You are on page 1of 2

DAILY SITE REPORT & ACTIVITIES

Project Title : Project No. : Project Site : HARAMAIN HIGH SPEED RAIL IIP-199 BR445 Date : Weather : Min. Temp.: Max. Temp.: December 13, 2012 Partly Cloudy

" EXECUTED WORKS TODAY AND PROGRAM FOR PROPOSED WORK"


SHADE MANPOWER TOOLS & EQUPIMENTS

INDIRECT
Construction Manager Tech. Dept. Head Sr. Superintendent General Foreman Engineer Tech. Dept. Safety Officer Planning Engineer Surveyor Surveyor Aide AutoCAD Operator Carpenter Foreman Foreman Steel Fixer Civil Foreman Secretary Leadman Carpenter Office Boy Leadman Steel Fixer Foreman Electrician Timekeeper Store Keeper Foreman Mason Sub - TOTAL

NO.
1 1 1 1 1 1 1 1 2 1 2 1 3 5

DIRECT
Carpenter Steel Fixer Mason Electrician Plumber L/M Labor Purchaser Erector/Rigger Painter Waterproof works Guard Heavy Equipment Operator Driver Bob cut operator Plumber Watchman Mechanic

NO.
3 1 1

Tools/Others
Grinder Big Grinder Small Jack hammer Small Jig saw Machine Hilti Drill Machine Makita Drill Machine Dewalt Drill Machine

NO.
1 1 1 3 2 1 2

Equipments
Air Compressor Generator ( NTC & Big) Bending Machine Shovel Loader (Big) Theodolite Total Station Level Machine Vibrator Hose Vibrator Machine Power Helicopter Welding Machine (Big)

NO.
1 4 1

Offset Cutter or Speed Makita Circular Saw Water Pump 1.5HP Water Pump 2HP

6 6

3 2

Steel Bar Cutter Screw Drill Makita Electric Planner Dewalt Electric Planner

1 1

Welding Machine Small Asphalt Cutter Electric Lifter Mobile Crane Bobcat Dump truck Tata pikup Blower

2 2

Spit Gun Ductile Water Tank Big Water Tank Small Electric Water cooler

1 1
24

Bus (50 Seater) Electric Hydraulic Bender Sub - TOTAL


16

2 2
17

Chain Block Chipping gun Sub - TOTAL


25

Sub - TOTAL

TOTAL SHADE MANPOWER

40

TOTAL TOOLS & EQUIPMENTS

42

RENTAL MANPOWER RENTAL MANPOWER


Carpenter Steel Fixer Leadman Steel Fixer Mason Heavy Equipment Operator Sub - TOTAL
124

NO.
35 83 6

RENTAL MANPOWER

NO.

RENTAL MANPOWER

NO.

RENTAL MANPOWER

NO.

Sub - TOTAL

Sub - TOTAL

Sub - TOTAL

TOTAL RENTAL MANPOWER


AL-OFI COMPANY SUBCON MANPOWER
Steel Fixer

124
SUBCON MANPOWER

NO.

SUBCON MANPOWER

NO.

SUBCON MANPOWER

NO.

SUBCON MANPOWER

NO.

Sub - TOTAL

Sub - TOTAL

Sub - TOTAL

Sub - TOTAL

TOTAL SUBCON MANPOWER


TOTAL MANPOWER @ SITE

164

ACTUAL EXECUTED WORK


STEEL WORKS 1.) Install top reinforcement bars at pier column 4 with a total weight of 1,186.96 kgs. 2.) Install fifteen layers ring bar and one layer inner hook bar at pier 32 with a total weight of 137.10 kgs. 3.) Install rebars at pier 31kicker and foundation with a total weight of 80.28 kgs. 4.) Repair and reinstall rebars at bearing area of pier column 3 with a total weight of 125.23 kgs. 5.) Install rebars of the girder beetween pier 14 and pier 15 with a total weight of 735.52 kgs. 6.) Install rebars for the girder bet. Pier 8 and pier 9 with a total weight of 1626.72 kgs. 7.) Manual hauling of rebars from workshop to girder between pier 8 and peir 8 with a total weight of 426.15 kgs. 8.) Install rebars a at pier 17 foundation with a total weight of 2,93.51 kgs. 9.) Install and align top rebars of the foundation 37 with a total weight of 227.28 kgs.

December 13, 2012

CARPENTRY WORKS 1.) Realign the sleeve pipe at pier column 3 2.) Fixing all the support at pier column 3 for final alignment. 3.) Fabricate formworks at girder between pier 14 and pier 15 with a total area of 32.4 sq.m 4.) Install scaffolding at pier 37 foundation 5.) Put planks for the access of the workers and consultant for inspection. 6.) Install interior shuttering at girder between pier 5 and pier 6 with a total area of 3.42 sq.m 7.) Install planks as the top support of the girde shuttering with a total of 320 bd.ft. 8.) Install shuttering of the girder between pier 14 nad pier 15 with a total area of 81 sq.m 9.) Install kicker and support at pier 31. 10.) Fixed all the exterior support of the foundation at pier 37. 11.) Cutting and bending of steel with a total weight of 10,779.70 kgs.

MASON 1.) Apply second coat betumin painting at pier 39 foundation with a total area of 92 sq.m 2.) Chiiping the loose concrete at pier 32 foundation.. 3.) Casting of concrete at pier column 14 1st stage and pier column 3 2nd stage with a total volume of 99 cu.m

SAFETY WORKS 1.) Cleaning and Removal of Construction Waste and Debris from the project site. 2.) Checking and Monitoring of Safety Rules and Regulations at the project site. MISCELLANEOUS WORKS

REMARKS:

Prepared By:

Approved By:

Engr. Tarek Hamed


Construction Manager - Shadeco, Ltd. Project Manager - Shadeco, Ltd.

You might also like