You are on page 1of 2

66832 Federal Register / Vol. 70, No.

212 / Thursday, November 3, 2005 / Notices

notification when a document is added City of Vernon, CA in addition to (866) 208–3676 (toll free). For TTY, call
to a subscribed dockets(s). For providing a notice of cancellation of (202) 502–8659.
assistance with any FERC Online Service Agreement No. 364. Magalie R. Salas,
service, please e-mail Filed Date: October 21, 2005.
FERCOnlineSupport@ferc.gov. or call Secretary.
(866) 208–3676 (toll free). For TTY, call Accession Number: 20051025–0087. [FR Doc. E5–6066 Filed 11–2–05; 8:45 am]
(202) 502–8659. Comment Date: 5 p.m. Eastern Time BILLING CODE 6717–01–P

Magalie R. Salas,
on Friday, November 11, 2005.
Secretary. Any person desiring to intervene or to DEPARTMENT OF ENERGY
[FR Doc. E5–6065 Filed 11–2–05; 8:45 am] protest in any of the above proceedings
BILLING CODE 6717–01–P must file in accordance with Rules 211 Federal Energy Regulatory
and 214 of the Commission’s Rules of Commission
Practice and Procedure (18 CFR 385.211
DEPARTMENT OF ENERGY Notice of Application for Amendment
and 385.214) on or before 5 p.m. Eastern of License and Soliciting Comments,
Time on the specified comment date. It Motions To Intervene, and Protests
Federal Energy Regulatory is not necessary to separately intervene
Commission October 27, 2005.
again in a subdocket related to a
Combined Notice of Filings #1 compliance filing if you have previously Take notice that the following
intervened in the same docket. Protests hydroelectric application has been filed
October 27, 2005. will be considered by the Commission with the Commission and is available
Take notice that the Commission in determining the appropriate action to for public inspection:
received the following electric rate be taken, but will not serve to make a. Application Type: Amendment of
filings. protestants parties to the proceeding. license to revise Article 401 of the
Docket Numbers: ER04–435–017; Anyone filing a motion to intervene or license.
ER05–612–002. protest must serve a copy of that b. Project No.: 1975–040.
Applicants: Southern California c. Date Filed: October 13, 2005.
document on the Applicant. In reference
Edison Company. d. Applicant: Idaho Power Company.
to filings initiating a new proceeding, e. Name of Project: Bliss Project.
Description: Southern California interventions or protests submitted on
Edison Co submits revised rate sheets to f. Location: The Project is located on
or before the comment deadline need the Snake River in Gooding, Twin Falls,
its wholesale distribution access tariff not be served on persons other than the
large generator interconnection and Elmore Counties in Idaho. The
Applicant. project occupies federal lands managed
procedures in compliance with FERC’s
October 3, 2005 Order. The Commission encourages by the Bureau of Land Management.
Filed Date: October 21, 2005. electronic submission of protests and g. Filed Pursuant to: Federal Power
Accession Number: 20051026–0009. interventions in lieu of paper, using the Act, 16 U.S.C. 791a–825r.
Comment Date: 5 p.m. Eastern Time FERC Online links at http:// h. Applicant Contact: Nathaniel F.
on Friday, November 11, 2005. www.ferc.gov. To facilitate electronic Gardener, Idaho Power Company, PO
service, persons with Internet access Box 70, Boise, Idaho 83707. Tel: (208)
Docket Numbers: ER05–1025–002.
388–2550.
Applicants: California Independent who will eFile a document and/or be
i. FERC Contact: Any questions on
System Operator Corporation. listed as a contact for an intervenor
this notice should be addressed to
Description: California Independent must create and validate an Vedula Sarma at (202) 502–6190 or
System Operator Corp in compliance eRegistration account using the vedula.sarma@ferc.gov.
with FERC’s September 23, 2005 Order, eRegistration link. Select the eFiling j. Deadline for filing comments and/
submits an amended Small Utility link to log on and submit the or motions: November 28, 2005.
Distribution Company Operating intervention or protests. k. Description of Filing: Idaho Power
Agreement. Company proposes to amend Article
Filed Date: October 21, 2005. Persons unable to file electronically
should submit an original and 14 copies 401 by deleting the following paragraph:
Accession Number: 20051025–0135. ‘‘When operating in a run-of-river
Comment Date: 5 p.m. Eastern Time of the intervention or protest to the
Federal Energy Regulatory Commission, mode, the licensee shall at all times
on Friday, November 11, 2005.
888 First St., NE., Washington, DC maintain the project reservoir at full
Docket Numbers: ER05–1249–001.
20426. pool while acting to minimize the
Applicants: National Grid USA. fluctuation of the reservoir surface
Description: National Grid USA on The filings in the above proceedings elevation by maintaining a discharge
behalf of its subsidiaries, Massachusetts are accessible in the Commission’s from the project so that at any point in
Electric Co et al. submits additional eLibrary system by clicking on the time, flows as measured immediately
information with respect to its July 26, appropriate link in the above list. They downstream from the project tailrace
2005 filing. are also available for review in the approximate the sum of inflows to the
Filed Date: October 21, 2005. Commission’s Public Reference Room in project reservoir.’’
Accession Number: 20051026–0013. Washington, DC. There is an Idaho Power Company proposes to
Comment Date: 5 p.m. Eastern Time eSubscription link on the Web site that replace the deleted paragraph with the
on Friday, November 11, 2005. enables subscribers to receive e-mail following:
Docket Numbers: ER06–61–000. notification when a document is added In operating in a run-of-river mode, the
Applicants: California Independent to a subscribed dockets(s). For licensee shall use a headwater control
System Operator Corporation. assistance with any FERC Online scheme that shall at all times maintain the
Description: California Independent service, please e-mail project reservoir surface elevation at or above
System Operator Corp submits a FERCOnlineSupport@ferc.gov. or call an elevation of 2652.5 feet mean sea level
Metered Subsystem Agreement with the (msl), 1.5 feet below the normal full pool

VerDate Aug<31>2005 18:27 Nov 02, 2005 Jkt 208001 PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 E:\FR\FM\03NON1.SGM 03NON1
Federal Register / Vol. 70, No. 212 / Thursday, November 3, 2005 / Notices 66833

elevation of 2654.0 feet msl, as measured at of the Applicant specified in the k. Description of Filing: Idaho Power
the dam. The intent of the headwater control particular application. Company proposes to amend Article
scheme shall be to ensure that the flows as p. Agency Comments. Federal, state, 401 by deleting the following paragraph:
measured immediately downstream from the
and local agencies are invited to file ‘‘When operating in a run-of-river mode,
project tailrace approximate the flows into
the project reservoir, as well as minimize comments on the described application. the licensee shall at all times maintain the
large tailwater elevation fluctuations that can A copy of the application may be project reservoir at full pool while acting to
occur with trying to maintain a precise obtained by agencies directly from the minimize the fluctuation of the reservoir
headwater elevation. Applicant. If an agency does not file surface elevation by maintaining a discharge
comments within the time specified for from the project so that at any point in time,
l. Locations of Applications: A copy of flows as measured immediately downstream
the application is available for filing comments, it will be presumed to from the project tailrace approximate the sum
inspection and reproduction at the have no comments. One copy of an of inflows to the project reservoir.’’
Commission in the Public Reference agency’s comments must also be sent to
the Applicant’s representatives. Idaho Power proposes to replace the
Room, located at 888 First Street NE., deleted paragraph with the following
Room 2A, Washington, DC 20426, or by q. Comments, protests and
interventions may be filed electronically paragraph:
calling (202) 502–8371. This filing may
via the Internet in lieu of paper. See, 18 ‘‘In operating in a run-of-river mode, the
also be viewed on the Commission’s licensee shall use a headwater control
Web site at http://www.ferc.gov using CFR 385.2001(a)(1)(iii) and the
scheme that shall at all times maintain the
the ‘‘eLibrary’’ link. Enter the docket instructions on the Commission’s Web
project reservoir surface elevation at or above
number excluding the last three digits in site at http://www.ferc.gov under the ‘‘e- an elevation of 2797.0 feet mean sea level
the docket number field to access the Filing’’ link. (msl), one foot feet below the normal full
document. You may also register online Magalie R. Salas, pool elevation of 2798.0 feet msl, as
at http://www.ferc.gov/docs-filing/ measured at the dam. The intent of the
Secretary. headwater control scheme shall be to ensure
esubscription.asp to be notified via e- [FR Doc. E5–6070 Filed 11–2–05; 8:45 am] that the flows as measured immediately
mail of new filings and issuances BILLING CODE 6717–01–P downstream from the project tailrace
related to this or other pending projects. approximate the flows into the project
For assistance, call toll-free 1–866–208– reservoir, as well as minimize large tailwater
3676 or e-mail DEPARTMENT OF ENERGY elevation fluctuations that can occur with
FERCOnlineSupport@ferc.gov. For TTY, trying to maintain a precise headwater
call (202) 502–8659. A copy is also elevation.’’
Federal Energy Regulatory
available for inspection and Commission l. Locations of Applications: A copy of
reproduction at the address in item (h) the application is available for
above. Notice of Application for Amendment inspection and reproduction at the
m. Individuals desiring to be included of License and Soliciting Comments, Commission in the Public Reference
on the Commission’s mailing list should Motions To Intervene, and Protests Room, located at 888 First Street NE.,
so indicate by writing to the Secretary Room 2A, Washington, DC 20426, or by
October 27, 2005.
of the Commission. calling (202) 502–8371. This filing may
n. Comments, Protests, or Motions to Take notice that the following also be viewed on the Commission’s
Intervene. Anyone may submit hydroelectric application has been filed Web site at http://www.ferc.gov using
comments, a protest, or a motion to with the Commission and is available the ‘‘eLibrary’’ link. Enter the docket
intervene in accordance with the for public inspection: number excluding the last three digits in
requirements of Rules of Practice and a. Application Type: Amendment of the docket number field to access the
Procedure, 18 CFR 385.210, .211, .214. license to revise Article 401 of the document. You may also register online
In determining the appropriate action to license. at http://www.ferc.gov/docs-filing/
take, the Commission will consider all b. Project No.: 2061–030. esubscription.asp to be notified via
protests or other comments filed, but c. Date Filed: October 13, 2005. email of new filings and issuances
only those who file a motion to d. Applicant: Idaho Power Company. related to this or other pending projects.
intervene in accordance with the e. Name of Project: Lower Salmon For assistance, call toll-free 1–866–208–
Commission’s Rules may become a Falls Project. 3676 or e-mail
party to the proceeding. Any comments, f. Location: The Project is located on FERCOnlineSupport@ferc.gov. For TTY,
protests, or motions to intervene must the Snake River in Gooding, and Twin call (202) 502–8659. A copy is also
be received on or before the specified Falls Counties in Idaho. The project available for inspection and
comment date for the particular occupies Federal lands managed by the reproduction at the address in item (h)
application. Bureau of Land Management and lands above.
o. Filing and Service of Responsive within the Hagerman Fossil Beds m. Individuals desiring to be included
Documents. Any filings must bear in all National Monument managed by on the Commission’s mailing list should
capital letters the title ‘‘COMMENTS’’, National Park Service. so indicate by writing to the Secretary
‘‘RECOMMENDATIONS FOR TERMS g. Filed Pursuant to: Federal Power of the Commission.
AND CONDITIONS’’, ‘‘PROTEST’’, or Act, 16 U.S.C. 791a–825r. n. Comments, Protests, or Motions to
‘‘MOTION TO INTERVENE’’, as h. Applicant Contact: Nathaniel F. Intervene—Anyone may submit
applicable, and the Project Number of Gardener, Idaho Power Company, P.O. comments, a protest, or a motion to
the particular application to which the Box 70, Boise, Idaho 83707. Tel: (208) intervene in accordance with the
filing refers. All documents (original 388–2550. requirements of Rules of Practice and
and eight copies) should be filed with: i. FERC Contact: Any questions on Procedure, 18 CFR 385.210, .211, .214.
Magalie R. Salas, Secretary, Federal this notice should be addressed to In determining the appropriate action to
Energy Regulatory Commission, 888 Vedula Sarma at (202) 502–6190 or take, the Commission will consider all
First Street, NE., Washington, DC 20426. vedula.sarma@ferc.gov. protests or other comments filed, but
A copy of any motion to intervene must j. Deadline for filing comments and/ only those who file a motion to
also be served upon each representative or motions: November 28, 2005. intervene in accordance with the

VerDate Aug<31>2005 18:27 Nov 02, 2005 Jkt 208001 PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 E:\FR\FM\03NON1.SGM 03NON1