cocena

June month Quotation for civil works


Sl
no
1.

Description of works.

Rate
Rs. p

Earth work:
a) Earth work excavation for all kinds of loose soils upto 500depth.
b) Same as above 500depth.
c) Excavation in column pits upto 500depth.
d) Same as above 500depth.
e) Earth work excavation in hard strata using chisel and hammer.

6.50
7.00
7.00
7.50
11.50

2.

a) filling with basement and foundation using excavated earth


consolidation ramming complete.

4.50

b) filling with basement and foundation using quarry dust or gravel sand 14.00
consolidation ramming complete.
3.

Plain cement concrete using 11/2 blue metal for foundation base
including leveling and ramming complete.

90.00

4.

Plain cement concrete using 1 blue metal for flooring 4 thick.

55.00

5.

R.R. Masonry using hammer dressed in foundation.

95.00

6.

R.C.C. works including centering, and laying of concrete roof height


upto 1000.
65.00
a) Sill concrete upto 4thick.

b) Plinth beams.

230.00

c) Lintels.

275.00

d) Sunshades.
e) One way slab

155.00
270.00
270.00

f) Two way slabs.


275.00
g) Beams.
275.00
h) Columns.
185.00
i) Column footing.
7.

72.00
Precaste slab casting , laying and finishing.

8.

Brick work for super structure including leading and scaffolding


complete.
87.00
a) For 4 1/2 tk. Wall.
143.00
b) For 9 tk. Wall.
145.00
c) For 131/2 tk. Wall.

9. Damp proof course 20mm tk. Including finishing.


10.
Wall plastering with sponge finishing including scaffolding and sand
sieving complete.
a) Plastering for walls inside.

27.50

23.50

b) Plastering with smooth finish .


26.00

c) Out side plastering.

25.50

d) Plastering for celing.

27.50

e) R.C. vertical surface and beams.

30.00

11. Hacking for ceiling using metal rods.

1.00

12. Border work including scaffolding


a) Rain water border.

35.00

13. Weathering course with lime surki concrete for an average tk.3
including chipping beating.

33.00

14. Weathering course top plastering

27.00

15. Weathering course top tiles laying and pointing including tiles.
47.00
16. Weathering tiles skirting laying and pointing including wall cutting.
37.00
17. Haunch finishing in parapet wall corner.

25.00

18. Lath plastering using chicken mesh with both side finishes.

80.00

19. Fixing of wooden doors, ventilators and windows.

250.00

20. Brick on edge work.

35.00

21. Surki concrete in toilet diperession.

50.00

23. Construction of manhole chambers including earth work,P.C.C.,brick


work and plastering with slurry finish upto16depth.
24

1800.00
Fabrication of reinforcement cutting bending laying and tying in position 51.00

te;
1. The above rates are excluding elevation and decorative works.
2. lifting charges 10% extra in each floor.
3. The rate will be valid for one year only.
4. Debries removal will be extra as per actual.
5. Water and electricity supplied by client.
6. All tools and accessories will be supplied by contractor.
7. Work will be done as per the customer satisfaction.
8. Once the work is started it will not be withhold for any petty reasons.
9. All designing and drawing will be supplied by the engineer.
10. Work supervision will be arranged by the contractor and will supervise the work
continuously and regularly.
16. All the above rates are excluding Service tax,and Sales tax,.
(Any government tax Extra.)
Basic rate of materials
5% rate increase is allowed ,cost difference above 5% will be settled by client as
per actuals.
River sand:
jelly
.1 metal
Bricks
Cement
Steel

Rs :3300/- 100 cft.


Rs :2500/- 100 cft
Rs :2200/-100 cft
Rs :16000/- 3000 nos.
Rs:310/- 1Bag
Rs: 45.00/- Kg