1. OPEN AN APPROVED SHOP DRAWINGS.


THIS SHOP DRAWINGS CONSIST OF
APPROVED DRAINAGE PIPE

Toilet details and mechanical pipe sleeves location for both indoor unit refrigeration pipes
and sanitary fixtures ventilation. Block work (except the shaft walls) and water proofing
activity should be done first before installation.

method of statement for drainage pipe installation

2. Waiting pipes, drainage pipe,stub pipes and fittings from risers and underground pipes
should be present before starting inside the toilet. Hollow vertical shaft or duct located
nearby the toilet will not be cover to work easily inside the toilet especially connection to
the risers.

3. Assign the location of pipes in the wall or floor that is exactly as mention on the
approved toilet details shop drawing. Mark with the line corresponds to the total area to
bury the pipe in the wall or floor (for lavatory and A/C drain).

4. Use block cutter or simply portable grinder to cut a side of block continuously along the
line that had been marked. Absolute care should be done not to cut or damaged the preinstalled

pipe

sleeves

of

fixture

vents

and

A/C

indoor

unit.

5. By using sharp- pointed steel rod and other proper chipping tools, chip the block side
to the thickness required to fixed the sanitary pipes.

6. Standard fittings and materials must be used and all drainage pipe and fittings must be
joined using the approved glue. Sanitary tee fittings for vent be fixed inclined 45 or slope
from center line of pipe it serve.

7. Level of the slab should be identified by surveyor before proceeding installation. Also
locate points as alternative reference point for pipe and pipe fittings installation.

8. Install / layout the pipes at designated height, location and slopes (1% slope for
sanitary fixtures and 0.5% slope for A/C drain). Sanitary fixtures outlet location should
also be installed and identified.

9. Connection of drainage pipes other than water closet drain (i.e. A/C drain, lavatory
drain, bidet drain, bathtub drain and shower tray drain) should be slope toward gully trap
floor drain based on the approved toilet details shop drawings.

10. Pipes and pipe fittings connection should be on the compacted fine sand and partly
small of cement mortar as its support. Height distance between gully trap bottom and
slab should be two (2) centimeter for all toilets.

11. Absolute care should be imposed not to damage the water proofing upon installation.

12. Install sleeves for pipes passing through the concrete or masonry walls. Put sealant
in between the pipes and sleeves.

13. Check the pipes securely fixed, joint and capped before leak testing.

14. Leak test for the installed drainage pipe is to be carried-out with presence of
inspector Engineer.

15. After the approval of Inspector Engineer, cover the drainage pipe with cement plaster
or sand to where it is applicable.