PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program,3rd May, 2011

S.l. No. Description


1 2 3 4 5 6 7 8

Work Program of 3rd May, 2011

Achievement of 2nd May, 2011


Shuttering work

Remarks

Open Drain (Western end) Concrete pouring of 1st lift PVD 300mm sand Blanket 150 mm Local sand lay Segment 1 Pre-cast Pile PVD driving at Segment-2A Coarse sand dumping at Segment-2A (part) Target Quantity =30 truck Top soil Removal for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Due to Friday Driving work Performed Coarse sand dumping at Segment-2A (part) in progress Actually layed=14 truck Top soil Removing in progress Welding & Shuttering work for Pre-cast Pile in progress. No work Interlocking Block=4100 Nos half day Due to Friday Dredge Sand supply is not available

Yard drainage ( RCC Pipe) 15 Nos Interlocking Block Interlocking Block=5000 Nos

Sub Contractor (Md.Mubarak) is not agree to work on Friday Executed new Trial Mix brought by Shahidul Islam(Head office),needed 2 hours to perform it

9 10

Dismantling work Dredge work

CC/RCC Dismantling work at Segment 3 & 4 No Dredge work

CC/RCC Dismantling work at Segment 3 & 4 in progress No Dredge work

NCT BACK-UP PROJECT, CHITTAGONG Work Program,22th May, 2011

S.l. No. Description


1 2 3 Segment 1A Segment 2A (part) Segment 1 (part)

Work Program of 22th May, 2011


Sand dumping and sand bagging of preloading 300mm Sand Blanket filling PVD Driving Clearing & Grubbing.

Achievement of 21th May, 2011


Sand dumping and sand bagging of preloading in progress 300mm Sand Blanket filling in progress 300mm sand Blanket filling and FDD test executed. Clearing & Grubbing in progress. Clearing & Grubbing in progress. Rebar fabrication in progress Concrete pouring in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

4 5 6 7 8

Segment 4 (part) Culvert (rail) RCC pipe Interlocking Block Dismantling work

Clearing & Grubbing. Rebar fabrication Concrete pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,26th May, 2011

S.l. No. Description


1 2 3 4 5 Segment 1A Segment 2A (part) Segment 1 (part) Segment 4 (part) Culvert (road)

Work Program of 26th May, 2011


Sand dumping and sand bagging of preloading 300mm Sand Blanket filling Clearing & Grubbing. Clearing & Grubbing. Rebar fabrication CC Casting.

Achievement of 25th May, 2011


Sand dumping and sand bagging of preloading in progress 300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress.

Remarks

Soling Executed. Rebar fabrication in progress

Culvert (rail)

Rebar fabrication Earth Excavation

7 8 9

RCC pipe Interlocking Block Dismantling work

Concrete pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

Concrete pouring in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,28th May, 2011

S.l. No. Description


1 Segment 1A

Work Program of 28th May, 2011


Sand dumping and sand bagging of preloading PVD Driving (part)

Achievement of 27th May, 2011


Sand dumping and sand bagging of preloading in progress

Remarks

2 3 4 5 6 7

Segment 2A (part) Segment 1 (part) Segment 4 (part) Culvert (road) Open Deep Drain Culvert (rail)

300mm Sand Blanket filling Clearing & Grubbing. Clearing & Grubbing. Base Concrete Casting Bracing Concrete Pouring Rebar fabrication Earth Excavation

300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress. Rebar binding in progress.

Rebar fabrication in progress

8 9 10

RCC pipe Interlocking Block Dismantling work

Concrete pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

Concrete pouring in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,29th May, 2011

S.l. No. Description


1 Segment 1A

Work Program of 29th May, 2011


Sand dumping and sand bagging of preloading PVD Driving (part)

Achievement of 28th May, 2011


Sand dumping and sand bagging of preloading in progress PVD Driving in progress 300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress. Base Concrete casting finished. Bracing Concrete pouring in progress. Rebar fabrication in progress

Remarks

2 3 4 5 6 7

Segment 2A (part) Segment 1 (part) Segment 4 (part) Culvert (road) Open Deep Drain Culvert (rail)

300mm Sand Blanket filling Clearing & Grubbing. Clearing & Grubbing. Rebar binding & Shuttering of wall. Bracing Concrete Pouring Rebar fabrication Earth Excavation

8 9 10

RCC pipe Interlocking Block Dismantling work

Concrete pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

Concrete pouring in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

(Engr.Nityananda Nandi) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 01 February, 2011

S.l. No. Description


1 Open Drain

Work Program of 01 February, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m Cement Concrete for Open drain South side.

Achievement of 31 January, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m in progress. Cement Concrete for Open drain South side.

Segment 2A

PVD driving Coarse sand laying for 200 mm sand Blanket Sand filling work Sand filling work in progress Top soil Removing in progress Welding & Shuttering work for Pre-cast Pile in progress. Concrete pouring for RCC Pipe in progress. Regular Production of Interlocking Block on going.

3 4 5 6 7 8 9

Segment 1 Pre-cast Pile

Top soil Removed for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Interlocking Block Dismantling work Lab test Dredging work Regular Production of Interlocking Block. CC/RCC Dismantling work at Segment 3 & 4 Compressive Strength test. Dredging work

Compressive Strength test of Interlocking Block.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG

Work Program for 01 January 2011

S.l. No. Description


1 2 3 4 5 6 Open Drain Segment 1A Dismantling work Interlocking Block Mix Design and Sampling Dredging work

Work Program of 01 January, 2011


Shuttering work for wall at Ch 0+535 to 0+566=31m Sand filling work. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 Dredging work

Achievement of 31 December, 2010


Shuttering work for wall at Ch 0+535 to 0+566 in progress Sand filling work in progress

Regular Production of Block on going Compressive strength test for C30 Dredging work on going

(Md. Saiful Islam Mia)


B.Sc. Engg. (Civil), BUET, FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG

Work Program for 02 January 2011

S.l. No. Description


1 2 3 4 5 6 Open Drain Segment 1A Dismantling work Interlocking Block Mix Design and Sampling Dredging work

Work Program of 02 January, 2011


Shuttering work for wall at Ch 0+535 to 0+566=31m Sand filling work. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 Dredging work

Achievement of 01 January, 2011


Shuttering work for wall at Ch 0+535 to 0+566 in progress Sand filling work in progress CC/RCC Dismantling work at Segment 3 & 4 in progress Regular Production of Block on going Compressive strength test for C30 Dredging work on going

(Md. Saiful Islam Mia)


B.Sc. Engg. (Civil), BUET, FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG

Work Program for 03 January, 2011

S.l. No. Description


1 2 3 4 5 6 Open Drain Segment 1A Dismantling work Interlocking Block Mix Design and Sampling Dredging work

Work Program of 03 January, 2011


Concrete pouring for wall at Ch 0+535 to 0+565=30m Sand filling work. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 Dredging work

Achievement of 02 January, 2011


Shuttering work for wall at Ch 0+535 to 0+565=30m Completed Sand filling work in progress CC/RCC Dismantling work at Segment 3 & 4 in progress Regular Production of Block on going Compressive strength test for C30 Dredging work on going

(Md. Saiful Islam Mia)


B.Sc. Engg. (Civil), BUET, FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG

Work Program for 04 January, 2011

S.l. No. Description


1 2 3 4 5 6 Open Drain Segment 1A Dismantling work Interlocking Block Mix Design and Sampling Dredging work

Work Program of 04 January, 2011


Shuttering work for wall at Ch 0+625 to 0+645=20m Sand filling work,Dry density test for sub-grade CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 Dredging work

Achievement of 03 January, 2011


Concrete pouring for wall at Ch 0+535 to 0+565=30m Sand filling work in progress CC/RCC Dismantling work at Segment 3 & 4 in progress Regular Production of Block on going Compressive strength test for C30 Dredging work on going

(Md. Saiful Islam Mia)


B.Sc. Engg. (Civil), BUET, FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG

Work Program for 05 January, 2011

S.l. No. Description


1 2 3 4 5 6 Open Drain Segment 1A Dismantling work Interlocking Block Mix Design and Sampling Dredging work

Work Program of 05 January, 2011


Shuttering work for wall at Ch 0+625 to 0+645=20m Sand filling work, Dry density test for sub-grade CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 Dredging work

Achievement of 04 January, 2011


Shuttering work for wall at Ch 0+625 to 0+645=20m in progress Sand filling work in progress,Dry density test CC/RCC Dismantling work at Segment 3 & 4 in progress Regular Production of Block on going Compressive strength test for C30 Dredging work on progress.

(Md. Saiful Islam Mia)


B.Sc. Engg. (Civil), BUET, FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG

Work Program for 06 January, 2011

S.l. No. Description


1 2 3 4 5 6 Open Drain Segment 1A Dismantling work Interlocking Block Mix Design and Sampling Dredging work

Work Program of 06 January, 2011


Shuttering work for wall at Ch 0+625 to 0+645=20m Sand filling work, Dry density test for sub-grade CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 Dredging work

Achievement of 05 January, 2011


Shuttering work for wall at Ch 0+625 to 0+645=20m in progress Sand filling work in progress, Dry density test CC/RCC Dismantling work at Segment 3 & 4 in progress Regular Production of Block on going Compressive strength test for C30 Dredging work on progress.

(Md. Saiful Islam Mia)


B.Sc. Engg. (Civil), BUET, FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG

Work Program for 07 January, 2011

S.l. No. Description


1 2 3 4 5 6 Open Drain Segment 1A Dismantling work Interlocking Block Lab test Dredging work

Work Program of 07 January, 2011


Concrete pouring for wall at Ch 0+625 to 0+645=20m B/S Sand filling work, CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test. Dredging work

Achievement of 06 January, 2011


Shuttering work for wall at Ch 0+625 to 0+645=20m Completed B/S Sand filling work in progress, CC/RCC Dismantling work at Segment 3 & 4 in progress Regular Production of Block on going Compressive strength testof ILB. Dredging work on progress.

(Asim kumer halder) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 08 January, 2011

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 08 January, 2011


1.Concrete pouring for wall 1st lift at Ch 0+625 to 0+645 = 20m 1.PVD Driving. 2.Sand filling work

Achievement of 07 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+535 to 0+565 = 30m in progress. 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 5 6 7

Segment 3 (Part) Dismantling work Interlocking Block Lab test Dredging work

1.Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work CC/RCC Dismantling work at Segment 3 & 4 in progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block Dredging work on going

( Asim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 09 January, 2011

S.l. No. Description


1 2 Open Drain Segment 2A

Work Program of 09 January, 2011

Achievement of 08 January, 2011

1.Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m in 1.Concrete pouring for wall 1st lift at Ch 0+625 to 0+645 = 20m B/S progress. 1.PVD Driving. 2.Sand filling work 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 5 6 7

Segment 3 (Part) Dismantling work Interlocking Block Lab test Dredging work

1.Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work CC/RCC Dismantling work at Segment 3 & 4 in progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block, FDT. Dredging work on going

( Asim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 10 January, 2011

S.l. No. Description


1 2 3 4 5 6 7 8 9 Open Drain Segment 1A Segment 1A & 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Coarse sand

Work Program of 10 January, 2011


Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m PVD Driving. Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work Coarse sand laying on Segment 1A & 2A.

Achievement of 09 January, 2011


Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m on progress. PVD Driving on progress. Sand filling work in progress Top soil Removing on progress CC/RCC Dismantling work at Segment 3 & 4 on progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block, FDT. Dredging work on going

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 11 January, 2011

S.l. No. Description


1 2 3 4 5 6 7 8 9 Open Drain Segment 1A Segment 1A & 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Coarse sand

Work Program of 11 January, 2011


Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m 300mm Sand Blanked, FDT and PVD driving. Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work Coarse sand laying on Segment 1A & 2A.

Achievement of 10 January, 2011


Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m on progress.

Sand filling work on progress Top soil Removing on progress CC/RCC Dismantling work at Segment 3 & 4 on progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand dumping on Segment 1A & 2A.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 12 January, 2011

S.l. No. Description


1 2 3 4 5 6 7 8 9 Open Drain Segment 1A Segment 1A & 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Coarse sand

Work Program of 12 January, 2011


Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work Coarse sand laying on Segment 1A & 2A.

Achievement of 11 January, 2011


Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m on progress. 300mm Sand Blanked, FDT and PVD driving. Sand filling work on progress Top soil Removing on progress CC/RCC Dismantling work at Segment 3 & 4 on progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand dumping on Segment 1A & 2A.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 13 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 13 January, 2011


1. Concrete pouring for wall 2nd lift at Ch 0+605 to 0+645 = 40m 2. Rod febrication for Open drain bracing

Achievement of 12 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m completed 2. Rod febrication for Open drain bracing 300mm Sand Blanked. Sand filling work on progress Top soil Removing on progress CC/RCC Dismantling work at Segment 3 & 4 on progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand dumping on Segment 1A & 2A.

2 3 4 5 6 7 8 9

Segment 1A Segment 1A & 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Coarse sand

PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work Coarse sand laying on Segment 1A & 2A.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 14 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 14 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m 2. Rod febrication for Open drain bracing

Achievement of 13 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m on progress 2. Rod febrication for Open drain bracing on progress PVD driving Sand filling work on progress Top soil Removing on progress CC/RCC Dismantling work at Segment 3 & 4 on progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand dumping on Segment 1A & 2A.

2 3 4 5 6 7 8 9

Segment 1A Segment 1A & 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Coarse sand

PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work Coarse sand laying on Segment 1A & 2A.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 15 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 15 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m 2. Rod febrication for Open drain bracing

Achievement of 14 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m on progress 2. Rod febrication for Open drain bracing on progress PVD driving Sand filling work on progress Top soil Removing on progress CC/RCC Dismantling work at Segment 3 & 4 on progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand dumping on Segment 1A & 2A.

2 3 4 5 6 7 8 9

Segment 1A Segment 1A & 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Coarse sand

PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work Coarse sand laying on Segment 1A & 2A.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 16 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 16 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m 2. Rod febrication for Open drain bracing 3. Lay out fixing for Open drain South side.

Achievement of 15 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+605 to 0+645 = 40m on progress 2. Rod febrication for Open drain bracing on progress

2 3 4 5 6 7 8 9

Segment 1A Segment 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Coarse sand

PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work Coarse sand laying on Segment 1A & 2A.

PVD driving on progress. Sand filling work on progress Top soil Removing on progress CC/RCC Dismantling work at Segment 3 & 4 on progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block, FDT. Dredging work on going Coarse sand dumping on Segment 1A & 2A.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 24 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 24 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m 2. Concrete pouring for Open drain bracing 3. 150mm Sand fill and soling for Open drain South side.

Achievement of 23 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m on progress

3. Earth excavation for Open drain South side on progress. Reinforcement febrication for RCC Pipe PVD driving on progress. Sand filling work on progress Top soil Removing on progress CC/RCC Dismantling work at Segment 3 & 4 on progress Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block, FDT. Dredging work on going

2 3 4 5 6 7 8 9 10

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Segment 2A Segment 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Coarse sand PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test, FDT Dredging work Coarse sand laying on Segment 1A & 2A.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 28 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 28 January, 2011


1. Concrete pouring for wall 2nd lift at Ch 0+535 to 0+570 = 35m 2. Concrete pouring for Pre-cast Pile. 3. Earth excavation for Open drain South side.

Achievement of 27 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m completed 2. Reinforcement binding for Pre-cast Pile. 3. Earth excavation for Open drain South side in progress. Concrete pouring for RCC Pipe 05 nos PVD driving in progress. Sand filling work in progress Top soil Removing in progress

2 3 4 5 6 7 8 9 10

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Segment 2A Segment 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Segment 1A PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test. Dredging work Coarse sand laying (200 mm Sand Blanket)

Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand laying (200 mm Sand Blanket) in progress.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 28 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 28 January, 2011


1. Concrete pouring for wall 2nd lift at Ch 0+535 to 0+570 = 35m 2. Concrete pouring for Pre-cast Pile. 3. Earth excavation for Open drain South side.

Achievement of 27 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m completed 2. Reinforcement binding for Pre-cast Pile. 3. Earth excavation for Open drain South side in progress. Concrete pouring for RCC Pipe 05 nos PVD driving in progress. Sand filling work in progress Top soil Removing in progress

2 3 4 5 6 7 8 9 10

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Segment 2A Segment 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Segment 1A PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test. Dredging work Coarse sand laying (200 mm Sand Blanket)

Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand laying (200 mm Sand Blanket) in progress.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 28 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 28 January, 2011


1. Concrete pouring for wall 2nd lift at Ch 0+535 to 0+570 = 35m 2. Concrete pouring for Pre-cast Pile. 3. Earth excavation for Open drain South side.

Achievement of 27 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m completed 2. Reinforcement binding for Pre-cast Pile. 3. Earth excavation for Open drain South side in progress. Concrete pouring for RCC Pipe 05 nos PVD driving in progress. Sand filling work in progress Top soil Removing in progress

2 3 4 5 6 7 8 9 10

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Segment 2A Segment 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Segment 1A PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test. Dredging work Coarse sand laying (200 mm Sand Blanket)

Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand laying (200 mm Sand Blanket) in progress.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 28 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 28 January, 2011


1. Concrete pouring for wall 2nd lift at Ch 0+535 to 0+570 = 35m 2. Concrete pouring for Pre-cast Pile. 3. Earth excavation for Open drain South side.

Achievement of 27 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m completed 2. Reinforcement binding for Pre-cast Pile. 3. Earth excavation for Open drain South side in progress. Concrete pouring for RCC Pipe 05 nos PVD driving in progress. Sand filling work in progress Top soil Removing in progress

2 3 4 5 6 7 8 9 10

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Segment 2A Segment 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Segment 1A PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test. Dredging work Coarse sand laying (200 mm Sand Blanket)

Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand laying (200 mm Sand Blanket) in progress.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 28 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 28 January, 2011


1. Concrete pouring for wall 2nd lift at Ch 0+535 to 0+570 = 35m 2. Concrete pouring for Pre-cast Pile. 3. Earth excavation for Open drain South side.

Achievement of 27 January, 2011


1. Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m completed 2. Reinforcement binding for Pre-cast Pile. 3. Earth excavation for Open drain South side in progress. Concrete pouring for RCC Pipe 05 nos PVD driving in progress. Sand filling work in progress Top soil Removing in progress

2 3 4 5 6 7 8 9 10

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Segment 2A Segment 2A Segment 1 Dismantling work Interlocking Block Lab test Dredging work Segment 1A PVD driving Sand filling work Top soil Removed for Sub grade Preparation. CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Interlocking Block. Compressive Strength test. Dredging work Coarse sand laying (200 mm Sand Blanket)

Regular Production of Interlocking Block on going. Compressive Strength test of Interlocking Block. Dredging work on going Coarse sand laying (200 mm Sand Blanket) in progress.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 29 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 29 January, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m Earth excavation for Open drain South side.

Achievement of 28 January, 2011


Concrete pouring for wall 2nd lift at Ch 0+535 to 0+570 = 35m Earth excavation for Open drain South side in progress. PVD driving in progress. Coarse sand laying for 200 mm sand Blanket in progress. Sand filling work in progress Top soil Removing in progress Reinforcement febrication for Pre-cast Pile.

Segment 2A

PVD driving Coarse sand laying for 200 mm sand Blanket Sand filling work

3 4 5 6 7 8 9

Segment 1 Pre-cast Pile

Top soil Removed for Sub grade Preparation. Reinforcement febrication & Shuttering work for Pre-cast Pile.

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Interlocking Block Dismantling work Lab test Dredging work Regular Production of Interlocking Block. CC/RCC Dismantling work at Segment 3 & 4 Compressive Strength test. Dredging work Compressive Strength test of Interlocking Block. Dredging work on going Regular Production of Interlocking Block on going.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 30 January, 2011

S.l. No. Description


1 Open Drain

Work Program of 30 January, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m Brick Flat Soling for Open drain South side.

Achievement of 29 January, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m in progress. Earth excavation for Open drain South side. PVD driving in progress.

Segment 2A

PVD driving Coarse sand laying for 200 mm sand Blanket Sand filling work

Sand filling work in progress Top soil Removing in progress Reinforcement febrication & Shuttering work for Pre-cast Pile.

3 4 5 6 7 8 9

Segment 1 Pre-cast Pile

Top soil Removed for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Interlocking Block Dismantling work Lab test Dredging work Regular Production of Interlocking Block. CC/RCC Dismantling work at Segment 3 & 4 Compressive Strength test. Dredging work Compressive Strength test of Interlocking Block. Dredging work on going Regular Production of Interlocking Block on going.

( Ashim kumer halder ) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,23th May, 2011

S.l. No. Description


1 2 3 Segment 1A Segment 2A (part) Segment 1 (part)

Work Program of 23th May, 2011


Sand dumping and sand bagging of preloading 300mm Sand Blanket filling PVD Driving Clearing & Grubbing.

Achievement of 22th May, 2011


Sand dumping and sand bagging of preloading in progress 300mm Sand Blanket filling in progress 300mm sand Blanket filling and FDD test executed. Clearing & Grubbing in progress. Clearing & Grubbing in progress. Rebar fabrication in progress Concrete pouring in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

4 5 6 7 8

Segment 4 (part) Culvert (rail) RCC pipe Interlocking Block Dismantling work

Clearing & Grubbing. Rebar fabrication Concrete pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,25th May, 2011

S.l. No. Description


1 2 3 Segment 1A Segment 2A (part) Segment 1 (part)

Work Program of 25th May, 2011


Sand dumping and sand bagging of preloading 300mm Sand Blanket filling PVD Driving Clearing & Grubbing.

Achievement of 24th May, 2011


Sand dumping and sand bagging of preloading in progress 300mm Sand Blanket filling in progress

Remarks

Clearing & Grubbing in progress. Clearing & Grubbing in progress.

4 5

Segment 4 (part) Culvert (road)

Clearing & Grubbing. Rebar fabrication Earth Excavation

Culvert (rail)

Rebar fabrication Earth Excavation

Rebar fabrication in progress

7 8 9

RCC pipe Interlocking Block Dismantling work

Concrete pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

Concrete pouring in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

(Engr.Nityananda Nandi) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 01 February, 2011

S.l. No. Description


1 Open Drain

Work Program of 01 February, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m Cement Concrete for Open drain South side.

Achievement of 31 January, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m in progress. Cement Concrete for Open drain South side.

Segment 2A

PVD driving Coarse sand laying for 200 mm sand Blanket Sand filling work Sand filling work in progress Top soil Removing in progress Welding & Shuttering work for Pre-cast Pile in progress. Concrete pouring for RCC Pipe in progress. Regular Production of Interlocking Block on going.

3 4 5 6 7 8 9

Segment 1 Pre-cast Pile

Top soil Removed for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Interlocking Block Dismantling work Lab test Dredging work Regular Production of Interlocking Block. CC/RCC Dismantling work at Segment 3 & 4 Compressive Strength test. Dredging work

Compressive Strength test of Interlocking Block.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 01 February, 2011

S.l. No. Description


1 Open Drain

Work Program of 01 February, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m Cement Concrete for Open drain South side.

Achievement of 31 January, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m in progress. Cement Concrete for Open drain South side.

Segment 2A

PVD driving Coarse sand laying for 200 mm sand Blanket Sand filling work Sand filling work in progress Top soil Removing in progress Welding & Shuttering work for Pre-cast Pile in progress. Concrete pouring for RCC Pipe in progress. Regular Production of Interlocking Block on going.

3 4 5 6 7 8 9

Segment 1 Pre-cast Pile

Top soil Removed for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Interlocking Block Dismantling work Lab test Dredging work Regular Production of Interlocking Block. CC/RCC Dismantling work at Segment 3 & 4 Compressive Strength test. Dredging work

Compressive Strength test of Interlocking Block.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 02 February, 2011

S.l. No. Description


1 Open Drain

Work Program of 02 February, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m Cement Concrete for Open drain South side.

Achievement of 01 February, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+570 = 35m in progress. Cement Concrete for Open drain South side.

Segment 2A

PVD driving Coarse sand laying for 200 mm sand Blanket Sand filling work Coarse sand laying for 200 mm sand Blanket Sand filling work in progress Top soil Removing in progress Welding & Shuttering work for Pre-cast Pile in progress. Concrete pouring for RCC Pipe in progress. Regular Production of Interlocking Block on progress.

3 4 5 6 7 8 9

Segment 1 Pre-cast Pile

Top soil Removal for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Interlocking Block Dismantling work Lab Test/Field Test Dredge work Regular Production of Interlocking Block. CC/RCC Dismantling work at Segment 3 & 4 Compressive Strength test. Dredge work

Compressive Strength test of Interlocking Block.

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 03 February, 2011

S.l. No. Description


1 Open Drain

Work Program of 03 February, 2011


Shuttering work for wall 2nd lift at Ch 0+535 to 0+565 = 30m Rod binding for open drain Ch-1033m to 1052m = 25m

Achievement of 02 February, 2011


Shuttering work for wall at Ch 0+535 to 0+565 = 30m in progress. Rod binding for open drain Ch-1033m to 1052m = 25m in progress

Segment 2A

PVD driving Coarse sand laying for 200 mm sand Blanket Sand filling work Coarse sand laying for 200 mm sand Blanket in progress Sand filling work in progress Top soil Removing in progress Welding & Shuttering work for Pre-cast Pile in progress. Concrete pouring for RCC Pipe in progress. Regular Production of Interlocking Block on progress. CC/RCC Dismantling work at Segment 3 & 4 in progress Compressive Strength test of Interlocking Block. Dredge work on going

3 4 5 6 7 8 9

Segment 1 Pre-cast Pile

Top soil Removal for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Yard drainage ( RCC Pipe) Concrete pouring for RCC Pipe Interlocking Block Dismantling work Lab Test/Field Test Dredge work Regular Production of Interlocking Block. CC/RCC Dismantling work at Segment 3 & 4 Compressive Strength test. Dredge work

( Ashim kumer halder ) Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program of 04 February, 2011

S.l. No. Description


1 Open Drain

Work Program of 04 February, 2011


Shuttering work for wall at Ch 0+535 to 0+565 = 30m Rod binding for open drain Ch-1033m to 1052m = 25m

Achievement of 04 February, 2011


Shuttering work for wall at Ch 0+535 to 0+565 = 30m completed Rod binding for open drain Ch-1033m to 1052m = 25m in progress PVD driving Quantity=440 Point 30 truck Actually layed=14 truck Top soil Removing in progress Welding & Shuttering work for Pre-cast Pile in progress. No work Interlocking Block=4100 Nos

Remarks

2 3 4 5 6 7 8

PVD 200 mm Coarse sand lay 150 mm Local sand lay Segment 1 Pre-cast Pile

PVD driving =1000 Point 40 truck Target Quantity =30 truck Top soil Removal for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Due to Friday Driving work Performed half day Due to Friday Dredge Sand supply is not available

Yard drainage ( RCC Pipe) 15 Nos Interlocking Block Interlocking Block=5000 Nos

Sub Contractor (Md.Mubarak) is not agree to work on Friday Executed new Trial Mix brought by Shahidul Islam(Head office),needed 2 hours to perform it

9 10

Dismantling work Dredge work

CC/RCC Dismantling work at Segment 3 & 4 No Dredge work

CC/RCC Dismantling work at Segment 3 & 4 in progress No Dredge work

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program of 06 February, 2011

S.l. No. Description


1 Open Drain (Navy Side)

Work Program of 06 February, 2011


Concrete Pouring of Base (24 rm)

Achievement of 06 February, 2011


Executed On progress No work Executed No work Top soil Removal on progress Welding & Shuttering work for Pre-cast Pile in progress. 1000 mm=3 Nos, 900 mm =1 No, 800 mm=2 Nos Interlocking Block=4980 Nos

Remarks

Open Drain (Country Side) Rebar fabrication and shuttering of Bracing 2 3 4 5 6 7 8 PVD 200 mm Coarse sand lay 150 mm Local sand lay Segment 1 Pre-cast Pile PVD driving =1000 Point 30 Truck Target Quantity =30 truck Top soil Removal for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Shortness of Fuel

Dredge Sand supply is not available

Yard drainage ( RCC Pipe) 10 Nos Interlocking Block Interlocking Block=5000 Nos

Labor shortness of Sub contractor

9 10

Dismantling work Dredge work

CC/RCC Dismantling work at Segment 3 & 4 Dredge work will continue

CC/RCC Dismantling work at Segment 3 & 4 in progress No Dredge work

(Mahibul Hasan) Senior Engineer NCT Back-up Project Chittagong

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program of 08 February, 2011

S.l. No. Description


1 Open Drain (Navy Side)

Work Program of 08 February, 2011


Wall Shuttering

Achievement of 08 February, 2011


On progress On progress Executed point =500 Nos. On progress No work Top soil Removal on progress Welding & Shuttering work for Pre-cast Pile in progress. 1000 mm=3 Nos, 900 mm =1 No, 800 mm=2 Nos Interlocking Block=4350 Nos

Remarks

Open Drain (Country Side) Rebar fabrication and shuttering of Bracing 2 3 4 5 6 7 8 PVD PVD driving

200 mm Coarse sand layer Sand lay 150 mm Local sand layer Segment 1 Pre-cast Pile Sand lay Top soil Removal for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Dredge Sand supply is not available

Yard drainage ( RCC Pipe) 10 Nos Interlocking Block Interlocking Block=5000 Nos

Due to mechanical fault

9 10

Dismantling work Dredge work

CC/RCC Dismantling work at Segment 3 & 4 Dredge work will continue

CC/RCC Dismantling work at Segment 3 & 4 in progress No Dredge work

(Mahibul Hasan) Senior Engineer NCT Back-up Project Chittagong

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program of 13th February, 2011

S.l. No. Description


1 Open Drain (Navy Side)

Work Program of 13 February, 2011


Concrete Pouring of wall (1st lift)

Achievement of 13 February, 2011


Executed. On progress No work On progress No work Top soil Removal on progress Welding & Shuttering work for Pre-cast Pile in progress. 5 Nos. executed Interlocking Block=1300 Nos

Remarks

Open Drain (Country Side) Earth excavation,Soling,CC work 2 3 4 5 6 7 8 PVD PVD driving

200 mm Coarse sand layer Sand lay 150 mm Local sand layer Segment 1 Pre-cast Pile Sand lay Top soil Removal for Sub grade Preparation. Welding & Shuttering work for Pre-cast Pile.

Dredge Sand supply is not available

Yard drainage ( RCC Pipe) Concrete Pouring . Interlocking Block Interlocking Block=5000 Nos

Due to mechanical fault

9 10

Dismantling work Dredge work

CC/RCC Dismantling work at Segment 3 & 4 Dredge work will continue

CC/RCC Dismantling work at Segment 3 & 4 in progress No Dredge work

(Mahibul Hasan) Senior Engineer NCT Back-up Project Chittagong

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 28 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 28 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving. 2. Sand filling work. 3. Field Density Test for 150 mm Local Sand Layer.

Achievement of 27 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565 in progress no driving 2. Sand filling work in progress

3 4 7 8

Dismantling work Interlocking Block Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 and C40 Dredge work in progress

no work Regular Production of Block on going

Dredge work in progress.

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 13 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A (Part)

Work Program of 13 December, 2010


1. Rod binding for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 12 December, 2010


1. Concrete pouring for base at Ch 0+535 to 0+566 = 31m

2. Sand filling work in progress

3 4 5 6 7 8

Dismantling work Interlocking Block Pre-cast Piling work Survey work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring Yard Drainage Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength check for trial mix

Strength check for trial mix Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 14 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A (Part)

Work Program of 14 December, 2010


1. Rod binding for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 13 December, 2010

2. Sand filling work in progress

3 4 5 6 7 8

Dismantling work Interlocking Block Pre-cast Piling work Survey work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring Yard Drainage Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength check for trial mix

Strength check for trial mix Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 15 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A (Part)

Work Program of 15 December, 2010


1. Rod binding for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 14 December, 2010

2. Sand filling work in progress

3 4 5 6 7 8

Dismantling work Interlocking Block Pre-cast Piling work Survey work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring Yard Drainage Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength check for trial mix Concrete pouring (09) Nine number

Strength check for trial mix Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 16 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A (Part)

Work Program of 16 December, 2010


1. Rod binding for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 15 December, 2010

2. Sand filling work in progress

3 4 5 6 7 8

Dismantling work Interlocking Block Pre-cast Piling work Survey work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring Yard Drainage Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength check for trial mix Concrete pouring (06) Six number

Strength check for trial mix Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 17December 2010

S.l. No. Description


1 2 Open Drain Segment 1A (Part)

Work Program of 17 December, 2010


1. Rod binding for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 16 December, 2010

2. Sand filling work in progress

3 4 5 6 7 8

Dismantling work Interlocking Block Pre-cast Piling work Survey work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring Yard Drainage Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 18 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A (Part)

Work Program of 18 December, 2010


1. Suttering work for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 17 December, 2010

2. Sand filling work in progress

3 4 5 6 7 8

Dismantling work Interlocking Block Pre-cast Piling work Survey work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring Yard Drainage Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength check for trial mix

Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 19 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A (Part)

Work Program of 19 December, 2010


1. Suttering work for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 18 December, 2010

2. Sand filling work in progress

3 4 5 6 7 8

Dismantling work Interlocking Block Pre-cast Piling work Survey work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring Yard Drainage Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength check for trial mix Concrete pouring (05) Five number

Strength check for trial mix Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 20 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 20 December, 2010


1. Suttering work for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 19 December, 2010

2. Sand filling work in progress

3 4 5 6 7 8

Dismantling work Interlocking Block Pre-cast Piling work Survey work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring Yard Drainage Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4

Concrete pouring (06) Six number

Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 21 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 21 December, 2010


1. Suttering work for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 20 December, 2010

2. Sand filling work in progress

3 4 5 7 8

Dismantling work Interlocking Block Pre-cast Piling work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring (06) Six Nos, Per Pile lenhth=15.00m Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4

Concrete pouring (06) Six Nos, Per Pile lenhth=15.00m

Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 22 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 22 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 21 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+566 in progress 1. PVD Driving in progress. 2. Sand filling work in progress 3. Field density tests CC/RCC Dismantling work at Segment 3 & 4 in progress

3 4 5 7 8

Dismantling work Interlocking Block Pre-cast Piling work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring (06) Six Nos, Per Pile length =15.00m Compressive Strength test for C30 and C40 Dredging work

Concrete pouring (06) Six Nos, Per Pile length =15.00m

Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 23 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 23 December, 2010


1. Concrete pouring for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 22 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 5 7 8

Dismantling work Interlocking Block Pre-cast Piling work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring (06) Six Nos, Per Pile length =15.00m Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring (04) Four Nos, Per Pile length =15.00m

Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 24 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 24 December, 2010


1. Concrete pouring for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work in progress 3. Area ready for Field density tests

Achievement of 23 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 5 7 8

Dismantling work Interlocking Block Pre-cast Piling work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring (06) Six Nos, Per Pile length =15.00m Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength Testing for the Block of Trial Production,Trial Mix

Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 25 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 25 December, 2010


1. Concrete pouring for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work. 3. Area ready for Field density tests

Achievement of 24 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 5 7 8

Dismantling work Interlocking Block Pre-cast Piling work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring (03) Three Nos, Per Pile length =15.00m Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Strength Testing for the Block of Trial Production,Trial Mix Concrete pouring (08) Eight Nos, Per Pile length =15.00m

Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 26 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 26 December, 2010


1. Concrete pouring for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving. 2. Sand filling work. 3. Area ready for Field density tests

Achievement of 25 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 5 7 8

Dismantling work Interlocking Block Pre-cast Piling work Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Curing and Strength Testing for the Block of Trial Production,Trial Mix

CC/RCC Dismantling work at Segment 3 & 4

Concrete pouring (03) Three Nos, Per Pile length =15.00m Compressive Strength test for C30 and C40 Dredging work Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 27 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 27 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving. 2. Sand filling work. 3. Area ready for Field density tests

Achievement of 26 December, 2010


1. Concrete pouring for wall at Ch 0+535 to 0+566 = 31m 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 7 8

Dismantling work Interlocking Block Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block will be start Compressive Strength test for C30 and C40 Dredging work

CC/RCC Dismantling work at Segment 3 & 4

Dredging work on going

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 28 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 28 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving. 2. Sand filling work. 3. Field Density Test for 150 mm Local Sand Layer.

Achievement of 27 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565 in progress no driving 2. Sand filling work in progress

3 4 7 8

Dismantling work Interlocking Block Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 and C40 Dredge work in progress

no work Regular Production of Block on going

Dredge work in progress.

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 29 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 29 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving. 2. Sand filling work. 3. Field Density Test for 150 mm Local Sand Layer.

Achievement of 28 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565 in progress no driving 2. Sand filling work in progress

3 4 7 8

Dismantling work Interlocking Block Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 and C40 Dredge work in progress

no work Regular Production of Block on going

Dredge work in progress.

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 30 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 30 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565=30m 1. PVD Driving. 2. Sand filling work. 3. Field Density Test for 150 mm Local Sand Layer.

Achievement of 29 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+565 in progress 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 7 8

Dismantling work Interlocking Block Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 and C40 Dredge work in progress

CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block on going

Dredge work in progress.

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager

PROJECT BUILDERS LIMITED (PBL) NCT BACK-UP PROJECT, CHITTAGONG Work Program for 31 December 2010

S.l. No. Description


1 2 Open Drain Segment 1A

Work Program of 31 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+566=31m 1. PVD Driving. 2. Sand filling work. 3. Field Density Test for 150 mm Local Sand Layer.

Achievement of 30 December, 2010


1. Shuttering work for wall at Ch 0+535 to 0+566 in progress 1. PVD Driving in progress. 2. Sand filling work in progress

3 4 7 8

Dismantling work Interlocking Block Mix Design and Sampling Dredging work

CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block Compressive Strength test for C30 and C40 Dredge work in progress

CC/RCC Dismantling work at Segment 3 & 4 Regular Production of Block on going

Dredge work in progress.

(Md.Saiful Islam Mia)


B.Sc.Engg.(Civil), BUET,FIEB

Project Manager