Professional Documents
Culture Documents
EXERCISE 1
SIMULATING POWER SYSTEM RESPONSE FOR POWER SYSTEM
STABILITY ANALYSIS
1.1
LEARNING OUTCOMES
1.2
ACTIVITIES
As power system engineers, you are required by power system planner to assess
the rotor angles stability of each machine for the system and the location of fault
shown in Figure 1. In order to do that, you are required to simulate the dynamic
responses of the system following disturbances in the system. The details of the
system are described in the following section. The software that your company
provides for the task is MATLAB R2013B [1] [2].
1.3
SYSTEM DESCRIPTIONS
The system consists of two similar areas connected by a weak tie [3]. Each area
consists of two coupled unit, each having a rating of 900 MVA and 20 kV. The
generator parameters in per unit on the rated MVA and kV base are as follows:
X d =1.8 ,
X q =1.7 ,
X l =0.2 ,
X ' d =0.3 ,
Ra=0.0025 ,
T ' d 0=8.0 s ,
A SAT =0.015 ,
B SAT =9.6 ,
H=6.175(G 3 and G 4 ) ,
X ' q =0.55 ,
T ' q 0=0.4 s ,
T 1=0.9 ,
H=6.5(G1 and G 2) ,
K D =0
Each step-up transformer has an impedance of 0+j0.15 per unit on 900 MVA and
20/230 kV base, and has an off-nominal ratio of 1.0.
The transmission system nominal voltage is 230 kV. The line lengths are identified in
Figure 1.1. The parameters of the lines in per unit on 100 MVA, 230 kV are:
bC =0.00175 pu /km
The system operating with area 1 exporting 400 MW to area 2, and the generating
units are loaded as follows:
Table 1.1 Generator loading conditions
Generator
G1
Voltage (V)
1.0320.2
G2
700 MW
235 MVar
1.01 10.5
G3
719 MW
176 MVar
1.03 6.8
G4
700 MW
202 MVar
1.0117.0
The load ( PL
Resistive load (
Inductive load (
PL )
7
9
1.4
967 MW
1767 MW
Capacitive load (
QL )
100 MVar
100 MVar
QC )
200 MVar
350 MVar
INSTRUCTIONS
Form a team to complete the project. The task needs to be completed within three
(3) weeks. Your team is required to present your progress each week. At the end of
this project, your team needs to present the outcomes and produce an extensive
report on with the following details:
1) Introduction of the study (background, scope, objectives, and literature
review).
2) The method used to model the system using the software.
4
3) The plot of rotor angles, rotor speeds, electrical power of each machine for at
least 5 different fault clearing times ranging from stable cases to unstable
cases to demonstrate the change of dynamic responses of each machine.
4) The discussions and the analysis of the results in the context of the rotor
angle stability of the system.
5) Conclusions.
6) References.
1.5
REFERENCES
[1] Transnergie Technologies Inc., "SimPowerSystems: For Use with Simulink,"
The MathWorks, Inc., Massachusetts, 2003.
[2] R. D. Zimmerman and C. E. Murillo-Sanchez, "Matpower 5.1: Users
Manual," Power Systems Engineering Research Center (PSERC), New York,
2015.
[3] P. Kundur, "Power System Stability and Control," McGraw-Hill Education, New
York, 1994.
EXERCISE 2
DESIGN PROJECT USING FINITE ELEMENT METHOD
MAGNETICS
EXERCISE 2
DESIGN PROJECT USING FINITE ELEMENT METHOD MAGNETICS
2.1
LEARNING OUTCOME
2.2
INTRODUCTION
Finite Element Method Magnetics (FEMM) is a suite of programs for solving low
frequency electromagnetic problems on two-dimensional planar and axis-symmetric
domains.
The
program
currently
addresses
linear/non-linear
magnetostatic
2.3
ACTIVITIES
2.3.1
2.3.1.1
Create Model
2.3.1.2
Select Properties|Materials on the main menu. Change the name of the property
from New Material to air.
2.3.1.3
inside the closed region between the outer surface of the conducting sphere and the
arc representing the exterior boundary.
Right click on the block label node and press space to open the selected block
label. Set the Block type to Air. Uncheck the Let Triangle chooses Mesh Size
checkbox and enter 0.025 for the Mesh size.
2.3.1.4
Select Properties|Conductors and then click on the Add Property button. Replace
the name New Conductory with Ground. Select the Prescribed Voltage radio
button. Enter a 0 as the value in the associated edit box and hit OK.
Repeat the above process but instead name the new boundary condition 1000V
and apply enter a prescribed voltage value of 1000.
Select arc from the toolbar then right click on the each of the two segments
belonging to the sphere. When a segment turns red, you have selected it. Now press
space bar and the Segment Properties window will appear. From the In
Conductor drop box, change the selection from <None> to Ground. Repeat this
process for the other sphere, but set the conductor type to 1000V.
For exterior boundary, select Properties|Boundary. Click the Add Property and
name it as open_bc and change the BC Type to Mixed. In the edit box for the c 0
coefficient (the c1 coefficient should be zero). Select the arc representing the exterior
boundary by right clicking on or near it (the Arc toolbar button must also be
depressed). Press space and assign the boundary condition to be open_bc.
Switching to Segment mode, assign the zero boundary condition to the line of
symmetry at z=0. In Block Mode, select the block label inside the domain by right
clicking with the mouse near the green node. Change the Block type to Air and the
Mesh size to 1.
2.3.1.5
Now save the file and click on the toolbar button with yellow mesh
to generate a
triangular mesh for your problem. Then click on the turn the crank button
to
2.3.1.6
Display Results
2.3.1.7
Post-Processing
dialog.
10
11
2.3.1.8
2.3.1.9
1)
Questions
Calculate the error of the maximum electric field, Emax between simulation and
calculation values, given the formula for calculating Emax for sphere gap is
given as:
Emax
x
a+ )
(
2
V
=0.9
x
Where,
V
2)
Using Emax values from simulation, calculate the field utilization factor, for
both gap lengths using this formula:
=
3)
E average
E max ;
where
Eaverage =
V
x
The field utilization factor, implies the degree of uniformity of the electrode
configuration, i.e. higher provides a more uniform electric field. Relate this
statement to your exercise.
4)
12
2.3.2
2.3.2.1
Create Model
2.3.2.2
, assign the material property for the C-I core which is M50
13
2.3.2.3
, select the region of the right side of the coil and press space bar. In
the property dialog, set Block type as 10 AWG, set In Circuit as the name defined in
Part 4, set Number of Turns as 500, and click OK.
To assign material for the left side of the coil, repeat Part 5, only this time set
Number of Turns as 500.
Create an exterior boundary and assign its open boundary condition (Hint: use
2*eo/R formula). Please ensure that the model sits at the center of this region.
Save your file and run the mesh generator as well as the solver.
2.3.2.4
Post-Processing
from the menu, and select Force via Weighted Stress Sensor.
Repeat the above procedures for different value of current (25 A, 75 A, and 100 A)
and sketch a graph for flux density versus current.
14
2.3.2.5
Questions
1)
2)
3)
Why does the area in Q2 have the highest field intensity (H)?
4)
If the average flux density in the core is taken as 2.0 T, calculate the
permeability (r) of the core
15
2.3.4
2.3.4.1
2.3.4.2
2.3.4.3
Now click on
. Place a block label in the coil region, and place one in the air
2.3.4.4
Select Properties|Materials Library off of the main menu. The drag-and-drop Air and
18 AWG into Model Materials. Click on OK.
16
2.3.4.5
Select Properties|Circuits off of the main menu. Name circuit by replacing the new
circuit name with Coil. Select the Series radio button. Enter 1 as the Circuit Current.
2.3.4.6
2.3.4.7
2.3.4.9
2.3.4.10
Questions
1)
2)
3)
4)
17
EXERCISE 3
MODELING OF ELECTRICAL PLAN DRAWING AND SINGLE
LINE DIAGRAM USING AUTOCAD SOFTWARE
18
EXERCISE 3
MODELING OF ELECTRICAL PLAN DRAWING AND SINGLE LINE
DIAGRAM USING AUTOCAD SOFTWARE
3.1
LEARNING OUTCOMES
3.2
ACTIVITIES
As power system engineers, you are required by power system planner to draw a
complete electrical plan drawing and single line diagram starting from the supply to
the end user for a new house floor plan as shown in Figure 3.1. The software that
your company provides for the task is AUTOCAD 2010 [1].
3.3
SYSTEM DESCRIPTIONS
The house floor plan layout consists of one bedroom, toilet, dining hall, kitchen, living
hall, reading room, hall, and porch. The electrical plan drawing should consist at
least the following electrical components:
1)
2)
3)
4)
5)
6)
7)
8)
9)
10)
11)
12)
13)
20
21
3.4
INSTRUCTIONS
Form a team to complete the project. The task needs to be completed within three
(3) weeks. Your team is required to present your progress each week. At the end of
22
this project, your team needs to present the outcomes and produce an extensive
report on with the following details:
1) Introduction of the study (background, scope, objectives, and literature
review).
2) The method used to model the electrical plan drawing and single line diagram
using the software.
3) The electrical plan drawing complete with its legend.
4) The single line diagram complete with its calculation of the total maximum
current of the entire installation and total current estimate for the entire
installation starting from the supply to the end user. Students should consider
the diversity factor in the calculation. Please show the size of consumer unit,
main switch, residual current circuit breaker (RCCB) and the main cables
used in the design.
5) The discussions and the analysis of the results in the context of how they
determine the suitability of the electrical appliances location, explanation on
the use of legend in the electrical layout drawing, how they determine the
calculation in the single line diagram, the advantages of using schematic
diagrams before wiring work is done and also explanation on the advantages
of using AutoCAD software in making the layout of the wiring accessories and
the single line diagram.
6) Conclusions.
7) References.
REFERENCES
[1]
23