Professional Documents
Culture Documents
PROJECT:
DOCUMENT TITLE:
DOCUMENT No.:
ITS/QA/01
CONTENTS
1.0 INTRODUCTION............................................................................................ 3
2.0 SCOPE......................................................................................................... 3
3.0 PERSONNEL................................................................................................. 3
4.0 METHOD...................................................................................................... 3
5.0 ARRANGEMNT OF ELEMENTS.........................................................................3
6.0 TEMPERATURE CONTROL..............................................................................5
7.0 THERMOCOUPLE........................................................................................... 6
8.0 THERMOCOUPLE POSITION...........................................................................6
9.0 THERMOCOULE COMPENSATION CABLE..........................................................7
10.0
RECORDER................................................................................................ 7
11.0
INSULATION.............................................................................................. 7
12.0
PROCEDURE REQUIREMENTS......................................................................7
13.0
REPORTING............................................................................................... 8
14.0
SAFETY..................................................................................................... 8
15.0
1.0
INTRODUCTION
The purpose of procedure to ensure that post weld heat treatment of piping welds Is
carried out correctly and in accordance with the requirements of the applicable
codes / standards and project specification.
2.0
SCOPE
2.1 This procedure covers the minimum requirement for post weld heat treatment
of weld joints on pip works.
2.2 This general procedure refers to the application of controlled heated bad
encompassing a butt welded joint in pipe to effect a pot weld heat treatment in
accordance with the governing code of practice, specification, or drawing
3.0
PERSONNEL
All technician conduct post weld heat treatment activities have at least 6
months experience in post weld heat treatment and supported by a group of
trained workers.
4.0
METHOD
Electrical resistance heating using modular, flexible ceramic pads, either of
standard rating and dimension or otherwise as maybe be necessary to suit
particular weld geometry.
5.0
ARRANGEMNT OF ELEMENTS
5.1 Horizontal Pipe Work: Pipe to Pipe Butt Weld.
5.1.1 For pipe to pipe butt welds, where the members are equal
thickness, the heating elements shall be applied systematically
about the weld centerline, either as one or more discrete bands.
5.1.2 Each band will comprise pads of equal width, and the same nomina
heating intensity.
5.1.3 The width if the heated band shall not be less than:
Rxt
3
5.3 A limits list of elements arrangements that will satisfy the requirements of
paragraph 5.1, 5.2. It is recognized that the listing provide one solution only
for a given weld geometry, other option being possible, and may be made
relevant in the prevailing circumstances. The listing also provide data for
pipe/pipe butt weld.
5.4 Complex geometry
Special elements and thermocouple arrangement shall be produced for pipe
joint more complex than those shall be defined within paragraph 5.1
5.5 General
5.5.1 Elements shall be securely fixed in contact with the work piece with
soft iron wire, stainless steel banding tape, or mild steel banding
tape to suit the application.
5.5.2 Heating elements shall be thoroughly examined before use in order
to ensure that the element wire is not exposed. Examination to be
made for broken beads in either the pad or leads. Twist lock
connection should also be examined to ensure that the insulation if
sound, and the electrical joint is made.
5.5.3 Where elements are manufactured with cold tails, care should be
taken to avoid trapping the cold tail and power supply cable
between the work piece and the insulation. Element tails should be
adequately supported to avoid undue strain at the element tail
junction and at the bot cold tail junction.
6.0
TEMPERATURE CONTROL
Each circuit heating elements shall be controlled by a contactor. In turn this circuit
shall be controlled by one of the following system:
6.1 Semi-automatic control using a combination of a set point controller and a
percentage time/energy regulator. The set point temperature controller shall
be employed to ensure the correct temperature control during the soaking
period.
6.2 An automatic pre-et program control units to control automatically the heat
treatment throughout the cycle.
6.3 No single control zone will comprise more than three heating elements All
elements in one control circuit shall have the same nominal power density
rating. (wall/m2).
7.0
THERMOCOUPLE
7.1 Thermocouple shall be made for Nickel-Chromium/Nickel-Aluminum wire to
BS1041, Part IV or equivalent.
7.2 Thermocouple shall be attached to the work piece by the direct wire
capacitance discharge method. The gap between to wire/work piece junction
shall not exceed 5mm.
7.3 Care shall be taken to ensure that thermocouple conductor wires do not touch
each other, or metallic components. Away from the hot junction.
7.4 Thermocouple hot junctions shall be protected by the application of a
minimum 5mm of layer temperature putty, applied locally.
7.5 Whenever possible, thermocouple shall not be located under a heating pad;
thermocouple shall be routed between heating pads or out through the
insulation to avoid close contact with the heating pads.
7.6 The thermocouple to compensating lead connections shall be minimum to
0.5m from the heating zone.
7.7 Following each heat treatment, a minimum of 150mm wire measured frm the
hot zone, shall be discarded.
8.0
THERMOCOUPLE POSITION
8.1 The minimum thermocouple position for pipe/pipe welds shall be as detailed in
figure 2. Additional thermocouples shall be fitted as necessary for control
purposes and to confirm ant other temperature requirements peculiar to the
ruling specification.
8.2 A minimum of one thermocouple shall, in any case, be fitted to correspond
with each independent circuit of heating elements. Thermocouple fitted for
control purposes shall be fitted at weld centerline and shall be located as per
figure 2.
9.0
9.2 The copper lead (+ve) shall be connected to the nickel-chromium conductor of
the thermocouple (non-magnetic), and the constantan lead (-ve) shall be
connected to the nickel-chromium conductors (magnetic).
10.0
RECORDER.
10.1 Temperature recorders shall be of the potentionmetric self-compensating
type, calibrated in degrees Celcius with respect to nickel-chromium/nickelaluminum thermocouple, type K.
10.2 Temperature recorders shall be calibrated at interval not exceeding 12
months. The calibrations shall be done by a competent Organization and
recorded and evidence to this effect kept with the instrument. The Calibration
Certificate must show both the as found and as left condition of the
instrument.
10.3 The chart speed shall be set at 50mm/h or other agreed standard ad shall
be checked during calibration. No artificial restriction on pen travel shall be
used.
11.0
INSULATION
11.1Ceramic fiber blanket, 25 or 50mm thick or equivalent material, shall be
provided for insulation. The use of asbestos-type insulating material is not
allowed.
11.2The number of layers maybe adjusted to meet the variation of wall thickness,
pipe diameter, gradient requirements and site conditions.
11.3Wherever possible, pipe and shall be blanked off internally before heat
treatment to limit convection effect.
12.0
PROCEDURE REQUIREMENTS
12.1
REPORTING
13.1 Reporting and recording of results shall be in accordance with relevant
procedures and recorded of PWHT Report (sample of report on page 10)
13.2 The PWHT temperature recorded shall have the following data recorded
on the chart:
- ISO drawing number.
- Line number.
- Joint number.
- Heating, soaking and cooling data.
- Material.
The chart shall be signed off and dated by QC Inspector.
14.0
SAFETY
14.1 All tools and equipment for the task are to be in sate condition and fi for
the purpose. Where possible registration papers and certification are to be
produced.
14.2 Dust masks and safety glasses shall be worn when working with thermal
insulation.
FIGURE 1
Note:
1.
2.
3.
4.
15.0
Reprt No.:
Page
Form: QF-001
Project:
Code/specification:
Chart no:
Date:
of
Item:
Material grade:
Chart speed:
Start time:
Finish time:
EQUIPMENT
Description: MANNING 65 KVA Power Unit, 6 Channel
Recorder No: ChinoEH-100, 12 channels
RESULTS
Unrestricted rate of rise to:
o
C
Soaking temperature:
o
C
Restricted rate of cooling:
o
C per hour
No.
Joint No
C per hour
Soaking time:
Dia. x Thk
Hours
Unrestricted rate of Fall to:
o
C
TC No
Sketch of thermocouple
Technician
Date:
Name:
Signature:
Client
Date:
Name:
Signature:
Client
Date:
Name:
Signature:
Cert. Authority
Date:
Name:
Signature:
10