliance
parking areas. You can add areas as submitted. at all times to prevent risks to the
needed using the Permit Acreage environment and the public, even
Increase Request Form. 33 A new permit number will be
issued. if noncompliance is the result of an
RR the dust control permit is good for action by an owner, subcontractor, or
one year (permits for shorter or 33 The project information sign trespasser.
longer periods are not available). should be updated with the new
permit number. 33 The provisions of an approved
RR a dust control permit is not Dust Control Plan are binding and
effective until the fee is paid.
Understand Your enforceable—if you don’t intend to
RR a dust control permit and the implement a provision of the plan
approved Dust Control Plan must Obligations don’t include it. Conversely, if you
be kept on site at all times. Work plan to take an action to control dust,
33 The applicant’s signature on the
cannot begin on the site until the ensure that action is included in your
dust control permit application
approved permit is received and permit as one of your options.
represents a binding agreement
onsite.
and obligates the applicant to 33 The approved Dust Control Plan
RR all project workers on your site, implement identified control is effective 24/7, including holidays.
including subcontractors, should measures on the permitted area Therefore, dust must be controlled
be familiar with the plan. for the life of the permit (i.e., one 24/7.

Helpful Hint
An easy way to ensure that
the permit and approved Dust
Control Plan are on site at all
times is to post a copy of the
permit document to some
semi-permanent onsite feature.
Alternatively, the permit can be
kept in a more secure location
onsite. The most important
thing is to ensure that the permit
can be produced during an
inspection. While affixing the
permit to a fence as shown in
the photo is acceptable, the site
superintendant should consider
having a backup copy handy
in case of vandalism or loss of
Posted Permit the documents.

1-5 March 2010


Section 2 - Dust Control Permit
Dust Abatement Handbook-Section 2 Dust Control Permit

The Dust Control Permit and Dust Control Plan


Applying for a Permit completed by someone familiar with
dust-generating operations.
Receiving Your Permit
The dust control permit application The completed permit will be sent to
package, which contains instructions Fees the applicant’s address. Allow up to
for filling out the permit application 14 days for permit processing plus
Basic fees for a dust control permit
forms as well as the Dust Control sufficient time for delivery by
(permit valid for one year) are
Plan associated with the dust control U.S. Postal Service First Class mail.
calculated on the basis of the total
permit, is located online on the
department’s website at http:// disturbed acreage (Note: this is a new
fee structure that went into effect on
What to Do When Your
www.maricopa.gov/aq/divisions/
compliance/dust/docs/pdf/ July 1, 2010). Fees are established Permit is about to Expire
according to the following schedule:
DustControlPermitApplicationPackage.
Still need a permit even though your
pdf.
$795 0.1 to less than one acre existing permit may soon expire?
Completed applications should be Apply for a new permit well before
submitted, along with payment of the your current permit is about to expire.
$1,325 One acre to less than ten
fee, to: Remember to allow up to 14 days for
acres
One Stop Shop the department to review the complete
501 North 44th Street, Suite 200 $3,855 Ten acres to less than 50 application, as well as time for postal
Phoenix, Arizona 85008 acres delivery.

Include the appropriate fee for your Keep in mind:


dust control permit application. $6,425 50 acres to less than 100
33 a new Dust Control Plan must be
The completed application can be acres
submitted with the new permit
submitted to the One Stop Shop in application.
person or by mail with payment by $9,635 100 acres to less than 500
check or money order. A credit card or acres 33 only include those areas that are
cash may be used for payment if the still disturbed. Hardscaped and
application is submitted in person at $15,415 500 acres or greater landscaped areas do not need to be
the One Stop Shop location. included.
33 a late fee of $100 is required for any
The Dust Control Plan application submitted in response to
33 a new permit number will be issued.
a violation. 33 the project information sign should
The Dust Control Plan is completed by be updated with the new permit
The fee for a block permit is $2,000.
the applicant and submitted as part number.
of the permit application. The Dust Make checks payable to “Maricopa
Control Plan is an integral part of the County Air Quality Department” or
permit and is effective upon approval “MCAQD.”
of the permit. Given its importance,
consider having the Dust Control Plan

Step 1 Step 2 Step 3 Step 4 Step 5


The Control Officer
approves the
permit and sends
the approved
permit and Dust
The applicant The Department Control Plan to the The approved
The One Stop Shop
completes permit conducts a permit applicant. permit and Dust
receives the
application, including technical review of Control Plan are
application, confirms
the Dust Control Plan, the application received at the
fee payment, and
and submits the and Dust Control project site and
determines if the
application with the Plan within 14 The Control Officer approved
application is
appropriate fee days after rejects the dust-generating
complete.
payment. submittal. application and activities can begin.
contacts the permit
applicant with
instructions. Return
to Step 3

Permitting Administrative Process


2-1 This page updated June 30, 2010
Dust Abatement Handbook-Section 2 Dust Control Permit

The Dust Control Plan (310 §402)


The Dust Control Plan is submitted as Changes Made at the Initiative permit holder requiring revisions to the
part of the permit application. Dust Control Plan. The permit holder
The department reviews each Dust of the Permit Holder must submit required revisions within
Control Plan for completeness and The permit holder may request changes 3 working days of receipt of the
technical accuracy. to the Dust Control Plan for: notice. If more than 3 working days
are needed, the permit holder can
33 changes in acreage. request an extension. Even though
33 changes in the designated Dust the extension is available, it is not
Control Coordinator and/or his or her guaranteed that the extension will be
contact information. granted. In any event, compliance with
Rule 310 is expected immediately.
33 substantive changes in operations.
33 any change requested by the Dust
Control Coordinator or designated

Updating the Dust


site representative. Helpful Hint
33 changes to primary or contingency OPEN YOUR MAIL - often
Control Plan control measures documents will have a deadline
or action date included. Don’t
The approved Dust Control Plan Changes Required by the miss critical deadlines by failing to
can be revised at the initiative of Department open mail from the department
the permit holder or as directed by immediately.
the department. At times, dust emissions may continue
to occur even if the control measures
Revisions to the Dust Control Plan are contained in the Dust Control Plan
not effective at time of submittal—they are followed. When this occurs, the
must be approved by the department department will issue a notice to the
before becoming effective. Changes
to the Dust Control Plan required by
the department’s control officer must
be submitted within 3 working days of
receipt of the control officer’s directive.

Helpful Hint
Allow at least 14 days for the
Department to approve revisions
to the Dust Control Plan. You
must follow your existing,
approved permit and plan until
you have received notice from the
department that your changes
have been approved.

2-2 March 2010


Dust Abatement Handbook-Section 2 Dust Control Permit

How is the Approved Dust Control


Z.1
Plan Used (310 §402)
Operations
P= Primary Control Measure
P
From the department’s perspective, the approvedC Apply
Dustwater
Control
(Fill outPlan is a I, “Water” on pp. 37-41)
Category

contract between the permit holder and the department—its terms are The first approach you
P C Pave (Choose one of the following): Beginning of Project* During Project*
enforceable, even against subcontractors working *Must
on aspecify
site. additional
The measures implement to controlEnddust
primary control measure(s) that will be in place prior to paving
of Project*

included in the Dust Control Plan are the measures that inspectors will expect emissions
P C Limit vehicle trips to no more than 20 per day per road AND limit vehicle speeds to no more than 15 m.p.h. In the
you to apply to your site. space provided, list the maximum number of vehicle trips on the unpaved access areas/haul roads each day (including
number of employee vehicles, earthmoving equipment, haul trucks and water trucks) and a description of how vehicle
Primary controls listed in the plan are to be used first.
speedsContingency
will be restricted tomeasures
no more than 15 m.p.h.: C= Contingency Control
are to be used when the primary controls are not effectively controlling dust Measure
emissions.
The backup strategy to be
C Cease operations, NOTE: This option CANNOT be considered a primary
If primary controls or contingency measures don’t result in effective used when the primary control
control, the approved Dust Control Plan mustP C revised.
be Other:
The obligation is measure is not effectively
clearly on the permit holder to control dust emissions. If emissions cannot
controlling dust emissions
be adequately controlled using all available
Or, explainmeasures, the project
why this sub-category willmeasures
and its control be in are not applicable
violation of Rule 310 and subject to enforcement by the department.

Z.1 Operations

P C Apply water (Fill out Category I, “Water” on pp. 37-41)

P C Pave (Choose one of the following): Beginning of Project* During Project* End of Project*
*Must specify additional primary control measure(s) that will be in place prior to paving

P C Limit vehicle trips to no more than 20 per day per road AND limit vehicle speeds to no more than 15 m.p.h. In the
space provided, list the maximum number of vehicle trips on the unpaved access areas/haul roads each day (including
number of employee vehicles, earthmoving equipment, haul trucks and water trucks) and a description of how vehicle
speeds will be restricted to no more than 15 m.p.h.:

C Cease operations, NOTE: This option CANNOT be considered a primary control measure.

P C Other:

Or, explain why this sub-category and its control measures are not applicable

This form has been correctly filled out.

Z.1 Operations

P C Apply water (Fill out Category I, “Water” on pp. 37-41)

P C Pave (Choose one of the following): Beginning of Project* During Project* End of Project*
*Must specify additional primary control measure(s) that will be in place prior to paving

P C Limit vehicle trips to no more than 20 per day per road AND limit vehicle speeds to no more than 15 m.p.h. In the
space provided, list the maximum number of vehicle trips on the unpaved access areas/haul roads each day (including
In this example, the number of employee vehicles, earthmoving equipment, haul trucks and water trucks) and a description of how vehicle
speeds will be restricted to no more than 15 m.p.h.:
form at right is incorrect
because ceasing
C Cease operations, NOTE: This option CANNOT be considered a primary
operations has been
marked as a primary P C Other:
control measure - a
choice which is not Or, explain why this sub-category and its control measures are not applicable

allowed.

This form has been incorrectly filled out.

Z.1 Operations 2-3 March 2010


Section 3 - Approved Training
Dust Abatement Handbook-Section 3 Approved Training

Dust Training (310 §309 and §310)


What Training is Certifications
Required? There are two levels of certification: Comprehensive Certification
basic and comprehensive. Comprehensive training is a six-hour
Rule 310 requires certain personnel at training that covers dust control
a permitted site to receive training on Basic Certification measures in detail. Individuals
dust control and emission reduction To earn basic certification, individuals who complete this training earn
strategies. The level of required must complete the three-hour training comprehensive certification and
training and which personnel must course. As indicated in the table, may be designated as a Dust Control
be trained depends on the amount of water truck and water haul drivers are Coordinator.
acreage disturbed within the permitted required to earn basic certification. On projects that disturb 5 or more
area. The table below shows who must
On projects that disturb more than 1.0 acres, the permit holder must identify
be trained and the level of training
acre, the permit holder must designate a certified Dust Control Coordinator
required by size of the disturbed area.
a site representative who has earned who must be present at all times during
Who Can Provide Training? basic certification. primary dust-generating activities.
In addition, a Dust Control Block Permit A Dust Control Coordinator must
The department has established an holder is required to have at least one complete the comprehensive training
approved training program to certify individual who has received the basic program once every three years.
individuals who have successfully dust training certification on those sites
completed required training. Training on which there is greater than one acre
must be given by a trainer who has of surface disturbance. Note: Comprehensive training includes
been approved by the department. basic certification.
A list of approved trainers is available Employees required to have the basic
on the department’s website at dust training must renew their training
www.maricopa.gov/aq/divisions/ certification once every three years.
Dust Control Coordinators:
compliance/dust/dust_control_
training/default.aspx. • Are required on projects
Visible Emission Certification that disturb five or more
Trainer Program Certification of Dust Control
acres
Interested in becoming a trainer? Coordinators is not required • Must have earned the
Contact the department for information but is strongly recommended. comprehensive certification
on the process.
• Must be identified in
the dust control permit
application (Part 2, Question
Training Requirements by Disturbed Area Acreage* #5)
Personnel • Must be onsite during dust-
generating activities.
Representative

Coordinator**
(Comprehensive
Dust Control
Water Truck/

3-hour course)

3-hour course)

6-hour course)
certification—

certification—

certification—
Water Haul
Driver
(Basic

(Basic
Site

Disturb ≥ 0.1 acre X Helpful Hint


Disturb 1.0-4.99 acres X X The need for the Dust Control
Disturb ≥ 5.0 acres X X Coordinator to be onsite during
*“Areas of disturbance” may include parking, staging, and stockpiling areas, as dust-generating activities cannot
well as driving over previously disturbed areas. be over emphasized. Experience
**The permit holder must give the Dust Control Coordinator authority to act has shown that violations often
to control dust. Permit holders who do not provide this authority can receive result when the Dust Control
an NOV. Dust Control Coordinators who accept work without the authority
to act to control dust can lose their certification. Coordinator is not available to
oversee operations.
Training Requirements By Disturbed Areas

3-1 March 2010


Dust Abatement Handbook-Section 3 Approved Training

Dust Training (310 §309 and §310) (cont’d)


Authority to Direct
Activities to Comply with
Remember: Helpful Hint
33 trained site representatives are Courtesy inspections and
Rule 310 required on projects that disturb 1.0- industry presentations given
4.99 acres; must be designated on the by department staff represent
To receive a dust control permit, dust control permit; and must have another opportunity for training.
the permit holder must name a basic certification. If you organize an event such as
site representative or Dust Control a gathering of your firm’s project
Coordinator who has the level of 33 dust Control Coordinators are superintendants, it is possible to
training required based on the area required on projects that disturb five schedule an inspector to provide a
disturbed by the project (see table on or more acres, must be designated presentation on aspects of
page 3-1). If a site representative or on the dust control permit, and must Rule 310.
Dust Control Coordinator is required have certification for attending the
based on the size of the project, he or Note: industry presentations
Comprehensive Dust Control training. are free of charge but do not
she must be given the authority to act
to control dust by the permit holder. 33 permit holders who do not give site take the place of formal training
This means the site representative or representatives and Dust Control certifications.
Dust Control Coordinator must be able Coordinators authority to act are
to direct actions within an area covered subject to enforcement under
by a permit to ensure compliance Rule 310.
of the project but there are additional
with Rule 310—including ceasing
33 a Notice of Violation can be issued if permitted, yet undisturbed, phases
operations, if necessary, to ensure that
a Dust Control Coordinator does not waiting to be developed.
dust is not generated.
have full authority to ensure that dust In this scenario, a Dust Control
control measures are implemented Coordinator would be required onsite
Helpful Hint on site. unless the undisturbed phases were
clearly identified in the dust control
Maintain a legible photocopy A Dust Control Coordinator is required permit, as well as the Dust Control
of the certification card for each whenever the disturbed area reaches Plan, and the undisturbed area on
trained personnel member in a or exceeds five acres. In some the project site was clearly marked
file or binder located onsite so instances, a permit area may develop with access restricted to those project
that it is accessible during an such that fewer than five acres of phases not yet active.
inspection. disturbed surface remain in one phase
When fewer than five acres of land (in
all phases of the project) remain to
be disturbed, then the Dust Control
Coordinator requirement would no
longer apply if previously disturbed
areas have been stabilized and notice
of stabilization has been provided to
the department.

The department’s director


has the authority to suspend
or revoke the Basic or
Comprehensive Dust Control
certification for cause. For
cause means:
33 inappropriate ethical activities
or conduct associated with the
dust control program or
33 repeated failure to follow
training requirements
Only approved trainers can provide certified dust control training

3-2 March 2010


Section 4 - Permit Signage and Recordkeeping
Dust Abatement Handbook-Section 4 Permit Signage and Recordkeeping

Project Information Signs (Rule 310 §308)


Information to Include When to Update the Sign Helpful Hint
For sites permitted at five acres or more, You must change your project To avoid uncertainty when
the project information sign must information sign to reflect changes to multiple entrances are used, a
contain the information shown below the dust control permit or Dust Control permit holder is encouraged to
(using text size of at least four inches) Plan, such as: place signs at each site access
and be placed at the main entrance of point, especially where another
33 a new contact name or phone project entrance is more visible
the site:
number. to the public. However, only one
33 project name. sign is required by Rule 310.
33 a change in the project name.
33 permit holder’s name. If only one sign is posted, it
33 a new permit number.
33 current dust control permit number. should be placed at the location

33 name and local phone number of Where to Post the Sign that would be viewed by
members of the public as the
person(s) responsible for dust control. main entrance to the site.
The main entrance to a site is that
In addition, your sign must include the which would normally be used by
following text: employees and subcontractors when
gaining site access. As a project
Dust Complaints?
matures, an additional entrance may be
Call Maricopa County Air Quality
established.
Department
(602) 372-2703 The purpose of the signage
requirement is to provide the
Should the official complaint phone
public with information about the
number ever change, the department
permit status of the project, and the
will send a notice to all permit holders
sign should be posted where that
providing the new number.
information is most prominently
observed by members of the public.
The project sign requirement is based
on the original acreage permitted. A
sign is still required even if a project is
reduced to under five acres.

ACME ESTATES, AZ123 DEVELOPMENT


Helpful Hint
Don’t forget to change the project
PERMIT NUMBER 144501 information sign to reflect
changes in your permit.
CONTACT: ANITA PERMIT (602) 000-000 For example:
• changes to the project name
DUST COMPLAINTS? or permit holder name
CALL THE MARICOPA COUNTY
• a new permit number
AIR QUALITY DEPARTMENT
• contact information for the
(602) 372-2703
project’s responsible official

Permit Sign Example

4-1 March 2010


Dust Abatement Handbook-Section 4 Permit Signage and Recordkeeping

Recordkeeping
(Rule 310 §502)
What Records are
Required?
33The dust control permit and all
updates (must be on site).
33The Dust Control Plan and all updates
(must be on site).
33 Dust control logs documenting dust
control measures used each day (must
be available within 48 hours).
Each day a self-inspection by the Water Meter
permit holder must be conducted
with notes taken to document
observations. This is an important
document and can be used to
33 what kind and when contingency
measures in the Dust Control Plan
Document Retention
show that site conditions have
were used. Records must be retained consistent
been carefully controlled. Critical
information that is required by 33 what subcontractors were on site, with the following timeframes and
Rule 310 includes: whichever is longer will apply:
include registration numbers.

33 observations of damp and crusted 33 a list of employees who have 33 two years from the date the record
soil. completed dust control training, was initiated, as long as operations
the date of the class, and the name are ongoing. For example, a five-year
33 trackout conditions and actions taken of the company or person who did project only needs a two-year record
to clean up trackout. the training. Keep copies of training log.
33 daily water usage (note how water is certificates on file. 33 all records must be retained for
applied, how often, and the amount - 33 all supporting documentation (e.g., six months following termination of
a rough approximation is acceptable). street sweeping or water truck site operations.
33 dust suppressant application. receipts).
33 when street sweeping occurred. 33 types and results of all test methods
33 maintenance of trackout controls conducted.
(what kind and when installed).

Helpful Hints
33 While no exact format is prescribed for recordkeeping, a three-ring binder is recommended for paper
records.
33 Electronic recordkeeping, used by some permit holders, is a valid form of recordkeeping.
33 A scanned copy of the Dust Control Permit accessible on a computer is an acceptable way to maintain an
on site copy.

4-2 March 2010


SELF INSPECTION AND CONTROL MEASURE APPLICATION MCAQD PERMIT #:___E089999_________
DATE Trackout Control STABILIZATION
Device Trackout Parking/staging Unpaved Roads Open Areas Storage Piles Water Application Water Supply

0845: Soil crust.


Self 0430: Observed pre-
0730: Exit 2: 1 " 1315: Some crust
1200: Trackout watering entire site (10k
Inspection river rock, 3 " measured 20 0630: No visible break down, called 0845: Visibly moist, gal truck). 0845: Watering
1 deep, 55' long, 20' ft. 1315: 50 ft, 0845: Visibly moist, emissions observed. in water truck with no visible emissions. continues: 1 water pull for 1 million gallon
- wide. Exit 1: phoned street visible emissions < 1200: No visible side sprayer. Silt 1315: Visible soil mass grade, 1 water water pond full at
M paved. sweeper. 20% opacity emissions. fence in place. crust. buffalo. 8:45 AM
a
y P / C P / C P / C P / C P / C P / C P / C P / C
- Control Maintenance Cleaning Moisture / Crust Moisture / Crust Moisture / Crust Moisture / Crust App. Equipment Source
0
8
Measure 0830: Applied 10K
Application - 0630: Removed gals. water. 1000: Total daily application
1200: Brooms.
Method, Exit 1 gravel pad, 1330:
Implemented Applied 30K gals. of 45K gals.via water
transitioned to contingency - Contingency, applied Water and Installed pull and water buffalo. Water Pond and 4
Frequency,
asphalt. Exit 2 street sweeper gravel. Primary not Stabilizer applied 21 silt fence to restrict 0800: 5K gals. Brooms and street - 3" metered
Intensity gravel refreshed. arrived. enough. March 08. access 10March 08 water applied. sweeper. hydrants
DATE Trackout Control STABILIZATION
Device Trackout Parking/staging Unpaved Roads Open Areas Storage Piles Water Application Water Supply

0500: Asphalt 0500: No 0500: Speed limit


Self TOCD. In good trackout. 0500: Pea gravel in signs in place. 0530: 0500: Soil crust 0500: Visible soil
Inspection repair, no maint. 0900: 20' of place, no bare spots or Observed trades (temp. inactive crust on all spoils
2 needed. No haul trackout on need for refreshing. vehicles in excess areas), visible piles. 0900: Visible 0500: One 3"
- operation Central Ave 1500: Observed visible of 20 trips, began moisture in active soil crust, no spoils 0500: 2 water trucks metered hydrant,
M scheduled. at East Exit. emission < 20%. contingency plan. disturbed areas. activity. operational operational.
a
Recordkeeping (Rule 310 §502) cont’d

y P / C P / C P / C P / C P / C P / C P / C P / C
- Control Maintenance Cleaning Moisture / Crust Moisture / Crust Moisture / Crust Moisture / Crust App. Equipment Source
0
Measure

4-3
8
Application - 0500: No action Total daily water
Method, Asphalt TOCD. In 0900: Swept required. 1530: 0430: Pre-watered application 110K gals.
Frequency, good repair, no 20' of Sprayed area with 0500: No action. all active and Brooms and street Metered hydrant
This example of a completed record keeping form can be found online at:

maintenance trackout water at end of work 0530: 25K gal. water inactive disturbed 0500: No action sweeper for trackout and Klein tank full
Intensity needed. manually. day. application. areas. (35K gals) required. 0900: N/A clean up. at end of day.
DATE Trackout Control STABILIZATION
Dust Abatement Handbook-Section 4 Permit Signage and Recordkeeping

Device Trackout Parking/staging Unpaved Roads Open Areas Storage Piles Water Application Water Supply

0
1530: 1100: Large spoils
Self 1530: Asphalt Observed 0530: Inactive areas pile in SWC
2
Inspection TOCD. In good 150 feet of 0900: Haul road dry, crusted, active areas disturbed, partially
M repair, no maint. trackout > 20% visible drying out, phoned crusted, phoned
a
y
needed. End of (Central Ave emissions, phoned water truck, to stay water buffalo. 1530:
work day. Exit). N/A water truck. in area all day long. Visibly wet. N/A N/A
0
P / C P / C P / C P / C P / C P / C P / C P / C
8
Control Maintenance Cleaning Moisture / Crust Moisture / Crust Moisture / Crust Moisture / Crust App. Equipment Source
c Measure 1545: Mr.
o
n
Application - Dirt street 0900 - 1530: 10K 1100: 5K gals
t Method, Asphalt TOCD. In sweeper water truck devoted 0545: 60K gals applied to large
. good repair, no cleaned to haul road. (50K water application to spoils pile at SWC.
Frequency,
maintenance (Central gals total active areas through 1530: No action
Intensity
http://www.maricopa.gov/aq/divisions/compliance/dust/docs/pdf/CompletedSampleDailyLogV1.0-25Jun08.pdf

needed. Ave). N/A application). end of work day. required. N/A N/A
*Maricopa County Rule 310 S502: A list of subcontractor names & registration numbers, as well as employee names who have successfully completed dust control training classes must be kept
up to date.
Example Recordkeeping Form
Maricopa County Air Quality Department Sample Log Version 1.0 (25Jun08)

March 2010
Section 5 - Accessible Areas
Dust Abatement Handbook-Section 5 Accessible Areas

Areas that are Accessible to the Public


The definition of “areas accessible to
the public” is “any paved parking lot
sidewalks are considered paved areas
accessible to the public, unless they
Helpful Hint
or paved roadway that can be entered are barricaded or marked off with The public is considered to have
or used for public travel primarily access to any paved area on your
signage. Trackout on sidewalks will
for purposes unrelated to the dust site unless access is clearly and
not be included in the cumulative
generating operation.” To determine effectively restricted. A sign and
distance trackout calculation; physical restrictions (e.g., rope
whether an area meets this definition,
however, trackout on sidewalks barriers, cones) may be needed to
consider the following:
must be removed by the end of the ensure that the public will avoid
33 any paved area with local non- workday. an area.
construction traffic is considered
33 parking lots, including those in
accessible to the public.
strip malls and churches, are always
33 to ensure that an area is closed to considered areas accessible to the
the public it must be clearly posted
(i.e., by using a sign that states
public unless marked otherwise with Helpful Hint
signage to restrict public access.
“Construction Traffic Only”). Any Trackout extending from your
The use of signs/barricades/ropes/ project onto paved areas off site is
place on a site where the area under fences can help to define a controlled a common violation.
construction and the area open to the area. While the use of yellow rope
public is indistinct will be considered or tape to separate the area is not If an area is restricted and trackout
an area accessible to the public. required, it has practical value in is present, it will not be cited as a
ensuring that the area is seen to be trackout violation.
separate from other areas where the
public has ready access.

Signage restricting access to paved area

5-1 March 2010


Section 6 - Working on Other Sites
Dust Abatement Handbook-Section 6 Subcontractors and Block Permits

Subcontractors
Subcontractor project’s dust control permit and Dust
Control Plan.
33 wet utility/dry utility installation
when opacity exceeds 20%.
Registration The subcontractor registration number 33 removal of barricades to avoid use of
must be displayed on a jobsite. Methods of a trackout control.
Subcontractors are hired by a permit displaying the subcontractor number may
holder to perform various tasks on a 33 untarped trucks exiting a site onto
include:
construction site. The department paved areas accessible to the public.
requires that subcontractors accessing 33 a sign at the project entrance.
sites covered by a dust control permit 33 truck freeboard limit exceeded and/or
33 painting it on a vehicle. spillage while crossing a public area/
obtain registration. This applies to
any subcontractor engaged in dust- 33 a paper sign affixed to the vehicle or roadway.
generating activities (e.g., driving on equipment. 33 creating visible emissions beyond
roads, landscaping, carpentry, etc.) property lines.
33 a magnet sign affixed to the vehicle, e.g.,
Registrations are good for one year on the door or bumper. While a subcontractor will be held
from the date the registration is
33 a rear view mirror hanger. responsible for their compliance
approved/issued.
with Rule 310, the responsibility of
While the permit holder is responsible
for all site activities that may result
Subcontractors are the permit holder and the actions of
a subcontractor can be difficult to
in a violation of the provisions of
Rule 310, subcontractors may, under
Subject to Enforcement separate. Factors that will be taken into
account in determining which party is
certain circumstances, also be held A subcontractor is required to abide by the responsible include, but are not limited
accountable. provisions of the dust control permit and to whether the:
Rule 310 and subcontractors will be cited for
Displaying Subcontractor violations of Rule 310. Potential violations
33 subcontractor was informed of their
obligations by the permit holder.
Registration Numbers may include:
33 subcontractor’s actions can be clearly
Anyone who enters an area that 33 not using a trackout control device.
documented.
is subject to a Rule 310 dust 33 grading when opacity exceeds 20%.
control permit must obtain and a 33 subcontractor acted in disregard of
subcontractor registration number 33 loading/unloading when opacity exceeds established site protocols.
and follow the requirements of each 20%.
33 subcontractor’s actions were
observed by a department inspector.
33 subcontractor can be readily
identified.
Subcontractors will be held
accountable for their violations if the
subcontractor can be easily identified
and the permit holder has established
appropriate fugitive dust controls. In
accordance with the department’s
subcontractor policy (dated April 18,
2006, and included in the appendices),
it should be noted that the permit
holder will be cited for a violation
caused by a subcontractor unless the
inspector can confirm that the permit
holder did not cause or contribute to
the violation by a subcontractor and
that a subcontractor ignored controls
put in place by the permit holder.  
The need for clear documentation
of a violation by a subcontractor
Subcontractor registration number located on vehicle bumper

6-1 March 2010


Dust Abatement Handbook-Section 6 Subcontractors and Block Permits

Subcontractors (cont’d)
is essential to avoid the issuance of
an NOV to the permit holder. For
example, a subcontractor who has
Helpful Hints
removed a barricade to avoid going Although not required by the
rule, subcontractors are encour-
Helpful Hints
over a trackout control device would It is also helpful to review the
be issued a NOV. The inspector would aged to have their employees
complete the comprehensive approved Dust Control Plan, as
have to observe the violation occurring well as the controls that have been
in order to issue the NOV to the dust control training (six-hour
course). established, with subcontractors
subcontractor. In the above scenario, prior to starting work.
if the subcontractor was not observed Coordinate with the department
and the surface was no longer stable as to schedule a dust control Clear communication with
a result of the subcontractor’s actions, presentation. subcontractors and active
then the permit holder would be monitoring of their on-site activity
Permit holders are encouraged can be effective methods to avoid
issued a violation for unstabilized soil
to ensure that their contractual creating conditions that could
(assuming the soil failed the applicable
agreements with subcontractors result in the issuance of an NOV.
stability standard).
include:
Ultimately, a permit holder is responsible A courtesy inspection could
33 provisions for the be held in conjunction with a
for all activity that occurs within a
subcontractors to conduct their meeting where subcontractors are
permitted area—including activities
that are performed by subcontractors. activities in a manner that is in invited.
While the permit holder is responsible compliance with department The department’s website
for the actions of subcontractors and rules. contains a useful set of Frequently
ensuring they conform to department 33 provisions that hold the Asked Questions about
rules when acting on their behalf, subcontractor liable for subcontractor registration at
the department reserves the right to
any penalties issued by the http://www.maricopa.gov/aq/
pursue enforcement action against the divisions/compliance/dust/
department that may be the
subcontractor and/or the permit holder subcontractorRegistration.aspx
result of subcontractor activity.
depending on the circumstances and
available evidence.

Subcontractor registration A permit holder cannot delegate primary obligations of the


is not required for the permit to a subcontractor to avoid compliance responsibility.
following activities: A permit holder may secure a subcontractor to perform activities within
a permit area that are considered to be primary permit obligations. For
33 lunch trucks or food vendors example, a subcontractor may be hired to install or maintain a trackout
33 waste management trucks control device. In the event that a violation occurs (for example, the trackout
control device is found to be improperly maintained such that it is no longer
33 vendor/supplier delivery
effectively controlling trackout) and the violation is due to the inaction or
trucks (except import, export untimely action of the subcontractor, the permit holder is responsible for
and stacking operations and compliance and subject to the penalties authorized by law. The permit
operations using ancillary holder is responsible for ensuring that onsite operations are being conducted
motorized equipment, such as in compliance with the permit. This obligation cannot be transferred to a
a forklift) subcontractor.
33 regulatory agencies Note: utilities are not considered to be subcontractors when operating under
their own block permit.

6-2 March 2010


Dust Abatement Handbook-Section 6 Subcontractors and Block Permits

Block Permits and Utility Responsibilities (Rule 310§404)


The purpose of the block permit is to
allow municipalities, governmental
Activity Occurring at Some block permit holders may
agencies, and utilities to conduct
similar activities at multiple sites across
Locations Not in the Block require contractors to obtain
their own dust permit and Dust
the county. Covered activities include Permit Control Plan. Remember to
routine operation and maintenance allow at least 14 days for the
For any project not listed in the Dust
of urban infrastructure, as well as
Control Block Permit application, the department to process a new
the expansion or extension of that
applicant is required to notify the permit application.
infrastructure such as roads, utilities
department at least three working days
(e.g., pipelines and electric substations)
in advance of initiating the activity.
and other public rights-of-way. This
category of permit can only be issued Similarly, at new subdivisions or
to municipalities, governmental commercial developments, a utility work are adequately stabilized. A
agencies, and utilities. While the will operate under its block permit and utility is obligated to meet minimum
permit is held by the authorized block is required to notify the department stabilization requirements of Rule 310.
permit holder, subcontractors to the of its intention to work on a specific
authorized permit holder may operate property. As with other areas, a block Utility access onto areas covered by a
under the cover of the permit as would permit holder is required to provide dust control permit appears to pose
the employees of the permit holder. the department with notification a special challenge. While the block
of its intent to operate at a location permit holder is obligated to maintain
The block permit will apply to those stability conditions when accessing
not previously identified in its block
locations that are listed in the permit a dust control permit holder’s area,
permit. Notification must be provided
application. To conduct work at a the permit holder is accountable for
in writing and with three working days
location not listed in the application, all site conditions within their permit
advance notice.
the block permit holder must notify area. A block permit holder can be
the department of the intent to work
in a new location at least three days Enforcement issued a violation for not restoring a
disturbed area to its former stabilized
in advance of the planned activity. The permit holder retains responsibility condition.
The notice must include information for all work conducted within the
describing the location and the area covered by the permit. However,
anticipated start date of the work. if a utility causes a non-compliant
New construction of infrastructure condition, the utility can be cited Rule 310 specifies that a
that is not an extension of an existing in accordance with Rule 310. This Dust Control Block Permit
system must be covered under a new includes the obligation to ensure application should include
dust control permit. that areas disturbed during utility a map of the owner’s and/or
operator’s service areas and a
list of sites that are 0.1 acre or
greater.

This activity resulted in a notice of violation being issued to a block


permit holder

6-3 March 2010


Section 7 - Trackout
Dust Abatement Handbook-Section 7 Trackout

Trackout Rule 310 §306


Trackout is one of the most frequently
cited violation by the department’s
inspectors. Controlling trackout must
be a priority. The department defines
trackout as:
“Any and all bulk materials that adhere
to and agglomerate on the surfaces
of motor vehicles, haul trucks, and/or
equipment (including tires) and that have
fallen or been deposited onto a paved
area accessible to the public.”

Trackout Clean-up
Requirements Sidewalk Trackout
Trackout must be removed immediately
when the cumulative distance of trackout
reaches 25 feet either in one segment
Active trackout controls are required
at work sites with a disturbed surface Helpful Hint
greater than two acres or hauling any Plan ahead and anticipate that
or reaches 25 feet when combined
amount of bulk materials off-site or 100 trackout will occur.
with smaller segments. The term
yd3 or more of bulk material on site,
“immediately” is viewed as when the
regardless of acreage. (See the Trackout
trackout occurs. The expectation is that past, staining itself is not considered
Controls in Section 7 for details about
trackout that extends 25 feet (either trackout under Rule 310, nor is it a
trackout control options).
alone or in combined segments) will violation.
be cleaned up immediately following
deposition on the roadway. The The Difference between The presence of trackout greater than
25 feet during working hours, even
presence of trackout at or exceeding
25 feet is cause for the issuance of an
Trackout and Staining though it may be in the process of
immediate NOV. being cleaned up, is subject to an NOV.
Trackout is the presence of material
While an inspector has discretion to
Lesser amounts of trackout (less than deposited on a road surface. Trackout
evaluate the on-site conditions and
25 feet in cumulative length) can be can become airborne particulate
actions of the permit holder, gener-
cleaned up at the end of the workday. matter when vehicles pass over and
ally, the greater the extent of trackout,
Note: Under the right circumstances, entrain the trackout into the air. In
the higher the probability that an NOV
even a small amount of trackout contrast, staining on a road surface is
will be issued. After working hours, the
could potentially result in an opacity not considered to be trackout. While
presence of any trackout will result in the
violation if it is driven over or staining may indicate that trackout may
issuance of a Notice of Violation.
otherwise disturbed. have been present at some time in the

“Trackout is an obvious indicator


of potential non-compliance.
Taking the time to assess the
presence and scope of trackout
and whether immediate
attention is required is an
essential practice to maintain
compliance”
—Air Quality Inspector

Wet Trackout
7-1 March 2010
Dust Abatement Handbook-Section 7 Trackout

Trackout (cont’d)

Helpful Hints
As a practical matter, it may
be easier to clean up trackout
immediately rather than measure
it to ensure there is less than
25 feet in distance. The presence
of trackout, however limited in
extent, can result in an inspection
based on field conditions.
Remember: erosion is
considered the same as
trackout and must be managed
accordingly.
Soil found on sidewalks and
in gutters is trackout. Soil on
sidewalks will not count in the
Staining
cumulative distance calculation
while trackout in gutters will.

Helpful Hint
Include the cost of trackout
control and maintenance in
your bid.

Trackout

7-2 March 2010


Dust Abatement Handbook-Section 7 Trackout

Trackout (cont’d)

Measuring Trackout
The distance of individual
trackout paths originating from
a permitted area are combined
to determine compliance. Here,
three trackout paths cumulatively
total 25 feet.
When trackout reaches a
cumulative distance of 25 feet it
must be cleaned up immediately.
Trackout is measured from an
exit onto a paved surface and
along the path of trackout to the
point where it ends. This may
follows the actual curved path
of trackout or the horizontal
distance may be used instead
(especailly where traffic/safety is
Calculating cumulative distance a concern). Line C in the graphic
below is an example.

The graphic at right shows


trackout extending from the exit
of a permitted area. The gray
rectangle represents a gravel pad.
While trackout can be measured
by using a surveyor’s wheel, on
busy streets, the inspector may
measure the distance along a line
adjacent to the road (represented
by line C) to determine trackout
length.
An inspector may also use paces
or a range finder to measure
distance.
In both examples on this
page, trackout has reached or
exceeded 25 feet in cumulative
distance and must be cleaned
immediately.

Measuring trackout

7-3 March 2010


Dust Abatement Handbook-Section 7 Trackout

Trackout Controls
Several trackout control options are
available. At all exits to paved areas
accessible to the public at least one of
the following controls must be used:
33 gravel pads: consisting of a layer of
washed gravel, rock, or crushed rock,
at least one inch in diameter; 30 feet
wide (unless impracticable), 50 feet
long (or as long as the longest haul
truck). If the unpaved surface exit
does not have an adequate width
to install a 30-foot wide gravel pad,
then the width of the gravel pad must Gravel pad
cover the full width of the unpaved
surface exit and be adequate to
prevent trackout.
33 a grizzly (20 feet long; bars must be
three inches tall and six inches apart).
33 a paved area: 20 feet wide; 100
feet long. (Note: the entire length
of pavement must be within the
permitted area to count as an
effective control. A shorter distance
of pavement within the permit area
cannot count unless pre-approved by
the department). Note: a paved area
that is blocked to public traffic may
also be used in whole or in part of this
requirement.
33 a wheel washer: use a standard wheel Grizzly
wash system.
33 pressure sprayers.

When trackout controls are required, if a vehicle


exits a permitted area and fails to use a designated
trackout control system (for example, by driving
around a trackout control device or leaving the
permit area at a non-designated exit) the permit
holder and/or subcontractor (if applicable) are
subject to receiving an NOV even if no trackout
was deposited on the paved area accessible to the
public.

Pavement

7-4 March 2010


Dust Abatement Handbook-Section 7 Trackout

Trackout Controls (cont’d)


Controlling and Changing Be sure to...
Helpful Hint
Exits During Construction Place trackout control devices at all
When exits are changed at the
designated exits from the permit area
Phases onto an area accessible to the public if:
project site, you must update
your Dust Control Plan.
Managing the flow of traffic entering 33 the disturbed area is two acres or
and leaving a permit area represents more or
one of the prime challenges faced by 33 you are hauling any amount of
a site superintendent trying to ensure
bulk materials off-site or 100 yd3 or
the integrity of their dust controls. For
some drivers and subcontractors, it can
more of bulk material onto a site, Helpful Hint
be tempting to take a short-cut across regardless of acreage. Questions to ask yourself:
a vacant parcel to a paved road rather 33 is a trackout control device in
than winding back some distance to place and effective?
the designated exit. While the actual
act of crossing disturbed land in a 33 does my trackout control
vehicle is not prohibited, it does trigger device need maintenance?
various provisions of Rule 310—for 33 do I adequately monitor
example, if there are many vehicles
trackout?
using an unauthorized exit, a new
unpaved access road has been created. 33 did I clean up trackout at the
Trackout is likely to be associated with end of the day?
an unauthorized exit and the absence
of a trackout control device at an
unauthorized exit is an NOV waiting to
happen.

Gravel pad installation at exit

7-5 March 2010


Section 8 - Stabilizing Your Site
Dust Abatement Handbook-Section 8 Stabilizing Your Site

Control and Stabilization (Rule 310 §304 and §305)


Ensuring that disturbed areas within
Operations
a permit area are stabilized is a
primary requirement of Rule 310.
Helpful Hint
Stabilization and fugitive emission
Remember, the site must be stabilized Maintaining moist disturbed
control is an ongoing activity. The
24/7, including holidays, nights, and surfaces is an ideal site
Dust Control Plan should provide three
weekends. There are two distinct management practice.
fundamental stabilization practices
stabilization standards that apply in while a site is being actively worked (Rule
two separate circumstances—those 310 § 305.11): Within permitted areas there will
that are active and those that are
33 apply water or a dust suppressant likely be disturbed areas which are
inactive for extended periods. An area
(the soil must be visibly moist) or not currently being worked. In those
covered by a permit may contain active
areas, stabilization should have been
and inactive areas at the same time. 33 maintain soil moisture content achieved as tasks on disturbed surfaces
at 12%* or
Pre-disturbance 33 install wind fences/barriers and one of
were completed. The following
standards apply (Rule 310 §304.3):
Before starting work, conduct a “site the above. 33 maintain a soil crust.
prep”— pre-water the site or phase
work to the smallest portion of the area Alternatively, one of the following
* Moisture content is determined by
that can be affected at any one time. If standards could apply in place of a
using ASTM Method D2216-05.
you have chosen phasing as a control visible crust:
measure, then project phases should 33 maintain a threshold friction velocity
be clearly identified in the Dust Control (TFV) of 100 cm/second or higher.
Plan.
During dust-generating 33 maintain a flat vegetative cover equal
Work Phases operations, the generation
of a limited amount of dust
to at least 50%.

Within a permit area, there may be 33 maintain a standing vegetative cover


is allowed. However, dust
several defined areas (representing emissions can never exceed 20% equal to or greater than 30%.
project phases). One phase may opacity. 33 maintain a standing vegetative cover
be active with ongoing surface
If dust emissions are present, that is equal to or greater than 10%
disturbance while another phase has
it may be an indicator that the when the TFV is equal to or greater
not yet been disturbed. Ensure that
areas not yet disturbed are clearly area is not sufficiently controlled than 43 cm/second.
demarcated, identified in the Dust and that the area requires
33 maintain a percent cover that is equal
Control Plan, and access is restricted. additional attention.
to or greater than 10% of the
When phasing work, it is important to non-erodible elements.
meet the stabilization requirements 33 comply with an alternative test
of Rule 310 §304.3 for areas that have
method approved by the Control
been disturbed but are not being
Officer.
actively worked.

Helpful Hint
Keep all disturbed areas visibly
damp/moist or meet one of the
stabilization standards.

8-1 March 2010


Dust Abatement Handbook-Section 8 Stabilizing Your Site

Control and Stabilization (Rule 310 § 304 and § 305) (cont’d)


Control Measures on
Disturbed Areas (no
activity for 30 Days or
longer)
When a disturbed area will remain in its
current disturbed state (with no futher
work taking place) for a period of 30
days or longer, achieve one or more of
the following (Rule 310 §305.11(c)):
33 cover the area using gravel,
pavement, or by using a suitable dust
suppressant.
33 establish a vegetative ground cover.
33 pave, apply gravel or apply a suitable
dust suppressant other than water or
establish a vegetative ground cover
and restrict vehicle access.
33 apply water and prevent access (using
signs, curbing, or barricades) sufficient
to prevent trespass. Note: the specific Project nearing completion
measures intended to prevent
trespass must be approved by the
Control Officer.
33 restore an area to a substantially
similar condition (vegetative ground
cover and soil characteristics) as that
of surrounding or nearby undisturbed
native conditions.
This stabilization standard should be
achieved within 10 days following the
completion of the dust-generating
operation.

Trespass
While a permit is still effective, the
permit holder is responsible for any
disturbance that occurs as a result of
illegal trespass. If an area is disturbed
after final stabilization and the permit
is still in effect, the permit holder is
obligated to ensure that stabilization Soil clearly without a visible crust
is restored. If disturbed areas that are
not stable are identified during an
inspection, a violation can be issued.

8-2 March 2010


Section 9 - Visible Emissions
Dust Abatement Handbook-Section 9 Visible Emissions

Visible Emissions (310 §303)


Essentially, Rule 310 is about ensuring that dust (particulate) 33 The standard for visible emissions beyond the
emissions are minimized. Emissions are subject to two property line of an area covered by a permit is
separate standards, depending on whether the emissions are simple—none are allowed. According to Rule 310
observed onsite or off-site. § 303.1, visible emissions are measured using the
standard that there shall be no visible emissions
Onsite Visible Emission Opacity Limits exceeding 30 seconds in duration during any
33 Within the boundary of the area covered by the permit, 6-minute period using EPA Reference Method 22.
visible emissions can never exceed 20% opacity. 33 When dust-generating activity occurs within 25 feet
The method used to determine whether visible emissions of the property line, visible emissions beyond the
exceed 20% opacity is found in Appendic C of the Maricopa property line are allowed. However, the emissions
County Rules and Regulations for Air Pollution Control. This cannot exceed 20% opacity (see Rule 310 § 303.2(d)).
method consists of the average of 12 observations of five
seconds each taken over a period not longer than one hour.
As a practical matter, the 12 observations will most likely be NOT OK

completed over the period of a few minutes.


NOT OK
Permitted Area
OK

NOT OK Owned Property

OK
NOT OK

Private Home

Keeping Opacity on Property

In the figure above, the brown area is covered by a dust


Suspect emissions >20% opacity control permit. Surrounding this area is an area in gray
that is owned by the dust control permit holder. Visible
emissions from the permit area are allowed onto this
adjacent area since the property is owned by the permit
Visible Emissions Beyond the holder - the emissions do not cross a property line.
Should the emissions extend further and onto the prop-
Property Line erty designated as a private home or onto the forested
area, the emissions are crossing a property line and are
33 A property line is that demarcation between the area not allowed.
contained within a dust control permit and the area outside
of the permit, when the area outside the permit is owned by
an entity other than the permit holder.
33 It is possible that, as a project matures, some areas within a
permit area will transition to private ownership and will no
Helpful Hints
longer be part of the permitted area (e.g., parcels within a Submitting a clear and accurate
housing subdivision that have been sold to homeowners). map in your Dust Control Plan
Emissions that extend from a permitted area onto privately can help you delineate your
held parcels violate Rule 310. property from others.

9-1 March 2010


Dust Abatement Handbook-Section 9 Visible Emissions

Visible Emissions (310 §303)

When the emissions originate further than 25 feet away


from the property line, no dust emissions are allowed to In the photo above, dust emissions are being generated
cross the property line. but emissions are not visible beyond the property line
(beyond the photo frame). Although the on-permit
area emissions may exceed the 20% opacity standard
(and be in violation), the emissions at the property line
boundary may or may not be in compliance. No visible
emissions are allowed to cross the property line if they
are generated more than 25 feet from the property
boundary.

Permitted Area

25ft
Property Line

Dust Emissions Beyond


Property Line <
_ 20% Opacity
When dust emissions are generated within 25 feet of the In the photo above, dust emissions are being generated
property line emissions are allowed to cross the property line within 25 feet of the property line and are clearly visible into
provided they do not exceed 20% opacity. the street. Although visible emissions are allowed beyond
the property line, they cannot exceed 20% opacity. Also,
in this instance, a serious public safety hazard is created by
impairing visbility in a traffic lane.

9-2 March 2010


Dust Abatement Handbook-Section 9 Visible Emissions

High Wind Conditions and Visible Emissions (310 § 303.2)


Site Operations During The New Requirement emissions exceeding 20% opacity are
not occurring due to a failure to fully
High Winds When wind conditions result in visible
emissions that exceed 20% opacity,
implement the Dust Control Plan.

High wind conditions have the


potential to dramatically degrade
despite implementation of measures
contained in the Dust Control Plan, the
Visible Emissions
air quality. Revisions to Rule 310 following steps must be taken: Originating from
adopted by the Maricopa County
Board of Supervisors in January 2010
First, ensure that all control measures
and requirements of the Dust
Adjacent Lands
substantially revised the rule language Control Plan are implemented and Conditions may arise where winds
affecting wind events. documented. Next, cease dust- will drive dust from one property
The intent of the new rule language is generating operations and stabilize (e.g., a vacant field) across another
to require escalating controls as winds any disturbed surfaces in a manner on which dust-generating operations
increase. Ceasing operations is the consistent with Rule 310 § 304.3. are occurring under a dust control
ultimate control when all else fails. As a practical matter, this will mean permit. Normally, visible emissions
Dust-generating operations must now maintaining a visible crust or establishing seen crossing the property line will
cease at a lower threshold (e.g., earlier visibly damp/moist soil on disturbed constitute a violation. However,
and more frequently). areas during windy conditions. where visible dust emissions are seen
transiting a permitted area and it can
The previous defintion of a “wind event’ Finally, document the cessation of be determined that no additional dust
has been deleted. operations and the implementation of emissions were contributed from the
control measures and the requirements permitted area, a violation will not have
of the Dust Control Plan. The intent occurred.
is to document that any visible

Wind driven dust crossing a road

9-3 March 2010


Section 10 - Onsite Operations
Dust Abatement Handbook-Section 10 Onsite Operations

Unpaved Parking Lots (Rule 310 §304.1)


As defined in Rule 310 §232, an lot should normally be designated determine that an area is being used as
unpaved parking lot should be in the Dust Control Plan. However, an unpaved parking lot:
designated as such in the approved identifying an unpaved parking lot in
33 use of an area by a surveying crew.
Dust Control Plan. In addition to the Dust Control Plan is not required for
vehicle parking, an unpaved parking an inspector to determine that one is 33 use of an area by a landscaping
lot includes the following activities: present based on the observed use. service.
maneuvering, material handling, or
To determine that a disturbed area 33 delivery of materials to a home
storing motor vehicles and equipment.
is an unpaved parking lot requires and unloading them (for example,
Automobile impound yards, salvage
observations of activities that reflect dropping off tile, drywall, or tools),
yards, material handling yards, and
actual use of the property for an activity provided those materials are not
storage yards would be considered to
similar in scope to those examples
be an unpaved parking lot under staged on the disturbed surface.
provided in the definition.
Rule 310. Unpaved parking lots must meet a
The definition also contains reference
While the use of an area for staging specified soil stability standard (silt
to the term “maneuvering.” After-the-
or for material storage may be clearly loading cannot equal or exceed 0.33
fact observation of tire tracks alone on
evident, an isolated instance of such oz/ft2) and operations on the lot cannot
an otherwise empty lot is not sufficient
use will not cause the area to be generate dust emissions greater than
to classify an area as an unpaved
designated as an unpaved parking lot. 20% opacity. If silt loading is equal
parking lot without some supporting
to or exceeds 0.33 oz/ft2, then the silt
An unpaved parking lot, as defined by evidence that the area has been used
content may not exceed 8%. (Note: As
Rule 310, is present when the use of an in the manner contemplated by the
a practical matter, there is very little
area by vehicles goes beyond what can definition.
difference between the two values).
be considered to be incidental use.
The following activities constitute
Whether an area is considered an
An area used as an unpaved parking incidental use and are not sufficient to
upaved parking lot or an otherwise
disturbed area, stabilization is always
required.

Incidental storage

“An isolated incident of ‘parking, maneuvering,


material handling, or storing motor vehicles Unpaved parking lot
and equipment’ does not convert a vacant area Evidence of multiple vehicle use
or property in use for the purpose described in
the dust control plan into a parking lot.” Draft
Notice of Final Rulemaking, Page 6

The presence of tire tracks alone may not be sufficient to


classify an area as an unpaved parking lot. The inspector
will rely on judgment and the responses from the permit
holder to determine whether the tracks represent
incidental use of the area by vehicles.

10-1 March 2010


Dust Abatement Handbook-Section 10 Onsite Operations

Unpaved Haul and Access Roads (310 §304.2 and §305.7)


Whether marked or unmarked, an 33 vehicle trips are limited to no more
unpaved haul or access road is a road
within a permitted area that is used to
than 20 per day and Helpful Hint
move material, equipment, or people 33 vehicle speeds are maintained below If you choose the option of
from one point to another. These roads 15 miles per hour. no more than 20 trips per day,
are likely to change location frequently always keep in mind that a trip to
and meeting the stabilization the site with one vehicle and off
Active control measures for unpaved the site with one vehicle counts
requirements is likely to require close
haul/access roads are required. One as two trips. (10 vehicles in and 10
attention.
of the following options must be vehicles out represent 20 trips).
By definition, an unpaved haul or implemented:
access road represents a permanent Note: once a project area meets
33 apply water so the surface is visibly a certain size, the number of trips
or semi-permanent disturbed area
that will require stabilization on an moist. becomes more difficult to control.
ongoing basis. At all times, visible 33 pave. Exercising this option implies
emissions from unpaved haul/access that a high level of scrutiny will
33 apply and maintain gravel, recycled be applied by the inspector to
roads must remain below 20% opacity.
asphalt, or other suitable materials. validate limited vehicle usage.
Additionally, Rule 310 §304.2 (a) sets silt
loading and silt content levels that can 33 apply and maintain a suitable dust Different control measures
never be exceeded. These levels are: suppressant other than water or may be selected for different
33 silt loading cannot equal or exceed 33 limit vehicle trips and speeds. If you areas provided they are clearly
0.33 oz/ft2. select this option be aware: identified in the Dust Control
Plan.
33if silt loading is equal to or exceeds RR vehicle trips must be limited to no
0.33 oz/ft2 then the silt content may more than 20 per day and
not exceed 6%. RR vehicle speeds must be maintained
Under limited conditions, unpaved haul below 15 miles per hour.
and access roads do not need to meet RR if vehicle trips and speeds are
the silt loading and silt content limits limited, the Dust Control Plan
set by Rule 310 §304.2 (a). These limited must provide details of how these
conditions are: measures will be accomplished,
33 if the Dust Control Plan contains a including the identification of how
description of how vehicle speeds will many trips are allowed.
Signs like this can help reduce dust.
be restricted and a discussion on the
Remember, dust emissions cannot exceed
number of vehicle trips and the type
20% opacity, regardless of speed.
of vehicles making those trips, and

Helpful Hint
Things to watch for on haul and
access roads:
RR while signage is not required,
it is helpful.
RR the silt load or content is
within acceptable limits.
RR the road is adequately
stabilized.
RR visible emissions

Unpaved Haul Road

10-2 March 2010


Dust Abatement Handbook-Section 10 Onsite Operations

Unpaved Haul and Access Roads (cont’d)

Unpaved Roads
An unpaved road is any road, including
an “equipment path,” used by motorized An unpaved access road can be very short.
vehicles. An unpaved road is different For example, a driveway located on a nearly
from an unpaved haul/access road only completed lot can be considered an access road.
by its designated use.
While an unpaved road is, by definition,
different from an unpaved haul/access
road, control and stabilization of the
disturbed area is still expected.
At minimum, an unpaved access road
must control visible emissions so that
emissions do not exceed 20% opacity,
the road surface is kept visibly moist, or
a crust has been formed on the surface.

If you choose to limit speeds, Even a driveway can be an access road


the method used must be
explained with specificity in the
Dust Control Plan.
Keep in mind that, in addition
to limiting vehicle speed, dust
emissions from vehicles must
not exceed the 20% opacity
limit.

Testing Requirements for Representative Areas

10-3 March 2010


Dust Abatement Handbook-Section 10 Onsite Operations

Trackout Control Devices


(310 §306.1)
Trackout control devices are required
at work sites with a disturbed surface
area two acres or larger, at any site where
any amount of bulk materials are hauled
off-site, and those sites where at least 100
cubic yards of bulk materials are hauled
onto the site each day:

At all exits to paved areas accessible to


the public at least one of the following
controls must be used:
33 gravel pads: consisting of a layer of
washed gravel, rock, or crushed rock, at
least one inch in diameter; 30 feet wide
(unless impracticable), 50 feet long (or
as long as the longest haul truck). If the Gravel pad at permitted area entrance/exit
unpaved surface exit does not have an
adequate width to install a 30-foot wide
gravel pad, then the width of the gravel
pad must cover the full width of the
unpaved surface exit and be adequate
to prevent trackout.
33 a grizzly: (20 feet long; bars must be
three inches tall and six inches apart).
33 a paved area: 20 feet wide; 100 feet long.
(Note: the entire length of pavement
must be within the permitted area or
a restricted area outside the permit
area, to count as an effective control. A
shorter distance of pavement within the
permit area cannot count unless pre-
approved by the department).
33 a wheel wash system. Here a grizzly has been added to the gravel pad as an extra control
measure

Even the best trackout control device


needs maintenance. During muddy
conditions the trackout control device Helpful Hint
can easily clog and become ineffective. Keep a stockpile of replacement
Rule 310 §306.1 requires that the trackout gravel near your trackout con-
control device be properly maintained so trol device and use it to refresh
that it prevents and controls trackout. If the gravel pad when it becomes
that is not occuring the trackout control clogged with mud.
device is not in complaince and a Notice of
Violation will be issued.

10-4 March 2010


Dust Abatement Handbook-Section 10 Onsite Operations

Hauling Bulk Materials (Rule 310 §305.1-3)

Tarped Untarped and Overloaded Tarp Sign

The use of haul trucks to move bulk If bulk materials are moved within a
materials from or within a site is permit area but do not cross a paved Be aware that spillage and dust
regulated. A haul truck can be any of a area accessible to the public: emissions from a tarped load
number of different types of vehicles. while driving on a highway
33 the speed of an onsite haul truck
For example, a small pick-up, a flatbed constitutes a violation.
cannot exceed 15 mph or
truck, an 18-wheeler, a paddle-wheel
scraper, a a front-end loader, or a trailer 33 water must be applied to the top of
towed by a motor vehicle. The purpose the load or
to which the vehilce is used is the
33 the load must be covered. Using any portion of an area
determining factor - not the inherent
nature or size of the vehicle. If bulk materials are moved within a accessible to the public (other
permit area and a paved area accessible than simply crossing the road)
Moving Bulk Materials to the public is crossed: will require the load to be
tarped. There is no minimum
33 the freeboard must be three inches or
If bulk materials are being moved threshold distance to travel.
more.
out of an area covered by a dust
control permit and onto a paved area 33 the highest point of the load cannot
accessible to the public: exceed the height of the truck’s
container.
33 the truck’s load must be covered by a
tarp. 33 there can be no spillage through
Haul Truck Load Cross Section
holes or seams in the container area.
33 the freeboard must be 3 inches or
more. 33 install a trackout control device at the
points where the publically accessible
33 the highest point of the load cannot
paved area will be crossed (Note: two
exceed the height of the truck’s
devices may be required if traffic is
container.
two-way).
33 there can be no spillage through
If bulk materials are moved within a
holes or seams in the container area.
permit area and a paved area accessible
33 even when the truck is not carrying a to the public is used for a short distance
load, the exiting haul truck must have to transit from one portion of a permit
a clean cargo bed or must be tarped area to another, the load must be
or otherwise covered/enclosed. tarped.
33 install a trackout control device (there
is no lower acreage limit that applies
when off-site hauling of bulk materials
is occurring).

10-5 March 2010


Dust Abatement Handbook-Section 10 Onsite Operations

Storage Piles, Bulk Material Stacking, Loading and Un-


loading 310 §305.4 and §305.5
Open Storage Piles (310 Managing Open Storage
Helpful Hint
§305.5 Piles (inactive) Open storage piles are
When an open storage pile has been challenging to manage. Extra
A pile of bulk materials with a silt
created and material is not being added care needs to be taken to ensure
content 5% or greater, exceeding a
or taken away, several management that they are in compliance.
surface area greater than or equal
to 150 ft2 and reaching a height of options are available, of which one
three feet (at any point) is an open must be used:
storage pile. By definition, an open 33 cover the storage pile with a tarp or
storage pile is presumed to have a other suitable material and ensure
silt content of 5% or more. that the tarp or other material is
A permit holder has the option to sufficiently affixed to prevent its being
conduct a test to show that the silt dislodged by wind.
content is less than 5%. This test
protocol is ASTM Method C136-06. 33 apply sufficient water at necessary
intervals to maintain moisture content
Managing Open Storage at 12%.
33 maintain a visible crust.
Piles (during active use) 33 construct a physical partial
Bulk materials encompass a wide enclosure (see details on enclosure
array of materials including earth, requirements at Rule 310 §305.5(b)
rock, sand, gravel, soil, aggregate or Rule 310 §305.5(c)) and apply
less than two inches in length or sufficient water at necessary intervals
diameter, and demolition debris to maintain moisture content at 12%
among many others (the full list or maintain a visible crust.
is found in Rule 310 §203). When
handled, bulk materials are capable
of producing fugitive dust emissions.
Prior to stacking, loading and
unloading:
- mix the material with water or mix
with a dust suppressant other than
water.
While stacking, loading and
unloading:
- apply water or apply a dust
suppressant other than water.

Open Storage Pile

10-6 March 2010


Dust Abatement Handbook-Section 10 Onsite Operations

Weed Abatement (310 §305.8)


Where vacant land is being disced,
scraped, or bladed to control weeds,
control measures must be applied. If a regulated weed abatement
These include:
activity is occurring on an area
0.1 acre or more, a dust control
33 before and during the activity, permit is required.
water or a dust suppressant must be
applied.
After weed abatement is completed,
the area that has been disced, scraped
or bladed must be stabilized in one of
the following ways:
RR apply water.
RR apply a dust suppressant other
than water.
RR establish vegetative ground cover.
RR apply gravel.
RR pave the area.

Uncontrolled Dust Emissions During Weed Abatement

10-7 March 2010


Section 11-Permit Administration
Dust Abatement Handbook-Section 11 Permit Administration

When is an Activity Completed? What Do I Need


to Do to Close Out a Permit? Helpful Hint
A disturbed area under a permit will Forms can be found on the
be considered eligible for permit department’s website at
cancellation when permanent http://www.maricopa.gov/aq/
stabilization is achieved. Generally, divisions/compliance/dust/
resources.aspx
this will occur when building and
landscaping is completed in an area,
the area is stabilized, and access is
restricted.
The permit holder should submit a
Permit Cancellation Request (PCR) form
when the above conditions are met.
The filing of a PCR form will trigger a
site inspection and the results of the
site inspection will determine areas that
can be released from permit coverage.
Steps:
1) use the PCR form.
2) attach a final status map of the
area and identify any areas being
transferred to other permit coverage
(if any).
3) ensure the entire area under permit
coverage is permanently stabilized in
all respects.
4) request a closeout inspection.
5) receive validation from the inspector
that the site is stabilized and the
permit is ready for termination.
(Note: if any violation of Rule 310
is observed during a close-out
inspection, especially unstabilized
soil, an inspector may issue a Notice of
Violation (NOV).)
6) receive affirmation from the
department that the transfer is
approved. (Note: This affirmation An area is covered by a permit until the permit expires, so,
will usually be the completed Permit when a project has been completed early, it is important
Cancellation Request (PCR) form to officially close out the permit. Even though a project is
signed by the inspector. complete and the permit holder may have ended their on
site work, they remain responsible for the area covered by
the permit as long as the permit is active. As long as the
permit is active, the permit holder could receive a notice of
violation if the property is inspected and found to be in non-
compliance.

11-1 March 2010


Dust Abatement Handbook-Section 11 Permit Administration

Changes in Ownership of Property


A change in ownership of property 4) an inspection will be conducted Helpful Hint
included in an area under a dust control by the department to verify on-site
Forms can be found on the
permit will trigger the need to secure conditions.
department’s website at http://
a permit status change—for example, 5) receive validation from the inspector www.maricopa.gov/aq/divisions/
when a portion of a property covered that the site is stabilized and suitable compliance/dust/resources.aspx
by a permit is being sold or a lease for transfer.
allowing access by the permit holder
6) document formal transfer and
is being terminated. Since the permit
holder will no longer have the legal
ensure that the new owner has
accepted future responsibility of the Helpful Hint
right to be on the property, a change in property. Uncertain about what to do in
permit status is needed.
7) modify physical access and other this or a similiar circumstance?
Steps: appropriate measures to ensure that Ask the inspector supervisor. You
1) use the Parcel Sale Notification Form. no encroachment occurs. can call the Desk Duty Supervisor
8) receive affirmation from the at (602) 506-6734.
2) clearly note the area to be
excluded from the permit on a map department that the transfer is
accompanying the form. approved.
3) ensure the area to be removed from 9) remember, if a project is reduced to
permit coverage is stabilized in all under five acres, a project sign is still
respects. This step is critical— required.
a property owner will not want
to assume the liability for an area
disturbed by a permit holder unless
it meets not only the department’s
rules, but also any contractual
obligations that were made between
the parties.

11-2 March 2010


Dust Abatement Handbook-Section 11 Permit Administration

Transferring a Permit
Transferring a permit to another
responsible party can be accomplished Helpful Hint
by completing the Permit Name Forms can be found on the
Change Request form. department’s website at http://
www.maricopa.gov/aq/divisions/
Steps:
compliance/dust/resources.aspx
1) complete the Permit Name Change
Request form.
2) attach a new dust permit application
front sheet with an original signature
of the new responsible party.
3) submit the form to the One Stop Shop
(Permit Center).
The permit name change will be
immediate upon processing of the
form. Both responsible parties (the
old permit holder and the new) should
verify receipt of the form by the
department and its being processed
before assuming the change is
effective.
Once approved, the existing approved
Dust Control Plan is transferred to the
new permit holder. If revisions to the
approved Dust Control Plan are desired,
the old approved Dust Control Plan
must be followed until a new plan is
approved.
While a permit transfer will not
automatically trigger an inspection, it is
not unusual for an inspection to occur
in close proximity to a transfer.

Changing an Address
or an Element of the
Dust Control Plan
If a change in address or a more
substantial change is required to the
Dust Control Plan (e.g., modifying a
primary dust control measure), use the
Dust Control Plan Change form.

11-3 March 2010


Dust Abatement Handbook-Section 11 Permit Administration

Permit Acreage Increase


Increasing the area covered by a dust If the Permit Acreage Increase Request Helpful Hint
control permit can be acomplished by form is being submitted in response
Forms can be found on the
submitting a Permit Acreage Increase to the permit holder having received a
department’s website at http://
Request form. Notice of Violation, then an additional
www.maricopa.gov/aq/divisions/
$100 late fee is required to be
The form requires the permit holder’s compliance/dust/resources.aspx
submitted with the form (in addition to
name and address, reason for acreage
any fee associated with the additional
change, and the new acreage.
acreage).
A new site plan showing the increased
site area must be submitted as well as
the appropriate fee corresponding to
the additional acreage amount.
• Sites that increase to one acre or
more may require modifications to the
originally submitted Dust Control Plan.
• Sites that increase to five acres or
more require a project information sign.

When a Permit Acreage Increase


Request is approved, the original
dust control permit expiration date
will not change; it will remain the
same.

Permit Renewal
A dust control permit is valid for a one
year period. Technically, a dust control
permit is not renewed - rather, a new
application is submitted and a new
permit is issued (with a new permit
number).

As noted previously, a permit applica-


tion must be submitted at least 14 days
prior to the expiration of the permit. If
submitted less than 14 days in advance,
the permit may not be renewed prior to
its expiration.

- a permit that expires while an


application is pending will be subject to
immediate enforcement for operating
without a permit.

11-4 March 2010


Section 12 - Inspections
Dust Abatement Handbook-Section 12 Inspections

Inspections
Compliance Warning Signs
All projects covered by a dust control
“While driving by a permit area,
an experienced inspector can
Helpful Hint
permit are expected to be fully get a good sense of whether After a Notice to Comply or
compliant with Rule 310 at all times. the project site will be in Notice of Violation is issued,
While all inspectors are assigned to compliance with Rule 310 in a department inspector will
conduct specific inspections, they may, conduct a “disposition inspection”
about 10 seconds.”
in the course of their duties, observe to ensure that the violation has
locations that exhibit “tell-tale” signs —Supervising Inspector been corrected. This will often
(e.g., the presence of trackout or dust take place the day after the initial
emissions), that suggest not only that observation of the violation.
an inspection is needed, but that the
site may not be in compliance.
Paying attention to these indicators
of potential non-compliance are
Specific Warning Signs
important. Identifying problems and 33 Trackout on paved areas or roads
correcting them is key to avoiding accessible to the public.
violations.
33 Visible emissions of dust.
33 Large, open storage piles.
33 A messy jobsite.

Helpful Hint 33 Disorganized parking areas.


33 Lack of an obvious source of water.
Stay and wait until an inspector
has completed the inspection 33 Ongoing hauling operations.
to receive a verbal inspection 33 Trucks entering or exiting a site that
report. You may be able to clarify
are either overloaded or without a
the inspector’s observations and
tarp.
gain useful information.
33 Lack of a permit sign or a sign that is
missing required information.

Inadequate trackout control

Load height violation Poorly maintained gravel pad Blown Straw

12-1 March 2010


Dust Abatement Handbook-Section 12 Inspections

Inspection Rights
As a prelude to an inspection, the fees for this inspection. 7) I understand that each person whose
department representative will present 2) I understand that I can accompany conversation will be
a copy of your inspection rights and the department representative(s) tape-recorded during the
ask that the facility representative sign inspection will be informed that the
on the premises, except during
the document acknowledging that conversation is being tape-recorded.
confidential interviews.
they were informed of their rights.
The Inspection Rights form includes a 3) I understand that I have the right to 8) I understand that if an
statement noting that the department’s copies of any original document(s) administrative order is issued or
Ombudsman can be contacted for taken during the inspection, and that a permit decision is made based
assistance. If a Notice of Violation is the department will provide copies of on the results of the inspection,
issued after an inspection, a request those documents at the department’s I have the right to appeal that
for Ombudsman review must be made expense. administrative order or permit
within10 days following receipt of the decision. I understand that my
4) I understand that I have a right to a
NOV. administrative hearing rights
split of any sample(s) taken during the
The inspection rights are: are set forth in A.R.S. § 49-482,
inspection, if the split of the sample(s)
§ 49-498 et seq. and Maricopa
1) The Maricopa County Air Quality would not prohibit an analysis from
County Air Pollution Control
Department (hereinafter “department”) being conducted or render an analysis
Regulation IV, Rule 400. If I have any
representative(s) identified above was/ inconclusive.
questions concerning my rights
were present at the above regulated 5) I understand that I have the right to
to appeal an administrative order
site at the above listed date and copies of any analysis performed on
or permit decision, I may contact
time. Upon entry to the premises, the sample(s) taken during the inspection
the department’s Ombudsman at
department representative(s) met with and that the department would
602-506-1813.
me, presented photo identification provide copies of this analysis at the
indicating that they are a department 9) I understand that the issuance of
department’s expense.
employee(s) and explained that: a Notice to Comply or a Notice
6) I understand that each person
of Violation is not appealable.
The purpose of this inspection is: interviewed during the inspection
I understand that if I have any
RR to determine compliance with will be informed that their statements
questions or concerns about this
Arizona Revised Statutes (A.R.S. may be included in the inspection
inspection, or I wish to dispute the
Title 49, Chapter 3, Article 3) and/ report.
inspection findings, I may contact
or Maricopa County Air Pollution the department’s Ombudsman at
Control Regulations. 602-506-1813.
RR to determine compliance with an 10) If a Notice of Violation is issued,
Air Quality Permit issued pursuant I understand that I may check its
to A.R.S. § 49-480, and Maricopa status.
County Regulations Rule 100, 11) While I have the right to decline
Section 105. to sign this form, the department
RR to determine compliance with an An Inspection Begins
representative(s) may still proceed
administrative or judicial order with the inspection/investigation.
issued pursuant A.R.S. § 49-491, §
49-511, § 49-512. To check on the status of a Notice of Violation use this weblink
This inspection is being conducted http://www.maricopa.gov/aq/divisions/enforcement/nov/nov_status.aspx
pursuant to A.R.S. § 49-473, § 49-474, §
49-488, and/or the inspection and entry
provisions in an Air Quality Permit or
conditional order. There are no direct Helpful Hint
While inspectors may offer constructive operational suggestions, you should
confer with your technical staff or consultant to determine your actions.

12-2 March 2010


Dust Abatement Handbook-Section 12 Inspections

Once an Inspection Begins, What Do Inspectors Look For?


An inspection can be a nerve-wracking required to be onsite during primary
experience or a validation of the
good on-site control practices being
dust-generating activities. For example,
if the only activity for the day is house
Helpful Hint
employed. When an inspector arrives, painting and no one is disturbing soil, Make someone in your
you can be reasonably sure several the Dust Control Coordinator may not organization accountable for
areas will be asked about. The brief be required that day. the environmental program.
list below highlights key points that an One person allows focus, creates
inspector will be reviewing. Water consistency, helps compliance,
and reduces costs. This person
Be able to document that water is
A Permit being used in sufficient quantities to
should be able to give direction,
arrange and track training, record
meet operational requirements.
Is the dust control permit onsite and subcontractor registrations, etc.
accessible? Has it expired?
Impacts on
Completed Records Sensitive Groups
Records should be clear and meet the
Site Conditions
Is a hospital, school, or senior
basic requirements. residential area nearby? Is there the Is there any visible trackout?
Are copies of all training certificates potential for sensitive groups to be Does trackout extend beyond 25 feet
onsite? exposed to dust from disturbed areas? in cumulative distance? Is someone
engaged in cleaning up trackout?
The Approved Dust Subcontractors Have disturbed areas been
adequately stabilized?
Control Plan In circumstances where a site
representative believes that a Are contingency control measures
Is the Dust Control Plan onsite? Are the subcontractor is directly responsible listed in the Dust Control Plan being
control measure commitments being for conditions that may result in used?
used? the issuance of an NOV, the site If required, does signage contain the
representative may request that required elements?
Whether a Dust Control the inspector confer with the
subcontractor to determine whether
Coordinator is on Site the subcontractor should be cited for
the violation.
Based on the size of your project,
a Dust Control Coordinator may be
The Dust Control Plan is
an enforceable document.
If commitments and/or
procedures contained within
the Dust Control Plan are not
being met, a Notice of Violation
can be issued.

12-3 March 2010


Dust Abatement Handbook-Section 12 Inspections

Courtesy Inspections
33 The intent of a courtesy inspection Note: if a courtesy inspection has been
is principally educational and is
encouraged to be scheduled early in
scheduled, but a complaint is made
before the courtesy inspection can take
Helpful Hint
place, the inspection will be treated as To arrange a courtesy inspection,
the term of a permit.
a complaint inspection rather than a call the Desk Duty Supervisor at
33 By taking advantage of a courtesy courtesy inspection and an NOV may (602) 506-6734.
inspection, it is easier to plan ahead to result.
ensure that follow-on activities will be
in compliance.
33 Courtesy inspections can be One courtesy inspection is Inspection Initiative
requested for each distinct phase allowed per project phase
of a project (typically demolition, (demolition, construction, The department has announced a
construction, vertical). vertical). new initiative - the Air Monitoring
Surveillance Project.
33 A request for a courtesy inspection
Some of the highest levels of
should be set up with adequate
particulate matter PM-10 (dust, smoke,
advance notice provided to the
fumes) pollution in Maricopa County
inspector (scheduling the inspection are found around the Durango, West
normally a takes a couple of days). 43rd Ave, South Phoenix, Higley,
33 During a courtesy inspection Buckeye, and Zuni Hills ambient air
observations of minor violations are quality monitors (map of the monitor
locations can be found at: http://
waived provided they are corrected
www.maricopa.gov/AirMonitoring/
while the inspector is onsite.
SitePollutionMap.aspx In an effort to
33 A major violation observed during a decrease pollution levels, the Maricopa
courtesy inspection may result in a County Air Quality Department, in
Notice of Violation being issued. conjunction with local cities and towns,
will focus inspection and surveillance
efforts within a two mile radius of
each of these monitoring sites for an
indefinite period of time. During the
enhanced surveillance period, there
will be an increase in the number of
inspections conducted on construction
sites, businesses, vacant lots and other
sources of PM-10.

An inspection underway

12-4 March 2010


Section 13 - Enforcement
Dust Abatement Handbook-Section 13 Enforcement

Enforcement
When a department inspector finds not involved in determining a penalty outstanding fees.
a condition that is non-compliant, offer. Penalities are calculated using In the event the recipient of the
he or she has a duty to issue either a the department’s penalty policy which enforcement action declines to accept a
Notice to Comply (NTC) or an Notice of can be reviewed on the department’s penalty offer, the department will refer
Violation (NOV). A Notice to Comply website, http://www.maricopa.gov/ the matter to the County Attorney’s
is not referred to the Enforcement aq/divisions/enforcement/docs/pdf/ office with a request to file a civil action
Division and is not considered in Penalty%20Policy.pdf. in Maricopa County Superior Court.
subsequent enforcement matters as a Once a penalty amount is determined,
factor in determining a penalty. If, in the rare event, an Order of
the NOV recipient is presented with a Abatement is issued (unilaterally by the
The Notice to Comply allows the permit settlement offer to resolve the NOV. department), the respondent has the
holder to correct the violation and The NOV recipient has the option of opportunity to seek a hearing before
not receive a penalty.* The Notice to engaging in a discussion with the the Air Pollution Control Hearing Board.
Comply is issued for only certain types department’s Enforcement Division to This appeal must be filed in writing
of non-compliance and under certain reach an agreed-upon penalty. If no and within 30 days of receipt of the
conditions (the policy document agreement can be reached, the case Order. An appeal to the Air Pollution
describes this in detail). The inspector is referred to the Maricopa County Control Hearing Board is also available
has only a limited amount of discretion Attorney’s Office where a penalty will following the issuance of a permit, a
to issue a Notice to Comply. A Notice be pursued through court action. A permit revision, or a conditional order.
to Comply will be converted into an permit holder has the right to legal
NOV if documentation is not provided representation at any point during the
to the department within a short time enforcement process.
validating that the non-compliant Most of the enforcement actions taken When an NOV is issued, and the
condition has been corrected. by the department result in an Order of permit holder believes that
If the recipient of the NOV does not Abatement by Consent—a document a subcontractor is primarily
seek Ombudsman review (or if the that outlines the violations and the responsible for the non-compliant
Ombudsman has affirmed the NOV, an penalty that is agreed upon between condition, the permit holder may
NOV will be referred to the department’s the department and the respondent. allow the subcontractor to pay
Enforcement Division where the case The Order of Abatement by Consent the agreed-upon penalty. If a
will be reviewed and a penalty amount may also contain additional provisions subcontractor agrees to accept
calculated by the enforcement officer necessary to achieving compliance, responsibility for the penalty it will
assigned to the case. The inspector is such as obtaining a permit or paying not have any bearing on the status
of the enforcement action against
the permit holder. An agreement
Violations Issued Jan09--Dec09 or understanding between a permit
holder and a subcontractor regarding
who will accept responsibility for a
violation will not be considered by
the department in the disposition of
an enforcement action.

169
153
The figure at left indicates the
frequency of violations issued for
non-compliance under Rule 310 for the
82
period of January through December
73
63 2009.
57
44

18
11
3
*The Notice to Comply policy is
No Permit Trackout Stability Control Record Project Post Training Opacity Expired included in the Resources section of
(§302) (§306) (§304) Measures Keeping Sign (§308) Permit (§309, (§303) Permit this handbook.
(§305) (§502) (§409) §310, (§406)
§410)

13-1 March 2010


Dust Abatement Handbook-Section 13 Enforcement

Ombudsman Review
The Office of the Ombudsman was decision. The services provided by
Office of the Ombudsman
created to provide an opportunity the Ombudsman are open to anyone,
Contact Information
for individuals seeking relief from including businesses, members of
some conflict with the department. public-interest groups, and private Dennis Dickerson
An Ombudsman provides assistance citizens. (602) 506-1813
to individuals and organizations with dickersond@mail.maricopa.gov
With regard to enforcement actions,
unresolved concerns and seeks to
the Ombudsman may offer an
achieve a fair resolution. Importantly,
independent review of a Notice to
the Air Quality Ombudsman reports
Comply, a Notice of Violation, or a
to the director of the department
review of the penalty assessment
and is empowered to work with
offered by the Enforcement Division.
department staff to resolve a
Generally, a request for Ombudsman
concern. The Ombudsman acts as
support must be initiated within 10
an impartial, unbiased party during
days of receipt of a Notice to Comply or
disputes. The Ombudsman can
an NOV or 10 days after receipt of the
investigate a complaint and make a
department’s final penalty offer letter.
recommendation, but has no direct,
legal authority to make or reverse a

Administrative Hearings
In addition to Ombudsman review, any
person receiving a final offer to settle
an enforcement action for a penalty
determined by the department has
the opportunity to request a hearing
before an Air Pollution Hearing
Officer. The hearing officer will take
evidence and make findings of fact
and conclusions of law that are then
presented to the department’s director
as a recommendation for a final
decision on a penalty offer.
A request for Ombudsman review of a
final offer letter will not be considered
a request for an administrative
hearing. A separate request for an
administrative hearing must be made
to the attention of the Hearing Officer.
The above chart shows the number of Ombudsman cases since the inception of the Om-
budsman program through December 1, 2009 as compared to the number of Notices of
Violation that have been issued during the same period.

13-2 March 2010


Dust Abatement Handbook-Section 13 Enforcement

Public Records Requests


Requests for public records are available through the Air Quality Records Man-
Submitting a
agement staff. All requests must be in writing and clearly state the records
sought. If the records request is vague or broad in nature, records management Public Records Request?
may ask for further clarification or for the requester to be more specific about the
records that are being requested.
By FAX
The form to initate a Public Records Act Request is available online at (602) 372-0997
http://www.maricopa.gov/aq/contact_us/public_records/docs/pdf/MCAQ_Re-
cords_Request_Non-Commercial_Purpose.pdf
By EMAIL
Records may be requested using the Air Quality Public Records Request Form or requestrecords@mail.maricopa.gov
by providing a written request with the following information:

- requester’s first and last name By MAIL


Maricopa Air Quality Department
- requester’s business/company name if applicable Attention: Records Management
1001 N. Central Avenue, Suite 125
- requester’s address or business address Phoenix, AZ 85004
- requester’s phone number and fax number
IN PERSON*
- record being requested (list business name, business address, and permit number
if known) 1001 N. Central Avenue, Suite 125
Phoenix, AZ 85004
- document what the records are requested for
*Submitting a request in per-
- document if the records are Commercial or Non-Commercial (see Commercial
son does not guarantee that the
Record Request Definition)
department will have the resources
immediately available to fulfill the
- indicate whether copies are being requested or if you wish to inspect the record in
request.
person.

More detailed information regarding requesting public records is available on


the department’s website at http://www.maricopa.gov/aq/contact_us/public_re-
cords/Default.aspx

13-3 March 2010


Section 14 - Test Methods
Dust Abatement Handbook-Section 14 Test Methods

Test Methods (Visible Emissions)


Test methods are identified in
Appendix C of the Air Quality Rules.
This section provides information on
these methods.

Determining The Presence


of Visible Emissions
Crossing a Property Line
EPA Reference Method 22
Visible emissions of dust (not requiring
opacity measurements) are determined
using EPA Reference Method 22. A
certified observer is not required. In
this method, emissions may not exceed
30 seconds in duration during any
six-minute period. The 30-second The above photos were taken during an ADEQ/ASU Smoke School held at
provision is cumulative, meaning
Mesa, Arizona on March 26, 2008. The plumes of smoke were generated
that emissions may be observed in
by a smoke machine that was calibrated on March 26, 2008 to meet
discrete segments that are shorter
than 30 seconds and which are then EPA Method 9 standards for smoke generator machines used to certify
added together. If the combined candidates for EPA Method 9 Visible Emissions Evaluator.
total of observed emissions exceeds Please note that the EPA Method 9 does not recognize photography as
30 seconds when collected during a a substitute for determination of opacity by human vision. Photographs
six-minute period, a violation has been may vary from picture to picture and camera to camera due to a variety of
observed.
physical conditions and camera operator variability. The photos should be
Determining Opacity of used as guidance to assist student learning.

Fugitive Emissions
seconds for each event over longer than one hour.
Appendix C, Parts 2, 3 and 4 a period not longer than one 4. Livestock activities (including
Opacity emissions of dust are hour. As a practical matter, the
corrals, pens, and arenas).
determined using Appendix C, Part 12 observations will most likely
This method uses momentary
3 and 4 of the Maricopa County be completed over the period
observations of plumes 1 meter
Air Pollution Control Rules and of a few minutes.
above the ground and taken at
Regulations. Observations made using
2. Continuous dust plumes, 15 second intervals. 13 readings
Appendix C require the observer to
including but not limited to, above 20% opacity represent a
be certified and to use very specific
plumes resulting from grading, violation.
protocols to determine opacity values.
trenching, blading, clearing,
There are several distinct protocols for leveling and raking. This
determining opacity based on the type method consists of the average
Note: EPA Method 9 is not used
of operation underway. of 12 observations with each
by Maricopa County Air Quality
1. Non-continuous dust plumes observation taken at intervals
Department staff for the determi-
including, but not limited to, of ten seconds.
nation of opacity values.
those plumes generated by bulk 3. For unpaved roads and unpaved
material loading/unloading, parking lots, two observations
non-conveyorized screening, per vehicle at one meter plume Information concerning “smoke
or trenching with backhoes. height. This method averages
This method averages 12 school” is provided in the
12 observations taken at 0 and Resources section.
observations taken at 0 and 5 5 seconds over a period not

14-1 March 2010


Dust Abatement Handbook-Section 14 Test Methods

Test Methods (Soil Stability)


Soil Crust Determination
(The Drop Ball Test)
A simple test to determine if a soil crust
is present is known as the drop ball test.
A relatively small (15.9 mm) steel ball
weighing between 0.56 and 0.6 ounces
is dropped onto a 1-foot square area
from a distance of 1 foot above the
surface. The ball is dropped three times
within this 1-foot square area.
If the observation of the dropped ball
passes the test criteria two out of each
three times the ball is dropped, the
area is considered to have passed the
test. The criteria for passing is for 1)
the dropped ball not to have sunk into
the surface such that it is partially or Drop Ball Test A Passing Grade
fully surrounded by loose grains of soil
and, 2) when the ball is removed, the
surface upon which it fell has not been
pulverized so that loose grains of soil
are visible.
Helpful Hint
The best test method is no test
method! If a project site is visibly
Does a failed drop ball test apply moist throughout, then an
to the whole project? inspector knows immediately that
any test method will pass, and
Yes. Each sample area selected
therefore a test method is
at random by an inspector is
not needed.
considered to be representative
of the soil type in the disturbed As a practical matter, the first test
area in its entirety. is a comon-sense visual (eyeball)
test.

Testing Requirements for Representative Areas

Threshold
Friction
Threshold
Representative Drop Ball/ Friction
Velocity
Silt Loading/
Flat Standing Visible Visible
Steel Ball Test
(TFV) with Vegetative Vegetative Emissions Emissions
Velocity Silt Content
Areas (TFV)
Rock Test Cover (FVC) Cover (SVC) Method 22 Appendix C
Method
(RTM)
Open Storage Pile X X
Unpaved Parking Lot
Unpaved Material Staging Area X X X
Unpaved Material Storage Area
Unpaved Haul Road
Unpaved Access Road X X X
Unpaved Equipment Path
Disturbed Surface X X X X X X X

14-2 March 2010


Dust Abatement Handbook-Section 14 Test Methods

Soil Test Methods (cont’d)


ASTM D2216 - 05 Standard Threshold Friction Velocity Threshold Friction Velocity
Test Methods for Threshold Friction Velocity (TFV) is with Rock Test Method
defined as the wind velocity necessary
Laboratory Determination to initiate soil erosion. A test can be Rock Test Method (Excerpted
readily performed in the field by an
of Water (Moisture) inspector to determine whether soil from the U.S. EPA Website)
Content of Soil and Rock conditions are susceptible to dust
entrainment. The TFV value is specified
This test method examines the wind-
resistance effects of rocks and other
by Mass in Rule 310 and soils that do not meet
this value are not stable and a condition
non-erodible elements on disturbed
surfaces. Non-erodible elements are
Determining soil moisture [12%, of non-compliance exists. objects larger than one cm in diameter
as required in Rule 310 §305.11(b) By sorting a soil sample through that remain firmly in place, even on
(2)] requires the use of a specific a series of sieves, which allow soil windy days. Typically, this includes
test procedure that is done using an particles of different sizes to pass rocks, stones, glass fragments, and
oven under laboratory conditions. through, a distribution of particle hard-packed clumps of soil lying on or
This method requires several hours sizes in a soil sample can be embedded in the surface. Vegetation
for proper drying of the sample. A determined. This distribution is then does not count as a non-erodible
synopsis of the test method is provided compared to a table contained in the element in this method. The purpose
on the ASTM website and the full test test methodology that allows the of this test is to estimate the percent
method is available through ASTM at determination of a TFV value. The cover of non-erodible elements on a
www.astm.org/Standards/D2216.htm. standard contained in Rule 310 is to given surface to see whether they take
maintain soil conditions such that the up enough space to offer protection
Determining Silt Content TFV value is 100 cm/sec or greater. to diminish the wind’s ability to
entrain dust. For details on this test
Using ASTM Method The details of this procedure are visit http://www.maricopa.gov/aq/
available for review at http://www. divisions/planning_analysis/rules/docs/
C136-06 maricopa.gov/aq/divisions/planning_ AppendixC-0404.pdf
analysis/rules/docs/AppendixC-0404.
Silt content is determined using ASTM pdf
Method C136-06—Standard Test
Method for Sieve Analysis of Fine and
Coarse Aggregates. The test is used
to determine the compliance status of
the resulting particle size distribution.
Details on the sample analysis
procedure can be found at
www.astm.org/Standards/C136.htm.

Determining Silt Loading


Silt loading is also determined using
ASTM Method C136-06—Standard Test
Method for Sieve Analysis of Fine and
Coarse Aggregates. The test is used
to determine the compliance status of
the resulting particle size distribution.
Details on the sample analysis
procedure can be found at www.astm.
org/Standards/C136.htm. The main Soil Testing
difference between silt loading and silt
content is a mathematical factor.

14-3 March 2010


Section 15 - More Helpful Hints
Dust Abatement Handbook-Section 15 More Helpful Hints

More Helpful Hints


33 Have any and all site supervisors read 33 To better control trackout, one 33 Restrict exits with fencing.
and initial the approved Dust Control successful practice is to monitor exits
33 Park only in designated areas that are
Plan. at least every 30 minutes.
identified in the Dust Control Plan or,
33 Review the approved Dust Control 33 Maintain records that provide a clear at minimum, in areas that are posted.
Plan with subcontractors. understanding of site operations—
33 Use courtesy inspections and
33 Keep the job site organized and recordkeeping should be conducted
other department programs, such
presentable. in tandem with site operations and
as the “Tailgate Talks” DVD, to aid
be used to help trigger corrective
33 Prominently post site rules for dust your compliance program. See the
action. For example, an observation of
control. Resources section to find out how to
trackout greater than 25 feet should
request your free copy.
33 Restrict access to non-active areas. be accompanied by notations of
immediate action taken to control 33 If you are hauling offsite, ask the
33 Establish subcontractor expectations. permit holder to spray water over
trackout.
33 Conduct frequent dust control your load before tarping to ensure
33 Be aware of sensitive areas that
tailgate meetings. that dust emissions while driving are
surround your site—anticipate
eliminated.
complaints and inspections to
investigate complaints.

Fenced exits

Maintaining moist soil

Watered haul road

15-1 March 2010


Section 16 - Resources
Dust Abatement Handbook-Section 16 Resources

Resources
Arizona Air Quality State Maricopa County Air Quality
Implementation Plan Department Website
http://www.maricopa.gov/aq/divisions/planning_ 3
3Dust Abatement Field Guide for the Construction
analysis/state_implementation_plan.aspx Industry
3
3Location, Hours, and Other Contact Information
3
3One Stop Shop
Courtesy Inspections 3
3Public Records Request
Call (602) 506-6734 to schedule courtesy 3
3Web Contact Form
inspections. http://www.maricopa.gov/aq/

Ombudsman
www.maricopa.gov/aq/divisions/Ombudsman/
Dust Control Application Guidance Default.aspx
http://www.maricopa.gov/aq/divisions/compliance/dust/
docs/pdf/DustControlPermitApplicationPackage.pdf
PM-10 Non-attainment Area, Area A,
and Other Planning Maps
Dust Control Forms, Instructions, http://www.maricopa.gov/aq/divisions/planning_
analysis/PlanningAreaMaps.aspx
Information, and Samples
www.maricopa.gov/aq/divisions/compliance/dust/
resources.aspx Report a Violation
Call (602) 372-2703 or visit:
www.maricopa.gov/aq/
Dust Duty Desk Supervisor contact_us/report_violation.aspx

(602) 506-6734
Rule 310 and Other Applicable Rules
3
3Rule 310—Fugitive Dust from Dust-Generating
Enforcement Operations
3
3Rule 200—Permit Requirements
Maricopa County Air Quality Enforcement Policy
www.maricopa.gov/aq/divisions/enforcement/ 3
3Appendix F—Soil Designations
resources/#public_enforcement 3
3Appendix C—Test Methods
www.maricopa.gov/aq/divisions/planning_analysis/
AdoptedRules.aspx

16-1 March 2010


Dust Abatement Handbook-Section 16 Resources

Resources (cont’d)
Subcontractor Registration
Information
www.maricopa.gov/aq/divisions/compliance/dust/
subcontractorRegistration.aspx

Training
www.maricopa.gov/aq/divisions/compliance/dust/
dust_control_training/default.aspx

Other Manuals on Dust Control

Clark County, Nevada – Construction Activities


Dust Control Handbook.
http://www.cleanairnet.org/caiasia/1412/articles-58190_
resource_1.pdf

Field Manual on PM-10 and Fugitive Dust Control,


Best Management Practices for Maricopa County,
Arizona.
Zbigniew D. Czupak and Dr. Edward Kavazanjian,
P.E., Arizona State University, Ira A. Fulton School of
Engineering.
http://pavement.engineering.asu.edu/pdf/BMPs%20
for%20Dust%20Control%20Reference%20Manual%20
-%20Final.pdf

16-2 March 2010


Section 17 - Appendices

Only Appendices B and C are contained in this document. All others can be
accessed by using the hyperlinks embedded in the handbook.

Appendix B
Draft Guidance Document for Issuing Notices of Violation Directly to
Subcontractors or to other Non-Permitted Entities Observed Violating
Rule 310 (April 18, 2006)

Appendix C
Notice to Comply Interim Policy
Maricopa County
Air Quality Department

INTEROFFICE MEMORANDUM

Date: April 13, 2009

To: Air Quality Department staff

From: Lawrence Odle, Director

Subject: Notice to Comply Interim Policy

21 Notice to Comply Interim Policy

Contents:
21.1 EFFECTIVE DATE
21.2 GENERAL PURPOSE
21.3 ISSUANCE
21.4 ENFORCEMENT

21.1 EFFECTIVE DATE


This interim policy is effective beginning April 13, 2009, and shall remain in effect until terminated or
superseded.

21.2 GENERAL PURPOSE


The purpose of this policy is to establish interim guidance to department staff concerning the use of a
Notice to Comply, commonly referred to as an NTC, option as an additional tool for documenting
activities or conditions that are not in compliance with statutes or regulations relating to air quality
(“Noncompliance”). The NTC serves as both a formal notice of Noncompliance and directs that
immediate conclusive action must occur to bring about compliance. The NTC is available to resolve
administrative and procedural violations that do not have the immediate potential to contribute to
emissions that would exceed a rule or permit condition. An NTC is a tool that allows staff to document
the existence of administrative and procedural violations that may be readily corrected in the field or can
be readily corrected through the completion of an administrative activity within a period of 24 hours.
An NTC is formal documentation of actual Noncompliance activity. Even though an NTC may be
issued, it does not eliminate the existence of a violation or a penalty that may be subsequently issued by
the department, should the department determine it is in the interest of public policy to do so.

21.3 ISSUANCE
The NTC is an administrative/enforcement tool that is available to staff when Noncompliance is
observed while conducting an inspection or reviewing required reports. The NTC is to be used only to
document a violation of air quality rules and regulations. When conditions warrant, and at the discretion
of the inspector, an NTC may be issued in lieu of a Notice of Violation.

1001 N. Central Avenue, Suite #900 Phoenix, AZ 85004 Phone: 602-506-6443 Fax: 602-372-2440.
April 13, 2009
RE: Notice to Comply interim policy
Page 2 of 2

Staff issuing an NTC shall inform the violator that compliance must occur within 24 hours and that a
written response to the NTC is required within 5 days of issuance. The written response shall include,
but not be limited to:

NTC number (or copy of the NTC);


Location of Noncompliance activity;
Certification of truth, accuracy and completeness;
A description of the Noncompliance activity, including its duration and cause;
Identification of the responsible source contact;
A description of what action has been taken to bring about compliance; and,
Date and time complete compliance was achieved.

The written response to an NTC shall be submitted to the issuing staff.

An NTC shall not be issued for any Noncompliance activity that constitutes actual emissions violation
or is/or would directly contribute to emissions that constitute a violation of a Rule or permit condition,
e.g., observations of opacity in violation of a rule or emissions calculated to exceed a permit condition.

An NTC shall not be issued if the site has a history of significant or recurring Noncompliance. For the
purposes of this policy, recurring Noncompliance is defined as 2 or more violations for the same or
similar Noncompliance issue(s) within any 3-year consecutive period at any facility under the common
ownership of the owner, or, under the common operation of the operator.

An NTC shall not be issued if the violation cannot be corrected immediately or in 24 hours for an
administrative violation.

21.4 ENFORCEMENT
Failure of a party to correct the Noncompliance activity within 24 hours or failure of the party to submit
a written response received by the Maricopa County Air Quality Department within 5 days of receipt of
an NTC shall result in the automatic issuance of the NTC into a Notice of Violation and the application
of the standard penalty assessment procedure. The NTC will remain issued and serve as historical
documentation that formal notice of the need to comply was provided.

You might also like