Safety Information 1 1. Information About the Installation 2 2. Installing the BBU in the APM308 3. Installing the BBU in the APM30H 15 4. Installing the BBU in the APM30 (+24 V)17 5. Installing the BBU in the 19-Inch Cabinet 19 6. Installing the BBU on the Wall 23 7. Installing the BBU in the PS4890 Cabinet 28 8. Installing the BBU in the OMB Cabinet 33 9. Installing the BBU in the TMC 38 10. Installing the BBU in the TMC11H40 11. Checking the Power-On Status of the BBU 41 12. Reference 42
Safety Information
Following All Safety Precautions
Before any operation, read the instructions and precautions in this document carefully to minimize the possibility of accidents. The Danger, Caution, and Note items in the documents do not cover all the safety precautions that must be followed. They only provide the generic safety precautions for operations. When operating Huawei products and equipment, you must comply with safety precautions and special safety instructions related to corresponding equipment provided by Huawei. The safety precautions in the document are related to only Huawei products. Huawei is not liable for any consequence that results from the violation of universal regulations for safety operations and safety codes on design, production, and equipment use.
Symbols
This symbol indicates that casualty or serious accident may occur if you ignore the safety instruction. This symbol indicates that serious or major injury may occur if you ignore the safety instruction. This symbol indicates that the operation may be easier if you pay attention to the safety instruction.
Safety of Personnel
The high voltage power supply provides power for running the system. Direct contact with the high voltage power supply or contact through damp objects may result in fatal danger. Non-standard and improper high voltage operations may result in fire and electric shock. In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or on a steel tower and mast. Ground the device before powering on the device. Otherwise, the personnel and device are in danger. Power off the device before performing operations on the power supply equipment. High power radio-frequency signals are harmful to human body. Before installing or maintaining an antenna on a steel tower or mast with a large number of transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter antennas are shut down. When handling optical fibers, do not stand close to, or look into the optical fiber outlet with unaided eyes. Protect yourself when drilling holes. Flying dust may hurt your eyes or you may inhale the dust. Power off the batteries before connecting the cables to the batteries. Otherwise, casualties may occur. When working at a height, be cautious about falling objects.
Device Safety
Check the electrical connection of the device before operation and ensure that the device is reliably grounded. The static electricity generated by the human body may damage the electrostatic sensitive components on the circuit board, such as the large-scale integrated circuit (LIC). Wear an ESD wrist strap or ESD gloves when performing the operation. When working on batteries, take measures to prevent short circuits in the batteries and electrolyte spill/loss. The electrolyte may erode metal and boards, or even cause rust of the equipment or short circuits in the boards. The BTS3900A must be powered on within one week after installation.
Copyright Huawei Technologies Co., Ltd. 2009. All rights reserved.
Installation Scenarios
2.APM30H
1.APM30
BBU
BBU
3.TEC
4.TEC11H
BBU
BBU
Installation Scenarios
6.PS4890
5.APM30 (+24V)
BBU BBU
7. In OMB cabinet
BBU
BBU
BBU
Alarm Equipment
Monitoring Equipment
Power System
BBU Power Cable E1 surge protection transfer cable E1 Cable Monitoring Cable
Board
Mandatory /Optional
Mandatory
Full Configuration
2
Installation Slot
S6 and S7
Remarks
WMPT
Preferentially configured in Slot 7. Preferentially configured in Slot 3, then Slot 2, at last Slot 0,1. Preferentially configured in PWR2. Only in the FAN slot. Preferentially configured in Slot 4, 5. Preferentially configured in Slot 4. Preferentially configured in Slot 4. Preferentially configured in PWR1.
WBBP
Mandatory
S0 to S3
UPEU
Mandatory
UBFA UTRP
Mandatory Optional
1 5
UELP
Optional
S0 and S4
UFLP
Optional
S0 and S4
UEIU
Optional
PWR1
Procedure
NO.
Cable From...
Installation Position To ... PWR on BBU INSIDE on UELP Transmission equipment MON1on BBU CPRI on RRU
1 2 3 4 5
LOAD3 on PDU E1/T1 on WMPT OUTSIDE on UELP TX/RX on APMI CPRI on BBU
Installing BBU
PDU
BBU
2 Slide the BBU case into the cabinet. 3 Check the DIP switches (see appendix).
Installing cables
1. Install power cable.
Connect the OT terminal of the power cable to the LOAD3 terminal of the PDU, and then fix the 3V3 connector of the power cable to the PWR port on the BBU. LOAD3 NEG(-) RNT(+)
PWR
Connect one end of the optical cable to CPRI0, CPRI1, or CPRI2 on the WBBP. Then, connect the other end to the RRU. Insert the optical module into CPRI0, CPRI1, or CPRI2. Turn outwards the puller on the optical module.
Remove the dustproof caps from the optical connectors. Insert the optical connector at one end of the CPRI optical cable into the optical module. lead the CPRI optical cable out of the cabinet along the left side of the cabinet. Wrap the fiber tail with the winding pipe till the first cable tie. The TX port on the BBU is connected to the RX port on the RRU. The RX port on the BBU is connected to the TX port on the RRU.
Optical cable connector Winding pipe
10
Cabling the E1 cable. Fix the DB26 connector of the E1 cable to the OUTSIDE port on the UELP. Strip the jacket off the E1 cable near the grounding point at the lower right corner of the cabinet to expose the shielding layer (25mm)
OUTSIDE
INSIDE
E1/T1
E1 transfer cable
Thread the E1 cable through the grounding clip. Then, tighten the screw on the grounding clip to make the shielding layer of the E1 cable in full contact with the grounding clip. Finally, connect the PGND cable on the grounding clip to the grounding bolt of the APM30.
11
Connect one end of the FE transfer cable to the FE0 port near the INSIDE label on the UFLP and the other end to the FE0 port on the WMPT.
Connect one end of the FE cable to the FE0 port near the OUTSIDE label on the UFLP. Then, lead the other end out of the cabinet along the right side of the cabinet. FE transfer cable FE cable Strip the jacket off the FE cable near the grounding point at the lower right corner of the cabinet to expose the shielding layer (25mm)
Thread the FE cable through the grounding clip. Then, tighten the screw on the grounding clip to make the shielding layer of the FE cable in full contact with the grounding clip. Finally, connect the PGND cable on the grounding clip to the grounding bolt of the APM30. Shielding layer of the FE cable
12
Fix the RJ45 connector at one end of the cable to the MON1 port on the UPEU. MON1
Monitoring signal cable between the APMI and the BBU
RJ45
8. Install the external alarm cable.
Connect one end of the alarm cable to the EXT-ALM port on the UPEU, and the other end to the associated alarm device. The port on the external alarm device is added depending on field requirements.
When the MON0 port on the BBU is available, fix the RJ45 connector of the EMUA monitoring signal cable to the MON0 port on the UPEU, and the DB9 connector to the corresponding port on the EMUA.
MON0
RS485
13
RS485
EMUA monitoring signal cable Pin on the RJ45 Connector X1.1 X1.2 X1.4 X1.5 Pin on the DB9 Male Connector X2.3 X2.7 X2.2 X2.6 White Orange Blue White Twisted pair Twisted pair TX+ TXRX+ RXColor Type Port on the APMI
14
The procedure for installing the BBU case in the APM30H is the same as that in the APM30. For details, see pages 814. The following figure shows the cable connections of the BBU. Page 16 shows how to install the monitoring signal cable between the HEUA and the BBU in the APM30H.
No.
Cable
Installation Position One end is connected to... The other end is connected to... PWR port on the BBU INSIDE port on the UELP External transmission device MON1 port on the BBU
1 2 3 4
BBU power cable E1 transfer cable E1 cable Monitoring signal cable CPRI optical cable
LOAD3 terminal of the PDU E1/T1 port on the WMPT OUTSIDE port on the UELP COM IN port on the HEUA
15
Installing the Monitoring Signal Cable between the HEUA and the BBU
16
The procedure for installing the BBU in the APM30 (+24 V) is the same as that in the APM30. For details, see pages 814. The following figure shows the cable connections of the BBU. Page 18 shows how to install the monitoring signal cable of the cabinet.
No.
Cable
Installation Position One end is connected to... The other end is connected to... PWR port on the BBU INSIDE port on the UELP External transmission device MON1 port on the BBU
1 2 3 4
BBU power cable E1 surge protection transfer cable E1 cable Monitoring signal cable CPRI optical cable
LOAD3 terminal of the PDU E1/T1 port on the WMPT OUTSIDE port on the UELP COM IN port on the HEUA
17
Pin assignment of the monitoring signal cable of the cabinet Pin on the RJ45 Connector X1.1 X1.2 X1.3 X1.6 X1.5 X1.4 X1.7 X1.8 Pin on the RJ45 Connector X2.1 X2.2 X2.3 X2.6 X2.5 X2.4 X2.7 X2.8 18 Wire Color Wire Type
Twisted pair
Twisted pair
Twisted pair
Twisted pair
No.
Cable From...
BBU power cable E1 cable FE cable (optional) Monitoring signal cable CPRI optical cable
2 3
19
Space Requirements
1. 25 mm on the left of the BBU for ventilation 2. 25 mm on the right of the BBU for ventilation 3. 70 mm in front of the BBU for cabling 4. 800mm for maintenance
Slide the BBU case into the cabinet. Then, tighten the four M6 screws.
20
PGND cable
2 Install the power cable.
PWR
EXT-ALM0
MON1
21
E1/T1
Insert the optical module into the CPRI0, CPRI1, or CPRI2 port. Turn outwards the puller on the optical module.
Optical module Puller Remove the dustproof caps from the optical connectors. Insert the optical connector at one end of the CPRI optical cable into the optical module. Lead the CPRI optical cable out of the cabinet along the left side of the cabinet.
22
RRU power cable CPRI optical cable BBU power cable DCDU-03C PGND cable
TO RRU
23
Space Requirements
DCDU-03C BBU
Mounting ear on the BBU case Mounting ear for wall installation
24
Wall
BBU
25
26
27
No.
Cable From...
1 2 3 4
LOAD6 terminal on the DCDU External transmission device External transmission device RS232/RS422 port on the PMU
BBU alarm cable (optional) Monitoring signal cable between the PMU and the BBU CPRI optical cable
28
Slide the BBU case into the PS4890 cabinet. Then, tighten the four M6 screws.
29
LOAD 6
PWR
30
Install the BBU alarm cable (optional). Install the monitoring signal cable between the PMU and the BBU.
RS232/RS422
EXT ALM1
MON0
31
Insert the optical module into the CPRI0, CPRI1, or CPRI2 port. Turn outwards the puller on the optical module.
E1/T1
Remove the dustproof caps from the optical connectors. Insert the optical connector at one end of the CPRI optical cable into the optical module. lead the CPRI optical cable out of the cabinet along the left side of the cabinet.
32
No.
Cable
Installation Position From... To... Grounding bar of the OMB cabinet DC input terminal of the DCDU PWR port on the BBU
PGND cable
LOAD6 output terminal on the DCDU E1/T1 port on the WMPT OUTSIDE port on the UELP CPRI port on the BBU
4 5 6
INSIDE port on the UELP External transmission device CPRI port on the RRU
33
34
3 Install the CPRI optical cable. 1. Insert the optical module into the CPRI0, CPRI1, or CPRI2 port. 2. Turn outwards the puller on the optical module.
35
E1/T1 INSIDE
36
37
No.
Cable From...
1 2 3 4
BBU power cable E1 transfer cable E1 cable Monitoring signal cable CPRI optical cable
LOAD6 terminal of the PDU E1/T1 port on the WMPT OUTSIDE port on the UELP Wiring terminal of cabinet monitoring CPRI port on the BBU
38
Slide the BBU case into the TMC cabinet. Then, tighten the four M6 screws.
Installing the TMC alarm cable: a. Fix the RJ45 connector at one end of the alarm cable to the EXT_ALM1 port on the BBU. b. Connect the two bare terminals X1.4 (blue) and X1.5 (white) to the alarm wiring terminals on the door status sensor. c. Connect the two bare terminals X1.1 (white) and X1.2 (orange) to the OUT+ and OUT- alarm wiring terminals on the APMI. d. Connect the two bare terminals X1.3 (white) and X1.6 (green) to the alarm wiring terminals on the DCDU.
39
No.
Cable
CPRI optical cable E1 transfer cable E1 cable BBU power cable Monitoring signal cable
2 3 4
E1/T1 port on the WMPT OUTSIDE port on the UELP LOAD6 terminal on the PDU
INSIDE port on the UELP External transmission device PWR port on the BBU
40
41
12 Reference
a
Cable PGND cable
Cable List
Connector OT terminal OT terminal Connects to Grounding bolt of the BBU3900 Protection grounding bar
3V3 connector Bare wire. The connector needs to be made on site according to the field requirements. (The following figure shows the BBU power cable by taking OT terminals as an example.)
DLC connector
Connect the fiber tails labeled 1A and 1B to the CPRI_W port on the RRU Connect the fiber tails labeled 2A and 2B to one of the CPRI0 to CPRI3 ports on the WBBP
DLC connector
E1 cable
E1/T1 port on the GTMU or WMPT, or OUTSIDE port on the UELP Peer device
42
12 Reference
c a
Cable List
Connector DB26 male connector DB25 male connector Connects to PWR port on the UPEU E1/T1 port on the GTMU or WMPT Cable E1 transfer cable
FE cable
FE transfer cable
FE0 port on the WMPT FE0 port near the INSIDE label on the UFLP
43
12 Reference
b
Engineering Specifications of the BBU
Item Dimensions Weight Input voltage Specification 86 mm (height) x 442 mm (width) x 310 mm (length) Typical configuration: 7 kg; full configuration: 11 kg 48 V DC or +24 V DC
Check the DIP switch settings of the WMPT, GTMU, UTRP, and UELP.
Wear an ESD wrist strap or a pair of ESD gloves when performing operations related to the boards, as shown in the figure below.
ESD strap
ESD gloves
44
12 Reference
c
Setting the DIP Switches
Set the DIP switches of the BBU. Settings of the DIP switches on the UELP
45
12 Reference
ed
Pin Assignment of the BBU Signal Cables
75-ohm E1 cable Pin on the DB26 Male Connector X1.1 X1.2 X1.3 X1.4 X1.5 X1.6 X1.7 X1.8 X1.19 X1.20 X1.21 X1.22 X1.23 X1.24 X1.25 X1.26 Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring Tip Ring 8 6 4 2 7 5 3 1 RX1+ RX1RX2+ RX2RX3+ RX3RX4+ RX4TX1+ TX1TX2+ TX2TX3+ TX3TX4+ TX4Wire Type Coaxial SN. Label
46
12 Reference
d
Pin Assignment of the BBU Signal Cables
120-ohm E1 cable Pin on the DB26 Male Connector X1.1 X1.2 X1.3 X1.4 X1.5 X1.6 X1.7 X1.8 X1.19 X1.20 X1.21 X1.22 X1.23 X1.24 X1.25 X1.26 Blue Twisted pair White Orange White Green Twisted pair White Brown Twisted pair White Grey Twisted pair White Blue Twisted pair Red Orange Twisted pair Red Green Twisted pair Red TX4TX3TX4+ TX2TX3+ TX1TX2+ RX4TX1+ RX3RX4+ Twisted pair RX1RX2+ RX2RX3+ RX1+ Wire Color Wire Type Label
47
12 Reference
d
Pin Assignment of the BBU Signal Cables
FE cable Pin on the RJ45 Connector X1.2 X1.1 X1.6 X1.3 X1.4 X1.5 X1.8 X1.7 Wire Color Wire Type Pin on the RJ45 Connector X2.2 X2.1 Twisted pair X2.6 X2.3 Twisted pair X2.4 X2.5 Twisted pair X2.8 X2.7
Twisted pair
Monitoring signal cable between the APMI and the BBU Pin on the RJ45 Connector Wire Color Pins on the X2, X3, X4, and X5 X2 Twisted pair X1.2 Orange X3 Twisted pair X1.4 Blue X4 Twisted pair X1.5 White X5 Twisted pair 48 RXRX+ TXWire Type Port on the APMI
X1.1
White
TX+
12 Reference
d
Pin Assignment of the BBU Signal Cables
EMUA monitoring signal cable Pin on the RJ45 Connector Pin on the DB9 Male Connector X2.3 Wire Color Wire Type Port on the APMI
X1.1
White
Twisted pair
TX+
X1.2
X2.7
Orange
Twisted pair
TX-
X1.4
X2.2
Blue
Twisted pair
RX+
X1.5
X2.6
White
Twisted pair
RX-
Alarm cable Pin on the RJ45 Connector X1.1 X1.2 X1.3 X1.6 X1.5 X1.4 X1.7 X1.8 Pin on the RJ45 Connector X2.1 X2.2 X2.3 X2.6 X2.5 X2.4 X2.7 X2.8 White/orange Orange White/green Green White/blue Blue White/brown Brown Twisted pair Twisted pair Twisted pair Twisted pair Wire Color Wire Type
49