You are on page 1of 5

NEC Engineering and Construction Contract - Wikipedia, the free enc...

https://en.wikipedia.org/wiki/NEC_Engineering_and_Construction_Co...

NEC Engineering and Construction Contract


From Wikipedia, the free encyclopedia

The New Engineering Contract (NEC), or NEC Engineering and Construction Contract, is a
formalised system created by the Institution of Civil Engineers that guides the drafting of documents on civil
engineering and construction projects for the purpose of obtaining tenders, awarding and administering
contracts.[1][2] As such they legally define the responsibilities and duties of Employers (who commission
work) and Contractors (who carry out work) in the Works Information. The contract consists of two key
parts the Contract Data part one (Data provided by the Employer) and Contract Data part two (Data
provided by the Contractor). Several approaches are included making it a family of options. It is used in the
UK and internationally in countries including New Zealand, Australia, Hong Kong and South Africa.[3]
There have been three editions, the first in 1993, the second in 1995, and the most recent in 2005.[4] The
June 2005 edition of the NEC3 was amended in June 2006, and again in April 2013.

Contents
1 Characteristics
2 Options
3 History
4 Comparison
5 Guidance Notes and Further Information
6 Footnotes
7 External links

Characteristics
The NEC is a family of standard contracts, each of which has these characteristics:
Its use stimulates good management of the relationship between the two parties to the contract and,
hence, of the work included in the contract.
It can be used in a wide variety of commercial situations, for a wide variety of types of work and in
any location.
It is a clear and simple document - using language and a structure which are straightforward and easily
understood.
The NEC3 complies fully with the Achieving Excellence in Construction (http://www.ogc.gov.uk
/guidance_achieving_excellence_in_construction.asp) (AEC) principles. The Efficiency & Reform Group of
The UK Cabinet Office recommends the use of NEC3 by public sector construction procurers on their
construction projects.

Options
The NEC contracts now form a suite of contracts, with NEC being the brand name for the "umbrella" of
contracts. When it was first launched in 1993, it was simply the "New Engineering Contract". This specific
contract has been renamed the "Engineering and Construction Contract" which is the main contract used for
any construction based project. It now sits alongside a number of other contracts that together should mean

1 of 5

25/10/2015 10:17 AM

NEC Engineering and Construction Contract - Wikipedia, the free enc...

https://en.wikipedia.org/wiki/NEC_Engineering_and_Construction_Co...

that the NEC suite is suitable for what ever stage of a lifecycle the project is at and for any party within a
project. The contracts available within the suite are:
Engineering and Construction Contract (ECC):
Suitable for any construction based contract between an Employer and a Contractor. It is intended to be
suitable for any sector of the industry, including civil, building, nuclear, oil & gas, etc. Within the ECC
contract there are six family level options of which the Employer will choose what he deems to be the most
suitable and give him the best option/value for money on that project:
Option A: Priced contract with activity schedule
Option B: Priced contract with bill of quantities
Option C: Target contract with activity schedule
Option D: Target contract with bill of quantities
Option E: Cost-reimbursable contract
Option F: Management contract
These options offer a framework for tender and contract clauses that differ primarily in regard to the
mechanisms by which the contractor is paid and how risk is allocated/motivated to control costs.
The core clauses (of the main option listed above) are used in conjunction with the secondary options and
the additional conditions of contract. The Efficiency and Reform group of The Cabinet Office in the UK
(formerly the OGC) has published generic public sector Z-clauses for the use with NEC3 contracts
(http://www.ogc.gov.uk/documents/PublicSectorZClausesForUseWithNEC3Contracts.pdf).
The clauses of these options have been be adapted for simpler less risky work (short contracts), for use as
subcontracts, and for professional services such as design as below.
The Engineering and Construction Subcontract Contract (ECS)
Very similar in detail and complexity of contractual requirements to the ECC contract above, but allows the
contractor to sub-let the project to a subcontractor imposing most of the clauses that he has within his
headline contract. There is very little difference between the ECC and the ECS, other than the names of the
parties are changed (contractor and subcontractor)and some of the timescales for contractual responses are
altered to take into account the timescales required in the ECC contract.
The Engineering and Construction Short Contract (ECSC)
This is an abbreviated version of the ECC contract and most suitable when the contract is considered "low
risk" (not necessarily low value) on a project with little change expected. This contract is still between the
employer and contractor but does not use all of the processes of the ECC making it simpler and easier to
manage and administer.
The Engineering and Construction Short Subcontract (ECSS)
Allows the contractor to sub-let a simpler lower risk contract down the line to a subcontractor. It is
back-to-back with the ECSC but is frequently used as subcontract when the main contract is under the ECS.
The Professional Services Contract (PSC)
This contract is for anyone providing a service, rather than doing any physical construction works.
Designers are the most obvious party that fit into this category. Whilst they are producing a design for an
employer or contractor, they would sign up and follow the clauses within the PSC. Most of the clauses
within this contract are the same or similar to those in the main ECC contract, so that all contractors,
designers and subcontractors have pretty much the same obligations and processes to follow as each other.

2 of 5

25/10/2015 10:17 AM

NEC Engineering and Construction Contract - Wikipedia, the free enc...

https://en.wikipedia.org/wiki/NEC_Engineering_and_Construction_Co...

The Professional Services Short Contract (PSSC)


This was added to the family in April 2013 and was co-developed with the Association for Project
Management. It is for simpler less complex assignments than the PSC, such as the appointment of small
team for managing an ECC contract on the Employer's behalf. E.g. the Project Manager and Supervisor. It is
frequently used as a subcontract to the PSC for design work.
Framework Contract (FC)
Parties enter into a "framework" of which work packages will then be let during the life of that framework.
Any individual projects will then be awarded using one of the other contracts within the suite, meaning that
the parties follow the headline clauses within the framework contract (which is a fairly slim contract) and
then the individual clauses within the chosen contract for that package. Different work packages can be let
using different contracts during the life of the framework.
Term Service Contract (TSC)
For parties on a project that is operational or maintenance based, e.g. maintaining highway signage, where
the contract is to ensure that a certain standard is maintained. This contract is not generally used for
constructing new works, but can include some amount of betterment. There is also a "Term Service Short
Contract" where the project is a relatively low risk project and/or the work is primarily re-active. It is an
abbreviated version of the main TSC.
Supply Contract/Short Supply Contract (SC/SSC)
These contracts were launched in 2010. This is for a supplier of supplies or goods to a project, and puts extra
contractual requirements on them during their procurement/manufacture period. The Supply Contract is for
big bespoke items i.e. designed and manufactured specifically for that contract, with the Short Supply
Contract potentially being for more run of the mill / commoditised items on a project. Neither of these
contracts cover working on a Site. I.e. as written they are not 'supply and install' contracts.
Adjudicator's Contract (AC)
If there is a dispute between the parties on a project then the Adjudicator will follow the clauses within this
contract in order to come to a decision.
Guidance Notes and Flowcharts
For each of the different contracts listed above each comes with its own set of guidance notes and flowcharts
which should aid understanding of the intent of the drafted clauses. The guidance notes expand on each
clause to give extra substance and intent of the original drafters as to how a clause should be understood and
interpreted. The flowcharts then map out each of the main processes within each contract and demonstrate
how it should operate and what to do next if a party has or has not carried out the next contractual action.

History
Originally contracts in the civil engineering and construction industries were bespoke and drafted by
Chancery pleaders using their knowledge of leases rather than building processes. In 1879, Royal Institute of
British Architects for construction projects created RIBA forms which lead to the Joint Contracts Tribunal,
JCT forms. For civil engineering the need for a formalized approach to contracts led the Institution of Civil
Engineers to produce the ICE formalized set of conditions of contract. In 1986, the ICE commissioned the
development of a new form of contract as it was felt that there was a need for a form that had clearer
language, clearer allocation of responsibilities and reduced opportunities for contractual gamesmanship. In
1991, this resulted in a consultative form of the New Engineering Contract form of contract. The first edition

3 of 5

25/10/2015 10:17 AM

NEC Engineering and Construction Contract - Wikipedia, the free enc...

https://en.wikipedia.org/wiki/NEC_Engineering_and_Construction_Co...

was published in 1993.[5] Wider use of the NEC was recommended by the Latham Report in 1994.

Comparison
The following demonstrates the differing approaches to drafting in the NEC and ICE forms of contract using
the illustration of circumstances when the contractor is entitled to additional time and cost for physical
conditions.
NEC Engineering and Construction Contract Second Edition Clause 60.1 (12)
The Contractor encounters physical conditions which
are within the site.
are not weather conditions and
which an experienced contractor would have judged at the Contract Date to have such a small chance
of occurring that it would have been unreasonable for him to have allowed for them.
ICE Conditions of Contract Sixth Edition Clause 12(1)
If during the execution of the Works the Contractor shall encounter physical conditions (other
than weather conditions or conditions due to weather conditions) or artificial obstructions which
conditions or obstructions could not in his opinion reasonably have been foreseen by an
experienced contractor the Contractor shall as early as practicable give written notice thereof to
the Engineer.

Guidance Notes and Further Information


Guidance Notes and Flow Charts are published by the ICE. These notes are supplemented by the Frequently
Asked Questions sections of the NEC website.[6] Prospective users of the NEC3 contract are encouraged to
study the FAQ's in order to avoid unintended contract provisions. The often unintended Option C scenario
where a Contractor is paid monies in excess of the Target Cost plus maximum share provisions is
specifically not addressed in the guidance notes / Frequently Asked Questions. Other common
misinterpretations are minutes of meetings as communications (http://www.neccontract.com
/FAQs/faq_detail.asp?ID=117&FAQCat=1&FAQSubCat=&Keyword=), deleted work
(http://www.neccontract.com/FAQs/faq_detail.asp?ID=53&FAQCat=1&FAQSubCat=&Keyword=) and
paying for correcting defects (http://www.neccontract.com/FAQs/faq_detail.asp?ID=60&FAQCat=1&
FAQSubCat=&Keyword=). Employers often utilise the additional conditions of contract (Z-clauses) to
amend or delete contract provisions relating to these items.

Footnotes
1. R Gerard (2005). Relational contractsNEC in
perspective (http://www.leanconstruction.org
/lcj/V2_N1/LCJ_05_006.pdf). Lean Construction
Journal, 2, 80-86.
2. Brook M. (2004). Estimating and Tendering for
Construction Work Butterworth-Heinemann ISBN
978-0-7506-5864-5

4 of 5

3. Patterson R (2007) Introducing NEC Wellington


Seminar (http://www.neccontract.com/documents
/events
/Introducing%20NEC%20-%20R%20Patterson.pdf)
4. NEC (2005) NEC3 Engineering and Construction
Contract Thomas Telford Ltd ISBN
978-0-7277-3359-7

25/10/2015 10:17 AM

NEC Engineering and Construction Contract - Wikipedia, the free enc...

5. Broome JC, Hayes RW. (1997). A comparison of


the clarity of traditional construction contracts and
of the New Engineering Contract. International
Journal of Project Management, 15, 255-261.
doi:10.1016/S0263-7863(96)00078-6

https://en.wikipedia.org/wiki/NEC_Engineering_and_Construction_Co...

(https://dx.doi.org
/10.1016%2FS0263-7863%2896%2900078-6)
6. www.neccontract.com (http://www.neccontract.com
/FAQs/index.asp)

External links
NEC Engineering and Construction Contract website (http://www.neccontract.com/)
Free independent NEC helpdesk (http://www.reachback.builtintelligence.com/nec3)
Retrieved from "https://en.wikipedia.org
/w/index.php?title=NEC_Engineering_and_Construction_Contract&oldid=683646788"
Categories: Building engineering Construction documents Law in the United Kingdom
Legal documents Project management
This page was last modified on 1 October 2015, at 16:35.
Text is available under the Creative Commons Attribution-ShareAlike License; additional terms may
apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia is a registered
trademark of the Wikimedia Foundation, Inc., a non-profit organization.

5 of 5

25/10/2015 10:17 AM

You might also like