No Activity/Description Present Status NTPL input Remark
Start Finish START-UP POWER 1 Start-Up power 11 KV Available from 10.02.14 10.02.14 Closing of cable trench between STto A row 2 Start-Up power 3.3 KV Charging of UAT1A & 1B on 22.02.14 & Soaking till 23.02.14(NTPL) 24.02.14 As committed it may be ensure sustained availability from 24.02.14 3 220 V DC Charged & in service Available 4 24 V DC Charged & in service Available 5 UPS supply Charged & in service Available CCR 6 CCR readiness `- For LU Temp enclosure & AC is provided & is ready - Flooring, Glass Partition work U/P (28/02/14) False Ceiling work awaiting for Fire Fighting system above ceiling (NTPL) (After NTPL Clearance 3-4 Weeks required to complete False Ceiling & Commission AC) WATER SYSTEM (SG) 7 Boiler Filling Pump Available 8 DMCW (SG)-A Motor trial 25.02.14 3.3KV Coupling and Pump trial 27.02.14 DM water Initial Filling 200KL +Make-Up 5KL/day PH 7+ 9 DMCW (SG)-B Motor trial 26.02.14 3.3KV Coupling and Pump trial 28.02.14 10 Temp ACW pump running Ready Available Cooling water initial filling 300KL +make- up by NTPL @the rate of 50KL/day IA & SA COMPRESSORS 14 IA-1 01.03.14 3.3KV 15 IA-2 03.03.14 3.3KV 16 IA-3 04.03.14 3.3KV 17 SA-1 02.03.14 3.3KV 18 SA-2 3.3KV DETERGENTFLUSHING 19 Detergent Flushing Pre Boiler System(BFD) 25.02.14 03.03.14 DM Water 4500 KL 20 Normalisation of Boiler Feed Piping (Discharge & Suction) 05.03.14 25.03.14 21 Detergent Flushing Condensate System 05.03.14 12.03.14 DM Water 2500 KL 22 Detergent Flushing Drip System 17.03.14 24.03.14 DM Water 2500 KL FANS & APH - A Pass 23 FD-A Lube oil Flshing Completed Completed Motor trial Completed 11KV Coupling Completed Fan trial 02.03.14 DM water Initial Filling 200KL +Make-Up 5KL/day 24 ID-A Lube oil Flshing Completed Completed VFD transformer charging Completed 11KV VFD Commng Channel 1 &2 Ch 1 Completed Ch in progress 11.02.14 22.02.14 Motor trial 01.03.14 Coupling 02.03.14 06.03.14 NTPL to ensure Un-interrupted supply Commissiong program 2x500MW NTPL - Tuticorin TPP - Unit 1 - Light-Up & EDTA Program S.No Activity/Description Present Status NTPL input Remark Start Finish Commissiong program Fan trial 07.03.14 ` -Chimney Clearance Scanner Air fan 25 AC fan Already run with temp supply 24.02.14 DC fan Already run with regular DC supply Completed 26 APH-A Motor trial Completed APH trial Completed 21.02.14 Soot blower 05.03.14 Air Blowing Deludge system Piping completed Water connection to deludge pipe Alternatively Water wash supply to be made ready FOPH LDO 27 LDO & Unloading System `- Erection Completed. Ready to receive LDO - Motors are run with temp. supply - UPS & Battery Charging - Commissioned - PLC Charging(Software loaded, Commissioning Linked to Availability of LDO) ` Fire Fighting System - LDO Supply (Advance communication is required to call vendor repersentative for PLC Commissioning) Availabilty of LDO must be ensured on or before 04.03.14 & advance communication on availability may be given by 02.03.14 Pump running with permanent supply ON ASSEMPTION LDO WILL BE AVAILABLE ON TANK ON 05.03.14 04.03.14 06.03.14 Availability of LDO @tank 04.02.14 `- Coupling to be done. 28 LDO forwarding system Pump running with permanent supply 05.03.14 07.03.14 Availability of LDO @tank 05.02.14 29 LDO system around boiler 08.03.14 Hose pipes completion Few days before LU 30 Checking of control system and instruments around boiler 08.03.14 31 Scanner and ignitor checking 08.03.14 32 SADC commng-AB elevation 08.03.14 33 Furnace bottom sealing Nearing completion 28.02.14 Water Filling BHEL ISG 34 CC pumps trial Pumps are assembled. Cooling water line (31.01.14) 02.03.14 06.03.14 Vendor to be informed in advance 35 BOILER LIGHTUP 09.03.14 `-DM Water initial fill 400KL -Availability of LDO `- ESP A&B will be ready 36 GD test 12.03.14 16.03.14 bet BLU and EDTA 37 EDTA cleaning 17.03.14 23.03.14 - DM water initial Filling +3000KL to complete the process - LDO - Dead Stock +25KL/Day Delivery of Chemicals requires 40 days advance Notice.