S.

No Activity/Description Present Status NTPL input Remark


Start Finish
START-UP POWER
1 Start-Up power 11 KV Available from 10.02.14 10.02.14 Closing of cable trench between STto A
row
2 Start-Up power 3.3 KV Charging of UAT1A & 1B on
22.02.14 & Soaking till
23.02.14(NTPL)
24.02.14 As committed it may be ensure
sustained availability from 24.02.14
3 220 V DC Charged & in service Available
4 24 V DC Charged & in service Available
5 UPS supply Charged & in service Available
CCR
6 CCR readiness `- For LU Temp enclosure & AC
is provided & is ready
- Flooring, Glass Partition work
U/P (28/02/14)
False Ceiling work awaiting for Fire
Fighting system above ceiling (NTPL)
(After NTPL Clearance 3-4 Weeks
required to complete False Ceiling &
Commission AC)
WATER SYSTEM (SG)
7 Boiler Filling Pump Available
8 DMCW (SG)-A
Motor trial 25.02.14 3.3KV
Coupling and Pump trial 27.02.14 DM water Initial Filling 200KL +Make-Up
5KL/day
PH 7+
9 DMCW (SG)-B
Motor trial 26.02.14 3.3KV
Coupling and Pump trial 28.02.14
10 Temp ACW pump running Ready Available Cooling water initial filling 300KL +make-
up by NTPL @the rate of 50KL/day
IA & SA COMPRESSORS
14 IA-1 01.03.14 3.3KV
15 IA-2 03.03.14 3.3KV
16 IA-3 04.03.14 3.3KV
17 SA-1 02.03.14 3.3KV
18 SA-2 3.3KV
DETERGENTFLUSHING
19 Detergent Flushing Pre Boiler
System(BFD)
25.02.14 03.03.14 DM Water 4500 KL
20 Normalisation of Boiler Feed Piping
(Discharge & Suction)
05.03.14 25.03.14
21 Detergent Flushing Condensate
System
05.03.14 12.03.14 DM Water 2500 KL
22 Detergent Flushing Drip System 17.03.14 24.03.14 DM Water 2500 KL
FANS & APH - A Pass
23 FD-A Lube oil Flshing Completed Completed
Motor trial Completed 11KV
Coupling Completed
Fan trial 02.03.14 DM water Initial Filling 200KL +Make-Up
5KL/day
24 ID-A Lube oil Flshing Completed Completed
VFD transformer charging Completed 11KV
VFD Commng Channel 1 &2 Ch 1 Completed Ch in progress 11.02.14 22.02.14
Motor trial 01.03.14
Coupling 02.03.14 06.03.14
NTPL to ensure Un-interrupted supply
Commissiong program
2x500MW NTPL - Tuticorin TPP - Unit 1 - Light-Up & EDTA Program
S.No Activity/Description Present Status NTPL input Remark
Start Finish
Commissiong program
Fan trial 07.03.14 ` -Chimney Clearance
Scanner Air fan
25 AC fan Already run with temp supply 24.02.14
DC fan Already run with regular DC
supply
Completed
26 APH-A
Motor trial Completed
APH trial Completed 21.02.14
Soot blower 05.03.14 Air Blowing
Deludge system Piping completed Water connection to deludge pipe Alternatively Water wash supply to
be made ready
FOPH LDO
27 LDO & Unloading System `- Erection Completed. Ready
to receive LDO
- Motors are run with temp.
supply
- UPS & Battery Charging -
Commissioned
- PLC Charging(Software
loaded, Commissioning Linked
to Availability of LDO)
` Fire Fighting System
- LDO Supply (Advance communication
is required to call vendor repersentative
for PLC Commissioning)
Availabilty of LDO must be ensured
on or before 04.03.14 & advance
communication on availability may
be given by 02.03.14
Pump running with permanent supply ON ASSEMPTION LDO WILL BE
AVAILABLE ON TANK ON
05.03.14
04.03.14 06.03.14 Availability of LDO @tank 04.02.14 `- Coupling to be done.
28 LDO forwarding system
Pump running with permanent supply 05.03.14 07.03.14 Availability of LDO @tank 05.02.14
29 LDO system around boiler 08.03.14 Hose pipes completion Few days
before LU
30 Checking of control system and
instruments around boiler
08.03.14
31 Scanner and ignitor checking 08.03.14
32 SADC commng-AB elevation 08.03.14
33 Furnace bottom sealing Nearing completion 28.02.14 Water Filling BHEL ISG
34 CC pumps trial Pumps are assembled. Cooling
water line (31.01.14)
02.03.14 06.03.14 Vendor to be informed in advance
35
BOILER LIGHTUP
09.03.14 `-DM Water initial fill 400KL
-Availability of LDO
`- ESP A&B will be ready
36 GD test 12.03.14 16.03.14 bet BLU and EDTA
37
EDTA cleaning
17.03.14 23.03.14 - DM water initial Filling +3000KL to
complete the process
- LDO - Dead Stock +25KL/Day
Delivery of Chemicals requires 40
days advance Notice.