You are on page 1of 41

5844 Bridge Manual Ch 17.0-17.

9/24/01

1:28 PM

Page 1

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

TABLE OF CONTENTS
RAILROAD BRIDGES
NOTATION
17.0

INTRODUCTION

17.1

TYPICAL PRODUCTS AND DETAILS


17.1.1 Piles
17.1.2 Pile Caps and Abutments
17.1.3 Superstructures
17.1.3.1 Slab Beams and Box Beams
17.1.3.2 Other Products
17.1.3.3 Connection Details

17.2

CONSTRUCTION CONSIDERATIONS
17.2.1 Advantages
17.2.2 Standard Designs
17.2.3 Train Operations
17.2.4 Construction Methods
17.2.5 Substructures

17.3

THE AMERICAN RAILWAY ENGINEERING AND MAINTENANCE-OF-WAY


ASSOCIATION LOAD PROVISIONS
17.3.1 AREMA Manual
17.3.2 AREMA Loads
17.3.2.1 Live Load
17.3.2.2 Impact Load
17.3.2.3 Other Loads
17.3.2.4 Load Combinations

17.4

CURRENT DESIGN PRACTICE


17.4.1 New Bridges
17.4.2 Replacement Bridges
17.4.3 Simple Span Bridges
17.4.4 Skew Bridges

17.5

CASE
17.5.1
17.5.2
17.5.3
17.5.4
17.5.5
17.5.6

STUDY NO. 1TRUSS BRIDGE REPLACEMENT


Existing Bridge
New Piles
New Intermediate Piers
New Superstructure for Approach Spans
Truss Removal
New Superstructure for Truss Spans

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 2

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

TABLE OF CONTENTS
RAILROAD BRIDGES
17.6

CASE
17.6.1
17.6.2
17.6.3
17.6.4

STUDY NO. 2TIMBER TRESTLE REPLACEMENT


Existing Bridge
New Superstructure
Substructure Construction
Superstructure Construction

17.7

DESIGN EXAMPLEDOUBLE-CELL BOX BEAM, SINGLE SPAN, NONCOMPOSITE, DESIGNED IN ACCORDANCE WITH AREMA SPECIFICATIONS
17.7.1 Background
17.7.2 Introduction
17.7.2.1 Geometrics
17.7.2.2 Sign Convention
17.7.2.3 Level of Accuracy
17.7.3 Material Properties
17.7.3.1 Concrete
17.7.3.2 Pretensioning Strands
17.7.3.3 Reinforcing Bars
17.7.4 Cross-Section Properties for a Single Beam
17.7.5 Shear Forces and Bending Moments
17.7.5.1 Shear Forces and Bending Moments Due to Dead Load
17.7.5.2 Shear Forces and Bending Moments Due to Superimposed Dead Load
17.7.5.3 Shear Forces and Bending Moments Due to Live Loads
17.7.5.4 Load Combinations
17.7.6 Permissible Stresses in Concrete at Service Loads
17.7.7 Estimate Required Prestressing Force
17.7.8 Determine Prestress Losses
17.7.8.1 Prestress Losses at Service Loads
17.7.8.1.1 Elastic Shortening of Concrete
17.7.8.1.2 Creep of Concrete
17.7.8.1.3 Shrinkage of Concrete
17.7.8.1.4 Relaxation of Prestressing Steel
17.7.8.1.5 Total Losses at Service Loads
17.7.8.2 Prestress Losses at Transfer
17.7.9 Concrete Stresses
17.7.9.1 Stresses at Transfer at Midspan
17.7.9.2 Stresses at Transfer at End
17.7.9.3 Stresses at Service Load at Midspan
17.7.9.4 Stresses at Service Load at End
17.7.10 Flexural Strength
17.7.10.1 Stresses in Strands at Flexural Strength
17.7.10.2 Limits for Reinforcement
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 3

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

TABLE OF CONTENTS
RAILROAD BRIDGES
17.7.10.3 Design Moment Strength
17.7.10.4 Minimum Reinforcement
17.7.10.5 Final Strand Pattern
17.7.11 Shear Design
17.7.11.1 Required Shear Strength
17.7.11.2 Shear Strength Provided by Concrete
17.7.11.2.1 Simplified Approach
17.7.11.2.2 Calculate Vci
17.7.11.2.3 Calculate Vcw
17.7.11.2.4 Calculate Vc
17.7.11.3 Calculate Vs and Shear Reinforcement
17.7.11.3.1 Calculate Vs
17.7.11.3.2 Determine Stirrup Spacing
17.7.11.3.3 Check Vs Limit
17.7.11.3.4 Check Stirrup Spacing Limits
17.7.12 Deflections
17.7.12.1 Camber Due to Prestressing at Transfer
17.7.12.2 Deflection Due to Beam Self-Weight at Transfer
17.7.12.3 Deflection Due to Superimposed Dead Load
17.7.12.4 Long-Term Deflection
17.7.12.5 Deflection Due to Live Load
17.8

REFERENCES

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 5

CHAPTER 17

NOTATION
RAILROAD BRIDGES
A
Ac
Aps
Aps
Av
Avh
a
B
b
be
bv
bw
CF
D
DF
d
E
Ec
Eci
Es
Es
EQ
e
ec
F
fb
f c
fcds
f ci
fcr
fd
flc
fle
flr
fls
fpc
fpe

fps

= area of cross-section of precast beam


= total transformed area of composite section
= area of one pretensioning strand or post-tensioning bar
= area of strands in the tensile zone
= area of shear reinforcement
= area of web reinforcement per unit length required for horizontal shear
= compression block depth
= buoyancy
= width of compression face of member
= top flange width of precast beam
= width of cross section at the contact surface being investigated for horizontal shear
= width of web of a flanged member
= centrifugal force
= dead load
= live load distribution factor
= distance from extreme compressive fiber to centroid of the prestressing force
= earth pressure
= modulus of elasticity of concrete at 28 days
= modulus of elasticity of concrete at transfer
= modulus of elasticity of pretensioning steel
= modulus of elasticity of non-pretensioned reinforcement
= earthquake (seismic)
= eccentricity of strands at transfer length
= eccentricity of strands at midspan
= longitudinal force due to friction or shear resistance at expansion bearings
= concrete stress at the bottom fiber of the beam
= specified concrete strength at 28 days
= concrete stress at the centroid of the pretensioning steel due to all dead loads except
the dead load present at the time the pretensioning force is applied
= specified concrete strength at transfer
= stress in the concrete at the centroid of the pretensioning steel
= stress due to unfactored dead load, at extreme fiber of section where tensile stress is
caused by externally applied loads
= loss of prestress due to creep of concrete
= loss of prestress due to elastic shortening
= loss of prestress due to relaxation of pretensioning steel
= loss of prestress due to concrete shrinkage
= compressive stress in concrete (after allowance for all prestress losses) at the centroid
of cross section resisting externally applied loads
= compressive stress in concrete due to effective pretensioning forces only (after
allowance for all pretension losses) at the extreme fiber of section where tensile stress
is caused by externally applied loads
= stress in the pretensioning steel at nominal strength
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 6

CHAPTER 17

NOTATION
RAILROAD BRIDGES
fpu
fse
ft
ftc
fy
h
hc
I
I
ICE
Ic
L
L
LF
M
Mcr
MD
Md
Mg
MLL+I
Mmax
Mn
MSDL
Mu
Mx
n
OF
Peff
Pse
Psi
R
Sb
Sbc
St
Stc
Stg
SF
s
V
Vc

= ultimate tensile strength of pretensioning steel


= effective stress in pretensioning steel after losses
= concrete stress at the top fiber of the precast beam
= concrete stress at top of fiber of the slab for the composite section
= specified yield strength of non-prestressed reinforcement
= overall depth of precast beam
= total height of composite section
= moment of inertia about the centroid of the non-composite precast beam
= the percentage of the live load for impact
= ice pressure
= moment of inertia of composite section
= span length
= live load
= longitudinal force from live load
= maximum service load design moment
= moment causing flexural cracking at section due to externally applied loads
= unfactored bending moment due to total dead load
= unfactored bending moment due to composite beam dead load
= unfactored bending moment due to precast beam self-weight
= unfactored bending moment due to live load + impact
= maximum factored moment at the section due to externally applied loads
= nominal moment strength of a section
= unfactored bending moment due to superimposed dead load
= factored bending moment at the section
= bending moment at a distance x from the support
= modular ratio of elasticity between slab and beam materials
= other forces (rib shortening, shrinkage, temperature and/or settlement of supports)
= effective post-tensioning force
= effective pretension force after allowing for all losses
= total pretensioning force immediately after transfer
= relative humidity
= non-composite section modulus of the extreme bottom fiber of the precast beam
= composite section modulus for extreme bottom fiber of the precast beam
= non-composite section modulus of the extreme top fiber of the precast beam
= composite section modulus for extreme top fiber of the slab
= composite section modulus for top fiber of the precast beam
= stream flow
= spacing of the shear reinforcement in direction parallel to the longitudinal reinforcement
= service load shear force
= nominal shear strength provided by concrete

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 7

CHAPTER 17

NOTATION
RAILROAD BRIDGES
Vci
Vcw
VD
Vd
Vg
Vi
VLL+I
Vp
Vs
VSDL
Vu
Vx
vdh
W
WL
w
wc
wequ
x
yb
ybc
ybs
yt
ytc
ytg
D
f
rp
y

= nominal shear strength provided by concrete when diagonal cracking results from
combined shear and moment
= nominal shear strength provided by concrete when diagonal cracking results from
excessive principal tensile stress in web
= unfactored shear force at section due to total dead load
= unfactored shear force due to composite beam dead load
= unfactored shear force due to precast beam self-weight
= factored shear force at section due to externally applied loads occurring simultaneously
with Mmax
= unfactored shear force at section due to live load plus impact
= component of pretensioning force in the direction of the applied shear
= nominal shear strength provided by shear reinforcement
= unfactored shear force due to superimposed dead loads
= factored shear force at the section
= shear force at a distance x from the support
= horizontal shear stress
= wind load on structure
= wind load on live load
= weight per foot
= unit weight of concrete
= equivalent uniform load
= distance from the support
= distance from centroid to extreme bottom fiber of the non-composite precast beam
= distance from the centroid of the composite section to extreme bottom fiber of the
precast beam
= distance from the center of gravity of strands to the bottom fiber of the beam
= distance from centroid to extreme top fiber of the non-composite precast beam
= distance from the centroid of the composite section to the extreme top fiber of the
slab
= distance from the centroid of the composite section to extreme top fiber of the
precast beam
= deflection
= strength reduction factor
= ratio of pretensioning reinforcement
= angle of harped pretensioned reinforcement

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 9

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

Railroad Bridges

17.0
INTRODUCTION

Precast concrete is playing an increasingly important role in railroad bridge structures. The economy, durability and speed of construction make precast concrete the
material of choice for new and replacement railroad bridges. The focus of this chapter is
on the specific requirements and guidelines for railroad bridges. Typical products and
details, construction considerations, and identification of applicable AREMA
(American Railway Engineering and Maintenance-of-Way Association, formerly
AREA) provisions are also discussed. Two case studies and a railroad superstructure
design example are presented.

17.1
TYPICAL PRODUCTS
AND DETAILS

A wide variety of precast products is used for railroad bridge construction. From the
ground up, these include concrete piles, pile caps, abutments and superstructure beams.
Over the years, many railroads have developed standards for precast concrete, including
concrete mixes, member design, member detailing and quality control.

17.1.1
Piles

Several railroads use precast, prestressed concrete piles, but their use may be limited by the
capacity of track-mounted pile drivers. Concrete piles are preferred for use in marine environments. In highly corrosive locations, precast concrete pile extensions are spliced to steel
pipe piles. This permits the embedment of the steel into the anaerobic soil zone and provides a more durable prestressed concrete pile in the more corrosive environment.

17.1.2
Pile Caps and Abutments

Precast concrete pile caps are widely used throughout the country. Typically, these are
fabricated with an embedded plate running along the bottom of the cap. This allows
welding of steel piles to the bottom of the cap. Concrete pile caps are sometimes used
to support steel or timber beams, as well as concrete beams. Some railroads are now
beginning to use precast concrete caps with precast concrete piles. The caps are cast
with a socket for the pile to fit into. Grouting is used to tie the components together after installation. Bridge abutments can also be prefabricated. The bases of these
abutments are similar to the pile caps and serve the same function of supporting the
superstructure. Abutment backwalls and wingwalls can be precast in sections and
bolted or welded together in the field.

17.1.3
Superstructures

Railroads use a wide variety of superstructure elements. Spans typically range from
12 ft to over 80 ft. Since many precast concrete spans are installed to replace timber
trestles, standard span lengths for a given railroad are frequently multiples of their
standard timber stringer span lengths (typically 14 to 16 ft). For spans of 12 ft to 20
ft, precast slab beams are frequently used. For spans in the 20- to 30-ft range, precast,
prestressed concrete box beams are the most common although tee-beams and Ibeams are occasionally used. For spans over 30 ft, box beams are dominant. Spans up
to 50 ft typically use two box beams per track. Generally, these are double celled with
through-voids. Through-voids allow fabricators to use removable and reusable void
forms in casting the beams. This helps reduce costs. Spans over 50 ft generally use
four single-void box beams per track. The shift from two beams per track on shorter
spans to four on longer spans is dictated by the lifting restrictions associated with the
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 10

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.1.3 Superstructures/17.1.3.2 Other Products

heavier weight of the longer beams. Shear keys and transverse post-tensioned steel tie
rods are frequently used to tie the box beams together with diaphragms provided at
the location of the tie rods. For spans greater than 70 to 80 ft, beams with composite cast-in-place concrete decks are frequently used.
17.1.3.1
Slab Beams and Box Beams

A variety of shapes with depth and width variations are available throughout the
country. Designers should contact the manufacturers and the specific railroad to
determine the properties and dimensions of products available for a proposed project. Typical superstructure shapes and span ranges applicable to railroad bridges are
shown in Figure 17.1.3.1-1.

Figure 17.1.3.1-1
Typical Precast Concrete
Superstructure Shapes

7'-0"
Varies from
1'-2" to 1'-8"
Slab Beam
Spans 12' to 20'
3'-6"

7'-0"
Varies
from
2'-6"
to
4'-0"

Varies
from
2'-6"
to
7'-0"
Single Cell Box
Spans 20' to 80'
17.1.3.2
Other Products

Double Cell Box


Spans 20' to 50'

There are a few other precast products used for different span ranges. Brief descriptions of these products are given in Figures 17.1.3.2-1 through 17.1.3.2-4.

Figure 17.1.3.2-1
Tee Beam
(Intermediate and Long Spans)

Tee Beam
(Intermediate
Span)

Super Tee
(Long Span)

Precast Cap

Steel Piling
w/Welded Plate
Connection to
Pile Cap

The solid single tee beam is used for spans of 20 to 34 ft, and the voided super tee
for spans up to 55 ft in length. Both beams are set on a precast concrete cap that has
a welded plate connection to the piles as needed.
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 11

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.1.3.2 Other Products

Figure 17.1.3.2-2
Box Beam
(Intermediate Spans)

Optional
Curb

Closed Ended
Voided
Box Beam

Open Ended
Voided
Box Beam

Precast Cap

Steel Piling
w/Welded Plate
Connection to
Pile Cap

24" Octagonal
Prestressed Piling
w/C.I.P. Cap

Voided box beams are used on 20- to 50-ft long spans, with optional diaphragms and
curbs. Boxes may be set on precast or cast-in-place concrete caps with piling.
Figure 17.1.3.2-3
Low Profile Slab
(Short Spans)

Optional
Curb

Concrete
Keeper

Low Profile
Slabs
Steel
Keeper
Precast Cap

Steel Piling
w/Welded Plate
Connection to
Pile Cap

Precast Prestressed Cap

Timber
Piling

Short span bridges up to 24 ft in length with limited headroom require the use of low
profile slabs. These slabs may be set on precast caps that are either prestressed or
non-prestressed.

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 12

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.1.3.2 Other Products/17.1.3.3 Connection Details

Figure 17.1.3.2-4
Ballast Deck
(With Steel Beams)

Integral Walkway

Precast Ballast Deck


on Steel Beam
Steel Beams

Precast Cap

Steel Piling
w/Welded Plate
Connection to
Pile Cap

Precast, prestressed concrete deck slabs are used in a variety of lengths and widths;
with new or existing steel beams. These slabs can be cast with single and double ballast curbs and with integral walkways to further speed up construction of the bridge.
17.1.3.3
Connection Details

Figure 17.1.3.3-1
Steel Tee between Box Beams

Structural steel tees or plates are frequently used to cover the longitudinal joint in slab
beams and double-cell box beams as shown in Figure 17.1.3.3-1. Transverse posttensioned steel tie rods, as shown in Figure 17.1.3.3-2, are generally provided in
multiple single-cell box beam superstructures to help the group act as a unit.
Concrete or structural steel keepers or retainers are usually provided at the ends of
the caps to limit lateral movement, as shown in Figure 17.1.3.3-3. Designers should
contact the specific railroad to determine their standards and preferred connection
details.

Steel Tee

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 13

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.1.3.3 Connection Details /17.2.1 Advantages

Figure 17.1.3.3-2
Post-Tensioned Steel Tie Rod

Post-Tensioned
Steel Tie Rod

Diaphragm

Bearing
Plate

Figure 17.1.3.3-3
Concrete and Steel
Keeper Details

Concrete
Keeper

Steel
Keeper

Pile Cap

17.2
CONSTRUCTION
CONSIDERATIONS
17.2.1
Advantages

Precast concrete offers many advantages in the construction of railroad bridges. These
include:
Speed of constructionPrecast concrete structures can usually be constructed
faster than bridges comprised of alternative materials.
Fabrication timeIn addition to saving construction time, the lead time for
fabricating elements is shorter than for competing materials such as steel.

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 14

CHAPTER 17

RAILROAD BRIDGES
17.2.1 Advantages/17.2.5 Substructures

DurabilityCompared with many older structures that require frequent inspections and maintenance, railroad engineers find the low maintenance requirements
of precast concrete attractive. Use of concrete with low permeability and strict
quality control in the casting plant help assure durable bridge components.
QualityThe higher quality control of workmanship and materials available in
casting plants compared to cast-in-place construction is another plus. Railroads can
work with precast suppliers to ensure that members are cast to their satisfaction.
Site constraintsThe remote locations of many railroad bridges make the precast aspect of precast construction very useful. When the nearest ready-mix
plant is many miles away from the site, cast-in-place construction within a railroads time constraints is virtually impossible.
Emergency responsePrecast concrete bridge elements provide components
for rapid repair of bridges as a result of damage caused by derailments or timber trestle fires. Several railroads keep entire precast bridges stockpiled for rapid
emergency replacement. Concrete bridges are less vulnerable to damage from
fire compared to steel or timber bridges.
17.2.2
Standard Designs

Most railroads have standard precast concrete trestle bridge designs that incorporate repetition of modular precast units. These standard designs are used for replacement of
existing bridges, as well as construction of new bridges. Railroads and contractors familiar with railroad bridge construction have developed low-cost methods of trestle bridge
construction. These methods minimize the time that railroad operations must be suspended. In addition, precast concrete bridge components are often shipped by rail,
which, in many cases, is the only way to deliver components to remote locations.

17.2.3
Train Operations

For construction of bridges, railroads normally only permit train operations to be


suspended from two to eight hours at any one time depending on the day and time.
If an alternate route is available, 12 to 72 hours are the normal acceptable range.
Additional costs of rerouting include obtaining operating rights on another railroad
and using the other railroads personnel. Use of either option is dependent upon the
type and density of train traffic and the availability of alternate routes.

17.2.4
Construction Methods

The various methods used to construct railroad bridges to support existing trackage
while minimizing disruptions to train operations include the following:
rolling spans on runways
floating spans on barges
pick and set
temporary rail line change
permanent rail line change
trestle bridge construction
These methods are utilized because train operations cannot be suspended for the
amount of time that would be required to construct the new bridge piece by piece in
its permanent location.

17.2.5
Substructures

In many bridges, the existing substructure is reused and, if necessary, modified for
replacement of the superstructure. Sometimes, the bridge may require new substructure elements. In both cases, the substructure work is performed beneath the existing
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 15

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.2.5 Substructures

track and superstructure so that the track is out of service for only very limited periods while driving piles or placing temporary supports. For replacement of existing
bridges utilizing this method, ballast removal, as well as relocating the decks and
beams of the existing bridge, may be required to allow pile driving for the new bridge.
It is often necessary to reduce the speed of traffic over existing bridges during construction due to reduced load carrying capacity resulting from relocating the decks
and beams.
Precast concrete beams are usually installed using pick and set methods. This method
requires access to the bridge construction site for cranes that have adequate capacity to
lift the beams. A typical bridge replacement procedure is illustrated in Figure 17.2.5-1.
Figure 17.2.5-1
Typical Bridge Replacement
Construction Sequence

SUSPEND TRAIN OPERATIONS


INTERMITTENTLY AS REQUIRED TO
INSTALL PILES OR SHAFTS

CONSTRUCT BENT CAPS

SUSPEND TRAIN OPERATIONS

DISCONNECT TRACK AT EACH END OF


BRIDGE OR SPAN TO BE REPLACED

REMOVE EXISTING
SUPERSTRUCTURE

INSTALL NEW PRECAST CONCRETE


SUPERSTRUCTURE ON BENT CAPS

RECONNECT TRACK

SURFACE AND ALIGN TRACK

RESUME TRAIN OPERATIONS

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 16

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.3 The American Railway Engineering And Maintenance-of-Way
Association Load Provisions/17.3.2.1 Live Load

17.3
THE AMERICAN
RAILWAY ENGINEERING
AND MAINTENANCEOF-WAY ASSOCIATION
LOAD PROVISIONS

This section briefly discusses the types of loads on railroad bridges. The emphasis is
on those loads that are different from highway bridge loads covered in Chapter 7.
Provisions of the American Railway Engineering and Maintenance-of-Way
Association (AREMA) Manual for Railway Engineering are introduced relative to
design loads and load combinations. In addition, applicable portions of the manual
are referenced.

17.3.1
AREMA Manual

The AREMA Manual provides the recommended practice for railroads and others concerned with the engineering, design and construction of railroad fixed properties, allied
services and facilities. Prior to starting the design of a project, design engineers should
discuss specific loadings, forces, standards and procedures with the appropriate railroad.

17.3.2
AREMA Loads

The AREMA Manual Chapter 8, Concrete Structures and Foundations, specifically


addresses reinforced concrete and prestressed concrete structures. Article 2.2.3 covers
the design loads and forces to be considered in the design of railroad structures supporting tracks, including bridges. Briefly, design loads include:
D
L
I
CF
E
B
W
WL
LF

17.3.2.1
Live Load

= Dead Load
= Live Load
= Impact
= Centrifugal Force
= Earth Pressure
= Buoyancy
= Wind Load on Structure
= Wind Load on Live Load
= Longitudinal Force from Live Load

= Longitudinal Force due to


Friction or Shear Resistance
at Expansion Bearings
EQ = Earthquake (Seismic)
SF = Stream Flow Pressure
ICE = Ice Pressure
OF = Other Forces (Rib Shortening,
Shrinkage, Temperature and/or
Settlement of Supports)
F

Design engineers familiar with highway bridge design will recognize the loads and
forces listed above. The magnitude of the loads and forces are explained in detail in
the AREMA Manual. Loads that are different from highway bridges are described in
the following sections.

8' 5' 5' 5' 9' 5' 6' 5' 8'

52,000
52,000
52,000
52,000

80,000
80,000
80,000
80,000

40,000

52,000
52,000
52,000
52,000

80,000
80,000
80,000
80,000

Figure 17.3.2.1-1
Cooper E 80 Load

40,000

The following description of live load is based on the AREMA Manual:


(1) The recommended live load in pounds per axle and uniform trailing load for each track
is the Cooper E 80 load, which is shown in Figure 17.3.2.1-1. Table 17.3.2.1-1 provides a table for live load bending moments, shear forces and reactions for simple span
bridges. Values for span lengths not shown are generally computed by interpolation.
(2) The Engineer (the Railroads Chief Engineer) shall specify the Cooper live load
to be used, and such load shall be proportional to the recommended load, with
the same axle spacing.
(3) For bridges on curves, provisions shall be made for the increased proportion carried by
any truss, beam or stringer due to the eccentricity of the load and centrifugal force.

8,000 lb per
lin ft

8' 5' 5' 5' 9' 5' 6' 5' 5'


SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 17

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.3.2.1 Live Load

(4) For members receiving load from more than one track, the design live load on the
tracks shall be as follows:
For two tracks, full live load on two tracks
For three tracks, full live load on two tracks and one-half on the other track
For four tracks, full live load on two tracks, one-half on one track, and onequarter on the remaining track
For more than four tracks, as specified by the Engineer
The selection of the tracks for these loads shall be that which produces the most critical
design condition in the member being designed.
Table 17.3.2.1-1
Maximum Bending Moments, Shear Forces and Pier Reactions for Cooper E 80 Live Load (Based on AREMA Manual Table 1-17)
All values are for one rail (one-half track load)

Span
Length
ft

Maximum
Bending
Moment
ft-kips

Maximum
Bending
Moment at
Quarter Point
ft-kips

End

5
6
7
8
9
10
11
12
13
14
16
18
20
24
28
32
36
40
45
50
55
60
70
80
90
100

50.00
60.00
70.00
80.00
93.89
112.50
131.36
160.00
190.00
220.00
280.00
340.00
412.50
570.42
730.98
910.85
1,097.30
1,311.30
1,601.20
1,901.80
2,233.10
2,597.80
3,415.00
4,318.90
5,339.10
6,446.30

37.50
45.00
55.00
70.00
85.00
100.00
115.00
130.00
145.00
165.00
210.00
255.00
300.00
420.00
555.00
692.50
851.50
1,010.50
1,233.60
1,473.00
1,732.30
2,010.00
2,608.20
3,298.00
4,158.00
5,060.50

40.00
46.67
51.43
55.00
57.58
60.00
65.45
70.00
73.84
77.14
85.00
93.33
100.00
110.83
120.86
131.44
141.12
150.80
163.38
174.40
185.31
196.00
221.04
248.40
274.46
300.00

Maximum Shear Forces


kips
Quarter
Point
30.00
30.00
31.43
35.00
37.78
40.00
41.82
43.33
44.61
47.14
52.50
56.67
60.00
70.00
77.14
83.12
88.90
93.55
100.27
106.94
113.58
120.21
131.89
143.41
157.47
173.12

Midspan

20.00
20.00
20.00
20.00
20.00
20.00
21.82
23.33
24.61
25.71
27.50
28.89
28.70(1)
31.75
34.29
37.50
41.10
44.00
45.90
49.73
52.74
55.69
61.45
67.41
73.48
78.72

Maximum
Pier
Reaction
kips

40.00
53.33
62.86
70.00
75.76
80.00
87.28
93.33
98.46
104.29
113.74
121.33
131.10
147.92
164.58
181.94
199.06
215.90
237.25
257.52
280.67
306.42
354.08
397.70
437.15
474.24

(1) AREMA table does not include a value for Cooper E 80 live load. A value of 28.70 kips is provided for alternative live load.

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 18

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.3.2.2 Impact Load/17.3.2.4 Load Combinations

17.3.2.2
Impact Load

For reinforced concrete (precast and cast-in-place), the impact load is a percentage of
the live load based on the ratio of live load to live load plus dead load:
100L
[AREMA Eq. 2-1]
L +D
The impact load shall not exceed 60% for diesel engines and 80% for steam engines.
I=

For prestressed concrete, the impact load is a percentage of the live load based on
span length in ft:
L 60 ft,
I = 35 - L2/500
[AREMA Eq. 17-1]
60 < L 135 ft, I = 14 + 800/(L - 2)
L > 135 ft,
I = 20%
where L = span length of member in ft
17.3.2.3
Other Loads

All other loads and forces are defined similarly to highway bridges although the magnitudes are different. The design engineer should refer to the AREMA Manual for
additional information.

17.3.2.4
Load Combinations

The various combinations of loads and forces to which a structure may be subjected are
grouped in a similar manner as highway bridges. Each component of the structure or foundation upon which it rests, shall be proportioned for the group of loads that produces the
most critical design condition. The group loading combinations for service load design and
load factor design are as shown in Table 17.3.2.4-1 and Table 17.3.2.4-2, respectively, and
are reproduced from AREMA Article 2.2.4.

Table 17.3.2.4-1
Group Loading Combinations
Service Load Design

Table 17.3.2.4-2
Group Loading Combinations
Load Factor Design

Group

Item

I
II
III
IV
V
VI
VII
VIII
IX

D + L + I + CF + E + B + SF
D + E + B + SF + W
Group I + 0.5W + WL + LF + F
Group I + OF
Group II + OF
Group III + OF
D + E + B + SF + EQ
Group I + ICE
Group II + ICE

Allowable
Percentage of
Basic Unit Stress
100
125
125
125
140
140
133
140
150

Group

Item

I
IA
II
III
IV
V
VI
VII
VIII
IX

1.4 (D + 5/3(L + I) + CF + E + B + SF)


1.8 (D + L + I + CF + E + B + SF)
1.4 (D + E + B + SF + W)
1.4 (D + L + I + CF + E + B + SF + 0.5W + WL + LF + F)
1.4 (D + L + I + CF + E + B + SF + OF)
Group II + 1.4 (OF)
Group III + 1.4 (OF)
1.4 (D + E + B + SF + EQ)
1.4 (D + L + I + E + B + SF + ICE)
1.2 (D + E + B + SF + W + ICE)
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 19

CHAPTER 17

RAILROAD BRIDGES
17.4 Current Design Practice/17.4.3 Simple Span Bridges

17.4
CURRENT DESIGN
PRACTICE

As with all engineering design practices, railroad industry practice continues to


change as experience and research is incorporated into the AREMA Manual and individual railroad company standards and procedures. This section will discuss current
railroad industry practice relative to overall railroad bridge design philosophy, skew
limitations and superstructure continuity. Designers should discuss philosophies,
standards and procedures with the specific railroad as applicable to the project.

17.4.1
New Bridges

New railroad bridges are constructed to support railroad tracks over existing waterways, roadways, and other railroads. In addition, new railroad bridges are built to
replace existing bridges due to:
unsatisfactory capacity to support current or future loadings
unsafe condition resulting from deterioration and/or poor maintenance
damage as a result of an accident or natural disaster
inadequate waterway opening
highway or railroad grade separation projects
navigation, drainage and flood control projects

17.4.2
Replacement Bridges

The large majority of railroad bridge projects usually involve existing trackage.
Consequently, one of the most important considerations for the railroad bridge
designer is to design the bridge such that construction will have minimal disruption
to train operations. This affects design details, construction methods and project
costs. Much of todays rail traffic is under contract with the customer and the contract often includes a guarantee of service between origin and destination. Penalties
and possible loss of a contract can result if unreasonable delays in the agreed upon
schedule are experienced. Taking a track out of service or reducing the speed of rail
traffic for an extended period of time for bridge construction can have a detrimental
economic effect on the railroad. The project must be properly planned and coordinated with the operating and marketing departments of the railroad during the
design and construction phases.
The use of standardized precast components speeds both the design and construction
of bridges. Replacement spans can be specified by length alone, and railroad bridge
workers are familiar with the sections and construction procedures. Since the vast
majority of precast concrete bridges have all the superstructure below track level, vertical and horizontal clearance is not limited by these structures. This allows wide
cargo or double stack containers to be shipped without clearance concerns and
reduces the threat of bridge damage caused by shifted loads.

17.4.3
Simple Span Bridges

Many railroads prefer simple span bridges to continuous structures, finding them easier to install and maintain. Since they are structurally determinate, simple spans are
better able to handle problems such as support settlement and thermal effects than
some continuous bridges. Precast concrete elements are particularly suited to simplespan construction. Additional reasons many railroads prefer simply supported bridges
to continuous span bridges include the following:
If repair or replacement of superstructure elements is necessary, less interruption to train traffic is incurred with a simple span bridge than with a continuous span bridge.
Installation of simple spans can be accomplished more quickly than continuous
spans.
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 20

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.4.3 Simple Span Bridges/17.5.3 New Intermediate Piers

If a bridge experiences substructure problems such as settlement, a continuous


span bridge may require immediate and more extensive work, thereby resulting
in greater interruptions to train traffic.
Simple span bridges have a proven history of performing well.
17.4.4
Skew Bridges

It is desirable to limit the end skew of railroad bridge precast beams to less than 30
degrees for constructibility and placement of reinforcing steel in the beam. When the
bridge skew relative to the substructure exceeds 30 degrees, staggered precast elements as shown in Figure 17.4.4-1 should be considered.

Figure 17.4.4-1
Layouts for Skewed Bridges

Skew 30

Skew > 30
17.5
CASE STUDY NO. 1
TRUSS BRIDGE
REPLACEMENT
17.5.1
Existing Bridge

This case study describes a Southern Pacific railroad truss bridge replacement
(Marianos, 1991). This project illustrates the use of precast concrete elements to
replace a structure without serious interruption to rail traffic. The existing structure
consisted of a 90-ft long timber trestle approach, two 154-ft long through-truss spans
and a 30-ft long plate-girder approach span.
The truss spans were nearly 90 years old and were at the end of their useful service
lives due to joint wear. Since the truss spans required replacement, the railroad decided to replace the entire bridge with precast concrete.

17.5.2
New Piles

Using a track-mounted pile driver, steel H-piles were driven through the track on the
timber trestle. The pile bents were spaced to give 30-ft replacement span lengths in
the trestle area. After the piles were cut off at the required elevation, precast concrete
bent caps were placed and the piles welded to steel plates embedded in the bottom of
the caps.

17.5.3
New Intermediate Piers

Since the truss spans crossed a creek subject to high flood flows, it was essential to
minimize obstruction of the waterway. For this reason, new intermediate piers with
four 79-ft long precast, prestressed box beams replaced the two 154-ft long truss
spans. The 79-ft long beams were beyond the span range of the railroad standards
and required a new design.
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 21

CHAPTER 17

RAILROAD BRIDGES
17.5.3 New Intermediate Piers/17.5.5 Truss Removal

Railroad crews built intermediate piers at midspan of each truss by driving piles
through the existing truss floor systems, and the 79-ft long box beams were ordered
and fabricated.
17.5.4
New Superstructure for
Approach Spans

When the substructure was completed, superstructure replacement began. The 90-ft
long timber trestle was replaced by 30-ft long spans of precast, prestressed box beams,
as shown in Figure 17.5.4-1. Two box beams placed side by side were used for each
span. Each box beam has two through-voids and an integral ballast retaining sidewall
and walkway cast on the outside edge. A shear key between the box beams helped
ensure load distribution between the two beams. The box beams were placed using a
track-mounted crane.
A similar 30-ft long box beam span was used to replace the steel plate-girder span on
the approach opposite the timber trestle. Precast concrete bolster blocks were used on
top of the existing masonry piers to obtain the proper elevation because the new
structure was shallower than the existing one.

Figure 17.5.4-1
Precast 30-ft Approach Span
on Precast Bolster Blocks

17.5.5
Truss Removal

After the approach spans were completed, preparation began for replacing the truss
spans. An area under the truss spans was filled with ballast and leveled. Railroad track
panels were laid perpendicular to the bridge on the fill below the structure. Steel
frames mounted on rail trucks were placed on these tracks and used to support the
trusses for removal. With these preparations for truss replacement complete, a carefully orchestrated construction effort began.

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 22

CHAPTER 17

RAILROAD BRIDGES
17.5.5 Truss Removal/17.5.6 New Superstructure for Truss Spans

First, the truss ends were jacked up to lift them off the pier. The truss was then
secured to the steel frames and rolled laterally clear of the work area, as shown in
Figure 17.5.5-1. The construction crew then finished preparations on the pier top
for placing the precast, prestressed concrete box beams. This work included removing the remaining truss attachments and placing elastomeric bearing pads.
Figure 17.5.5-1
Roll-Out of Truss Span
to be Replaced

17.5.6
New Superstructure
for Truss Spans

Each 154-ft long steel truss was replaced by two spans of precast box beams. When
the pier preparation was completed, the four box beams of the first span were lifted
into position using truck cranes. While workmen epoxied the longitudinal joints and
shear keys between these beams, the box beams for the second span were being
placed. After the joints of both spans were epoxied and handrail cables strung along
the walkways, prefabricated panels of railroad track were placed on the spans. This
allowed a hopper car to be moved out on the track to dump ballast on the new spans.
After the ballast was tamped and the track reconnected, the new spans were ready for rail
traffic. Replacing a 154-ft long truss span was completed in a 12-hour track closure.
Several weeks later, the second truss span was replaced, completing the reconstruction.
The use of precast elements, as shown in Figure 17.5.6-1, allowed the speedy and
economical replacement of the structure, using the railroads own work force.

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 23

CHAPTER 17

RAILROAD BRIDGES
17.5.6 New Superstructure for Truss Spans/17.6.2 New Superstructure

Figure 17.5.6-1
Completed Structure

17.6
CASE STUDY NO. 2
TIMBER TRESTLE
REPLACEMENT
17.6.1
Existing Bridge

This case study discusses a timber trestle bridge replacement on the Union Pacific
Railroad system. Bridge 177.81 is located approximately 1.59 miles west of
Marysville, CA on Union Pacific Railroads Canyon Subdivision. The existing bridge,
shown in Figure 17.6.1-1, consisted of numerous timber trestle spans and a steel
plate-girder span over the Yuba River. The plate-girder was to remain in place and the
timber trestle portion of the bridge was to be replaced.

Figure 17.6.1-1
Existing Plate-Girder and
Timber Trestle Spans.

17.6.2
New Superstructure

Due to the volume of rail traffic and importance of on-time delivery by the Union
Pacific Railroad, minimal disruption to train operations was mandatory. Substructure
construction was to be performed without interference or downtime to the railroad.
Superstructure change-out would be performed during windows approved by the
railroad. A precast, prestressed concrete superstructure system was selected based on
economics, speed of erection and the ability to meet the construction constraints
associated with the need for minimal disruption to train operations.
SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

1:28 PM

Page 24

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.6.2 New Superstructure/17.6.3 Substructure Construction

The existing timber trestle spans varied in length with an average span of slightly less
than 15 ft. Based on a field survey of the timber bent locations, new bent locations
were selected to minimize interference with existing timber pile bents and optimize
beam spans. A span length of 44 ft was selected for the new superstructure. For this
span length, 45-in. deep double-cell, prestressed concrete box beams were determined to be the most economical structural system.
17.6.3
Substructure Construction

Based on field conditions, prevalent construction practice in the area and construction constraints governed by railroad operations, cast-in-place reinforced concrete
bents were selected for the substructure. The bents consisted of 100-ft long, 4-ft
diameter drilled shafts, 4-ft diameter cast-in-place reinforced concrete column extensions and cap beams. All structural components were designed in accordance with the
AREMA Manual and Union Pacific Railroad standards and procedures.
The sequence of construction was as follows:
The existing bridge footwalk and handrail were removed as required to facilitate
drilled shaft installation. The drilled shafts were spaced at 15-ft centers perpendicular to the track to allow installation of the drilled shafts without interference to railroad operations. Continuous train operations were maintained throughout the entire
construction of the substructure. Due to foundation conditions, steel pipe casing was
necessary for drilled shaft installation. The pipe casing was installed using a vibratory hammer. Reinforcing steel cages were set and the holes were filled with 4,000 psi
compressive strength concrete. Drilled shaft column extensions, bent cap beams and
the abutment were constructed under the existing timber superstructure. Due to the
depth of the new concrete beams, the bent and abutment construction were completed without interfering with the existing timber superstructure, as shown in
Figure 17.6.3-1.

Figure 17.6.3-1
Completed Concrete Bents
under Existing Timber Trestle

SEPT 01

5844 Bridge Manual Ch 17.0-17.6

9/24/01

PCI BRIDGE DESIGN MANUAL

1:28 PM

Page 25

CHAPTER 17

RAILROAD BRIDGES
17.6.4 Superstructure Construction

17.6.4
Superstructure
Construction

Working within railroad approved construction windows, the timber structure was
removed and precast beams were set. In a continuous, well-planned procedure, the
ballast, ties and rail were placed and train operations were resumed. The use of precast concrete allowed the Union Pacific Railroad to replace a timber trestle with a
stronger, more durable structural system with minimal disruption to railroad service.
The completed bridge is shown in Figure 17.6.4-1.

Figure 17.6.4-1
Completed Bridge Structure

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 1

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7 Design ExampleDouble-Cell Box Beam, Single Span, Non-Composite, Designed
in Accordance with AREMA Specifications/17.7.2 Introduction

17.7
DESIGN EXAMPLE
DOUBLE-CELL BOX BEAM,
SINGLE SPAN, NONCOMPOSITE, DESIGNED
IN ACCORDANCE WITH
AREMA SPECIFICATIONS
17.7.1
Background

Prestressed concrete double-cell box beams and solid slab beams are commonly used
in the railroad industry. Solid slab beams are used for spans up to 20 ft, especially
when superstructure depth has to be minimized. Prestressed concrete double-cell box
beams are used for spans up to 50 ft in length. Prestressed concrete single-cell box
beams are more economical for spans longer than 40 ft and are used for span lengths
up to 80 ft. When span lengths exceed 80 ft, prestressed concrete I-beams with a
composite deck become more feasible from a design, economic and construction
point of view. This example illustrates the design of a non-composite, prestressed
concrete, double-cell box beam.

17.7.2
Introduction

In non-composite design, the beam acts as the main structural element. Therefore,
the beam has to carry all the dead loads, superimposed dead loads and live load. The
beams are assumed to be fully prestressed under service load conditions. The dead
load consists of the self-weight of the beam including diaphragms. The superimposed
dead loads consist of ballast, ties, rails, concrete curbs and handrails, as shown in
Figures 17.7.2-1 and 17.7.2-2. The live load used for this bridge is Cooper E 80,
which is described in the AREMA Manual, Chapter 8, Part 2, Reinforced Concrete
Design, Article 2.2.3. The prestressed concrete beams are designed using the AREMA
Manual, Chapter 8, Part 17, Prestressed Concrete Design Specifications for Design of
Prestressed Concrete Members. The beams in this example are checked for both serviceability and strength requirements.

Figure 17.7.2-1
Bridge Cross-Section

C
L Track & Bridge
8'-0" Min. Clear

Timber ties

Ballast

3'-10 7/8"

8'-0" Min. Clear


Handrail post (Typ.)

Precast curb
and walkway

30" Prestressed
concrete box
beam

8" Min.
1/2" Gap
7'-0"

7'-0"

Void drain, typ.


1 ea. end, ea. cell

Steel tee (Typ.)

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 2

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.2 Introduction/ 17.7.2.2 Sign Convention

Figure 17.7.2-2
Bridge Elevation

30'-1" Face to face of backwalls

Well
compacted
granular fill
Cast-in-place
abutment CL
Abutment No.1
17.7.2.1
Geometrics

17.7.2.2
Sign Convention

30" prestressed concrete


box beam
Flow line

Cast-in-place
abutment
CL
Abutment No.2

For design, the bridge has the following dimensions:


Beam length = 30.0 ft
Beam width = 7.0 ft
Center-to-center distance between bearings = 29.0 ft
Bearing width (measured longitudinally) = 8 in.
Bearing length (measured transversely) = 6.67 ft
Depth of ballast = 15 in.
Timber ties: length = 9 ft; width = 9 in.; depth = 7 in.
Rail section = 132 RE (Bethlehem Steel Co.)
No. of tracks = one
For concrete:
Compression positive (+ve)
Tension negative (-ve)
For steel:
Compression negative (-ve)
Tension positive (+ve)
Distance from center of gravity:
Downward positive (+ve)
Upward negative (-ve)

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 3

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.2.3 Level of Precision/17.7.3.2 Pretensioning Strands

17.7.2.3
Level of Precision

Item
Concrete Stress
Steel Stress
Prestress Force
Moments
Shears
For the Beam:
Cross-Section Dimensions
Section Properties
Length
Area of Prestressing Steel
Area of Mild Reinforcement

Units
ksi
ksi
kips
ft-kips
kips
in.
in.
ft
in.2
in.2

Precision
1/1000
1/10
1/10
1/10
1/10
1/100
1
1/100
1/1000
1/100

Some calculations are carried out to a higher number of significant figures than common practice with hand calculation. Depending on available computation resources
and designer preferences, other levels of precision may be used.
17.7.3
Material Properties
17.7.3.1
Concrete

Concrete strength at transfer, f ci = 4,000 psi


Concrete strength at 28 days, f c = 7,000 psi
Concrete unit weight, wc = 150 pcf
Modulus of elasticity of prestressed concrete, Ec
Ec = wc 33 f c , psi
1.5

[AREMA Art. 2.23.4]

where
wc = unit weight of concrete, pcf
f c = specified strength of concrete, psi
Modulus of elasticity of concrete at transfer, using f ci = 4,000 psi, is:
E ci = (150) (33) 4, 000 / 1, 000 = 3, 834 ksi
1.5

Modulus of elasticity of concrete at 28 days, using f c = 7,000 psi, is:


E c = (150) (33) 7 , 000 / 1, 000 = 5, 072 ksi
1.5

17.7.3.2
Pretensioning Strands

1/2-in. diameter, seven wire, low-relaxation strands


Area of one strand, Aps = 0.153 in.2
Ultimate tensile strength, fpu = 270.0 ksi
Modulus of elasticity, Es = 28,000 ksi

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 4

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.3.3 Reinforcing Bars/
17.7.5.1 Shear Forces and Bending Moments Due to Dead Load
17.7.3.3
Reinforcing Bars

17.7.4
Cross-Section Properties
for a Single Beam

Yield strength, fy = 60,000 psi


Modulus of elasticity, Es = 29,000 ksi
For cross-sectional dimensions of a single box beam, see Figure 17.7.4-1. Note that
the depth varies from 30 in. to 31 in. to provide drainage

Figure 17.7.4-1
Box Beam Cross-Section

Relative vertical position


of prestressing strand to
mild steel

(24)#6 Bars (place as shownadjust as required to clear


prestressing strands)
7"

6"
1 1/2"
2'-0" Clr.
(Typ.)

3x3"
Fillet 1'-5 1/2"
(Typ.)
#4 Stirrups

5"

2'-8 3/4"

#4 Bars
1'-5 1/2"

8 1/2"

2'-7"

6 1/2"
2'-8 3/4"

5"

7'-0"
A = area of cross-section of precast beam = 1,452 in.2
h = average depth of the precast beam = (0.5)(31 + 30) = 30.5 in.
I = moment of inertia about the centroid of the precast beam = 171,535 in.4
yb = distance from centroid to extreme bottom fiber of the precast beam = 15.25 in.
yt = distance from centroid to extreme top fiber of the precast beam = 15.25 in.
Sb = section modulus for the extreme bottom fiber of the precast beam = 11,248 in.2
St = section modulus for the extreme top fiber of the precast beam = 11,248 in.3
NOTE: Section properties do not include precast curbs and walkway. Reinforcement
in curbs and walkway not shown for clarity
17.7.5
Shear Forces and
Bending Moments
17.7.5.1
Shear Forces and Bending
Moments Due to Dead Load

Self-weight of beam =

1, 452(150)
= 1.513 kip/ft
1, 000(144)

Weight of end diaphragm = 1.7 kips

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 5

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.5.1 Shear Forces and Bending Moments Due to Dead Load/
17.7.5.2 Shear Forces and Bending Moments Due to Superimposed Dead Load

The equations for shear force (Vx) and moment (Mx) for uniform loads on a simple
span (L) are given by:
L

Vx = w x
2

Mx =

(Eq. 17.7.5.1-1)

wx
(L x)
2

(Eq. 17.7.5.1-2)

where
w = weight/ft = 1.513 kip/ft
L = span length, ft
x = distance from the support, ft
Using the above equations, values of shear forces (Vg) and bending moments (Mg)
are computed and given in Table 17.7.5.1-1.
Table 17.7.5.1-1
Shear Forces and
Bending Moments

x, ft
V g , kip
Mg , ft-kips
V SDL , kip
MSDL , ft-kip
V LL+I , kip
MLL+I , kip

1.27**
20.0

4.0
15.9

6.0
12.8

0.0

26.6

75.7

104.4

20.1
0.0

18.4
24.5

14.6
69.5

164.6
0.0

150.7
194.5

0.0*
21.9

7.25
10.9

10.0
6.8

14.5
0.0

119.3

143.7

159.1

11.8
95.8

10.1
109.5

6.3
132.0

0.0
146.0

104.8
785.7

86.8
892.0

46.8
1,033.0

* At the support
** At the critical section for shear (See Section 17.7.11)

Diaphragm Load: Since distance between the centerline of the bearing and center of
gravity of the diaphragm is less than the effective depth, ignore the effect of the
diaphragm load in this example.
17.7.5.2
Shear Forces and Bending
Moments Due to
Superimposed Dead Load

Superimposed dead loads consist of ballast, ties, rails, curbs and handrails.
Ballast, including track ties at 120 pcf
= 15/12(7 + 0.04/2 gap)(0.120) = 1.053 kip/ft
Track rails, inside guardrails and fastenings at 200 plf /track =

[AREMA Art. 2.2.3]


0.200
= 0.100 kip/ft
2

For this example, assume concrete curb at 1.5 ft2 + handrail post at
5% = (1.5)(0.150)(1.05) = 0.236 kip/ft
Total superimposed dead load per beam per linear ft = 1.389 kip/ft
Using a uniform load of 1.389 kip/ft and Equations 17.7.5.1-1 and 17.7.5.1-2,
values of shear forces (VSDL) and bending moments (MSDL) are computed and given
in Table 17.7.5.1-1.
SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 6

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.5.3 Shear Forces and Bending Moments Due to Live Load/
17.7.7 Estimate Required Prestressing Force
17.7.5.3
Shear Forces and Bending
Moments Due to Live Load

The actions caused by the Cooper E 80 live load can be determined by using the
tables in the AREMA Manual, Chapter 15, Art. 1.15 Appendix or by using any commercially available computer program. A distribution factor (DF) equal to 0.5 is
used, since there are two beams supporting one track.
For span lengths less than 60 ft, the impact factor is:

L2
( 29) 2
I = 35
= 35
= 33.32% of live load

500
500

[AREMA Eq.17-1]

The values of shear forces (VLL+I) and bending moments (MLL+I) for live load plus
impact for one beam were determined using a computer program and are given in
Table 17.7.5.1-1.
17.7.5.4
Load Combinations

For Group I loading:


Service Load Design = D + (L + I)(DF)
Load Factor Design = 1.4(D + 5/3(L + I)(DF))

[AREMA Table 2-2]


[AREMA Table 2-3]

Values of shear forces and bending moments for service load design and factored load
design are determined from Table 17.7.5.1-1 and given in Table 17.7.5.4-1.
Table 17.7.5.4-1
Shear Forces and Bending
Moments for Design

Self Wt
(g)

Dead
(SDL)

Live +
Impact
(L+I)

Total
Service
Load

Total
Factored
Load

Max. Shear Force


at 1.27 ft, kips

20.0

18.4

150.7

189.1

405.4

Max. Bending
Moment at
Midspan, ft-kips

159.1

1,46.0

1,033.0

1,338.1

2,837.5

The maximum value of shear occurs near the supports while the maximum value of
bending moment occurs near midspan for a simply supported span.
17.7.6
Permissible Stresses in
Concrete at Service Loads

17.7.7
Estimate Required
Prestressing Force

At transfer (before time-dependent prestress losses):


[AREMA Art. 17.6.4]

Compression: 0.60 f ci = 0.60(4,000) = 2.400 ksi


Tension: 3 f ci without bonded reinforcement = 3 4, 000 = 0.190 ksi
At service loads (after allowance for all prestress losses):
[AREMA Art. 17.6.4]

Compression: 0.40 f c = 0.40(7,000) = 2.800 ksi


Tension in precompressed tensile zone: 0 ksi
Try eccentricity of strands at midspan, ec = yb - 2.5 = 12.75 in.
Bottom tensile stress due to applied loads:
fb =

M g + M SDL + M LL + I
Sb
SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 7

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.7 Estimate Required Prestressing Force /17.7.8 Determine Prestress Losses

where
fb
= concrete stress at the bottom fiber of the beam
Mg = unfactored bending moment due to precast beam self-weight, ft-kips
MSDL = unfactored bending moment due to superimposed dead load, ft-kips
MLL+I = unfactored bending moment due to live load plus impact, ft-kips
fb =

12(159.1 + 146.0 + 1, 033.0)


= 1.428 ksi
11, 248

Since allowable tensile stress in bottom fiber at service load is zero, required precompression is 1.428 ksi.
Bottom fiber stress due to prestress after all losses:
P
Pe
f b = se + se c
A
Sb
where Pse = effective pretension force after allowing for all losses
Then 1.428 =

Pse
P (12.75)
+ se
1, 452
11, 248

and Pse = 783.7 kips


Since losses are generally between 15 and 20%, assume 18% final prestress losses.
Allowable tensile stress in prestressing tendons immediately after prestress transfer is
the larger of 0.82fpy = (0.82)(0.9fpu) = 0.738 fpu or 0.75fpu
0.75 fpu = 0.75(270) = 202.5 ksi
Number of strands required =

[AREMA Art. 17.6.5]

783.7
= 30.8 strands
(1 0.18)(0.75 )(270)( 0.153)

Try 32 strands at bottom, ybs = 2.5 in.


Plus 4 strands at mid-height, ybs = 15.25 in.
Plus 6 strands at top, ybs = 27.50 in.
Total No. of strands = 32 + 4 + 6 = 42 strands
Center of gravity of strands, ybs =

32( 2.5) + 4(15.25) + 6( 27.50)


= 7.29 in.
42

Eccentricity of strands, ec = yb - ybs = 15.25 - 7.29 = 7.96 in.


Total initial prestressing force before loss = 202.5(0.153)(42) = 1,301.3 kips
17.7.8
Determine
Prestress Losses

To determine effective prestress, fse, allowance for losses of prestress due to elastic
shortening of concrete, fle, creep of concrete, flc, shrinkage of concrete, fls, and relaxation of prestressing steel, flr, will be calculated.

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 8

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.8.1 Prestress Losses at Service Loads/
17.7.8.1.4 Relaxation of Prestressing Steel
17.7.8.1
Prestress Losses at
Service Loads
17.7.8.1.1
Elastic Shortening
of Concrete

f le =

Es
f cr
E ci

[AREMA Eq. 17-16]

where
fcr = stress in concrete at centroid of prestressing reinforcement immediately after
transfer, due to total prestress force and dead load acting at time of transfer,
and is calculated as follows:
=

Psi Psie c2 M g e c
+

A
I
I

where
Psi = pretension force after allowing for initial losses. Taken as 0.69 fpu
fcr =

42(0.69)(0.153)( 270) 42(0.69)(0.153)(270)(7.96) 2


+
1, 452
171,535

f le =

17.7.8.1.2
Creep of Concrete

159.1(12)(7.96)
= 0.824 + 0.442 0.089 = 1.177 ksi
171,535

28, 000
(1.177 ) = 8.6 ksi
3, 834

flc = 12fcr - 7fcds

[AREMA Eq. 17-18]

where
fcds = concrete stress at centroid of prestressing reinforcement, due to all dead
loads not included in calculation of fcr
=

M SDL e c 146.0(12)(7.96)
=
= 0.081 ksi
171,535
I

fls = 12(1.177) - 7(0.081) = 13.6 ksi


17.7.8.1.3
Shrinkage of Concrete

Assume relative humidity, R = 70% (see also AREMA Fig. 17-1):


fls = 17,000 - 150 R
[AREMA Eq. 17-19]
=

17 , 000 150(70)

= 6.5 ksi

1, 000
17.7.8.1.4
Relaxation of
Prestressing Steel

For pretensioning tendons with 270 ksi low-relaxation strand:


flr = 5,000 - 0.10fle - 0.05(fls + flc)
[AREMA Eq. 17-21]
=

5, 000
- 0.10(8.6) - 0.05(6.5 + 13.6) = 3.1 ksi
1, 000

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 9

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.8.1.5 Total Losses at Service Loads/17.7.9.1 Stresses at Transfer at Midspan

17.7.8.1.5
Total Losses at Service Loads

Total prestress losses = 8.6 + 13.6 + 6.5 + 3.1 = 31.8 ksi


Final prestressing force, Pse = (202.5 - 31.8)(0.153)(42) = 1,096.9 kips
31.8
Percentage prestress losses =
100 = 15.7%
202.5

17.7.8.2
Total Losses at Service Loads

Losses due to elastic shortening, fle = 8.6 ksi


Total initial prestress losses = 8.6 ksi
Initial prestress force after loss, Psi = (202.5 - 8.6)(0.153)(42) = 1,246.0 kips
8.6
Percentage initial prestress losses =
100 = 4.25%
202.5

17.7.9
Concrete Stresses

Stresses need to be checked at several locations along the beam to ensure that the
design satisfies permissible stresses at all locations at both transfer and service loads.
For this design example, stresses will be checked at midspan and at the ends, which
will govern straight strand designs without debonding.

17.7.9.1
Stresses at Transfer
at Midspan

Compute concrete stress at the top fiber of the beam, f t:


ft =

Psi Psie c M g

+
A
St
St

Mg is based on overall length of 30 ft


Mg = wL2/8 = 1.513(30)2/8 = 170.2 ft-kips
ft =

1, 246 (1, 246)(7.96) 170.2(12)

+
1, 452
11, 248
11, 248

= 0.858 - 0.882 + 0.182 = 0.158 ksi


Compare with permissible values:
0.190 ksi < 0.158 ksi < 2.400 ksi

O.K.

Compute concrete stress at the bottom fiber of the beam fb:


fb =
=

Psi Psie c M g

+
A
Sb
Sb
1, 246 (1, 246)(7.96) 170.2(12)
+

1, 452
11, 248
11, 248

= 0.858 + 0.882 - 0.182 = 1.558 ksi


Compare with permissible values:
-0.190 ksi < 1.558 ksi < 2.400 ksi O.K.

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 10

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.9.2 Stresses at Transfer at End/
17.7.10.1 Stress in Strands at Flexural Strength
17.7.9.2
Stresses at
Transfer at End

Stresses should be checked at the end of the transfer length when designing a prestressed beam (see Section 9.1.8.2 for an example of this check). However, in this
design example, a standard beam design is being checked. Therefore it is conservative to check the stresses at the very end of the member, assuming the full prestress
force is effective at that location. Since the strands are straight and all strands are
bonded for the full length of the beam, the concrete stresses at the end are simply the
stresses at midspan without the stress due to dead load moment.
f t = -0.023 ksi, which is within permissible values shown above O.K.
fb = 1.740 ksi, which is within permissible values shown above O.K.

17.7.9.3
Stresses at Service
Load at Midspan

Compute concrete stress at the top fiber of the beam, ft:


ft =
=

Pse Psee c M g + M SDL + M LL + I

+
A
St
St
1, 096.9 (1, 096.9)(7.96) 1, 338.1(12)

+
1, 452
11, 248
11, 248

= 0.755 - 0.776 + 1.428 = 1.407 ksi < 2.800 ksi

O.K.

Compute concrete stress at the bottom fiber of the beam, fb:


fb =

Pse Psee c M g + M SDL + M LL + I


+

A
Sb
Sb
1, 096.9 (1, 096.9)(7.96) 1, 338.1(12)
+

1, 452
11, 248
11, 248

= 0.755 + 0.776 - 1.428 = 0.103 ksi > 0.0 ksi


17.7.9.4
Stresses at Service
Load at End

O.K.

The prestress force is at its maximum value at release and service loads do not affect
stresses at the end of the beam. Therefore, stresses at release will govern at the end of
the beam, so there is no need to check stresses at the end at service loads.

17.7.10
Flexural Strength
17.7.10.1
Stress in Strands at
Flexural Strength

In lieu of a more accurate determination of stress in pretensioning strands at nominal


strength, fps, based on strain compatibility, the following approximate value of fps is
used:

f pu
f ps = f pu 1 0.5 p , provided fse is greater than 0.5 fpu
fc

[AREMA Eq. 17-2]

where
fse = effective stress in pretensioning steel after losses
= 202.5 - 31.8 = 170.7 ksi > 0.5(270) = 135.0 ksi

O.K.

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 11

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.10.1 Stress in Strands at Flexural Strength/17.7.10.3 Design Moment Strength

rp =

A ps
bd

where
Aps = total area of pretensioning steel in tension zone
= 36 (0.153) = 5.508 in.2
b = effective flange width = 7(12) = 84.0 in.
d = distance from extreme compression fiber to centroid of pretensioning force
32( 2.5) + 4(15.25)
= 30.5 = 26.58 in.
36
Note: In many cases, strands near or above midheight are neglected when computing d for calculating the average stress in strands at flexural strength. This is
because, at the flexural strength, the strands located higher in the cross-section will
not reach a strain (and stress) as high as the bottom strands. However, for this standard beam design, the strands at midheight have been included as shown above. A
strain compatibility analysis (described in Sections 8.2.2.5 and 8.2.2.6) can be used
to compute the strain and stress in the strands at midheight. Such an analysis for
this beam indicates that the strands at midheight would reach a stress of approximately 251 ksi, which is reasonable when compared with the stress, fps, computed
below. The same analysis indicates that the strands in the bottom row would reach
a stress of nearly 260 ksi. Therefore, in this case, incorporating the strands at midheight has provided a reasonable result. If the strands at midheight are neglected,
the strength of the section at midspan would prove to be inadequate.
rp =

A ps
bd

5.508
= 0.00247
84( 26.58)

270
fps = 2701 (0.5)(0.00247 )
= 257.1 ksi

7.0
17.7.10.2
Limits for Reinforcement

Assuming a rectangular section, compute the reinforcement ratio as:


p

f ps
f c

0.00247 ( 257.1)
= 0.0907 < 0.30
7.0

O.K.

[AREMA Art. 17.5.4]

When the reinforcement ratio exceeds 0.30, design moment strength shall not be
taken greater than the moment strength based on the compression portion of the
moment couple.
17.7.10.3
Design Moment Strength

Assuming beam acts as a rectangular section::

f ps
fMn = f A psf psd 1 0.6 p
f c

a
= f A psf ps d

[AREMA Eq. 17-3]

[AREMA Eq. 17-4]

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 12

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.10.3Design Moment Strength/17.7.10.5 Final Strand Pattern

where
Mn = nominal moment strength of a section
f = strength reduction factor for flexure = 0.95
a

A psf ps
0.85 f c b

[AREMA Art.17.5.2]

5.508( 257.1)
= 2.83 in.
0.85(7 )(84)

[AREMA Art.17.5.4d]

Average depth of top flange = 6.5 in. > 2.83 in.


Therefore, rectangular section assumption is appropriate.
Using AREMA Eq. 17-4:

2.83 1
fMn = 0.95 5.508( 257.1) 26.58
= 2,821.2 ft-kips

2 12

Factored moment due to dead and live loads from Table 17.7.5.4-1 = 2,837.5 ft-kips.
Percentage over =

17.7.10.4
Minimum Reinforcement

17.7.10.5
Final Strand Pattern

( 2, 837.5 2, 821.2)
(100) = 0.58% (insignificant) say ok.
2, 821.2

The total amount of prestressed and non-prestressed reinforcement should be adequate to develop an ultimate moment at the critical section at least 1.2 times the
cracking moment, Mcr: fMn 1.2Mcr. The calculation (not shown here but similar
to the calculation in Section 9.1.10.2) yields 2,821.2 ft-kips > 2,427.3 ft-kips O.K.

Final strand locations are shown in Figure 17.7.10.5-1

7'-0"

Figure 17.7.10.5-1
Strand Pattern

4"
3 1/2"

10"

1'-8"

1'-4"

1'-8"

10"

4"
2 1/2"

3'-3 3/4"

4 1/2"

2'-1"
1'-3 1/4"

6 Strands
2'-1"
4 Strands

Void Drains
Drip
2 1/2"
3" 17 Spaces @ 2" = 2'-10" 10" 17 Spaces @ 2" = 2'-10"

2 1/2"
3"
32 Strands

Note: Curbs and warkway not shown

SEPT 01

5844 Bridge Manual Ch 17.7

10/8/01

11:43 AM

Page 13

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.11 Shear Design /17.7.11.2.1 Simplified Approach

17.7.11
Shear Design
17.7.11.1
Required Shear Strength

Prestressed concrete members subjected to shear are designed so that


Vu f (Vc + Vs)
[AREMA Eq. 17-8]
where
Vu = factored shear force at section considered
Vc = nominal shear strength provided by concrete
Vs = nominal shear strength provided by shear reinforcement
f = strength reduction factor for shear = 0.90
[AREMA Art. 17.5.2]
Per the AREMA Manual, Article 17.5.9b, the critical section for shear is located at a
distance h/2 from face of support. In this design example, the critical section for shear
is calculated from the centerline of the bearings since the pads are not rigid and have
the potential to rotate.
h/2 = 30.5/2 = 15.25 in. = 1.27 ft
Vu = 405.4 kips (from Table 17.7.5.4-1)

17.7.11.2
Shear Strength Provided
by Concrete
17.7.11.2.1
Simplified Approach

The shear strength provided by concrete, Vc, can be calculated by using AREMA
Manual Eq. 17-9, provided that the effective prestress force is not less than 40% of
the total tensile strength provided by the flexural reinforcement.

Vu d

Vc = 0.6 f c + 700
b wd
Mu

where
Mu = factored bending moment at the section

[AREMA Eq. 17-9]

= 1.4 26.6 + 24.5 + (194.5) = 525.4 ft-kips

3
bw = total web width = 5 + 8.5 + 5 = 18.5 in.
d = 26.58 in. > 0.8h = (0.8)(30.5) = 24.4 in.
Therefore, use d = 26.58 in.
Vu d 405.4( 26.58)
=
= 1.71 > 1.0, use 1.0
525.4(12)
Mu

[AREMA Art. 17.5.9c]

Vc = 0.6 7 , 000 + 700(1.0) 18.5( 26.58) / 1, 000 = 368.9 kips


However, the maximum value of Vc is limited to:
5 f c b w d = 5 7 , 000 (18.5)( 26.58) / 1, 000 = 205.7 kips < Vc = 368.9

NO GOOD

AREMA Manual Art. 17.5.9c allows higher values of Vc if a more detailed calculation
is made. According to this method, Vc is the lesser of Vci or Vcw.
SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 14

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.11.2.1 Simplified Approach/17.7.11.2.2 Calculate Vci

where
Vci = nominal shear strength provided by concrete when diagonal cracking
results from combined shear and moment
Vcw = nominal shear strength provided by concrete when diagonal cracking
results from excessive principal tensile stress in web
17.7.11.2.2
Calculate Vci

Vci = 0.6 f c b w d + VD +

ViM cr
M max

[AREMA Eq. 17-10]

but not less than 1.7 f c b w d


where
VD

= shear at section due to service dead load = Vg + VSDL = 20.0 + 18.4


= 38.4 kips
= moment causing flexural cracking at section due to externally applied loads

Mcr

= S b 6 f c + f pe f d

where
fpe= compressive stress in concrete due to effective prestress force only, at the
extreme fiber of section where tensile stress is caused by externally applied
loads
fpe =
=

Pse
Pe
+ se c
A
Sb
1, 096.9 1, 096.9(7.96)
+
= 0.755 + 0.776 = 1.531 ksi
1, 452
11, 248

fd = stress due to unfactored dead load at extreme fiber of section where tensile stress is caused by externally applied loads
fd =

Mcr
Vi
Mmax

M g + M SDL
Sb

(26.6 + 24.5)12 = 0.055 ksi


11, 248

11, 248
6 7 , 000
=
= 1,854.0 ft-kips
+ 1.531 0.055
12
1, 000
= factored shear force at section due to externally applied loads occurring
simultaneously with Mmax = Vu - VD = 405.4 - 38.4 = 367.0 kips
= maximum factored moment at the section due to externally applied
loads = Mu - Mg - MSDL = 525.4 - 26.6 - 24.5 = 474.3 ft-kips

Vci = 0.6 f c b w d + VD +

= 0.6

ViM cr
M max

[AREMA Eq. 17-10]

7 , 000
367.0(1, 854.0)
(18.5)(26.58) + 38.4 +
= 1,497.7 kips
1, 000
474.3

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 15

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.11.2.2 Calculate Vci /17.7.11.3.2 Determine Stirrup Spacing

7 , 000
(18.5)(26.58) = 69.9 kips
but not less than 1.7 f c b w d = 1.7
1, 000
Therefore,
Vci = 1,497.7 kips
17.7.11.2.3
Calculate Vcw

Vcw = 3.5 f c + 0.3f pc b w d + Vp

[AREMA Eq. 17-11]

where
fpc = compressive stress in the concrete (after allowance for all pretension losses)
at the centroid of cross section resisting externally applied loads
Vp = vertical component of effective prestress force at section
= 0 for straight strands.
Transfer length of strands = 50 strand diameters = 50(0.5) = 25 in. from end of beam.
Since the distance h/2 = 15.25 in. is closer to end of member than the end of the
transfer length of the prestressing strands, a reduced pretensioning force will be considered when computing Vcw.
[AREMA Art. 17.5.9c(2)(c)]
Effective prestress force at distance h/2 from centerline of the bearing,
Pse =
fpc =

(15.25 + 6.00) (1, 096.9) = 932.4 kips


25

932.4
= 0.642 ksi
1, 452

Therefore,

3.5 7 , 000
+ 0.3(0.642) (18.5)( 26.58) + 0 = 238.7 kips
Vcw =

1, 000
17.7.11.2.4
Calculate Vc

17.7.11.3
Calculate Vs and
Shear Reinforcement

Vc = lesser of Vci and Vcw


Vc = Vcw = 238.7 kips
Vs =

Vu
405.4
Vc =
238.7 = 211.7 kips

0.9

[AREMA Eq. 17-8]

17.7.11.3.1
Calculate Vs
17.7.11.3.2
Determine Stirrup Spacing

Required stirrup spacing is calculated as follows:


Vs =

A vf yd
s

[AREMA Eq. 17-14]

where Av = area of shear reinforcement within a spacing, s


SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 16

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.11.3.2 Determine Stirrup Spacing/17.7.11.3.4Check Stirrup Spacing Limits

Try two closed stirrups, which provides (4) # 4 bars,


Av = 4(0.20) in.2 = 0.80 in.2
Stirrups are provided at 4 in. spacing to satisfy the minimum flexural requirements of
the top slab of the box beam. Calculations for the top slab flexural reinforcement are
not provided in this example.
A vf yd

Spacing required, s =

Vs

0.80(60)( 26.58)
= 6.1 in. > 4 in.
210.4

O.K.

Use # 4 stirrups (4 legs) at 4-in. centers.


Av provided = 4(0.20) = 0.80 in.2
Shear strength provided by stirrups,
Vs =

17.7.11.3.3
Check Vs Limit

0.80(60)( 26.58)
= 319.0 > 210.4 kips
4

O.K.

Allowable maximum shear strength provided by stirrups is:


8 f c b w d = 8 7 , 000 (18.5)( 26.58) / 1, 000
= 329.1 kips > Vs

17.7.11.3.4
Check Stirrup
Spacing Limits

[AREMA Art. 17.5.9d(5)]

O.K.

Check for maximum spacing of stirrups


4 f c b w d = 4

7 , 000
(18.5)( 26.58) = 164.6 kips < Vs
1, 000

[AREMA Art. 17.5.9d(3)]

Therefore, maximum spacing is lesser of 3/8h = 3/8(30.5) = 11.4 in. or 12 in.


Provide # 4 stirrups (4 legs) at 4-in. centers < 11.4 in. O.K.
Calculations for shear at other sections along the beam are not provided in this example.
For shear reinforcement details, see Figures 17.7.4-1 and 17.7.11.3.4-1
Figure 17.7.11.3.4-1
Elevation Showing
Non-Prestressed Reinforcement

#6 Bars
2 1/4"

#4 Bar

Note:
#6 Bars at web not
shown for clarity

#4 Stirrups

(4) #4 End
bars
(Typ.)
3 1/4"

11 Spaces @
4" = 3'-8"

#6 Bars
Spacing @ About 6" Centers
CL
Girder
(Symm.)
SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

Page 17

CHAPTER 17

PCI BRIDGE DESIGN MANUAL

RAILROAD BRIDGES
17.7.12 Deflections/17.7.12.5 Deflection Due to Live Load

17.7.12
Deflections

Camber and deflection calculations are required to determine the bridge seat elevations and maintain the minimum ballast depth. They are also required for the design
of the elastomeric bearings.
1, 219.7 (7.96)( 29(12))
P e L2
= - 0.223 in.
= si c =
8(3, 834)(171,535)
8E ciI
2

17.7.12.1
Camber Due to
Prestressing at Transfer

5(1.513 / 12)( 29(12))


5wL4
=
=
= 0.037 in.
384E ciI (384)(3, 834)(171,535)
4

17.7.12.2
Deflection Due to Beam
Self-Weight at Transfer

5(1.389 / 12)( 29(12))


5wL4
= 0.025 in
=
=
384E cI (384)(5, 072)(171,535)
4

17.7.12.3
Deflection Due to
Superimposed Dead Load
17.7.12.4
Long-Term Deflection

According to PCI Design Handbook - 5th Edition, Table 4.8.2, long-term camber and
deflection of prestressed concrete members can be calculated by an approximate method
using multipliers. Calculations are shown in Table 17.7.12.4-1.

Table 17.7.12.4-1
Calculated Deflection, in.

Prestress
Self-Weight
Dead Load
Total

At Release
(a)
0.223
+ 0.037
N/A
0.186

Multiplier
(b)
1.80
1.85

Erection
(c) = (a)(b)
0.401
+ 0.068
+ 0.025
0.308

Multiplier
(d)
2.45
2.70
3.00

Final
(e) = (a)(d)
0.546
+ 0.100
+ 0.075*
0.371

* This is the result of multiplying the dead load deflection at erection (c) by multiplier (d)

17.7.12.5
Deflection Due to Live Load

Live load deflection is generally calculated using influence lines. At this point, use of
a computer program becomes very useful. However, for short span bridges, the
designer can quickly calculate an approximate value for deflection by using the equivalent uniform load. The equivalent uniform live load, wequ, for a simply supported
beam can be derived from the maximum moment at midspan,
MLL + I =
wequ =

D=

w equ L2
8

8M LL + I 8(1, 033.0)(12)
=
= 0.819 kip/in.
2
L2
(29(12))
5(0.819)( 29(12))

384(5, 072)(171,535)

= 0.180 in.

Maximum allowable deflection =


=

29(12)
= 0.544 in. > 0.180 in.
640

L
640
O.K.

[AREMA Art. 17.6.7a]

SEPT 01

5844 Bridge Manual Ch 17.7

9/24/01

1:37 PM

PCI BRIDGE DESIGN MANUAL

Page 19

CHAPTER 17

RAILROAD BRIDGES
17.8 References

17.8
REFERENCES

AREMA Manual for Railway Engineering, 2000 Edition, American Railway


Engineering and Maintenance-of-Way Association, Landover, MD, 2000
Marianos, W. N., Jr., Railroad Use of Precast Concrete Bridge Structures, ACI
Concrete International, V. 13, No. 9, September 1991, pp. 30-35
PCI Design Handbood, Fifth Edition, Precast/Prestressed Concrete Institute, Chicago,
IL, 1999, 690 pp.

DEC 00

You might also like