1. Which project progress technique includes the essential features of a project plan,
budgeted cost of work scheduled and budgeted cost of work performed?
Critical path method
Gantt chart
Cost analysis
Earned value management
2. A work breakdown structure is
a simple list of the activities making up a project
a structure that is incompatible with the Critical Path Method
a hierarchy of tasks, subtasks, and work packages
a Cost and Performance tracking schedule
3. Which of the following identifies a key principle of Reengineering?
Merge information-processing work into the real work that produces the information.
Organize around tasks.
Capture information both at the source and where it is interpreted.
Downsize (lay-off) workers and do the same amount of work as before.
4. Consulting firms typically use which of the following techniques to plan and monitor
the engagements of the firm or specific projects?
CPM/PERT
Qualitative forecasting
Quantitative layout
Materials requirements planning (MRP)