You are on page 1of 32

JAMBATAN KEDUA SDN. BHD.

(824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 1 & Package 2
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View of Main Navigation Span from P24 to P27
P24
P26
P25
Package 1
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View from P25 to P26
P26
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View from P26 to P27
P26
P27
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
No. Balance of Works Percent Completed Target Completion Date
1.
Maintenance Gondola Rail
Installation
70% 03 Oct 2013
2. Form Traveller Dismanting 63% 31 Aug 2013
3. Scaffolding Dismanting 0% 20 Sept 2013
4.
Premix & Parapet Finishing
(Pylon Area)
0% 30 Sept 2013
5. Rubber Fender Installation 54% 03 Oct 2013
6. Steel Fender Diagonal Stripes 0% 18 Sept 2013
7. Stainless Steel Railing Installation 0% 03 Oct 2013
8. Road Premix 100% 28 Aug 2013
9. Expansion Joint Installation 0% 20 Sept 2013
10.
Road Marking & Signages
Installation
0% 26 Sept 2013
11. Decorative Lighting 70% 03 Oct 2013
12. Navigation Aids 5% 12 Sept 2013
13. Street Lighting 44% 30 Aug 2013
14. Ligthning Protection System 65% 12 Sept 2013
15. Final Testing & Commissioning 0% 03 Oct 2013
16. Load Test 0% 25 Sept 2013
Package 1 - Balance of Works
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 2
View from P0 to P24
Main Navigation Span
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View from P27 towards Batu Kawan
Package 2
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View towards Batu Kawan
Line marking
Package 2
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View from Batu Kawan towards Main Navigation Span
Main Navigation Span
Package 2
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
No. Balance of Works Unit Total
Quantity
Actual Balance
Quantity
Percentage
(%)
Target Completion
Date
1.
Removal Steel Barrier
( 8 nos. At MCO & * nos. At
motorcycle lane / NJB )
nos. 16 0 16 0.00 25 Sept 2013
2. Pavement spans 578 314 264 54.66 21 Sept 2013
3. Expansion Joints nos. 94 1 93 38.27 26 Sept 2013
4. Road Markings spans 578 0 578 0.00 26 Sept 2013
5. Traffic Signages nos. 91 0 91 0.00 30 Sept 2013
6.
Installation of Street Lighting
Poles
nos. 578 564 14 95.42 26 Aug 2013
7.
Power Supply Cables to Main
Navigation Span
meters - - - 96.13 15 Sept 2013 (TBA)
8. Substation - - - -
Material / equipment
for Main Substation
completed.
Steel Grating (nos.) nos. 8092 1280 6812 15.82 29 Sept 2013
9. Testing & Commissioning - - - - TBA
Package 2 - Balance of Works
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 3A, 3B, 3C & 3D
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 3A Balance of Works
Overall view of Package 3A
Ramp 2
Ramp 1
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 3A Balance of Works
Overall view of Ramp 1 and Ramp 2
Ramp 2 Completion: 15 Oct 2013
Ramp 1 Completion: 26 Sep 2013
P3
P4
P5
P6
P7
P2
P1
PA
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View from Marine Bridge towards the ramps
Ramp 3
Ramp 1
Ramp 2
Ramp 4
Package 3A Balance of Works
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View from Pier 0 towards Batu Maung Interchange
Pier 0
Package 3A Balance of Works
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 3A Balance of Works
Balance of Critical Works Status
1. Ramp 1 Pier 2-1-A To complete by 26 Sep 2013
2. Ramp 2 Pier 7-6-5-4-3 To complete by 10 Oct 2013
3. Expansion Joint Repairs, Regulating Layers To complete by 12 Oct 2013
4. Pavement ACWC Works
To start on 17 Sept 2013
To complete by 14 Oct 2013
5. Bayan Lepas Expressway
Critical Areas: Ch 545 Ch 675 , Surcharge to be removed To start removal on 15 Sept 2013
6. OVERALL COMPLETION On 15 Oct 2013
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Balance of Works Status
1. Sg Nipah To complete by 30 Sept 2013
Y-Beam, Deck Slab, Diaphragm Beam, Cast In-Situ Parapet c/w Railing
2. M1 To complete by 30 Sept 2013
Parapet (86%), Pavement , Expansion Joint, Road Marking, Drainage Outlet,
Brass Plaque
3. M2 To complete by 30 Sept 2013
Parapet (99%), Pavement, Expansion Joint, Road Marking, Drainage Outlet,
Gantry, Brass Plaque
4. Ramp 1 To complete by 10 Oct 2013
Box Girder (85%), Parapet Installation (60%), Expansion Joint, Road Marking,
Drainage Outlet, Brass Plaque, M&E Works
5. Ramp 2 To complete by 15 Oct 2013
Box Girder (55%), Parapet Installation, T-Beam Launching (13%), Diaphragm Beam (13%)
Deck Slab (13%), Pavement, Expansion Joint, Road Marking, Drainage Outlet,
Brass Plaque, M&E Works
6. Ramp 3 To complete by 30 Sept 2013
Parapet Installation (97%), Pavement , Expansion Joint, Road Marking, Drainage Outlet,
Brass Plaque, M&E Works
7. Ramp 4 To complete by 30 Sept 2013
Box Girder (85%), Parapet Installation (97%), Pavement, Expansion Joint, Road Marking,
Drainage Outlet, Brass Plaque, M&E Works
Package 3A Balance of Works
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Balance of Works Status
1. RE Wall Ramp 1 To complete by 30 Sept 2013
RE Wall Installation, Coping Wall, Catch Pit Drain, Bankseat, Transition Slab,
Parapet, Pavement, Road Marking, M&E Works
2. RE Wall Ramp 2 To complete by 30 Sept 2013
Catch Pit Drain, Parapet, Pavement, Road Marking, M&E Works
3. RE Wall Ramp 3 To complete by 30 Sept 2013
Parapet, Pavement, Road Marking, M&E Works
4. RE Wall Ramp 4 To complete by 30 Sept 2013
Coping Wall, Parapet, Pavement, Road Marking, M&E Works
5. RC Wall A To complete by 30 Sept 2013
Parapet and Handrail
6. RE Wall B To complete by 30 Sept 2013
Base & Wall, Parapet and Handrail
7. RE Wall C To complete by 30 Sept 2013
Base & Wall, Parapet and Handrail
8. RE Wall D To complete by 30 Sept 2013
Base & Wall, Parapet and Handrail
9. Existing Wall To complete by 30 Sept 2013
Drilling, Wall, Parapet and Handrail
Package 3A Balance of Work
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Balance of Works - Continued Status
1. TUN DR LIM CHONG EU EXPRESSWAY To complete by 15 Oct 2013
Roadside Drain
Culvert
Shoulder Drain, Median Drain, Cascade Drain
Earthwork
Pavement
Road Marking
Guardrail
Kerb
Road Signages
Gantry
TCSS
2. ACCESS ROAD 1,2,3 To complete by 15 Oct 2013
Package 3A Balance of Work
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View towards Land Bridge
Package 3B
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View of CH 17000 to CH17700
PDC Bridge
Package 3B
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
View of CH 18100 towards Land Bridge View of CH 19600 onwards
PE 3 towards Bridge over Sg. Tengah (RHS)
Deck Slab of Pier 6 to Pier 11 at Bridge
over Sg. Tengah
Package 3B
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Concrete pavement of PLUS Toll Plaza
Deck Slab of Bridge over Canal
Arch Culvert
Ramp 4
Package 3B
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
No. Balance of Works Unit Total Quantity Actual Balance
Quantity
Percentage
(%)
Target
Completion Date
1. Street Lighting nos. 236 78 158
33.0 30 Sept 2013
- Street Lighting Double Arm nos. 96 52 44
- Street Lighting Single Arm
12m
nos. 87 26 61
- Street Lighting Single Arm
6m
nos. 53 0 53
2. High Mast nos. 29 26 3 89.6 15 Sept 2013
3. NJB (km) km 6.7 5.8 0.9 87.0 15 Sept 2013
4. Arch Culvert Transition Piling 50 % completed 15 Sept 2013
5. DBM (tonne) tonne 54651 37935 16716 76.6
30 Sept 2013 6. ACBC (tonne) tonne 41075 11890 29185 58.4
7. ACWC (tonne) tonne 30535 486 30049 50.4
8. Bridge Over Sg. Tengah spans 11 8.5 2.5 77.0 30 Sept 2013
Bridge Over PDC Completed until deck slab 20 Sept 2013
11. Bridge Over Canal Completed until deck slab 20 Sept 2013
12. Road Markings & Signages - - - 0.00 08 Oct 2013
13. Expansion Joints nos. - - - 0.00 19 Sept 2013
14. Guardrails km - - - 0.00 30 Sept 2013
Package 3B - Balance of Works
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Pier 1
Abut A
Pier 3
Pier 2
Package 3C
Overall view of Bridge Over NSE
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
M001 LHS Pavement in progress MSL 04 Pavement in progress
M001 RHS Pavement in progress MSL 3 Overall View
Package 3C
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 3C Balance of Works
Balance of Works Status
1. Bridge Over NSE To complete by 2 Oct 2013
Downstand Plinth, Deck Slab, Parapet
2. Drainage Works To complete by 13 Sept 2013
Berm/Toe Drain, Shoulder Drain, Median Drain
3. Roadworks (Mainline)
ACBC To complete by 13 Sep 2013
ACWC by others To complete by 27 Sep 2013
ACWC bridge over PLUS To complete by 10 Oct 2013
4. Roadworks (Merging to PLUS)
Sub grade To complete by 20 Sep 2013
Roadbase To complete by 27 Sep 2013
Wet Mix To complete by 1 Oct 2013
DBM To complete by 2 Oct 2013
ACBC To complete by 4 Oct 2013
Regulating Works at PLUS Expressway To complete by 7 Oct 2013
5. Road Furniture To complete by 15 Oct 2013
Roadline Marking, Signboards & Signages, Guardrail, NJB, Frontage Road
6. M&E Works To complete by 13 Sept 2013
Relocation of PLUS services, Ducting Works,
7. Street Lighting & Highmast To complete by 15 Oct 2013
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
PB2X TNB Substation completed
Package 3D PB2X
Supervision Building Roof Slab and
Staircase in progress
Admin Building 1
st
floor slab and column
in progress
Surau Glass and tiling works in progress
Comp: 15/9/2013
Comp: 15/10/2013
Comp: 15/10/2013 Energize: 15/9/2013
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Info Center Plastering work in progress
Package 3D PB2X
Contractors Office Window frame
installation in progress
Maintenance Building Roof truss in
progress
Public Toilet Water tank installation in
progress
Comp: 30/9/2013 Comp: 30/9/2013
Comp: 20/9/2013 Comp: 20/9/2013
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 3D PB2X
Refuse Chamber Plastering work in
progress
Excavation of piles for toll canopy in
progress
Guard House Roof covering in progress
Comp: 20/9/2013 Comp: 25/9/2013
Comp: 15/10/2013
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 3D PLUS
Surau Installation of UCO wall in progress
Supervision Building 1
st
floor column and
roof beam work in progress
TNB Substation Installation of equipment
completed
Refuse Chamber Plastering work in
progress
Comp: 15/10/2013 Energize: 22/9/2013
Comp: 30/9/2013 Comp: 10/10/2013
JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Package 3D PLUS
Northern Pilecap in progress
Guard House Roof installation completed Public Toilet roof installation completed
Comp: 15/10/2013
Comp: 15/10/2013
Comp: 30/10/2013
Southern Buttress Holding down bolt
installation in progress