REF.

: SOIL/QTN/2013/ 255

DATED : 06 FEBRUARY 2013

ASST. PROJECT MANAGER, HUSK POWER UNIVERSITY, HUSK POWER SYSTEMS PVT. LTD. MOBILE NO. .: +91-8084100778. EMAIL: avinash@huskpowersystems.com KIND ATTN.: MR. AVINASH KUMAR, SUB.: REF. : GEOTECHNICAL INVESTIGATION WORKS FOR A 4.75 ACRES LAND IN MOTIHARI, EAST CHAMPARAN, BIHAR YOUR EMAIL DATED- 06/02/2013.

Dear Sir, As desired by you, we submit herewith our offer for the above cited subject. 1.0 ENCLOSURES
Schedule of Rates (Geotechnical Investigation) :: Annexure 1

2.0 METHODOLOGY The bore holes will be advanced by Shell and Auger equipment (engine driven) with full length flush jointed casings. Undisturbed tube samples will be collected by open drive method from cohesive or partly cohesive deposits @ 3.0M interval. Standard Penetration Tests will be conducted @ 2.0M in all types of soils. Disturbed samples will be collected @ 1.0M interval or at every change of strata. When rate of progress by boring become less than 300 mm per hour and SPT N value become more that 100 in two consecutive tests, it will be deemed to conclude that rock layer has struck and further progress will be made by rotary core drilling using by TC /Diamond bit. Based on the laboratory test results, field tests records and analysis of the data, a detailed Geotechnical investigation report will be prepared and presented giving bearing capacity, recommended foundation depth, settlement potentiality, pile capacity etc. as required.

3.0 SCOPE OF WORK

Description
Bore Hole Electrical Resistivity Test Block Vibration Test Permeability Test

Qty.
08 03 02 04 Nos. (25 meter depth per bore hole) Nos. Nos. Nos.

4.0 A) B) C) D) E) F)

LIST OF EQUIPMENTS TO BE DEPLOYED AT SITE Boring-cum-Drilling Rig or Boring and Drilling Rig (Not Hydraulic Rig) Sampling Assembly SP Testing Assembly Electrical Resistivity Test Equipment Block Vibration Test Equipment Permeability Test

01 01 01 01 01 01

Set Set Set Set Set Set

G:\WINDOC\QTN\Husk Power_Bihar\Offer Ltr_130206..doc

Page 1 of 2

5.0 A) B) C) D) E)

COMPLETION TIME Mobilisation to site Field work Laboratory Testing Draft final Report Final Report

We propose the time schedule is given below. Within 02 weeks of order / handing over of the site Within 06 weeks of order / handing over of the site Within 07 weeks of order / handing over of the site Within 08 weeks of order / handing over of the site Within 01 week after receiving your comments.

to to to to

us. us. us. us.

We propose our payment terms as follows for this job. 6.0 PAYMENT TERMS A) Progressively R/A bills will be 80% of the bill/executed value shall be paid to us raised. within 10 (Ten) days of bill submission. B) After submission of final Report 20% Balance payment shall be paid to us within 20 (Twenty) days of bill submission. The payment shall be made to us through On Line OR Demand Draft. 7.0 VALIDITY Our offer is valid for a period of two months only.

8.0 SALES & SERVICE TAXES No Sales Tax on works contact shall be deducted from our bill as Sales Tax is not applicable from our job. SERVICE TAX :: Service Tax and Education Cess shall be charged extra over and above our each bill as available on the date of billing. The present rate of Service Tax is 12.36%. Our Service Tax Regd. No. AABCC0609BST001. Service Tax shall be paid to us along with our each bill. 9.0 GENERAL TERMS A) You shall hand over the site free from all encumbrances. B) We shall be allowed to work from 08-00 hrs. to 18-00 hrs. on all days including Sundays & Holidays. C) We shall be allowed to erect tents at site inside your premises for the purpose of temporary accommodation of our workmen. D) You shall depute one representative at site from your end and for the entire duration of field work for checking and certification of our work. E) You shall provide us with the facility of water at site both for the purpose of boring and drinking. F) All samples as collected at site will be brought to our own laboratory at Kolkata for the purpose of testing. G) For idling of our equipment and personnel arising out of no fault of us, we shall be compensated @ Rs. 6,000/- per day against each set of equipment. H) Our rate quoted for boring/drilling work on land only. I) All the payments shall be made as per the actual executed quantity.

Hope you will find our offer reasonable and entrust us with your valued work order. Thanking you and assuring you the best of our services at all times. Yours faithfully, FOR C. E. TESTING COMPANY PVT. LIMITED

( R. P. DUTTA) Encl. : As stated above.

G:\WINDOC\QTN\Husk Power_Bihar\Offer Ltr_130206..doc

Page 2 of 2

Annexure - I

SCHEDULE OF QUANTITIES WITH RATES FOR GEOTECHNICAL INVESTIGATION FOR A 4.75 ACARES LAND IN MOTIHARI, EAST CHAMPARAN, BIHAR
Sr. No. 1 Description Mobilisation of necessary equipment and man power at the project site and demobilization of the same on completion of field work. Shifting of Equipments, tools and plants from one bore hole to other bore hole. Qty 1 Unit L.S. Rate (Rs.) Date : 06/02/2013 Amount (Rs.)
2,00,000.00

2,00,000.00

2 3

Nos.
Mtr.

1,500.00 800.00

10,500.00 1,60,000.00

200 Boring of 150 mm dia. 25m - 8 Nos. Borehole by shell and auger equipment through all types of soil but excluding Rocks and Boulders and including collection of Disturbed samples, Undisturbed samples and conducting S.P. Tests. Drilling through all type of rock upto a required depth Rate only using rotary drilling equipment including recovery of cores and provision of core boxes, all as specified

Mtr.

1,850.00

5 6

Conducting Electrical Resistivity tests as per IS 3043 Conducting Block Vibration Test Carrying out In-situ Field Permeability Test in borehole and establishment of Permeability Coefficient.

3 2 4

Nos. Nos. Nos.

4,000.00 55,000.00 4,000.00

12,000.00 1,10,000.00 16,000.00

8 Nos. Conducting Routine Laboratory Tests on Soil samples for Sieve analysis, Hydrometer, LL and PL, Specific gravity, NMC, Consolidation Tests, Triaxial shear test/Direct shear etc. as per standard norms. Conducting Routine Laboratory Tests on Rock samples Rate only Bore Hole Density, Sp. Gravity, Porosity, Water Absorption, Crushing Strength, Point Load Index etc. Water sample collection and carrying out chemical 2 Bore Hole testing for pH, sulphate and chloride.

2,500.00

20,000.00

1,500.00

500.00

1,000.00

10 11

Chemical testing of soil samples for pH, sulphate and chloride. Preparation and submission of Report giving all the Field and Laboratory Test Results, Graphs, Charts, cables etc. along with Recommendations on Foundation system, bearing capacity, pile capacity etc.

2 1

Nos. L.S.

500.00 35,000.00

1,000.00 35,000.00

Total Add. Service Tax@12.36%


Sub Total

5,65,500.00 69,896.00 6,35,396.00

For C. E. Testing Company Pvt. Ltd.

( R. P. DUTTA )

G:\WINDOC\QTN\Husk Power_Bihar\BOQ_130206.xls