Professional Documents
Culture Documents
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes wire, cable, pathways, connecting devices, installation, and testing for
wiring systems to be used as signal pathways for voice, CATV and high-speed data
transmission.
1.3 DEFINITIONS
1.4 REFERENCES
I. UL Testing Bulletin.
1.5 SUBMITTALS
A. Provisioning Section
Submit under provisions of Section 01000, “Coordination Drawings” for owner approval.
C. Manufacturer’s Instructions
Indicate application conditions and limitations of use stipulated by product testing agency
specified under regulatory requirements. Include instructions for storage, handling, protection,
examination, preparation, operation and installation of product. A technical data sheet from the
manufacturer should be included with the response for each product proposed. This data sheet
shall include the physical specifications, as well as the following electrical and transmission
characteristics:
D. Pre-Qualification Certificate
Submit a letter of approval from the manufacture indicating completion of pre-qualification
requirements. Training certificates for design, engineering and installation of the proposed
products shall be submitted with the proposal
E. Factory Test
Vendor shall submit all factory test information prior to installation to the Project Manager. If
equivalent product(s) are substituted, the equivalent product(s) must show demonstrated and
documented equivalence to the product(s) specified.
F. Bid
Vendor will submit complete detailed bids. Lump sum bids will not be accepted.
G. Material Guarantee
The wiring vendor (installer) shall guarantee at the time of the bid that all Category 5 Enhanced
and Category 6 cabling and components meet or exceed specifications (including installation) of
appropriate sections of TIA/EIA-568B and 569A.
H. Material Provided
Vendor shall be certain that all correct parts are ordered and installed. Vendor shall submit
complete parts and part numbers prior to installation of equipment.
J. As-Built Documentation
Upon completion of the project, The Cable Contractor is to prepare "As Built" documentation
showing actual site conditions and installation as constructed, and provide copies of such docu-
mentation. Submit newly prepared information, legible and readable, drawn to accurate scale.
Highlight, encircle or otherwise indicate deviations from Contract Documents. Do not repro-
duce Contract Documents or copy standard information (product data, etc.) as basis of Shop
Drawings. Standard information prepared without specific reference to the Project is not consi-
dered a Shop Drawing. Shop Drawings not complying with these requirements may be rejected
& returned for resubmittal.
1. Riser and Cross connection diagrams - includes:
a. Cable routing
b. Position of all components and apparatus
c. Detailed layout of the wall field
K. Shop Drawings: Include dimensioned plan and elevation views of each individual component.
Show equipment assemblies, method of field assembly, workspace requirements, and access for
cable connections.
L. Product Certificates: For each type of cable, connector, and terminal equipment, signed by
product manufacturer.
M. Operation and Maintenance Data: For voice and data communication cabling to include in
emergency, operation, and maintenance manuals.
A. Manufacturer
The products specified on the drawings and in this specification are the basis of design. Alter-
nates may be considered with prior approval from owner before bid due date. Manufacturer
shall have a minimum of five (5) years’ experience and ISO Certified 9001.
C. Installer Resume: A resume shall be submitted with the proposal including the following:
1. A list of recently completed projects of similar type and size with contact names and
telephone numbers for each project.
2. A list of test equipment proposed for use in verifying the installed integrity of metallic
and fiber optic cable systems on this project.
3. A technical resume of experience for the installer’s Project Manager and on-site
installation supervisor who will be assigned to the project.
4. A list of technical product training attended by the installer’s personnel that will be
working on the project.
D. Source Limitations: Obtain all products except twisted-pair and fiber-optic cables through one
source from a single manufacturer.
E. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
1.7 COORDINATION
A. Coordinate building entrance with other utility entrances. Coordinate layout and installation of
voice and data communication cabling with Owner's telecommunications and LAN equipment
suppliers, and campus site plan if applicable. Follow all code requirements including any
private or utility locates during construction.
1.8 WARRANTY
A. No less than a 20-year Extended Product Warranty and System Assurance Warranty shall be
provided for the cabling system solution.
C. System Assurance
The System Assurance shall cover the failure of the wiring system to support the application
D. System Certification
Upon successful completion of the installation and subsequent inspection, Owner shall be pro-
vided with a registered certificate, from the manufacturing company, certifying the installation.
1.9 DESCRIPTION
A. General Descriptions
C. BDF
BDF shall house data network equipment, voice components (PBX), building distribution rack,
servers and active components.
A. Cable Pathway
In suspended ceilings where duct, J-hooks or conduit have not been specified, the Contractor
shall bundle, in groups of 50 or less, all station wiring with plastic or Velcro cable ties snug, but
not to the point of deforming the cable geometry. All cable bundling shall be supported by Ca-
ble Tray and/or J-Hooks attached to the existing building structure and framework at a maxi-
mum of five (5) foot intervals. Sleeves shall be appropriately sized to all applicable codes and
standards; provided and installed for all wall penetrations. Cabling shall be plenum rated and
the cabling contractor shall adhere to the manufacturers’ requirements for bending radius and
pulling tension of all data and voice cables.
B. Fire Stopping
Any Penetrations created and/or utilized for cable passage between floors or through fire-
/smoke-rated barriers and assemblies will be firestopped by the cabling contractor. Firestopping
materials and methods shall be in accordance with all Manufacturers requirements and shall be
accomplished in an acceptable manner with all-local fire and building authorities having juris-
diction over the work. Any penetrations created for the passage of telecommunications, either
by or for cabling contractor, which remains vacant at the completion of the installation, will also
be firestopped by the cable contractor as part of this work.
1.11 TRAINING
A. Contractor shall provide a minimum of 8 hours of staff training at a time to be coordinated with
the owner. The purpose of this training is to provide necessary information to the owner’s staff
in the proper use and maintenance of the installed systems.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Cable:
a. AMP NetConnect
b. Systimax SCS
c. Molex Premise Networks
d. Ortronics.
e. Panduit Corp
A. General: Coordinate the features of materials and equipment so they form an integrated system.
Match components and interconnections for optimum future performance.
B. Expansion Capability: Unless otherwise indicated, provide spare fibers and conductor pairs in
cables, positions in cross-connect and patch panels, and terminal strips to accommodate no less
than 20 percent future increase in active workstations.
A. Raceways and Boxes: Comply with Division 16 Section "Raceways and Boxes."
1. Approximate Module Dimensions: 84 inches (2130 mm) high by 22 inches (560 mm)
wide (nominal 19” wide rack space).
2. Finish: Baked-polyester powder coat.
2.4 OUTLETS
All Category 6 outlets shall conform to TIA/EIA 568B2.1 Commercial Building Telecommuni-
cations Cabling Standard, Horizontal Cable Section, and be part of the UL LAN Certification
and Follow-up Program, and shall meet or exceed the following electrical and mechanical speci-
fications:
1. Electrical Specifications:
a. TIA/EIA 568B2.1 minimum requirements for specified category.
b. Insulation Resistance: 500 MW minimum.
c. Dielectric withstands voltage 1,000 VAC RMS, 60 Hz minimum, contact-to-
contact and 1,500 VAC RMS, 60 Hz minimum from any contact to exposed
conductive surface.
2. Mechanical Performance:
a. Plug Insertion Life: 750 insertions
b. Contact Force: 3.5 oz (99.2 g) minimum using FCC-Approved modular plug
c. Plug Retention Force: 30-lb (133 N) minimum between modular plug and jack
d. Temperature Range: -14° to 150°F (-10° to 60°C)
B. Outer jacket: Provide plenum rated cable where required, provide white sheath for voice jacks
(upper jack in combination outlets and wall phones), provide blue sheath for all data jacks.
A. The racks shall be made of lightweight metal, black in color and include steel mounting
hardware for mounting patch panels and other equipment to the frame. In addition, the rack
must provide vertical and horizontal wireways for cross-connect cabling. Racks shall be four
post enclosed with glass door and fan.
B. The minimum rack size shall be a standard 19-inch rack with sufficient rack space to allow the
structured cabling to terminated at the top of the rack with room remaining for Owner supplied
network and electronic security equipment to be placed in the lower part of the rack. Wire
management panels will be installed between patch panels for front and rear cable management.
Vertical wire manager will be installed in-between and on outer edges of racks.
C. Racks shall be mounted on an isolation pad and utilize non-conductive washers to secure the
rack to the floor. Floor mounted open racks will be secured from the top rail to the backboard
in the room with a length of cable runway to prevent movement. All racks will be grounded to
the isolated ground bar within the MDF/IDF using a standard ground lug and #6 jacketed green
cable.
D. All racks to be supported with bracket attached to the wall directly or through attachment to
ladder rack.
A. Provide Category 6 Modular Patch Cords for each port on the patch panels, as well as 10’ patch
cords for all work area outlets. All cords shall conform to the requirements of EIA/TIA 568-B2.1
Commercial Building Telecommunications Cabling Standard, Horizontal Cabling Section.
Contractor will install all patch cords within closets.
A. The data termination blocks shall be a patch panel to support the appropriate Category 6
applications and facilitate cross connection and inter connection using modular patch cords.
A. Cable Manufacturer’s suggested cable pulling lubricant, shall be utilized when pulling all cable.
A. Ladder rack shall be used for vertical cabling and shall be eighteen (18) or twelve (12) inches
wide with one and one-half (1-1/2) inch solid bar stringer, and rungs spaced at nine (9) inches.
2.11 J-HOOK
A. J-hooks shall be used for backbone and horizontal cabling where specified.
C. The space between every J-hook shall not be more than 5 feet.
A. Cat 5e Rated
C. Wall Mounted
3.1 EXAMINATION
A. Examine pathway elements intended for cables. Check raceways, cable trays, and other
elements for compliance with space allocations, installation tolerances, hazards to cable
installation, and other conditions affecting installation. Proceed with installation only after
unsatisfactory conditions have been corrected.
A. Horizontal Cable for Voice & Data Service: Use Category 5e for data and voice cables for runs
between wiring closet and workstation outlets.
3.3 INSTALLATION
A. Wiring Method: Install wiring and optical fiber in raceway and J-hooks except within consoles,
cabinets, desks, and counters. Use UL-listed Plenum cable in environmental air spaces,
including plenum ceilings. Conceal raceway and cables except in unfinished spaces.
B. Install cables using techniques, practices, and methods that are consistent with Category 5e
rating of components and that ensure Category 5e performance of completed and linked signal
paths, end to end.
D. Do not bend cables, in handling or in installing, to smaller radii than minimums recommended
by manufacturer.
1. Pull cables simultaneously if more than one is being installed in same raceway.
2. Use pulling compound or lubricant if necessary. Use compounds that will not damage
conductor or insulation.
3. Use pulling means, including fish tape, cable, rope, and basket-weave wire or cable grips,
that will not damage media or raceway.
G. Install exposed cables parallel and perpendicular to surfaces or exposed structural members and
follow surface contours where possible.
H. Secure and support cables at intervals not exceeding 30 inches (760 mm) and not more than 6
inches (150 mm) from cabinets, boxes, fittings, outlets, racks, frames, and terminals.
J. Separation of Wires: Comply with TIA/EIA-569-A-7 rules for separating unshielded copper
voice and data communication cabling from potential EMI sources, including electrical power
lines and equipment.
K. Make terminations only at indicated outlets, terminals, and cross-connect and patch panels.
A. Absolutely No cable splices will be allowed within the scope of this project.
3.5 GROUNDING
A. Comply with Division 16 Section "Grounding and Bonding” and/or ”Basic Electrical Materials
And Methods." Comply with ANSI/TIA/EIA J-STD-607, NEC Section 250, 800-40, and all
applicable codes.
B. The Telecommunications Grounding and Bonding System shall be independent of the Electrical
Grounding and Bonding System except where the Telecommunications Main Grounding Busbar
(TMGB) is bonded to the Electrical Main Grounding Busbar.
C. Ground equipment to eliminate shock hazard and to minimize ground loops, common-mode
returns, noise pickup, cross-talk, and other impairments.
D. Telecommunications Main Grounding Busbar (TMGB): TC shall furnish & install on wall of
equipment room (MDF) with standoff insulators. TC shall coordinate to ensure adequate
length, proper location, etc.
F. Telecommunications Bonding Backbone: TC shall bond all TGBs to the TMGB using
minimum grounding conductor size, compliant with ANSI/TIA/EIA J-STD-607.
G. Individual items may be loop connected to the Telecommunications Bonding Backbone (TBB)
provided length sizing criteria are followed. All TBB’s shall terminate on a TMGB. TMGB
shall be installed as indicated on the contract documents. TMGB shall be bonded to main
building electrical service ground at the service entrance.
A. Install plywood backboards on walls of equipment rooms and wiring closets from floor to
ceiling where indicated on drawings. Plywood shall be 4’ x 8’ x ¾” fire-rated.
B. Mount patch panels on racks; terminal strips, and other connecting hardware on backboards,
unless otherwise indicated.
D. Use patch panels to terminate cables entering the space, unless otherwise indicated.
A. Perform the following field tests and inspections and prepare test reports, or engage a qualified
testing and inspecting agency to do so:
3.10 TESTING/WARRANTY
C. Documentation shall be provided in both hard copy and CD-R to the point of contact.
D. Additional Warranty
The Cable Contractor shall state any additional Contractor supplied warranty.
E. The owner shall have the right to observe and witness all SCS Testing. The owner shall be
notified at least two weeks prior to testing, and be provided with a testing schedule.
A. At the completion of the Cable System, the Cable Contractor will restore to its former
condition, all aspects of the project site and on a daily basis, shall remove all waste and excess
materials, rubbish, debris, tools and equipment resulting from or used in the services provided
under this Contract. All clean up; restoration, and removal noted above will be by the Cable
Contractor and at no cost to the owner. If the Cable Contractor fails in its duties under this
3.12 INSPECTION
A. The Project Manager and/or the SCS System Manager shall perform periodic progress
inspections throughout the duration of the cabling construction. All work shall be performed in
a high quality manner and the overall appearance shall be clean, neat and orderly. The
following points will be examined and must be satisfactorily noted as complete and meeting
standards established by Owner for System Acceptance:
1. Are all of the cables properly labeled, from end-to-end?
2. Is the cable type suitable for its pathway? Are the cables bundled in parallel?
3. Have the pathway manufacturer's guidelines been followed? Are all cable penetrations
properly installed and fire stopped according to code?
4. Have the Cable Contractors avoided excessive cable bending?
5. Have potential EMI and RFI sources been considered?
6. Is Cable Fill Correct?
7. Are hanging supports within 1.5 meters (5 feet)?
8. Does hanging cable exhibit some sag?
9. Are telecommunications closet (MDF/IDF) terminations compatible with applications
equipment?
10. Have Patch Panel instructions been followed?
a. Jacket removal point
b. Termination positions
c. All pair termination’s snug without pair distortion
d. Twists maintained up to Index Strip
11. Have Modular Panel instructions been followed?
a. Cable dressing first
b. Jackets remain up to the Connecting Block
c. All pair termination’s snug and undistorted
d. Twists maintained up to the Connecting Block
12. Are identification markings uniform, permanent and readable?