You are on page 1of 8

Rate Analysis of HDPE pipe

Guide to use tool: i) In column C, yellow cells, put current rates of pipes. ii) These rates are FOR,NCR, Excise 8.24% included, CST at 2% against form C included, Inspection extra. As such
transportation, excise duty and CST taken at 0%. If not included put suitable % in row 5 iii) Inspection is to be paid separately to inspection agency as such not included in these rates if otherwi
it may be added separately. iv) In row 5, green cells some percentages are given which may be reviewed and revise/update if required.
HDPE Pipes
Supply, Laying, Jointing, Field Testing, Commissioning Rate of Pipe Transport Excise
CST at
Local
Laying Testing
Contractor Total Rate
complete at site of HDPE (PE80 Grade Coumpound)
ation at
Duty at
Handling and
and
s Profit at
Pipes PN-8.0 (8.0 kg/sqcm) as per IS:4984 and
& storage Jointing commissio
specifications for water application, including all cost of
at
at
ning at
material, labour required, transportation, loading,
unloading & stacking etc. complete.

110mm PN8
125mm PN8
140mm PN8
160mm PN8
180mm PN8
200mm PN8
225mm PN8
250mm PN8
280mm PN8
315mm PN8
355mm PN8
400mm PN8
450mm PN8
500mm PN8
560mm PN8
630mm PN8

M/S kriti letter

0%

0%

0%

261.19
335.93
420.00
547.48
694.14
855.38
1,078.91
1,334.26
1,669.80
2,113.74
2,676.70
3,475.93
4,398.75
5,423.37
6,795.87
8,547.90

1%
2.61
3.36
4.20
5.47
6.94
8.55
10.79
13.34
16.70
21.14
26.77
34.76
43.99
54.23
67.96
85.48

3%

4%

7.84
10.08
12.60
16.42
20.82
25.66
32.37
40.03
50.09
63.41
80.30
104.28
131.96
162.70
203.88
256.44

10.45
13.44
16.80
21.90
27.77
34.22
43.16
53.37
66.79
84.55
107.07
139.04
175.95
216.93
271.83
341.92

10%
28.21
36.28
45.36
59.13
74.97
92.38
116.52
144.10
180.34
228.28
289.08
375.40
475.07
585.72
733.95
923.17

310.29
399.08
498.96
650.41
824.64
1,016.19
1,281.75
1,585.10
1,983.72
2,511.12
3,179.92
4,129.40
5,225.72
6,442.96
8,073.49
10,154.91

ded, Inspection extra. As such


cluded in these rates if otherwise then

Specials Total Rate


at % of including
total cost specials

10%
31.03
39.91
49.90
65.04
82.46
101.62
128.17
158.51
198.37
251.11
317.99
412.94
522.57
644.30
807.35
1,015.49

341.32
438.99
548.86
715.45
907.10
1,117.81
1,409.92
1,743.61
2,182.09
2,762.24
3,497.91
4,542.35
5,748.29
7,087.26
8,880.84
11,170.40

Rate Analysis: MDPE Pipes


Guide to use tool: i) In column C, yellow cells, put current rates of pipes. ii) These rates are FOR,Jalgaon as such transportation added, Excise included as such 0% added ,
CST not included as such added extra, iii) Inspection is to be paid separately to inspection agency as such not included in these rates if otherwise then it may be added
separately. iv) In row 4, green cells some percentages are given which may be reviewed and revise/update if required.
Service Connections: Supply, Laying, Jointing, Field
Quotation of firm
Excise
Transporta CST
Local
Breakag Laying Contractor
Testing, Commissioning complete at site of MDPE (PE
applicable tion cost
applicabl handling e at
and
s profit at
80 Grade Coumpound) Pipes PN-16 (16 kg/sqcm) as per
e
and
jointing
ISO4427 and specifications for water application,
storage at
cost
including all cost of material, labour required,
transportation, loading, unloading & stacking etc.
complete.
Jain irrigation

20 mm Dia SDR 9
25 mm Dia SDR 11
32 mm Dia SDR 11
40 mm Dia
50 mm Dia
16 mm Dia

Rates FOR Jalgaon,


excise included,
CST/LST extra
22.85
29.10
47.95

0%

10%

2.29
2.91
4.80
-

4%

0.91
1.16
1.92
-

1%

0.23
0.29
0.48
-

1%

0.02
0.03
0.05
-

3%

0.69
0.87
1.44
-

10%

2.70
3.44
5.66
-

included as such 0% added ,


se then it may be added
Total Rate

29.68
37.80
62.29
-

Rate Analysis: Ductile Iron (DI) Pipes


Guidance for use of Tool: i) Adopt current market rate in column Consitions about excise duty, transportation, CST to be suitably accounted. ii) Rate in colomn 3 are with Nill Excise du
Exemption certificate to be provided by the buyer along with the order / before production Central Excise Notification No. 6/2006 as amended by Central Excise Notification No. 6/2007 da
However, if excise duty is leviable than put suitable % in cell D3.Inspection charges included. These rates are FOR NCR as such transportation taken 0% however if transportation is extra
E3. These rates are with CST zero against form C. If it is to be added then take suitable % in cell F3. Rubber gasket included in rate. if not included then add suitble cost for rubber ring. iii
reviewed and suitably revised/updated if needed.
Supply, Laying, Jointing Field Testing & Commissioning complete at Rate of
Transporta CST
Excise
Local
Breakage Total
Laying
site as per specifications of centrifugally cast (spun) Ductile Iron
Rs per Meter
tion at
duty at
handling at
and
Pressure Pipes (S &S) ISI marked for water conforming to IS
and
Jointing
8329/2000 with push on type EPDM 'ISI marked' rubber gasket
storage at
of pipes
jointing as per IS 5382 specifications. Pipe shall be outside Zinc
&
coated with finishing layer of Bitumen and have factory cement
hydraulic
mortar lining as per IS 8329/2000. The rates includes all cost of
testing at
material, labour required, transportation, loading, unloading &
stacking etc. complete and also includes the cost of EPDM 'ISI
marked' rubber gasket

100 mm K7
150 mm K7
200 mm K7
250 mm K7
300 mm K7
350 mm K7
400 mm K7
450 mm K7
500 mm K7
600 mm K7
700 mm K7
750 mm K7
800 mm K7
900 mm K7
1000 mm K7

Electrosteel rate
vide letter 449/4- 0.00%
2-09
832
1,065
1,540
2,005
2,543
3,197
3,833
4,547
5,325
7,015
9,622
11,135
12,550
15,314
18,354
-

0.00%

0.00%
-

1%

1%

8.32
10.65
15.40
20.05
25.43
31.97
38.33
45.47
53.25
70.15
96.22
111.35
125.50
153.14
183.54

8.32
10.65
15.40
20.05
25.43
31.97
38.33
45.47
53.25
70.15
96.22
111.35
125.50
153.14
183.54

2.50%
848.64
1,086.30
1,570.80
2,045.10
2,593.86
3,260.94
3,909.66
4,637.94
5,431.50
7,155.30
9,814.44
11,357.70
12,801.00
15,620.28
18,721.08

21.22
27.16
39.27
51.13
64.85
81.52
97.74
115.95
135.79
178.88
245.36
283.94
320.03
390.51
468.03

Note: Rate in colomn 3 are to be taken as per prevalent market rates.

in colomn 3 are with Nill Excise duty against valid Excise Duty
al Excise Notification No. 6/2007 dated 1st March 2007.
% however if transportation is extra then put suitable % in cell
n add suitble cost for rubber ring. iii) Green cells may be
Contractors Total
Profit at

10%
86.99
111.35
161.01
209.62
265.87
334.25
400.74
475.39
556.73
733.42
1,005.98
1,164.16
1,312.10
1,601.08
1,918.91

Specials Total Rate


at
inclusive
of specials

3%
957
1,225
1,771
2,306
2,925
3,677
4,408
5,229
6,124
8,068
11,066
12,806
14,433
17,612
21,108

28.71
36.74
53.13
69.18
87.74
110.30
132.24
156.88
183.72
242.03
331.97
384.17
432.99
528.36
633.24

986
1,262
1,824
2,375
3,012
3,787
4,540
5,386
6,308
8,310
11,398
13,190
14,866
18,140
21,741

You might also like