You are on page 1of 17

menu

Try Critical Path in Smartsheet (/try-it?lpv=stkcta&trp=8514)

In any given project, you may have hundreds of tasks and dozens of dependencies. It can feel almost impossible to identify the most important tasks; the ones
that, if missed, will impact your whole project. In other words, the ones you really need to worry about to make sure you meet your deadlines.
The critical path method, a project management technique created in the 1950s, allows you to identify these important tasks and stay on track throughout your
project. Starting as hand-drawn diagrams and evolving into automated software, the critical path method has become an essential part of planning a project.
Share
(http://www.facebook.com/sharer.php?u=https%3A%2F%2Fwww.smartsheet.com%2Fcritical-path-method)
url=https%3A%2F%2Fwww.smartsheet.com%2Fcritical-path-method&text=&hashtags=smartsheet)
url=https%3A%2F%2Fwww.smartsheet.com%2Fcritical-path-method)

(http://twitter.com/share?

(https://plus.google.com/share?

(http://www.linkedin.com/shareArticle?

mini=true&url=https%3A%2F%2Fwww.smartsheet.com%2Fcritical-path-method)
(mailto:?
Subject=The%20Ultimate%20Guide%20to%20the%20Critical%20Path%20Method%20&Body=https%3A%2F%2Fwww.smartsheet.com%2Fcritical-path-method)

What Is the Critical Path Method (CPM)?

The Project Management Body of Knowledge (PMBOK), an internationally recognized collection of processes and knowledge areas accepted as best practice for
the project management profession, denes the critical path as the sequence of scheduled activities that determines the duration of the project. It is the longest
sequence of tasks in a project plan that must be completed on time in order for the project to meet its deadline. If there is a delay in any task on the critical path,
then your whole project will be delayed. Although many projects have only one critical path, some projects may have multiple critical paths.
The critical path method is a step-by-step project management technique to identify activities on the critical path. It is an approach to project scheduling that
breaks the project into several work tasks, displays them in a ow chart, and then calculates the project duration based on estimated durations for each task. It
identies tasks that are critical, time-wise, in completing the project.

Dr. Larry Bennett (https://www.linkedin.com/pub/f-lawrence-bennett/5b/521/b99), a civil engineer, project manager, and author of four books, including a guide on
critical path written in 1978 and titled, Critical Path Precedence Networks (http://www.amazon.com/Critical-Precedence-Networks-LawrenceBennett/dp/0442121903/ref=la_B001HMQP5Y_1_3?s=books&ie=UTF8&qid=1434480925&sr=1-3), explains that the critical path method helps manage projects in
two different ways: It produces a planned schedule to guide the project team, and it forms the basis for tracking project schedule performance by comparing
actual with planned task progress.

The Critical Path Method According to Two Experts


We asked two critical path users for the best way to explain it. Here's what they had to say:

"The critical path is just a fancy way of saying 'How long does each task take before you can nish the project? Use this information to gure out the project's end
date.'If a task takes longer than anticipated, the end date is pushed back. There are some tasks that don't immediately impact the project's end date that can be
pushed back for some time. There are a whole bunch of calculations that go into guring out what-ifs, forecasting, and scheduling, but that's where project
management software comes in and makes everyone's lives easier. "
Rachel Burger (https://www.linkedin.com/in/rachelmwburger), Capterra Construction
Twitter:@CapterraBuilder (https://twitter.com/CapterraBuilder)

"Some of the activities must happen in parallel.For example, if you tried to make a fried breakfast by doing one task at a time, and one after the other, things would
go wrong. The plates need to be warming while other activities are going on. The toast needs to be toasting while the sausages are frying, and at the same time
the bacon and sausages are under the grill. The eggs need to be fried last. A critical path analysis is a diagrammatical representation of what needs to be done
and when. Timescales and costs can be applied to each activity and resource."
Terence Jackson (https://www.linkedin.com/pub/terence-jackson-ph-d/10/184/576), Ph.D and CEO/Managing Partner at WEpiphany LLC

Background & History of Critical Path


Using the Critical Path Method for Project Management

Dr. Bennett is no stranger to critical path. He has applied critical path scheduling to a wide variety of projects since 1965. He has also spent 29 years on the
engineering faculty at the University of Alaska Fairbanks, teaching undergraduate and graduate courses in technical management, including project management
and scheduling.
In addition to hisbooks (http://www.amazon.com/F.-Lawrence-Bennett/e/B001HMQP5Y), he has written more than 50 professional papers and articles on topics
ranging from construction management to network techniques for project scheduling.
Dr. Bennett points out that critical path has come a long way. In fact, the original critical path method was done by hand. As Dr. Bennett describes it:

The original critical path method used arrows to represent tasks and tied them together by connecting their beginning and end at nodes, so that proper
sequencing was developed. This approach persisted for a decade, when a different method, with the same results, became popular.Professor John W. Fondahl, a
professor of construction management at Stanford University, proposed in a 1961 paper that each task be represented by a node square, circle, or oval and the
nodes be tied together with lines or arrows representing the sequence between tasks. This approach, referred to as the activity-on-node (AON) or precedence
method, caught on rapidly and has supplanted the earlier activity-on-arrow (AOA) method in nearly all uses.

How the Critical Path Method Was Created


Using the critical path method to schedule projects began in the late 1950s, with two simultaneous, unrelated projects. The US Navys Fleet Ballistic Missile
(Polaris) Program was behind schedule and needed help resolving the problem. The suggested solution was to divide the project into several thousand tasks,
represent each task by an arrow, connect the arrows in proper sequence, estimate the duration of each task, and calculate the project duration and the degree of
schedule criticality of each task.
At about the same time, the EI DuPont de Nemours Company, an American chemical company, was experiencing delays in its plant turnarounds, a project to
rearrange production facilities for different products. They, too, needed help and the proposed answer was similar to that of the Polaris Program.
The developers of the Polaris Programs approach called their solution the Project Evaluation and Review Technique (PERT), while the DuPont method was called
Critical Path Method (CPM). Although these methods are similar, they used different techniques for estimating task duration.
The PERT method used three different time estimations for each task duration and calculated the probability of project completion by any given time. The DuPont
approach used one time duration for each task; it was concerned not only with project completion time, but also with analyzing the extra costs that would accrue if
the project duration were decreased.
Dr. Bennett says that today, the terms PERT and CPM are used interchangeably, both meaning any network scheduling method and PERT having lost its inclusion
of three time estimates and probabilities.

The Everyday Advantages of Critical Path


Although it originated in the late 1950s, critical path is still incredibly important to project managers today. It provides a visual representation of project activities,
clearly presents the time required to complete tasks, and tracks activities so you dont fall behind. The critical path method also reduces uncertainty because you
must calculate the shortest and longest time of completion of each activity. This forces you to consider unexpected factors that may impact your tasks and reduces
the likelihood that an unexpected surprise will occur during your project.
According to Dr. Bennett, the critical path method also has three main benets for project managers:
Identies the Most Important Tasks: First, it clearly identies the tasks that you will have to closely manage. If any of the tasks on the critical path take more time
than their estimated durations, start later than planned, or nish later than planned, then your whole project will be affected.
Helps Reduce Timelines: Secondly, if, after the initial analysis predicts a completion time, there is interest in completing the project in a shorter time frame, it is
clear which task or tasks are candidates for duration reduction, said Dr. Bennett.When the results from a critical path method are displayed as a bar chart, like a
Gantt chart, it is easy to see where the tasks fall in the overall timeframe. You can visualize the critical path activities (they are usually highlighted), as well as task
durations and their sequences. This provides a new level of insight into your projects timeline, giving you more understanding about which task durations you can
modify, and which must stay the same.
Compares Planned with Actual: And lastly, Dr. Bennett says the critical path method can also be used to compare planned progress with actual progress.As the
project proceeds, the baseline schedule developed from the initial critical path analysis can be used to track schedule progress. Throughout a project, a manager
can identify tasks that have already been completed, the predicted remaining durations for in-progress tasks, and any planned changes to future task sequences
and durations. The result will be an updated schedule, which, when displayed against the original baseline, will provide a visual means of comparing planned with
actual progress.

Experts Share the #1 Advantage of Critical Path

"For me, the biggest advantage of the critical path method is that it makes risk assessment easy. If Ive got dependencies laid out and plans change, its very easy
to say, 'Because you missed that deadline, the next deliverable is going to be late by X days, and that puts us beyond our plan by Y days.'Simple. That said, I dont
think you have to fully adopt a method like critical path to do this on projects. Its best to adopt the parts of any method that work for your project and your team
being adaptable as a PM will help you nd true success."
Brett Harned,digital project management consultant (http://brettharned.com/), writer, speaker, and community builder.
Twitter:@BrettHarned (https://twitter.com/brettharned)

"Two issues that continue to plague projects are the competing priorities of cross functional team members and distractions from 'noise' on the project. With so
much activity, the critical path enables a clear, pointed view of what must happen next and 'who is on the clock' for meeting project commitments."
Robert Kelly, co-founder of@PMChat (https://twitter.com/PMChat)and managing partner ofKelly Solutions (http://kellyprojectsolutions.com/), a project management
rm.
Twitter:@rkelly976 (https://twitter.com/rkelly976)

"I especially like the 'unintended benets'critical path (CP) analysis brings, including discoveries of hidden dependencies and resource conicts.CP analysis also
often leads to better prioritization and redistribution of team-members. And CP can expose the needs / opportunities for inserting lags / leads to further improve
the schedule."
Jeff Furman, PMP, author of"The Project Management Answer Book" (http://www.amazon.com/Project-Management-Answer-BookSecond/dp/1567264468/ref=sr_1_2?ie=UTF8&qid=1417492519&sr=8-2&keywords=JEFF+FURMAN)
Twitter:@PMAnswerBook (https://twitter.com/pmanswerbook)

Product

"The critical path method brings an important level of clarity to your project. It is a visual depiction of the fragility of the balance of your constraints: If one of the
activities on the path gets delayed,
your project gets delayed. It is also a great way to determine where to invest resources if the project has fallen behind
Solutions
schedule."
Enterprise

Cesar Abeid,host of the Project Management for the Masses Podcast (http://pmforthemasses.com/)
Twitter:@PM4TM (https://twitter.com/pm4tm)

Key Steps in the Critical Path Method

Customers
(https://www.smartsheet.com/customers)

There are six steps in the critical path method:

Step 1: Specify Each Activity


Support

Using the work breakdown structure, you need to identify each activity (or task) involved in the project. This activity specication list should only include higherPricingare
(https://www.smartsheet.com/pricing)
level activities. When detailed activities
used, the critical path analysis may become too complex to manage and maintain.

Company

Contact Us (https://www.smartsheet.com/contact)
or call +1 (844) 324-2360 (tel:1-844-324-2360)

A work breakdown structure breaks down projects into manageable sections.


The rst step is to identify the main deliverables of a project. Then you can start breaking down the high-level activities into smaller chunks of work.
You can choose how to display your work breakdown structure. Some people use a tree structure, while others use lists or tables. An outline is one of the easiest
ways to represent a work breakdown structure.

Step 2: Establish Dependencies (Activity Sequence)


Some activities will depend on the completion of others. Listing the immediate predecessors of each activity will help you identify the correct order. To correctly
identify activities and their precedence, ask yourself these three questions for each activity on your list from step one:
Which task should take place before this task happens?
Which tasks should be nished at the same time as this task?
Which tasks should happen right after this task?

Step 3: Draw the Network Diagram

Once youhave identied the activities and their dependencies, you can draw the critical path analysis chart (CPA), known as the network diagram. The network
diagram is a visual representation of the order of your activities based on dependencies.
This critical path diagram used to be drawn by-hand, but there are now software programs that can create this diagram for you.

Step 4: Estimate Activity Completion Time


Using past experience or the knowledge of an experienced team member, you must now estimate the time required to complete each activity. If you are managing
a smaller project, you will most likely estimate time in days. If you are working with a complex project, you may have to measure time in weeks.
If you dont feel comfortable using your best-guess estimates, you can use the 3-point estimation method, which is designed to put more weight on the most
realistic timeframe.
In three-point estimation, you must come up with three time estimates for every task, based on prior experience or best guesses. The estimation method is
presented in formulas in order to calculate the time duration more accurately.
a = the best-case estimate
m = the most likely estimate
b = the worst-case estimate
These three values identify what happens in an optimal state, what is the most likely, and what happens in the worst case scenario.
Once youve identied these values, you can use them in two different formulas. The rst is used to nd the Weighted Average, which puts more weight on the
Most Likely value. The formula is as below. E stands for Estimate, and the 4 and 6 represent the standard method to place more weight on the most realistic
value.
E = (a + 4m + b) / 6

The second way of using these values is known as Triangular Distribution. The main difference is that this method doesnt put more weight on the Most Likely
value. The formula is as below. E stands for Estimate, and the 3 represents the standard method.
E = (a + m + b)/3

Step 5: Identify the Critical Path

There are two ways you can now identify the critical path. You can eyeball your network diagram and simply identify the longest path throughout the network -- the
longest sequence of activities on the path. Be sure to look for the longest path in terms of longest duration in days, not the path with the most boxes or nodes.
You can also identify critical activities with the Forward Pass/Backward Pass technique, identifying the earliest start and nish times, and the latest start and nish
times for each activity.
If you have multiple critical paths, you will run into network sensitivity. A project schedule is considered sensitive if the critical path is likely to change once the
project begins. The more critical paths in a project, the higher the probability of a change in schedule.

Step 6: Update the Critical Path Diagram to Show Progress


As the project progresses, you will learn the actual activity completion times. The network diagram can then be updated to include this information (rather than
continuing to use estimations).
By updating the network diagram as new information emerges, you may recalculate a different critical path. You will also have a more realistic view of the project
completion due date and will be able to tell if you are on track or falling behind.

Other Scenarios in the Critical Path Method


One of the biggest benets of the critical path method is identifying the crucial tasks that, if missed, will impact your projects completion date. It will also provide
visibility into your projects status, allowing you to see if you are on track.

Shortening Your Schedule


As youre going through the critical path method, you may nd that you want to intentionally shorten the duration of your project or that you need to compress
your project schedule in order to meet the deadline. There are two ways to do this: fast tracking or crashing.
Fast Tracking
In fast tracking, you look at the critical path and decide which activities can be done parallel to each other, to move the project along faster. You only need to
review the activities on the critical path because all the other activities have oat (if you shorten the duration of those activities, youre only giving them more
oat).
While fast tracking reduces your project timeframe, it also involves risk because you are performing parallel activities that were originally planned to be performed
in sequence.
Crash Duration
Crash duration, or crashing, refers to the shortest possible time for which an activity can be scheduled. This happens by adding more resources to completing that
certain activity. However, crashing the critical path results in lower quality of work because the goal in crash duration is speed.

Managing Resource Constraints


As you manage your project, you may also run into resource constraint issues that could change the critical path. If you try to schedule certain activities at the
same time, you may nd that you need more people than are available. As a result, those activities will need to be rescheduled. Resource leveling is the process of
resolving these conicts.
Resource Leveling and Expansion
With resource leveling, you can resolve conicts over allocating resources. A resource-leveled schedule may include delays due from resource bottlenecks (a
resource being unavailable at the necessary time).
Resource leveling may also result in a previously shorter path becoming the longest or most resource critical path. This happens when the tasks on the critical
path are affected by resource constraints.
A similar concept is called the critical chain, which protects activity and project durations from unexpected delays due to resource constraints.

Assessing the Final Project


These scenarios demonstrate all the unexpected changes that can occur when managing a project, and how they can affect the critical path. While things are
always subject to change, the good news is that you can measure the variance from your original project schedule and track how it impacted your nal project.
Flexibility and Assessing Delays

A schedule created from the critical path method naturally involves a lot of uctuation because you have to use best-guess estimates to calculate time. If one
mistake is made in activity completion time, your whole critical path schedule could change. Or, you may need to purposefully delay project activities due to
resource constraints.
Sorting out these delays and determining what caused them can help you avoid similar issues in the future. An important part of your post-project plan is the As
Built Critical Path, which analyzes the specic causes and impacts of changes between the planned schedule and actual schedule implemented. The As-Built
Critical Path is a schedule that shows the dates that the activities actually occurred and allocates time by determining the responsibility for the delays on the critical
path.

How to Use PERT in the Critical Path Method


If you recall the history of the critical path method described earlier in this article, youll remember that the PERT (Program Evaluation and Review Technique),
developed by the Navy in the late 1950s to help produce missiles faster, is a variation on the critical path method that takes a more skeptical view of activity time
estimates.

What is PERT?
Critical path method and PERT are often used in the same contexts and scenarios. Although they are similar, you should understand each concept and their
differences.
A PERT chart, or activity-on-arrow diagram, is a visual representation of your projects schedule, showing the sequence of tasks and which can be completed at the
same time. A PERT chart is made with a lot of the same information that is used in the critical path method, like earliest and latest start dates, earliest and latest
nish dates, and slack (or oat) between activities.
But, the biggest difference between the critical path method and PERT is in time estimation. In the critical path method, time variance is not accounted for. Youre
using best-guess estimates for completion time, and those times may change. With PERT, youre putting more weight on the most realistic completion time.

Critical Path Method and PERT


You can use PERT in your critical path method in step four of the process, when you have to estimate activity completion times. The purpose of using PERT is to
bias time estimates toward the most likely scenario and move away from unrealistically short timeframes.
To use PERT, you must estimate the shortest possible time each activity will take, the most likely length of time, and the longest time it might take if the activity lasts
longer than expected.
With that information, you can use this formula when you have to estimate activity completion times in the critical path method (step four).
Shortest time + 4x likely time + longest time / 6 = expected activity completion time

How to Find the Critical Path on a PERT Chart


You can identify the critical path on a PERT chart because the chart includes the same information needed for the network diagram in the critical path method.

A PERT chart is drawn with circles for each activity, with the name of the activity and estimated duration in each circle. Arrows represent the paths that relate to
dependencies.
To nd the critical path on the PERT chart, rst identify how many paths you can take from start to nish. Then, add up the total duration of activities on that path.
For example,
Path 1 duration: 12 days (task 1 and task 3)
Path 2 duration: 11 days (task 2 and task 3)
Path 3 duration: 10 days (task 4)
In this case, the critical path is task 1 and task 3 because it has the longest duration.

Critical Path Software


When the critical path method was rst developed, you had to identify the critical path by hand, drawing the network diagram with nodes to present the stages of
a project and connecting the nodes with arrows or arcs.
However, drawing nodes, tables, and arrows can be a time-consuming, dicult task, especially when things are constantly changing at the beginning of a project.

Rather than relying on hand-draw diagrams, there are a number of project management software programs available today that will do the work for you and
identify the critical path with the click of a button.
Here are two different toolswith critical path features:

Find the Critical Path with Microsoft Project


You can display the critical path in the Gantt chart view of Microsoft Project.
First, you must enter all your tasks, their start and end dates, the duration of each task, and identify the predecessors. Then, you can adjust the view of your MS
Project le to display the critical path.
Click View > Gantt Chart.
Click Format and then select the Critical Tasks check box.

Tasks on the critical path now have red Gantt bars.

Identify Critical Path in Other Views


You can see the critical path in any task view by highlighting it.
Click the View tab and select a view from the Task Views group.
Staying within the View tab, click Critical from the Highlight list. The critical path shows up in yellow.
To see only the tasks on the critical path, click the Filter arrow and select Critical.

In a network diagram, tasks on the critical path automatically show up in red. No highlighting is needed.

See the Critical Path in a Master Project

Entire subprojects can be on the critical path when youre managing a master project. To identify subprojects on the critical path, you can adjust Microsoft Project
to treat the subprojects like summary tasks.
Click File > Options.
Select Schedule and then scroll down to the Calculation options for this project.

Make sure the Inserted projects are calculated like summary tasks box is selected.

Change the Tasks on the Critical Path


Critical tasks typically have no slack. However, you can tell Microsoft Project to include tasks with one or more days of slack on the critical path, so you can identify
any potential problems that may arise.
Click File > Options.
Click Advanced, then scroll down to the Calculation options for this project area.
Add a number to the Tasks are critical if slack is less than or equal to box.

Identify the Critical Path in Seconds with Smartsheet


Keep Projects on Track ...

Smartsheet, a work management and collaboration tool in a spreadsheet layout, offers a pre-formatted Gantt chart template (https://www.smartsheet.com/ganttchart-software)to make it even easier to nd the critical path.
With this pre-made Gantt chart template, complete with sections, sub-tasks, and sub-sub-tasks already formatted, all you need to do is enter your own project
planning information. A Gantt chart will automatically be made for you, and with the click of a button, you can identify the critical path on the Gantt chart.
Heres how to nd the critical path in Smartsheet, using a Gantt chart template:

1. Choose a Gantt Chart Template


Go to Smartsheet.com and login to your account (or start a free 30day trial (https://www.smartsheet.com/try-it-2?trp=8514)).
From the Home screen, click Create New and choose Browse Templates.
Type dependencies in the Search Templates box and click the magnifying glass icon.
Select the Basic Project with Gantt & Dependencies and click on the blue Use Template in the upper-right corner.
Name your template, choose where to save it, and click the OK button.

2. List Your Task Information


A pre-made, formatted template will open with sample content lled in for reference. This section is where you add your activities, or tasks, from your work
breakdown structure. This is also where you can show the hierarchy, or relationship, between tasks.
The yellow cells at the top are there simply for instructional reference. To delete them,right-click on each yellow box and select Delete Row.
Add your tasks under the Task Name column.
Use the cells named Section 1, Section 2, and Section 3 to establish hierarchy (for more information on hierarchies, click here
(http://help.smartsheet.com/customer/portal/articles/504734-hierarchy-indenting-outdenting-rows)).
If you need to delete a row, right-click on the cell in the row youd like to delete and select Delete Row.

On the left side of each row, you can attach les directly to a task or start a discussion with a colleague about a task, adding more context to your project.

3. Provide Start and End Dates


Add start and end dates for each task. If you click and drag either end of a green task bar on the right in the Gantt view, Smartsheet will automatically change the
matching dates in the task table.
Select a cell in the Start Date or End Date column.
Click on the calendar icon and choose a date.


You can also manually enter a date in the cell. Smartsheet will automatically calculate the duration of each task for you.

4. Add % Complete and Assigned To Information


The % Complete and Assigned To columns provide more context around your project. In the Gantt view on the right side, you can quickly see how much of a task
has been completed by the length of the thin grey bars inside the task bars.
The Assigned To column allows you to assign the task to a particular team member, providing visibility into who is doing what.
In the % Complete column, enter the percentage of work complete for that task. Enter a whole number and Smartsheet will auto-ll the percentage sign.
In the Assigned To column, choose a name from the drop-down menu or manually enter a new name.

5. Establish Predecessors
Predecessors are used to create dependencies between tasks (identifying which tasks need to happen before or after another task).
On the far-left of the sheet, each row is assigned a number. In the Predecessor column, enter the row number that represents the row of the preceding task. This
will create a link from the current row (the dependent task) to the specied row (the predecessor task).
Enter the row numbers of all other predecessors in the Predecessor column.

You can also create predecessor dependencies from the Gantt chart on the right. Drag the bottom, right-corner of a Gantt bar down to the Gantt bar of the task
that should follow it. The Predecessor column will be automatically updated.

6. Identify the Critical Path


Now that you have created a Gantt chart in Smartsheet, you can identify the critical path on the Gantt chart with the click of a button.
On the right side of the screen, where your Gantt chart is displayed, click the far-right button that depicts a critical path (the two red Gantt bars).
On the Gantt chart, the tasks that are on the critical path will be outlined in red.

How to Import a Microsoft Project File (.MPP) into Smartsheet


Smartsheet works with Microsoft Project, so if you already have your project planning information stored in Microsoft Project, you can easily import that directly to
Smartsheet.
Click the Home tab and click the grey Import button.
Choose the Import MS Project File.

Click Select, choose the le you would like to import, and click Open.
Click Continue and an Import Settings form appears. Select the row in the form that contains your column headers (it will probably be the rst row) and click Import.
The imported le will appear as a new sheet within Smartsheet. Click on the sheet name to open it.

Studying for the PMP Exam? Heres What You Need to Know about the Critical Path Method
Learn Critical Path Method (CPM) for PMP Exam

To earn your Project Management Professional (PMP) credential, you need to pass the PMP exam, a 200-question, multiple choice test offered by the Project
Management Institute (PMI).

Critical path is an important part of the PMP Exam and there will certainly be questions about it on the test. Youll need to be able to draw a network diagram,
identify the critical path, use the Forward Pass/Backward Pass technique, and calculate slack.
Here is an overview of the most important things to know about the critical path method to help you pass the PMP exam:

How to Draw a Network Diagram


On the PMP Exam, you will be asked to draw a network diagram. The exam will list all the activities in a project and will tell you when the activities can start. With
that information, youll be asked to identify the critical path and its duration.
To explain how to draw a network diagram, Bennett has created a sample eight-task project:
Design Tank Project (10 days) can start right away.
Construct Tank Foundation (25 days) and Select Tank Supplier (8 days) can start as soon as Design Tank Project is nished.
Manufacture Tank Components (10 days) can start as soon as Select Tank Supplier is nished.
Deliver Tank to Jobsite (4 days) can start as soon as Manufacture Tank Components is nished.
Prepare Installation Drawings (3 days) can start as soon as Select Tank Supplier is nished.
Assemble Tank (15 days) can start as soon as Deliver Tank to Jobsite, Prepare Installation Drawings and Construct Tank Foundation are all nished.
Test & Commission Tank (4 days) can start as soon as Assemble Tank is nished.
After Test & Commission Tank is nished, the project is complete.

To answer the question, youll need to draw a network diagram.


Heres how:
Draw a box and label it as your rst activity (Design Tank Project). In the box, make sure to write the duration in days (in this case, it is 10 days).
Begin your diagram by drawing the relationship between Design Tank Project, and Construct Tank Foundation and Select Tank Supplier. You can do this by
drawing a box for the other activities, and drawing arrows to these boxes from Design Tank Project.
Continuedrawing boxes to represent activities, and arrows to represent when an activity can begin.

After you have drawn the network diagram, you will be able to nd the critical path. Remember: the critical path is the longest duration path throughout the
network in days, not the path with the most boxes.
In this example, the critical path is Design Tank Project, Construct Tank Foundation, Assemble Tank, and Test & Commission Tank, with a total duration of 54 days.
You can identify the critical path by eyeballing the diagram to nd the longest duration in days, or you could use the Forward Pass/Backward Pass Technique
outlined in the next section.

How to Use the Forward Pass/Backward Pass Technique


The Forward Pass/Backward Pass technique is another way to nd the critical path. It is best used when you have multiple branches, or multiple entry points, for an
activity.
You may also need to use the Forward Pass/Backward Pass technique if you are asked to identify the earliest start or nish times, or latest start or nish times, for
an activity. Or, to nd the slack (or oat) for each activity.
Before you start using the Forward Pass/Backward Pass technique, here are some terms that you rst need to understand:
Earliest start time (ES): The earliest time an activity can start once the previous dependent activities are completed.
Earliest nish time (EF): The earliest start time for the activity plus the time required to complete the activity (the earliest an activity can be completed).
Latest nish time (LF): The latest time an activity can be completed without delaying the entire project.
Latest start time (LS): The latest nish time minus the time required to complete the activity.
As you run the Forward Pass/Backward Pass technique through your network diagram, arrange each value according to the follow legend (SL stands for slack,
which well cover in the next section).

How to Do the Forward Pass: Finding the Earliest Start Time and Finish Time
There are two formulas in the Forward Pass/Backward Pass technique. The rst is the Forward Pass formula for you to use as you move from beginning to end in
your network diagram (from your rst activity to your last). This formula will nd the earliest start time (ES) and the earliest nish time (EF) for each activity.
To start the Forward Pass, make the ES of the rst task zero. For all other tasks, the ES is the same as its immediate predecessors EF.
Use this formula to calculate EF:
EF = ES + Duration
So, for Design Tank Project, the ES is zero and, the EF is 10 (10+ duration of 0). We also know that the ES for Select Tank Supplier is 10 and the EF is 18 (10 +
duration of 8). Continue like this throughout the network diagram.

How to Do the Backward Pass: Finding the Latest Start Time and Finish Time
The second formula is for Backward Pass, when you are moving from the last activity to the rst activity (you are moving backwards). This formula will nd the
latest start time (LS) and latest nish time (LF) for each activity.
To start the Backward Pass, make the last activities LF the same as its EF. For all other tasks, the LF is the same as its immediate predecessors LS.
Use this formula to calculate LS:
LS = LF - Duration
For the Test & Commission Tank, the LF is 54 and, the LS is 50 (54 - duration of 4). For Assemble Tank, the LF is also 50 and, the LS is 35 (50 - duration of 15 days).
Continue this formula throughout the network diagram.
To check that youve done Backward Pass correctly, the rst activity (Activity A) should have an LS (latest start time) of 0.
Heres the completed Forward Pass/Backward Pass technique:

Two Rules to Remember for Forward Pass/Backward Pass


During the Forward Pass,if you nd activities that join (multiple activities that ow into one activity), you must run the Forward Pass formula for each entry point and
use the highest value from the formulas.
During the Backward Pass, if you have activities that join, you must run the formula for each entry point and use the lowest value.

How to Calculate Float or Slack on the PMP Exam


Now that you have calculated ES and LS for each activity, you can nd the oat (or slack).
The slack time, also known as oat time, for an activity is the time between the earliest and latest start time. Critical activities, activities on the critical path, will
always have zero slack.
There are two formulas to calculate slack based on the values you identied in the Forward Pass/Backward Pass technique.
Slack = LF - EF
Slack = LS - ES
You will have to use this process if you are asked to identify an activitys slack on the PMP exam. Or, if youre not sure which activities are on the critical path, you
could nd the slack of each activity, knowing that activities on the critical path always have zero slack.

The nal gure below shows the slack values for each task. You can see that the four tasks on the critical path have zero slack -- Design Tank Project, Construct
Tank Foundation, Assemble Tank, and Test & Commission Tank.

Key Critical Path Terms for the PMP Exam


Here are the most important terms related to the critical path method that you should understand before taking the PMP exam.
Critical path method (CPM): The critical path method is a step-by-step project management technique for process planning that identies critical and noncritical
tasks, preventing timeframe problems and process bottlenecks.
Critical Path DRAG (Devauxs Removed Activity Gauge): The amount of time that an activity on the critical path is adding to the projects duration. Or,
alternatively, the amount of time the project completion date would be reduced by decreasing a critical path activitys duration to zero.
Criticality Index: Used in risk analysis, the Criticality Index shows how often a particular task was on the critical path during analysis. Tasks with a high Criticality
Index are more likely to cause delay to the project since theyre more likely to be on the critical path.
Earliest start time: The earliest time an activity can start once the previous dependent activities are completed.
Earliest nish time: The earliest start time for the activity plus the time required to complete the activity.
Latest nish time: The latest time an activity can be completed without delaying the entire project.
Latest start time: The latest nish time minus the time required to complete the activity.
Total oat: The amount of time an activity can be delayed from its early start date without delaying the entire project.
Free oat: The amount of time an activity can be delayed without delaying the early start date of a successor activity.
Forward pass: The process to determine the early start or early nish times for activities in the critical path method.
Backward pass: The process to determine the late start or late nish times for activities in the critical path method.
Network diagram: A schematic display of the relationships between project activities, always drawn from left to right to reect the order of the project.
Network analysis: The process of breaking down a complex project into components (activities, durations, etc) and plotting them to show their interdependencies
and interrelationships.

The Easiest Way to Find the Critical Path

The critical path method is one of the most frequently used and most effective techniques in project planning. When youre managing dozens of tasks,
dependencies, and people, the critical path method helps you keep your project on track and on budget, providing visibility into the most important tasks of your
project.

The good news is that nding the critical path in your project continues to get easier and easier. Traditionally drawn by hand, you can now nd the critical path in
seconds with project management software.
When it comes to the right tools, Smartsheet is the easiest, fastest way to identify critical path. Smartsheet is a cloud-based work collaboration tool that is powerful
enough for project managers, yet easy enough for anyone to use. Built with a familiar, spreadsheet-inspired layout, Smartsheet enables you to coordinate
anything: creating project plans, sharing content, providing visibility, and of course, nding the critical path.
Experience rsthand how easy it is to use Smartsheet in your project planning and sign up for a free 30-day trial (https://www.smartsheet.com/try-it?trp=8514).
There is no obligation and trial users have access to a number of templates, training, and support resources to get started in minutes.

If you liked this article, visit our Resources page (http://www.smartsheet.com/resources) for more tips and best practices in project management.

Comments
Risk and Change (https://www.smartsheet.com/comment/37756#comment-37756)
Submitted by Dave Schnell (not veried) (https://www.smartsheet.com/blog/author/dave-schnell) on Mon, 08/31/2015 - 09:12
Permalink (https://www.smartsheet.com/comment/37756#comment-37756)
From a "battle-scarred veteran," CPM is a great tool, I've used it on almost all of my projects. However, some additional considerations for the novice-on any large
and/or complex, especially long duration projects, the CP will change, sometimes weekly. The CPM is only as good as the estimates of the task resources and
effort, so it's critical to continuously reevaluate the CP and task estimates and not just chase the initial critical path. Especially on technology projects, where
percent complete is often a matter of speculation. Also, consider task risk. Some high risk tasks may not show up on the CP until the risk is realized, so be sure to
ag these high risk tasks and watch them as well. Finally, I've also encountered some PMs who thought, if a task wasn't on the CP, it didn't need to be completed
(go gure)...if you're thinking this, then ask why are you doing the task at all?
reply (https://www.smartsheet.com/comment/reply/3717/37756)

RE: Risk and Change (https://www.smartsheet.com/comment/37758#comment-37758)

Submitted by Emily Esposito (https://www.smartsheet.com/blog/author/emily-esposito) on Mon, 08/31/2015 - 13:48


Permalink (https://www.smartsheet.com/comment/37758#comment-37758)
Hi Dave -- Great points! Those are important things to remember when developing the critical path. Thanks for reading. -Emily
reply (https://www.smartsheet.com/comment/reply/3717/37758)

Critical Path Conventions (https://www.smartsheet.com/comment/38399#comment-38399)

Submitted by Dr. Paul D. Gia... (not veried) (https://www.smartsheet.com/blog/author/dr.-paul-d.-giammalvo) on Wed, 12/02/2015 - 04:39
Permalink (https://www.smartsheet.com/comment/38399#comment-38399)
Question Dave...... Why do we continue to contravene standard mathematical convention by putting the Early dates (the subtrahend) on the TOP and the Late
dates (Minuend) on the bottom? I've done some research and it appears that the only reason John Fondahl did it this way is because it was how the US Navy did it
to schedule their ships. Other than that, there is no logical or rational reason so why should we continue to perpetuate a practice that totally contravenes
mathematical convention?
reply (https://www.smartsheet.com/comment/reply/3717/38399)

CPM (https://www.smartsheet.com/comment/38437#comment-38437)

Submitted by Bahara Muradi (not veried) (https://www.smartsheet.com/blog/author/bahara-muradi) on Wed, 12/09/2015 - 16:41


Permalink (https://www.smartsheet.com/comment/38437#comment-38437)
was really useful video and explained in a great way thank you very much.
reply (https://www.smartsheet.com/comment/reply/3717/38437)

Add new comment


Your name
Subject
Comment *

Save

Contact Us (https://www.smartsheet.com/contact)
or call +1 (844) 324-2360 (tel:18443242360)

Follow Us

(https://www.linkedin.com/company/smartsheet
(http://www.facebook.com/smartsheet)
(http://twitter.com/smartsheet)
(https://plus.google.com/+smartsheet/posts)
com)
(http://www.youtube.com/user/Sm
Download our Mobile App

Language: English

(//privacy.truste.com/privacy-seal/Smartsheet,-Inc-/validation?rid=fc25c0bf-a7a4-425b-a6c0-77cb0b376cf2)

2016. All Rights Reserved Smartsheet.com

You might also like