You are on page 1of 4

Community Market Place _Standard BoQ TEMPLATE

Item
N0.

Description of works

Unit

Spec.

QTY

Unit
Cost

Total
Cost

Contribution
CommunityCDRD

1.10 Substructure work


Allow for clearing the site from any debris,
1.11 trees,roots etc, filling hollows and levelling.

LS

0.00

M3

0.00

M3

0.00

M3

0.00

M3

0.00

M3

0.00

M3

0.00

Excavation of found trench 0.4m x


1,12 0.5m depth.

1.13

1.14

1.15
1.16

Mass concrete in 50 mm thick blinding


layer (1:4:8 mix ) under the foundation
wall.
Rubble stone foundation wall in
cement & sand mortar 1:4 ( 0.8 m x
0.4m wide) min. 15cm above ground
level.
R.C (1:2:4 mix) in ground beam
(0.4m x0.15m ), with 4N0. Y12 re-bars
& R6 links @ 300 mm c/c.
200 mm thick stone hardcore filling
well compacted and leveled.

75mm thick murram or other approved


backfill material, well compacted and
1.17 leveled.
Total for Item 1.10

0.00

1.20 Bill of materials for Item 1.10


1.21
1.22
1.23
1.24
1.25

(Substructure works)
Ordinary portland Cement
Bags
River sand or other approved sand
tonne
Stone ballast (20mm size)
tonne
Foundation stone
tonne
Hardcore stone
tonne

1.26 Murram or approved backfill material


1.27
1.28
1.29
1.30
1.31
1.32
1.33
1.34
1.35

Re-bar Y12
Re-bar R 6
White timber 12x1
White timber 2x1
Wire nails 3
Binding wire
Water
Total materials
Transport cost
Labour Costs
Total transport & labour
Total for I tem 1.20

0.00
0.00
0.00
0.00
0.00

tonne

0.00

Pcs

0.00

Pcs

0.00

Pcs

0.00

Pcs

0.00

Kg

0.00

Kg

0.00

Truck

0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
%

0.00

0.00
0.00
0.00

2.10 Superstructure works including conc. floor slab


Mass concrete (1:3:6 mix ) in conc. floor
2.11 slab 50 mm thick.
40cm thick rubble stone walling in cement
2.12 & sand mortar 1;4 mix

0.00
0.00
0.00
0.00
0.00

M3

0.00

M3

0.00

0.00
0.00

20cm thick cement block walling laid in


cement & sand mortar 1:4 mix ( rate to
2.13 include making of blocks)

R.C (1:2:4 mix) in two level conc. ring


beams (40 cm x15 cm ), each with
4N0. Y12 re-bars & R6 links @ 250
2.14 mm c/c.
R.C (1:2:4 mix) in 20 cm x 20 cm
column shaft, each with 4N0. Y12 re2.15 bars & R6 links @ 200 mm c/c.
R.C (1:2:4 mix) in display tables (1m x
2.16 0.7m x 0.05m x 12 N0. ).

M2

0.00

M3

0.00

M3

0.00

M3

0.00

Total for Item 2.10

0.00

2.20 Bill of materials for Item 2.10 ( Superstructure works )


2.21 Ordinary portland Cement

bags

0.00

2.22 River sand or other approved sand

tonne

0.00

2.23 Stone ballast (20mm size)


2.24 Re-bar Y12

tonne

0.00

Pcs

0.00

Pcs

0.00

2.25 Re-bar R 6
Well cured Sand /cement hollow blocks
2.26 (size 40x20x20 cm)
2.27 Walling stones

Pcs

0.00

tonne

0.00

2.28 Water
2.29 White timber 12x1

Truck

0.00

Pcs

0.00

2.3 White timber 2x3


2.31 White timber 2x1

Pcs

0.00

Pcs

0.00

2.32 Wire nails 3


2.33 Binding wire

Kg

0.00

Kg

0.00

Total materials
2.34 Transport cost
2.35 Labour Costs
Total transport & labour
Total for Item 2.20

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
%

0.00

0.00

0.00
0.00

0.00
0.00

3.10 Roof work


Roof with timber rafters covered with N0.
28 GCI sheets with two coats anti- rust
3.11 paint
Supply and fix 200mm x 20mm fascia
3.12 board, including two coats enamel paint
Supply and erect 75 mm diam black steel
pipes (or class A pipes), to include two
coats gloss paint, for verandah roof
3.13 support.

M2

0.00

LM

0.00

Pcs

0.00

Total for Item 3.10


3.20
3.21
3.22
3.23
3.24
3.25

Bill of materials for Item 3.10 ( Roof work )


White timber 3 x 2
Pcs
White timber 2 x 2
Pcs
White timber 6 x1
Pcs
White timber 12x1
Pcs
GCI Sheets ( N0.28 )
Pcs

0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

3.26 Roofing nails


3.27 Wire nails (assorted)
3.28 75 mm diam. Class A steel pipes
Total materials
3.29 Transport cost
3.30 Labour Costs
Total transport & labour
Total for Item 3.20
4.10 Plastering and other finishing
External & internal plastering ,12 mm
thick, cement / sand mix 1:5, with
4.11 wood float finish.
Apply two coats white wash and
distemper paint to the plastered wall
4.12 surface.
40 mm thick 1;3 cement/sand floor
4.13 screed.

Kg
Kg
Pcs

0.00
0.00
0.00

0.00
0.00
0.00

0.00
%

0.00

0.00
0.00

0.00
0.00
0.00

0.00

M2

0.00

M2

0.00

M2

0.00

Total for Item 4.10

0.00

4.20 Bill of materials for Item 4.10 ( Plastering & other finishes )
4.21 Ordinary portland Cement
bags
4.22 River sand or other approved sand
tonne
4.24 Water
Trucks

0.00

0.00
0.00

0.00

0.00

0.00

4.25 Lime
4.26 Emulsion paint

bags

0.00

0.00

Litres

0.00

0.00

4.27 Gloss paint

Litres

0.00

0.00

Total materials
4.29 Transport cost
4.30 Labour Costs

0.00
%

0.00

0.00

0.00

0.00

0.00

0.00

Total transport & Labour


Total for Item 4.20

0.00

5.10 Gates, Doors & Windows


Supply and fix wooden panel doors (2.0m
x 0.9m) single leaf, complete with hinges &
locks and to include two coats of gloss
paint.

Pcs

Metal

0.00

0.00

Supply and fix metal gate ( 3m x 2.5m)


complete with hinges and locks and to
5.12 include 2 coats of gloss paint.

Pcs

0.00

0.00

Supply and fix wooden panel windows


(1.0m x 1.2m ) complete with wooden
frame, hinges & locks and to include two
5.13 coats of gloss paint.

Pcs

0.00

0.00

Total for Item 5.10

0.00

6.10 Provisional Items (includes materials & labour )


6.11 Water tank / Plumbing works

LS

6.12 Standard latrine units as per BoQ


6.13 Electrical installation works

LS
LS

1
1

0.00

0.00

0.00

0.00
0.00

0.00

Total for Item 6.10

0.00

7.10 Other inputs


7.11 Land

0.00

7.12 Miscellaneus

0.00

Total for Item 7.10

0.00

Grand Total (Bill of materials, provisional items & other inputs

0.00

Grand Total

0.00

(BoQ, provisional items & other inputs)

0.00
0.00

0.00

0.00

Note: 1) Ideally the two Grand Totals should be the same, but this is difficult to achieve as long as the
estimation methods are not based on exactly the same assumptions and criteria.

2) The higher of the two totals should be considered for costing purposes.
Percentage of community contribution

#DIV/0!

You might also like