Professional Documents
Culture Documents
By:
Wayneworth G. Hamilton
A major research project submitted in partial fulfilment of the requirements for the Bachelor of
Science Degree in Surveying and Geographic Information Sciences.
ii
APPROVAL PAGE
By:
Wayneworth G. Hamilton
ID. #: 0416981
Approval Date:
September 2011.
.............................................................................
Mr. Kepton Smith - Supervisor
......................................................................................
Mr. Glendon Newsome Project Coordinator
...............................................................................
Mr. Garfield Young - Project Coordinator
iii
DEDICATION
iv
Abstract
The current approach to Project Management on the New Harbour Village II project
undertaken by Gore Developments Ltd. includes the use of aerial photographs, AutoCAD files,
Microsoft Access and Excel files, Microsoft Project Schedule, archived records from
stakeholders and written records by supervisors. This approach does not facilitate centralized
data storage, link between spatial and non-spatial data, quick retrieval, computerized quality
control and monitoring. Consequently it was considered that the integration of a GIS Model with
Project Management would be a solution to these deficiencies.
This research took the format of an applied research. Quantitative and qualitative
methodologies were included in that data was gathered by primary and secondary means to
investigate the applicability and feasibility in developing and implementing GIS in Construction
Management. The research methods also included case studies, interviews and questionnaires.
The findings and results of the research highlighted the benefits and capabilities of the
GIS Model in that it provided a single storage medium for all project information, a seamless
link between spatial and non-spatial data, visualization of the progress of works, demonstrated
computerized quality control, aided in material inventory checking, quantification of work to
support payment and earned value analysis and demonstrated its potential to aid in disaster
response. The findings spoke to correlation between age, years of service and unwillingness to
change which will encumber efforts of retraining to utilize GIS technology.
The GIS Model was successfully developed and replicated the needs of Management in a
timelier, efficient, and logical setting which spoke to improved efficiency. A theoretical analysis
backed by local and international uses of GIS in Construction Management in addition to the
results was utilized to provide validation and further recommendations.
Acknowledgement
I would like to express my sincere gratitude, to everyone who assisted in the completion
of this research project. Firstly, thanks to GOD, for his guidance, blessings and mercy. To my
family, for their understanding, patience, inspiration, encouragement, support and love during
this very challenging course of study.
Special thanks to Mr. Christopher Gore, General Manager of Gore Developments Ltd.
(GDL), Mr Israel Pinchas, Project Manager (GDL), Mr. Asaf Keren, Site Manager of New
Harbour Village II Project, individually and collectively for their input. Thanks also to the staff
of GDL/ New Harbour II Project.
Thanks to Mr. Kepton Smith, my project supervisor for his guidance, suggestions and
assistance in completing this research. He was always available for my questions and pointed me
in directions beyond my inclination and knowledge.
Thanks to Mrs. Jenevy Smith and Mrs. Andrea Williamson my lecturers of Land and
Geographic Information Sciences theory and practical respectively, for their insight, critique,
encouragement and for always demanding more of me.
Thanks to Ms. Nadine Smith (National Housing Trust), Mr. Ian Bennett (National Water
Commission), and Mr. Damian Graham (Spatial Innovision Ltd.) for the taking time out of their
busy schedules to answer questions relating to industry operations, practices and prices.
vi
Table of Contents
Dedication .......................................................................................................................................ii
Abstract ..........................................................................................................................................iii
Acknowledgement .........................................................................................................................iv
List of Tables .................................................................................................................................xi
List of Figures ......................................................................................................................xii - xiii
List of Abbreviations ...................................................................................................................xiv
Definition of Terms .............................................................................................................xv - xvii
vii
viii
ix
xi
xii
List of Tables
xiii
List of Figures
Figure 1.0 - Research Model
Figure 2 Study Area
Figure 3 - Study Area Generated by Google Earth
Figure 4 AutoCAD 2009 Drawing File illustrating Lots, Buildings, Easements & Reserved
Roads
Figure 5 Illustration of Relationship Class
Figure 6 - Creation of Topology
Figure 7 Map Document of Compiled GIS Model
Figure 8 - Map Document illustrating all Scopes of Work
Figure 9 - Schematic Flow of Project Managers Queries
Figure 10: Visual Representation of All Operating Sewer Manholes
Figure 11: Generated Report All Operating Sewer Manholes
Figure 12: Visual Representation of All Completed & Approved Sewer Mains
Figure 13: Visual Representation of All Installed Laterals
Figure 14: Visual Representation of Storm Water Mains Approved
Figure 15 - Visual Representation of Storm Water Elements Approved
Figure 16 - Visual Representation of Roads undergoing Laying of Curb Walls
Figure 17 - Visualization of Construction Stage of Buildings
Figure 18 - Generated Report of Dynamic Nature of Construction Activities
Figure 19 - Generated Report of Sales Records
Figure 20 - Visual Representation of Approved Water Supply Mains
Figure 21-Visual Representation of Concentric Reducers
xiv
xv
List of Abbreviations
CAD
CPM
DBMS
DEM
ESRI
FCC
GDL
GIS
GPS
GUI
LIS
OBS
PCC
PM
Project Management
PMBOK
WBS
xvi
Definition of Terms
Aerial Photography, photographs taken of ground from an elevated position; the term usually
refers to images in which the camera is not supported by a ground based structure.
AutoCAD, DXF (Drawing Interchange Format, or Drawing Exchange Format) is a CAD data
file format, developed by Autodesk as their solution for enabling data interoperability between
AutoCAD and other programs.
Building Construction, Installation of the formworks for foundation and building, the
installation of the requisite reinforcement, conduits, pipes and the subsequent placing of concrete
to the requisite standards.
Geodatabase, a database or file structure used primarily to store, query, and manipulate spatial
data. Geodatabases store geometry, a spatial reference system, attributes, and behavioural rules
for data. Various types of geographic datasets can be collected within a geodatabase, including
feature classes, attribute tables, raster datasets, network datasets, topologies, and many others.
Geodatabases can be stored in IBM DB2, IBM Informix, Oracle, Microsoft Access, Microsoft
SQL Server, and PostgreSQL relational database management systems, or in a system of files,
such as a file geodatabase.
xvii
Geodatabase data model, the schema for the various geographic datasets and tables in an
instance of a geodatabase. The schema defines the GIS objects, rules, and relationships used to
add GIS behavior and integrity to the datasets in a collection.
Geodatabase Schema, refers to the structure of the database. This includes tables feature data
sets, feature data classes, subtypes, relationships, fields, data types etc.
GPS, acronym for Global Positioning System. A system of radio-emitting and -receiving
satellites used for determining positions on the earth. The orbiting satellites transmit signals that
allow a GPS receiver anywhere on earth to calculate its own location through trilateration.
Developed and operated by the U.S. Department of Defense, the system is used in navigation,
mapping, surveying, and other applications in which precise positioning is necessary.
xviii
mains, storm drains, water mains, electricity, and telecommunication lines which are included in
the design.
Lot Demarcation. Design of a Subdivision to form the basis of the development, the marking
(monumentation) of lot boundaries and the preparation of Surveyors Identification Reports.
Project Management. Application of a collection of tools and techniques to direct the use of
diverse resources toward the accomplishment of a unique, complex, one-time task within time,
cost and quality constraints. Each task requires a particular mix of these tools and techniques
structured to fit the task environment and life cycle (from conception to completion) of the task
1.2 Background
Gore Developments Ltd. (GDL) has established itself as one of the leading providers of
affordable housing solutions in Jamaica over the last 27 years. (www.goredevelopments.com)
They are reputed for excellence and quality in the areas of construction and development. GDL
are developer/ contractor for projects such as:
1. Bogue Village and Rhyne Park in St. James
2. Innswood Village, St. Catherine
3. Braeton Newtown and West Cumberland in Portmore, St. Catherine
4. Presently Florence Hall in Trelawny and New Harbour Village II in Old Harbour
The New Harbour Village II project is located along the Old Harbour Bay main road and is
comprised of 2500 housing units which are to be constructed over ten years. This research sought
to utilize Phase Three of the New Harbour Village II project as a pilot. Presently construction is
in progress in this phase and as such this phase was seen as ideal for providing the dynamic data
which will serve as a basis for monitoring each scope of work.
The management of construction projects of this magnitude can be quite a substantial task.
The project manager utilizes aerial photographs (Appendix A) for spatial reference and
visualization of the progress of works with reference to a schedule of works. In addition to aerial
photographs for visualization, supervisors are assigned to each scope of works to monitor
progress, maintain quality control and give periodic reports with respect to quantities and stage
of construction.
1.2.1
The fact that housing units were delivered to owners does not speak to maximum
efficiency in managing the various component activities of the project. Optimum efficiency
of the current approach was affected by the following fundamental deficiencies:
1. Whereas the aerial photographs provide a degree of the spatial layout of the progress of
works, no exact quantification is readily available by simply viewing the photographs.
2. Scope of works such as those of a sub-structural nature (such as pipelines) and those of
super-structural nature (such as interior finishing, installation of fixtures and fittings) are
beyond the capabilities of aerial photography. This is manifested by pipelines already
backfilled will not be shown in the photographs as well as the internal works are not
shown in the photographs as roofing is a predecessor activity to internal finishing.
3. The information reported by supervisors is without an immediate spatial reference which
is often pertinent to decision making.
4. The current approach lacks fast quantification of materials used/ stored in that no query
can provide details of material inventory instead research would be required and a
manual merging of data.
5. The approach also lacks self-checking or quality control mechanisms in that there is no
super-imposed environment where design is cross referenced with as-built data.
These inherent deficiencies have rendered the present approach as ineffective and inefficient.
Therefore a more efficient and effective method of project monitoring must be found.
1.2.2
Hypothesesis: A more efficient and effective approach to result from the utilization
of a Geographic Information System in the management of civil projects.
such as finishing work such as tiling, installation of fixtures and fittings cannot be shown from
an aerial perspective as roofing precedes internal works.
The component of supervisor reports will provide quantities and progress of works but
are not under-pinned by an immediate visualization and as such will require cross reference with
a drawing or map. This becomes more challenging with the inclusion of more datasets,
particularly where the manager will need a super-imposed view of different scopes of work such
as sewage and electricity.
In response to these deficiencies, the necessity to ascertain a legitimate solution arose.
The requisite solution should have the capacity to provide a visualization of all scopes of work
both individually and collectively. It should provide a central storage and seamless link with all
datasets both spatial and non-spatial. The proposed system should have the capability of
quantifying materials; facilitate the rules and regulations governing the processes involved
thereby providing a quality control mechanisms. Additionally, it should generate reports to aid in
procurement, payments and progress reporting for all works. The systems should serve as a
premise to develop safety schemes and the solution of spatial problems and finally foster a
culture of greater professionalism through better data collection and storage.
The practical application of GIS_GDL will be manifested in that the project manager
will be able to query the progress of each scope of works, in addition to having at his disposal an
advanced analytical tool for determining the best way to approach tasks where they are
conflicting with each other as in the case of excavating a road for storm water when it is needed
for access to facilitate to the passage of concrete trucks, such a problem can be identified and
solved by querying alternate access routes.
GIS_GDL will seek to enhance the up to date status of the scope of works as the database
of the project can be updated daily by trained personnel. This system will at best dispense with
the need for the current mausoleum of records relating to the scope of works associated with
projects of this nature or at least provide a legitimate backup. Generally GIS_GDL will provide
the Project Management team with a cost effective system to operate more efficiently with
regards to monitoring and decision making by:
1. Providing storage of construction data to aid decision making.
2. Function as a scheduling tool.
3. Facilitate document management.
4. Aid in logistics, costing and cost analysis.
4. What are the challenges in developing and utilizing GIS in construction management?
5. What are the implications of employing a GIS as a project management tool?
10
Additionally, Vijay (2006) indicated that the construction industry has a huge number of
tasks and cost involved in these projects is also very large. The project managers must monitor
the projects between site and office. They have to visit the site to ascertain the progress of works.
The complexity coupled with the huge quantity of information in the building design and
construction project require an efficient system that may aid in the integration of various types of
data and provide the required information and data in a timely manner that will finally support
various decision and construction operations. The information required for planning and design
are stored in different forms, such as drawings, specifications, and bar charts. In the planning
process, the planner has to continually interpret and structure the information collected from
various resources which can be tedious and prone to errors (Cheng and Yang, 2001).
Geographic Information Systems (GIS) is an appropriate technology for managing
construction projects and can improve the construction planning and design efficiency by
integrating spatial and thematic information in a single environment. It provides capabilities to
solve problems, involving creation and management of data, integration of information,
visualization and cost estimation to which most of the construction management software is
lacking. In construction management, GIS leads to the improvement in collective decisionmaking among planners, designers and contractors (Bansal and Pal, 2005).
High levels of efficiency in construction management are crucial in the construction
industry. A large number of data involved in the planning and design phases of construction
projects are usually stored in various forms such as drawings, tables, and charts. These data need
to be sorted properly to ensure it can be retrieved and manipulated by related parties when
needed. (Coors, et-al, 2010)
11
Kartam (1997) further extrapolated that the construction industry is perceived to be one
of the most hazardous occupations, and ranked low in safety, quality control, and proper
information system. Both Vijay (2006) and Kartam (1997) discussed that these circumstances
therefore indicates that there is need to have effective computerized methods which would
efficiently integrate safety and quality control, during construction as well as the incorporation
and evaluation of other important aspects of a project such as costs. One such identified system
would be a Geographic Information System, because of its extensive areas of application across
the construction industry (Kartam, 1997). In this case the Geographic Information Systems
would be utilized as a computerized tool used for capturing, storing, querying, analyzing and
displaying the geographic information. Like any other information system, GIS is a special class
of information system, which has four components involving a computer system, GIS software,
human expert and data. (Bansal, 2007)
In recent years, evidence has shown that GIS applications have proliferated in the
construction industry. This fact has been illustrated by the growing number of articles being
published in civil engineering and construction journals and conference proceedings, in addition
to the handful of special publications devoted to GIS (Oloufa et al., 1994). GIS use has also
spanned in different areas of applications in construction which includes but is not limited to
progress monitoring system in construction, networking solution, 3-D data analysis, site location
and client distance, comparison of data, construction scheduling and progress control with 3-D
visualization, Government Regulations. (Oloufa et al., 1994)
The term Project Management is generally defined as The application of knowledge,
skills, tools and techniques to project activities to meet project requirements." (PMI, 2008). It is
also characterized as "the planning, monitoring and control of all aspects of the project and the
12
motivation of all those involved in it to achieve the project objectives on time and to the
specified cost, quality and performance. (PRINCE2).
Vijay(2006) further stipulated that the traditional approach of project management for
scheduling and progress control techniques involves using tools such as bar charts and the
critical path method, which are still predominant means being used present day by the project
managers for planning. There is usually constant pressure on the project managers to shorten the
delivery times and thus the current scheduling and progress reporting practices are in need of
substantial improvements in quality and efficiency. As it relates to large scale projects, a visual
representation of the schedule utilizing a GIS would be essential in extended monitoring, not
only the construction process itself, but also to all the auxiliary activities, including onsite plant
and equipment. In addition, the practical and educational benefits of being able to visualize
construction at a fine level of detail are significant. Visualizing construction progress provides
the construction project manager with a more intuitive view of the construction sequence.
Visualization allows the construction manager to view the construction activities during any
stage of the construction process.
13
14
construction of 28 miles of waterline along the most populous roads within the water district.
Phase 2, an additional nine miles of waterline, is in the planning stage with an estimated
construction start date in the summer of 2006. The complexities of managing such a large
construction project in many different areas of the town has led the Wendel Duchscherer firm to
evolve common construction management practices and looked to new technologies and the
ideals of GIS to improve the water district's communication and data sharing capabilities.
Carter and Seider (2006) has pointed out that all documentation were developed and
controlled through a geographically driven interface using MapObjects software alongside
Primavera Expedition, Web-enabled project management software from Primavera Systems,
Inc., of Bala Cynwyd, Pennsylvania. By taking advantage of advances in technology and
engineering, the town turned the field inspector's reports and sketches into electronic forms to be
filled out and stored on Tablet PCs. To ensure a smooth transition from paper to digital form and
minimize training for field inspectors, the town staff re-created the standard hydrant and water
service inspection paper forms via database input forms to provide easy, organized access to all
collected information.
Each form, sketch, or documented progress photo was input through a customized
MapObjects application combining Newstead base mapping information with CAD design plans
of the water project. Documentation input of all inspected features is initiated by clicking on the
desired location in the created map window. Other information, such as daily field reports,
material installed by the contractor, and correspondence, was recorded through Expedition. To
fully utilize and combine the capabilities of each application, a migration of the existing program
to ArcObjects for a seamless integration with Expedition is being designed.
15
16
estimating and planning new construction projects and suggested the use of GIS-based
methodology to develop a database for foundations analysis, design and construction planning.
As surface and sub-surface conditions influence construction methods and choice of
equipment, which in turn affect cost and scheduling of projects. Therefore, the study by Oloufa
et al (1994) used database management capability of GIS to store descriptive soil data and to
relate this data with the corresponding locations of boreholes.
17
operations. ArcView, which utilizes the dynamic linkage between spatial and attribute data, was
used for this purpose.
18
prefabrication and transport of structural elements to job site are developed based on installation
schedule. The study suggested that the use of GIS environment improves the real time schedule
monitoring system and construction process as well as improves construction efficiency.
19
20
shapefiles. The shapefiles are simple non-topological format for storing geometric location and
attribute information of geographic features. Layers transferred into ArcGIS from AutoCAD may
be merged together according to the activities as defined earlier in schedule generated in
Microsoft Excel. Thus, components of a drawing that belong to same activity but are located at
different positions in space are joined together to construct spatial data for each activity. Linking
an activity with its schedule involves in adding a field called key to schedule and its attribute
table. The field key is common between two tables (i.e. schedule and attribute table of different
components) and used to establish the connection between the spatial aspect and the
corresponding activity in the schedule. All the entries in the field key are to be entered manually
and should be unique in both schedule and attribute tables of an activity.
Since one objective of this project is to display the progress and sequence of construction
work in 2-D while synchronizing this information with a formal CPM work schedule. This
would assist in visualizing the progress in a natural way, hence minimizing delays and cost
overruns. In addition to monitoring the schedule, the system can also be extended to monitor
quantities of materials, costs, and resources.
Vijay (2009) developed a run time application using Visual Studio 5.0 in C++ language.
With the assistance of this run-time application a User Interface was developed which facilitated
the transfer of the percent complete information to the schedule every time a progress evaluation
is made and the application is run. MS Project was run to generate the updated schedule network.
The updated schedule shows the progress for all the activities as of the new date of the update
(e.g. at the end of every month or daily updates) and the percent complete information.
21
22
2.6 Conclusion
It is the objective of this paper is to demonstrate that GIS can be integrated with project
management software for construction progress visualization and an integrated information
system. Literature on Geographic Information Systems application in Project Management is
somewhat extensive but appears to be quite limited in relation to Jamaica. Importantly though
there are the lessons garnered from previous studies from around the world that indicate the
importance of having GIS implemented in housing project management. According to
(Bestebreutje, 1997), a project manager has to build his project organization keeping this in
mind. In order to have a successful project it must be: on schedule, within budget, of good
quality, complete, and accepted by the customer. Choosing an appropriate methodology to do
these things is critical in accomplishing this difficult task.
23
24
how these datasets would be integrated in order to develop the geodatabase and subsequently the
GIS model in order to effectively match the capabilities of the model with the project and the
organisations requirements. A conceptual schema was then developed to illustrate the structure
of the GIS model which will satisfy the requirement of the management team.
This user needs assessment also highlighted the existing procedures currently employed
to monitor works (Research Question1) in addition to how the proposal of a GIS based
monitoring approach will impact the project and the organisation. (Research Question5)
Finally a Geographic Information System (GIS) model was developed in effect to
integrate feature classes relating to parcels, buildings, electricity, storm water drainage, sewage
and potable water. This integration facilitated advanced query, analysis with reference to a
schedule of construction activities, display the spatial relationship between data sets as well as
the respective phase of each activity.
It is required the resultant GIS_GDL should provide the following capabilities;
1. Since successful project control is a challenging responsibility for all construction
managers. The main aim is to provide graphical and textual information regarding the
progress of each scope of work in order to create a reference with the Schedule of works
so as to provide a basis for further analysis and planning.
2. Visualization of information is an important benefit for any project. This will be
facilitated by advanced queries whereby works which are no longer accessible (substructural) can also be analysed.
3. Provide a spatial component to tracking works and providing a solution with regards to
planning equipment movement, and access roads.
25
4. The system can also be extended to support decision making by providing comprehensive
information in an effective manner about quantities of materials, costs, and resources.
Based on the ability of the model to fulfil its required functions and in the case where it is
deemed to be a feasible approach to aid in managing a construction project, a recommendation
will be made to Gore Developments Limited for a full implementation of a GIS, particularly
since the nature of projects is long term. Full implementation of this GIS will require significant
funding and as such the inherent benefits must be demonstrated. The benefits of this model will
be reflected in it potentials demonstrated by tangible results. (Research Question 3)
3.2 Population
The operations of the Developer/ Contractor, Gore Developments Ltd. (GDL) are
characterized by five (5) departments which are as follows:
1. Infrastructure
2. Housing
3. Special Projects
4. Store Keeping
5. Batching Plant
The GIS model was designed to incorporate data from all departments in order to
generate a comprehensive report with respect to progress of works, cost of works and quality
control. Time sensitivity was a key feature of data so as to encapsulate the dynamic nature of
construction activities.
26
Finally, the GIS model can be queried by the Project Manager to ascertain the progress of
works with reference to a schedule, the cost of works with reference to a budget and the quality
of works with respect to design/ operational industry standards.
3.3 Sampling
The sampling method employed was Probability/ Representative Sampling in that an area
was selected to represent both the strategies employed to monitor works as well as the
multiplicity of works required to deliver the product of the project. This method produced a
Stratified Sample which is essentially a mini representation of the overall activities of mass
construction and its monitoring. This sample is constituted of all the scope of works which
characterize the overall operations of the work required to deliver the product of the project.
These scopes of work are categorized as building, sewage (manholes, mains, and laterals), storm
water drainage, cold water supply, parcels, roads and electricity.
Though this method facilitates an accurate replication of the requisite activities it poses
the disadvantages of a large amount of categories identified for monitoring coupled with the need
for information from various sources in various formats.
3.4 Sample
The case study area for this paper is the New Harbour Village II (Phase 3), which is
located approximately 1.68 km South East of Old Harbour along the Old Harbour Bay main road
in the parish of St. Catherine. New Harbour Village II is comprised of 2500 residential lots.
However, the study area of Phase Three (3) is comprised of 186 Residential Lots, 1 Recreational
27
Lot, 6 Easements and 3 Roads, which account for an area of 103,141.9072 Sq. meters (2.3678
Hectares).
Study Area
28
New Harbour Village II (Phase 3) was selected based on the following criterion:
1. Based on research deficiencies that were identified in the current approach employed at
the project regarding the monitoring of works.
2. The fact that Phase 3 is in the process of construction it provided an ideal premise for
monitoring the dynamic activities involved.
3. The need to effect a solution to a real world problem through the knowledge acquired
from lectures I participated in at the University of Technology, Jamaica specifically those
of Land and Geographic Information Systems I & II.
29
4.
This project offered the combination of the principles of Project Management and the
Practices of Mass Production Construction Activities which inherently involves a
multiplicity of activity and relationships which are spatially referenced.
30
31
Soft copies of aerial photographs (JPEG Format) of the site were also acquired from the archive
of the organisation. (Appendix A) copies of testing results by the relevant agencies such as
National Water Commission (N.W.C), JETS Laboratory (Appendix M), the quantity (cu.yds),
strength (p.s.i.) and location of use for concrete batched and delivered by the GDL Batching
Plant were gathered from the archive of GDL New Harbour Site Office.
The material listing corresponding to each stage of work, the data of inspection results,
date and inspectors were also collected. All available records relating to the houses such as sales,
inspection, materials were also acquired. Secondary data was also based on textbooks, articles,
maps and internet searches relating to the utilization of GIS in the construction industry.
32
entities are the real world features which are of the interest from a Project Management
Monitoring perspective.
The next step involved the identification of the attributes or characteristics of each entity
which are of relevance to the management of the project. For example the Parcel Entity
contained the attributes of Lot #, Parcel Type, Scheme Address, Boundary Status, Perimeter and
Area. It was deemed necessary by the management team to monitor the status of a parcel through
these attributes.
Having identified the entities and their attributes the next step was to establish the
relationships between entities using attributes as keys. Note that each entity will create a table of
attribute; the relationship between entities can take the following form:
1. One to One (one record in a table is related to only one record in another table)
2. One to Many (one record in a table is related to many records in another table)
3. Many to One (many records in a table is related to only one record in another table)
4. One to Many (one record in a table is related to many records in another table)
The completed schema was used as the blueprint for the Geodatabase. (Appendix B)
33
AF Engineering Ltd. These drawings were already geo-referenced and provided the premise for
the creation of shapefiles and the entry of all attribute (tabulated) information to subsequently
develop the GIS Model.
Figure 4 AutoCAD 2009 Drawing File illustrating Lots, Buildings, Easements & Resvd. Roads
The Aerial Photographs (JPEG) were not incorporated in the model but formulated a
premise for comparison of the Proposed GIS based approach with the current Photograph/
Management Meeting approach.
34
35
36
A relationship class relates two objects in a geodatabase. Relationships can have one-to one, oneto-many, many-to-one and many-to-many cardinalities. Relationships are established through
keys: an origin key and a foreign key, corresponding to the origin class and the destination class,
respectively. (Olivera, 2004)
37
changing the view type to Preview and preview type to Geography. This procedure was repeated
for all features by adding shape files to their respective feature classes.
3.13 Relationships
Since the model will be a Relational Database Model which is a collection of tables
(relations), each of which will be prepared, maintained and edited separately; these tables are
however joined or related to each other for data search and retrieval. The two basic elements of
in the designing a relational database are the key and the type of data relationship. The key
establishes a connection between corresponding records in two tables and the type of data
relationship dictates how the tables are actually linked. (Chang 2010)
For example a relationship was established between Parcel and Owner as One to One
since all parcels must have owners and the key was selected as Lot #, since it uniquely identify
each parcel as no two parcels of the development have the same lot number.
38
39
40
41
The challenges in developing and subsequently maintaining the GIS_GDL will be documented
and compared to industry approach so as to provide a premise for validity or alteration in future
studies. (Research Question 4)
3.18 Metadata
This is an explanation or description of the data in the model, relating to data sources,
date of collection, relating images, etc. The creation of metadata was facilitated by ArcCatalog
with the edit metadata tab. Both textual and graphical inputs can be made, edited and updated at
any time.
3.20 Queries
The objectives of the Project Manager and the potentials of the GIS Model were realized
through queries. The query by attribute tool in ArcMap 10.0 was utilized to fulfil these
requirements. Importantly queries were structured and sequenced to replicate the Project
Management Teams queries of the current approach.
42
43
44
45
The objectives of the project management team were simplified as delivering a housing
unit within the time restrictions of the project schedule, to the requisite construction standards of
the relevant stakeholders (National Water Commission, Jamaica Public Service, Portico Ltd.,
Jets Laboratory, etc) and within the budgetary allocation. The objectives were accomplished
46
mainly through monitoring the progress of all the activities included in the delivery of the
product of the project. Monitoring was facilitated by the development of a geodatabase that
stores various types of information required for the construction of a housing project. The
required information was extracted from the geodatabase for a given activity of the project by
using queries. Data collection and input were concluded on February 22, 2012 so the queries
will reflect the progress of all works up to that date.
The results of this research highlighted how this GIS model can assist a project
management team in delivering the product to the purchaser by providing effective monitoring of
all scope of works involved in the project.
47
1.Sewage
Manholes,Mains&Laterals
QualityControl
8.Landscaping&Lot
Demarcation
5.ElectricityNetwork
9.PracticalCompletion
Certification
2.StormWater
Inlets,Mains,EarthDrains
&PavedDrains
(PorticoLtd.)
3.RoadConstruction(A)
CuttingtoSubgrade,Marl
&Compaction,
6.WaterSupplyMains
10.HandingOverHousing
Unit
13.AdvancedVisualAids
11.RouteOptimizationfor
Equipment
12.DisasterResponse
7.RoadConstruction(B)
4.BuildingConstruction
KerbWalls&Asphaltic
Paving
4.3 Sewage
The initial scope of works will be installing sewer mains, manholes and laterals. In the
case of a phased development as the New Harbour Village II project, it may become necessary to
advance a particular scope of work beyond the confines of the subject area so as to facilitate
service for completed areas. This was the case with the sewer network as a connection was
necessary between Phases I, II and the Sewerage Plant located in Phase IV. Consequently, lines
were installed in Phase 3 prior to the commencement of the phase.
48
The infrastructure manager can simply query the operating status of sewer manholes to
ascertain the manholes which are facilitating the transmission of sewage from the completed
phases by running a query by attribute. ( Operational_Status = Operating)
49
The visual output as well as the generated report can aid in planning the remaining work,
from the perspectives of procurement of material in that it can be ascertained what materials and
services will be required to complete the task, it will aid in the mobilization and deployment of
equipment such as excavators, and backhoes. and finally prevent the disruption of service to
existing users. Having planned for this scenario, construction can commence, during which time
periodic queries can be done to ascertain the progress of works.
50
Stage 7 represents completion and approval of a particular sewer main so a relating query
can be executed as Sewer_Installation_Stage = Stage 7.
Figure 12: Visual Representation of All Completed & Approved Sewer Mains
Figure 12 will enable the project manager to implement the installation of sewer laterals.
Sewer laterals can then be queried at all stages once the model is updated with a degree of
regularity sufficient to facilitate the needs of the project manager. An example of such a query is
Sewer_Lateral_Status = Inst.
51
Owing to the fact that the information generated by the GIS Model is premised on as-built data,
quantities can be checked to verify invoices for payment as well as Store Keeping Inventory.
52
53
Block
Shape_Length
Pipeline_Dia.
Invert_In
Invert_Out
P67
Block A
58.103492 1200mm
13.48m
13.37m
P79
Block B
80.49081 1200mm
13.37m
12.66m
P81
Block C
100.55771 1200mm
12.66m
P82
Block D
97.541544 1200mm
<null>
Block D
P93
Contractor
Construction Stage
Approved_By
Anthony Dunne
Approved
James Williams
Approved
11.92m
James Williams
Approved
11.92m
11.43m
James Williams
Approved
27.856272 <null>
<null>
<null>
James Williams
Approved
Block D
7.319893 600mm
12.08m
12.02m
Anthony Dunne
Approved
P94
Block D
23.32607 600mm
12.08m
11.92m
Anthony Dunne
Approved
P95
Block G
90.198579 600mm
11.92m
11.40m
Anthony Dunne
Approved
P98
Block G
40.628882 1200mm
11.40m
11.28m
James Williams
Approved
P97
Block G
7.303958 900mm
11.84m
11.40m
James Williams
Approved
P96
Block F
77.545079 900mm
12.49m
11.84m
James Williams
Approved
P91
Block E
14.341658 600mm
12.92m
12.83m
Anthony Dunne
Approved
P92
Block F
70.50622 600mm
12.83m
12.62m
Anthony Dunne
Approved
P85
Block I
7.295134 600mm
13.27m
13.21m
Anthony Dunne
Approved
P86
Block I
60.306864 600mm
13.21m
13.00m
Anthony Dunne
Approved
P87
Block F
19.420225 600mm
13.00m
12.94m
Anthony Dunne
Approved
P88
Block H
10.069891 600mm
12.72m
12.65m
<null>
Approved
P89
Block H
33.176282 600mm
12.65m
12.49m
<null>
Approved
P90
Block H
23.359883 600mm
12.49m
12.14m
<null>
Approved
P74
<null>
7.886623 600mm
14.07m
14.07m
James Williams
Approved
P73
<null>
38.337654 600mm
14.07m
13.87m
James Williams
Approved
P71
Block J
7.314076 600mm
13.57m
13.50m
James Williams
Approved
P72
Block J
38.534452 600mm
13.50m
13.40m
James Williams
Approved
P68
Block B
7.33178 600mm
13.47m
12.66m
James Williams
Approved
P69
Block C
7.316219 600mm
12.56m
11.92m
James Williams
Approved
<null>
<null>
20.780739 <null>
<null>
<null>
<null>
<null>
The visual representation can be used to direct dependent activities such as the in-situ
construction of the various storm water elements such as inlets and outlets.The generated report
(Table 1) can be exported to Microsoft Excel to be used for quantity verification as the as-built
length of each line is provided. It can formulate or validate claims for payment for each subcontractor. It also provides a quick reference when remedial work is required as it can clearly
identify the sub-contractor responsible for each line.
54
Upon completion of the storm water mains , the progress of the following step (storm
water elements) can also be easily ascertained by viewing the values of the layer or simply by
query.(Construction_Stage = Stage6)
From Figure 15, a clear indication was achieved with regards to the elements which are
approved, but also of note is that once the map layer of the storm water mains is turned on, both
the mains and elements which are approved can be easily ascertained by simply viewing the
table of contents on the left of the viewport.
55
56
Roads
Road_Name
Construction Stage
Unit_Weight
Test_Specification Technician
Bay Circle
91.5%
<null>
<null>
Bay Circle
95.7%
<null>
<null>
99.5%
<null>
<null>
97.3%
<null>
<null>
Lagoon Circle
Asphaltic Paving
92.5%
1.75 in
2.128
Lagoon Circle
94.0%
<null>
<null>
Lagoon Circle
94.1%
<null>
<null>
Lagoon Circle
Asphaltic Paving
94.7%
2.00 in.
1.719
107.3 p.c.f
Lagoon Circle
Asphaltic Paving
93.0%
1.69 in.
2.139
Waves Avenue
Asphaltic Paving
92.5%
10
1.94 in.
2.128
This query highlights the section of roadway where laying of kerb walls is being done,
while the associated report (Table 2) can be used to provide more comprehensive detail of the
progress, quality, and quantity of work done.
57
58
At a simple glance at the model the various stages of buildings can be known (Figure 17),
however coupled with the generated reports a far more comprehensive analysis of building
activities can be achieved. The generated reports can be used to encapsulate the dynamics of
construction activities in that date are recorded for each stage of the construction. These dates
provide the basis for time management which essentially involves the processes required to
accomplish timely completion of the project. The actual date each activity occurs was stored in
the GIS model and was referenced to the Microsoft Project schedule.
59
Figure 18 speaks to the scheduled activities required to complete the project and their
relating dates which provide the premise for monitoring those activities. This report can be the
premise for developing trend analysis. Figure 19 encapsulates the sales of the units; the
developer/ contractor will take a keen interest in sales as these units arent built to order but
rather built then marketed so the process is ultimately driven by sales. The report bears contact
information of purchasers so they can be contacted if the need arise.
60
61
is a realisation of WGS84, a simple handheld GPS receiver can be used to relocate any
component part of the line to facilitate repairs, upgrading or maintenance.
In the event that the project manager may need to upgrade a line to a greater diameter to
increase pressure to provide a more cost effective route to an adjoining phase, he will need to
identify all concentric reducers so as to ascertain which location is best suited for his proposal.
Such a query can be made as Fitting_Type = Concentric Reducer3.
62
63
64
This is particularly useful to the management team as in the case of a block where the
architect will be called in for Practical Certification of Completion (PCC) inspection; the entire
infrastructure must be operational. This will be useful in the case where a particular item of work
is delayed the manager may deem it prudent to delay the PCC and inform the purchaser of a
change in handing over date.
This graphical output of progress aids in decision making in that construction activities
are often interrelated and as such one activity can be somewhat dependent on the progress of its
predecessor. With regards to electricity circuit, a particular circuit will be ready for the
installation of energy guards (EGs), mid-span connectors and phase transformers, so if the
65
model depicts a circuits as Approved then the sub-contractor can be asked to make the
aforementioned installations.
The GIS model facilitates accurate checks on material inventory as the usage of materials
can be queried with respect to the quantity procured and in addition to a visual representation, a
detailed report will illustrate the quantity used as the model was populated by as-built data.
Checking the quantity of 12.0m poles installed can be was executed by a simple query.
(Pole_Height = 12.0m)
66
The generated report can be used as a basis for verifying a sub-contractors invoice for
payment as the quantities for claim can be verified by both the visual and textual responses from
the model. The need for enhanced safety systems has been highlighted by Karam (1997) who
extrapolated that the construction industry is perceived to be one of the most hazardous
occupations, and ranked low in safety, quality control, and proper information system. This
Model can certainly enhance safety on site as it is commonly found in a phased development that
the deployment of equipment such as cranes are key to the execution of casting activities, the
GIS model will highlight where lines are energized so as to safely mobilize/ demobilize
equipment without danger of damage to equipment, disruption of service to customers and
certainly without loss of life or injury.
67
68
69
70
Having queried or identified each map layer, and satisfied with the quality of work, the
project manager can now call in the architect for PCC inspection. The results of this PCC
inspection is given as a written report, with recommendations specified where approval is
denied. The results of the PCC inspection (Appendix N) can be loaded to the GIS model by
simply scanning and hyper-linking it to the associated building or if available in tabular form it
can be joined to the attribute data.
Having updated the model with this information, a simple query can show the PCC
approval status of each building. The project manager can easily retrieve this information by a
71
72
73
Task Name
Duration
Start
Finish
19 22
139
3 days
Wed 10/19/11
Fri 10/21/11
140
141
3 days
Sun 10/23/11
Tue 10/25/11
3 days
Wed 10/26/11
Fri 10/28/11
142
143
3 days
3 days
144
3 days
Tue 11/08/11
Thu 11/10/11
145
Clean House
3 days
Fri 11/11/11
Tue 11/15/11
146
147
148
90 days
149
23 days
Wed 10/05/11
Thu 11/03/11
150
3 days
Wed 10/05/11
Fri 10/07/11
151
Plastering
3 days
Wed 10/05/11
Fri 10/07/11
152
Install Windows
2 days
Wed 10/05/11
Thu 10/06/11
153
2 days
Wed 10/05/11
Thu 10/06/11
154
3 days
Wed 10/05/11
Fri 10/07/11
Thu 11/17/11
Thu 11/17/11
74
From the Figure 31, the project manager can ascertain with relative ease that based on the
scheduled date of Practical Certification of Completion of Block A (November 16, 2011) that
BLOCK A was late by twelve days since the generated report of actual dates speaks to
November 28, 2011. From this information he can analyse why this delay occurred and perform
his schedule control operations which may include rescheduling the following successor
activities. From the data gathered it cannot be concluded why this delay occurred but it was
highlighted and as such it will aid in rescheduling the following tasks.
75
76
Proper sequencing will enhance safety in the site in addition to improved efficiency
which can be manifested in the delivery of the product faster. This may be a contributing factor
in delay as two cranes arrive to cast the same building or one is in operational radius of the other
and has to re-position itself to facilitate the completion of the task. There are obvious cost
savings underpinning efficiency as time and fuel is wasted, which ultimately translates money
wasted.
77
Not only was the nearest hydrant (78.2m) located but an emergency route was charted
through easement #2. The response personnel was told all this information so that they will travel
with hoses in excess of this length so that they can refill without even moving the trucks as
opposed to driving 2km to Old Harbour in peak hour traffic.
78
79
80
This feature is particularly useful when data sharing will be done, the end user can
determine when was the last update, who collected the data, etc. which will determine the extent
of its suitability or applicability.
81
Water Course,
Fishing Ponds,
Phase 3 Site
This feature provides a useful location map of the subject in that can be used in disaster
management to chart evacuation routes; it can easily identify flood prone areas in relation to the
site. As shown in Figure 39, the roads in close proximity are shown as well as water bodies and
water ways.
82
Considerations
Total Cost
(USD)
(USD)
Supplier
10,584.00
10,584.00
Dell
2,203.99
2,203.99
Dell
449.99
449.99
Dell
599.99
599.99
Best Buy
AutoCAD LT 2012
914.99
914.99
Dell
GIS Analyst
2,786.08 /
Factor
UTech
month
GIS Training
465.00/
465.00
Mona
1 persons
Arc Editor Software +
7,000.00
Geoinformatics
14,000.00
Maintenance (3 years)
Licence + Maintenance
Innovision Ltd.
2
(3 years)
APC Smart-UPS 750VA
Spatial
15,000.00/
15,000.00
2 persons
1
339.99
Spatial
Innovision Ltd.
339.99
Best Buy
Source: Hamilton (2012)
83
InterestinGISImplementation
PersonsNot
Interestedinthe
Implementation
ofaGIS
(42%)
Persons
Interestedinthe
Implementation
ofaGIS(58%)
In response to question 5, would you be willing to participate in GIS training to aid you
in the workplace? (Appendix E), six of thirteen workers expressed a willingness to participate in
GIS training to be able to utilize the proposed GIS_GDL.
84
WillingnesstoParticipateinGIS
Training
Willingto Participate inTraining
45%
55%
In response to question 6, what age group are you in?(Appendix E), the age group of 2633 years old accounted for 55% of the New Harbour Village II Project staff.
AgeofRespondents
Age18 25
27%
Age2633
Age34&Over
18%
55%
85
In response to Question 7, how long have you been employed at Gore Developments
Ltd.?(Appendix E), persons with 2-5 years working with GDL accounted for 64% of the staff.
YearsofEmployment
1YrEmployed
25YrsEmployed
610YrsEmployed
Over10YrsEmployed
9%
18%
9%
64%
Findings of Interviews
86
The interviews also highlighted the components of the work breakdown structure
(Appendix H) which is a deliverable based decomposition of the tasks required to complete the
product of the project. This was of particular significance owing to the fact that the deliverables
will help to formulate the design of the conceptual schema of the geodatabase design.
The interview revealed that the project management team at the New Harbour Village II
project employs a strategy which is hinged on a Microsoft Project Schedule which decomposes
the project into interrelated tasks, their duration, start and finish dates as well as relationships.
During the interviews an explanation was given to the schedule of works which was produced by
the project manager in a one point estimate approach, which was justified as being the most
experience person in the organisation, having presided over the construction of in excess of five
similar housing developments. The schedule was created and updated using Microsoft Project
2007. (Appendix I)
The project manager is supported by a site manager who has a direct responsibility to
execute the tasks as scheduled. The site manager is supported by managers of each sector of the
project; these managers are responsible for infrastructure, stores, housing, and batching concrete.
Each manager is supported by their respective staff. (Appendix G)
The project manager convenes a fortnightly meeting during which a report on the
progress of the tasks associated with the project is given by the manager responsible for that item
of work. This process also spoke to the daily duties of supervisors, the role of private and public
stakeholders such as the National Water Commission, Jamaica Public Service Co. Ltd., Parish
Council, National Environmental Protection Agency, National Land Agency, Jets Laboratories
Ltd., Portico Ltd., etc. These are the agencies which are responsible for testing, checking and in
many instances certifying the final product/ service.
87
Aerial photographs were previously taken by a consultant but are currently taken courtesy
of a helicopter owned by Gore Development Ltd. at the end of every month. These photographs
are acquired to provide a visualization of the status of construction activities.
The project manager also uses AutoCAD 2009 to illustrate whether by hard copy or on a
projector screen whatever spatial information he wants to convey to his management team.
The housing manager uses Microsoft Excel and Access to store his inventory information
as well as sales which include names, TRN, address and contact information of each purchaser.
This information can be readily applied to a GIS based model as information is structured in a
tabular format which facilitates easy update and data entry. This manager updates his sales
information daily. However the information required for monitoring the construction stages of
the house is not kept.
The store manager execute his record keeping by written documents which are not very
detailed in that the specific location of material usage is not given and in many instances the date
of dispatch is also missing. This system speaks to lack of proper records which will result in poor
inventory management.
The batching plant manager employs Microsoft Excel to very good effect to keep records
of concrete volumes batched and location of use, strength, date of casting, truck driver, volume
of aggregates, cement, etc. These records are updated daily as casting is done on a daily basis.
This information fits seamlessly in a GIS database as information is up-to-date and tabulated.
The stages of building construction relating to concrete such as casting foundation and wall were
acquired from these records.
During a fortnightly meeting each manager reports on their progress as well as any
problems they may have encountered, the accountant provide a financial statement where
88
quantities and earned value are checked. The project manager also revealed in the interview that
all rates of payment for work and workers were based on the Incorporated Master builders
Association of Jamaica Construction Manual. (Appendix P)
In an interview with four departmental managers based on the questions compiled in
(Appendix #D) with particular reference to question 6-8, three manager had an idea of what GIS
was, based on what they read on the internet, those three persons were also willing to change
their current methodologies of data gathering, storage and presentation but all four expressed a
willingness to participate in GIS training. Based on the respondents from this group, there is a
clear interest is the implementation of GIS to aid in management.
89
more informed assessment and reporting; secondly, project managers can visualize progress
integrated with qualitative data.
According to Nadine Smith, (2012), a product of the Business Intelligence approach is
the use of Microsoft Project Server which facilitates powerful business collaboration platform
services with structured execution capabilities to provide flexible work management solutions.
Project Server is built on Microsoft SharePoint and unifies project and portfolio management to
help organizations align resources and investments with strategic priorities, gain control across
all types of work, and visualize performance by using powerful dashboards. The practical benefit
of this approach is seen on the Longville Housing Project where the various schedules and work
flow documents are shared through this medium.
The N.H.T.s proposed development of the GIS will include the use of ArcGIS for
SharePoint. The useofArcGIS for SharePoint will add geospatial view to the organization's data
by offering interactive and configurable mapping components. Since Microsoft Project Server
will integrate all textual components inclusive of schedule, the addition of the ArcGIS for
SharePoint will create a link between the spatial data and the project schedule. This proposed
approach can serve as a premise to formulate integration of the geodatabase and the project
schedule which would provide an automated update of the schedule.
90
91
According to Ian Bennet (2012), the rationale for utilizing the Microsoft bundle of
software include the relative ease of which interoperability was achieved, the cost compared to a
customized software, the fact that the strengths of each software can be maximized to yield a
more comprehensive project management tool and finally it can be developed faster than writing
programs to fulfill the same purposes.
Ian Bennet (2012) indicated that the benefits of this approach includes the fact that it
requires less data intensive methods of updating the GIS as field officers, managers can email
updates from the field in hypertext markup language (.html) format to the GIS, which once
vetted by the input personnel is automatically uploaded. Another benefit is that it was developed
at a far cheaper cost that the corresponding approach of writing several scripts to enable the
aforementioned functions. The GIS is beneficial in that it is capable of storing and manipulating
multiple projects far easier than a conventional database plus the added bonus of visualization.
The use of this system was extended to pipeline analysis whereby the proposed route was
mapped; the progress of the work is mapped and referenced to schedules. This aspect of the GIS
bears distinctive similarity to essence of this final year project. This approach has also employed
mechanisms and scripts to create a seamless link between all datasets which is the ultimate aim
of all databases.
92
5.1: What are the Current Project Management Techniques/ Tools employed at the New
Harbour Village II Project? (Research Question1)
The current approach to project management at the New Harbour Village II project does
not manifest the maximization of efficiency. Aerial photographs have to be supplemented by
AutoCAD drawings which highlight the inefficiencies in regards to progress reporting and
spatial layout.
The current approach epitomizes the absence of a single system for data storage, whereby
the housing manager uses Microsoft Excel and Access, the batching manager also uses Excel for
record keeping while the store manager keeps written records. There is no data sharing among
managers, which resulted in each manager keeping records of material used which is the ultimate
responsibility of the store manager. Thus overlaps exist with regards to material.
The current approach represents a total contrast to the GIS model (GIS_GDL) since the
model offers a platform for mass storage as it contains a large quantity of graphical and textual
information. Figure 8 (page 45) illustrates that all twenty construction activities were replicated
in the model. These activities are represented by a map layer and relating attribute tables of the
93
pertinent fields, forming a single medium for all forms of data. The model integrates all datasets
to enable spatial reference, advanced query and analysis. The current approach offers no such
integration and as such result in overlaps in information as seen where the Store and Batching
Plant have the same records for aggregates, cement and concrete admixtures while there are no
records of the dynamic processes of the construction stage of buildings and infrastructure.
Though photographs (Appendix A) exist which give some level of graphical
representation of the subject area, the relational model offers a more comprehensive and accurate
alternative as it is not adversely affected by relief displacement which affects aerial photographs.
All datasets in the GIS model have the same scale factor, the same map projection and the same
terrestrial reference system; hence data can be accurately represented both relatively and
absolutely.
Ideally it would be the preferred option to replace meetings with a simple query or series
of queries but realistically no system can truly dispense with the need for meetings. The GIS
model will provide an avenue to equip the personnel in the meeting with information which will
facilitate faster and more logical decision making than the current approach.
5.2: What is the Rationale for GIS in Project Management at GDL? (Research Question 2)
Both Vijay and Kartam suggested a need for effective computerized methods in
construction management which would efficiently integrate safety and quality control, during
construction as well as the incorporation and evaluation of other important aspects of a project
such as costs. The GIS model illustrated Figure 8 (page 45) the capability of seamlessly
integrating twenty elements of work. This integration will result in the elimination of overlaps in
data storage as observed with material inventory in addition to facilitate the sharing of data
94
which can improve efficiency as time is not wasted collecting data which was previously
collected.
The local cases of the National Housing Trust and the National Water Commission
certainly provide a blueprint for seamless integration of all project information, both spatial and
non-spatial in addition to a more automated link between the project schedule and the spatial
layers of deliverables.
The current approach employs field reports to be stored as hand written documents with
sketches whereas the GIS model offers a more standardized approach. Data gathered and stored
in various formats such as AutoCAD drawings for each scope of work was converted to shape
files and Microsoft Excel tables for all quality control, quantities, progress, sales, etc. were
stored as attribute tables. This resulted in the reduction of the disjoint in information which will
support decision making and schedule control.
The case study of the water supply project of Newstead, New York gives validity to the
approach of using GIS to aid in construction management, particularly on large projects
undertaken in phases. The contractor Wendell Duchscherer sought to improve his data collection,
storage and sharing through GIS technology which simplified his operations, reduced duplication
of data and improve his efficiency. Similarly, the GIS model simplifies the project managers job
with specific reference to monitoring scopes of work in that the complexity involved in
interpreting and structuring data from a multiplicity of sources in various formats are all handled
by a geodatabase, which essentially links locational to thematic data in one environment. In the
current approach at GDL thematic and locational data are separately compiled and require some
manual arrangement to ascertain the overall picture.
95
The GIS model provides capabilities to solve problems, involving creation of reports,
visualization of activities simultaneously and aid in quantity and quality checks to which no
component of the current approach has the capacity to deliver, neither individually nor
collectively.
Efficiency level is directly proportional to success level in the construction industry and
as such is critical to construction management. The quantity of data associated with a 2500 lots
housing development can be quite substantial and will require a system which will standardize,
store, manipulate and update data so that it can be retrieved in a format necessary to support
decision making without losing its accuracy.
As demonstrated in the results (Figures 32 & 33) the GIS was utilized to rationalize crane
operations as well as support disaster response (Figure 35), so the GIS Model was able to
provide solutions by efficiently integrating safety and quality control, during construction as well
as disaster. The real scenario depicted in Figure 35, provided a refilling solution to fire trucks,
which in its absence truck would have gone further a field in search of the same service, so this
use of the model has reduced the refill period. In the situations accounted for in Figures 32 & 33,
the operational routes for cranes were pre-determined by the GIS model (GIS_GDL) and can
serve as a guide to the operators of both cranes so as to eliminate conflict in their duties as well
as maintaining safe working distance between them.
The GIS_GDL demonstrated that it can be used to evaluate claims for payment, serve as
the basis for earned value/ planned value analysis thus preventing overruns. As in the case of
(Table 1), quantities can be verified to substantiate payment requests, material inventory and asbuilt records.
96
As laid out in the methodology of the model development (Section 3.15) the GIS model
(GIS_GDL) also provided a computerized quality control mechanism through topology where
rules are set which will highlight aspects of the work which contravenes the applicable laws,
building codes and operational safety regulation. The previous approach operated on a more
manual mode which can result in codes, laws and regulations to be easily overlooked.
GIS is ideally suited for large scale projects such as New Harbour Village II, where a
visual representation of the progress of all works would be essential in extended monitoring, not
only for the construction process itself, but also to all the auxiliary activities, including the onsite
batching plant, store keeping facility and equipment. Visualization allows the construction
manager to view the construction activities during any stage of the construction process thus
facilitating more logical decision making.
5.3: What are the Potentials of a GIS Model for Construction Management? (Research
Question 3)
The potentials of the GIS model are aligned to the requirements of the project
management team, which were ascertained through interviews. The potentials were manifested
by queries of the model in a structured sequence characterized by Figure 9 which replicated the
order of activities of the study area.
97
II Project is comprised of 2500 housing unit and is scheduled to have duration of ten years; such
a project will no doubt have an enormous amount of data which can be stored in a GIS. The fact
that the GIS model has the additional capabilities of querying, analyzing, and displaying data it
can aid in monitoring project tasks and rational decision making.
98
99
the field denoted by shape_length, hence the summation of this field yields the total quantity.
This report can be interpreted to derive quantities per block, quantities done by a specific subcontractor and certainly quantity approved.
This capability also provides a premise for costing from the perspective that the quantity
of pipes installed, at a certain rate per block, over a specific period can give an estimate of the
cost to complete a block. This capability can aid a project manager in determining the earned
value of a particular scope of work. The earned value is essentially the value of the work
performed expressed in terms of the approved budget assigned to that scope of work for a
schedule activity or WBS component. (PMBOK, 2004)
This earned value will subsequently help the project manager to derive an objective
measurement of the performance of the project progress by simply comparing earned value to the
budgeted cost or planned value of the work.
100
101
all scope of works, in buildings the compacted marl pad must yield a minimum of 90%
compaction from a density test as a prerequisite to casting foundations.
Similar examples include the water supply mains must meet the standards of
microbiological tests of the laboratory of the National Water Commission prior to been
approved, and the electricity circuit must meet earthing (grounding) standards prior to been
energized. All quality control parameters are uploaded to the GIS model, which facilitate queries
and provides a basis for continuity in the work.
The GIS model can highlight cases where buildings straddle boundaries as defined by the
topology described in chapter 3; however there were no occurrences of this problem.
5.3.8 Safety
The case of redeploying equipment such as cranes it can be derived from the model the
height of poles in addition to the energy status of transmission lines which will aid in the
decision of the mobilization/ de-mobilization routes.
102
Another real world occurrence of a recent bush fire brought to fore the usefulness of GIS
in disaster response as within seconds a route and refilling point was derived without even a
simple query, but simply by a visualization of all the components of the scenario.
5.4 What are the Challenges in the Developing and Utilizating the GIS Model (Research
Question 4)
The current approach utilized methods which were not entirely conducive to a GIS based
environment, so inherently there will be challenges regarding data collection and storage. The
cost of software and hardware will also pose challenges from a student research perspective.
103
National Water Commission as in their case data is gathered for a GIS environment so the
records are complete, up to date and standardized.
The completeness of record keeping may have been a hindrance but wherever dates were
kept they were referenced to the schedule as shown in the results where the date of the Practical
Certification of Completion (PCC) of a block was referenced to its scheduled date resulting in a
check of the overall process as since PCC is the final stage it spoke to the ability of the model to
track a series of activities. In this example the scheduled date of Practical Certification of
Completion of Block A (November 16, 2011) and the actual date was November 28, 2011.
This situation shows a delay of twelve days which can be further analysed by a GIS Model if
proper records existed.
104
5.5 What are the Implications of Employing a GIS as a Project Management Tool in
Construction Management? (Research Question 5)
Proposing a change in some aspects of the managerial approach on a construction project
will certainly have implications on the organisation; the foreseeable implications are cost of the
proposed approach, staff, maintenance/ updating of the new system and finally how this system
will impact overall efficiency.
105
5.5.1 Cost
Any new approach to management structure will have cost implications, in the case of
implementing GIS_GDL to aid in monitoring all scopes of work at the New Harbour Village II
project there will be the requirement of an investment into GIS related technologies. The project
manager at GDL, expressed that he is willing to implement a new system to aid in his duties
under the condition that it is within his budget, so despite the capabilities illustrated in the results
chapter, cost is a major factor.
The costs which will be considered at this stage are related to hardware, software and
personnel. The hardware considerations include personal computers, work stations, peripherals,
internet and networks devices. Software considerations will include the ArcEditor Software and
Licensing Agreements. Personnel considerations will include staff training and/or employment
of a new employee.
Since all departmental managers and staff have computers with ethernet and Wifi
capabilities, the immediate requirements will be a server and another personal computer for a
newly employed GIS analyst. The hardware and software listed in (Table 6) will be sufficient to
execute the steps discussed in the methodology of this research. The total cost of hardware and
software considerations is 44,557.95 USD, if this cost is spread over the duration of the project
which is ten years the cost per year of this system would be 4,455.795 USD.
Based on the Incorporated Master builders Association of Jamaica Construction Manual
(01.02.2011 to 31.01.2012) the rate per day (8-hour day) for a labourer is 1,761.25 JMD (20.16
USD) which suggests that for a labourer employed for a year (49 week @ 5 days/ week) the cost
of employment would be 4,939.20 USD. The projected increment of increase in rate for a
labourer for 2012 to 2013 is 5% which would translate to a salary of 5,186.16 USD. (Appendix
106
P) The cost of the GIS to Gore Developments Ltd. would be less than the cost of the least paid
employee per year with considerably more capabilities and benefits than the current approach.
5.5.2 Staff
New approaches to work require new expertise and this means hiring new personnel or
retraining of existing personnel or both. The final decision will be based on the cost to hire new
personnel, the willingness and ability of existing personnel to be retrained and the organisational
policies.
From the interviews it was revealed that of the current staff, no one has GIS qualification,
expertise or experience. The staff structure in the organisational breakdown structure (Appendix
G) shows each person assigned specific duties and as such the implementation of a GIS would
require GIS training or the hiring of GIS personnel. The case of training staff will incur costs as
well as hiring new personnel. The organisation will have to decide on the approach to be taken
whether to hire, train or both. The staffing arrangement could also involve job losses as
personnel may be replaced by persons with GIS capabilities who can fill current roles.
From the result of the questionnaire (Appendix E) completed by eleven members of staff,
55% (6 persons) of the staff expressed willingness to participate in GIS training and 58% (7
persons) of staff expressed an interest in the implementation of GIS to aid in monitoring all
scopes of work. This speaks to the need to train the staff to be competent in GIS. Of five persons
(45%) not willing to participate in training, three were among the age group of over 34 years old
and the other two are employed to GDL for over two years.
107
These statistics show a correlation between age, years of employment and unwillingness to be
trained in GIS technology. Thus the older members of staff and those longest serving have
expressed an unwillingness to participate in GIS training.
108
The National Housing Trust offers web enabled links to their system where marketing
personnel as well as customers can access information relating to certain products. Both these
web enabled capabilities could significantly advance the efficiency of the operations of a
construction project.
109
This level of efficiency means there should be no lag between successive tasks, as is evident in
the fact that once the buildings are approved by the architect, the project manager can authorize
handing over.
110
6.1 Conclusion
The aim of this research was realized in that GIS model (GIS_GDL) was successfully
developed to map all deliverables by the use of map layers and attribute tables. The GIS model
has demonstrated its capabilities to monitor the progress of works and its ability to provide
further aid in analysis of site activities.
The objectives of this research were also realized in that the GIS model facilitated the
storage, integration, and query all project information which aided in making faster and more
logical decisions. The GIS model also aided in schedule control as each activity was tracked with
reference to a schedule. The model also provided reports which can be the premise for payments
and material inventory. The model also provided aid in safety in the site activities and aid in
disaster response.
The methodology, results and applicability of this research have been grounded in similar
applications of GIS both locally (N.H.T and N.W.C) and internationally (Newstead Water
Supply Project, New York) which speaks to a level of validity of this research and more
importantly a legitimate case for GIS based application in the construction industry in Jamaica.
111
6.2 Recommendation
1. The Surveying and GIS programme should be extended to include Database Management
and Programming as the possibilities of GIS software can be expanded immensely by
customized scripts and since GIS is rooted in database technology, it is logical to include
it in a module.
2. Group projects should be undertaken, but the possibility that the group can be comprised
of student from other programmes of the faculty or of other faculties must exist. This
would be beneficial in this research as the level of knowledge would be wider if students
with programming, construction and project management was included in a group. I think
that process would be more likely to generate a more useful project to the society as
opposed to just a requirement to complete a programme.
3. Construction projects of duration in excess of five years should utilize GIS in project
management as the benefits will outweigh the implementation costs over this period.
112
113
References
Bansal, V. K., and Pal, M. (2005). GIS in Construction Project Information System
Proceedings of Map India, 8th annual international conference and exhibition in the field
of GIS, GPS, Arial Photography, and Remote Sensing. New Delhi, India.
Bansal, V.K. and M. Phal. (2006). GIS based Projects Information System Construction
Management. Asian Journal of Civil Engineering (Building and Housing). 7(2): 115-124.
Bennett, I. (2012, March 15), Interview on Current Capabilities and Utilization of GIS at the
National Water Commission.
Burrough, P.A. and McDonnell .(1998). Principles of Geographic Information Systems: Spatial
Information Systems and Geostatistics. New York, USA: Oxford University Press.
Bestebreurtje, J.A. (1997). GIS Project Management. Netherlands, Amsterdam: Manchester
Metropolitan University.
Boxe, N., Spence, D. and Lane, K. (2003). Basic Construction Manual - For A Single Storey
Domestic Dwelling. Incorporated Masterbuilders Association of Jamaica.
Carter, N. and Seider, D. (2006) GIS Improves Construction Management, Newstead, New
York.
Cheng, M.Y and Yang, C.Y. (2001). GIS-Based Cost Estimate Integrated with
Material Layout Planning. Journal Construction Engineering and Management, Vol.
127, no. 4, pp. 291-299.
Clarke, J., (2008.) Appetite for Construction. Presentation. Australia: Thiess.
Easa, S., and Chan, Y. (2000). Urban Planning and Development Application of GIS.
USA, AL: American Society of Civil Engineers (ASCE).
114
115
Project Management Institute. (2008). A Guide to the Project Management Body of Knowledge:
PMBOK Guide fourth Edition. Pennslyvania, USA: Project Management Institute, Inc.
Richardson, K., (2011). Enhancing the Commercial Real Estate Life Cycle. California, USA:
ESRI, retrieved September 25, 2011, http://www.esri.com/news/arcuser/0611/enhancingthe-commercial-real-estate-life-cycle.html.
Seaman, K., (2008). Commonwealth of Dominica: Multipurpose Cadastre Project.
Smith, N. (2012, March 07 & 14), Interview on the State of the National Housing Trust GIS.
Sultan, K. and Turker. M. (2001). Developing a Cadastral Information System with a
Spatiotemporal Modeling Approach. ankaya Ankara, Turkey, Middle East Technical
University.
Toprakli, Y., GIS use in Construction Management. Retrieved September 27, 2011,
http://w3.gazi.edu.tr/web/toprakli/research_materials/GIS%20use%20in%20CONSTRU
CTION%20MAN%20I.pdf.
Zhang, J., Zhong, D. and Hu, C., (2005). GIS-Based Simulation of Engineering Construction
Schedule (Vol. 11). Tianjin, China: Tianjin University.
116
Phase 3
117
Appendix B Conceptual Schema for Monitoring Scopes of Work at New Harbour Village II
Project
118
119
120
Appendix C
INTERVIEW QUESTIONS TO PROJECT MANAGER
121
Appendix D
INTERVIEW QUESTIONS TO DEPARTMENT MANAGERS
122
Appendix E
QUESTIONSTIONAIRE TO STAFF MEMBERS
1. Do you think there is room for improvement in the execution of your duties?
Yes
No
No
TV
Journals
Internet
Other
4. Would you like to see the implementation of a GIS Model to improve efficiency in
managing the project?
Yes
No
5. Would you be willing to participate in GIS training to aid you in the workplace?
Yes
No
26 33 yrs
34 and Over
2 5 Yrs
6 10 Yrs
Over 10 Yrs
123
124
PROJECTMANAGER
ISRAELPINCHAS
SITEMANAGER
ASAFKEREN
ADMINISTRATIVE
ASSISTANT
B.BONNIE
HOUSINGENGINEERING
MANAGER
SURVEYOR
INFRASTRUCTURE
STOREMANAGER
MANAGER
L.PENNANT
E.ALDAXA
INFRASTRUCTURE
SUPERVISOR(ROADS)
C.REID
J.ZITSPERGER
HOUSING
SUPERVISOR
C.FULLER
HOUSING
SUPERVISOR
L.GORDON
REMEDIALWORKS
SUPERVISOR
INFRASTRUCTURE
SUPERVISOR
(DRAINAGE&SEWAGE)
O.FERGUSON
SPECIALPROJECT
SUPERVISOR
A.DOUGLAS
F.GRANT
W.HAMILTON
LANDSCAPING&
AGGREGATES
O.GORDON
BATCHING
MANAGER
J.PRINCE
SCALECLERK
N.HENRY
EQUIPMENT
SUPERVISOR
C.PARKER
ACCOUNTANT
C.SMALL
SECURITY
U.BROWN
125
CONSTRUCTIONOFPHASE3,NEW
HARBOURVILLAGEII
SEWER
STORM
DRAINAGE
ROADS
BUILDINGS
COLDWATER
SUPPLY
ELECTRICITY
SUPPLY
PARCEL
HANDINGOVER
InstallManholes
InstallPipelines
Construction
Stage
Lot#,Owner,
Address,Block
ElementType,#
ElementType,#
Lot#,Type
DeliverPractical
Certificateof
Completion
InstallMain
Pipelines
Install/
Construct
Elements
Inspection
Construction
Stage
Installation
Stage
Installation
Stage
BoundaryStatus
DeliverKeys
InstallLaterals
Construction
Stage
Approval
Mold#,Crane#
Testing&
Inspection
Testing&
Inspection
Construction
Stage
Testing&
Inspection
Inspection
Approval&
Certification
Approval&
Certification
Testing&
Inspection
Approval&
Certification
Approval&
Certification
Approval&
Certification
HandingOver
BlockEnergized
126
Task Name
Duration
70
1 day?
71
Paved Inlet1
1 day?
72
Storm Line 67
1 day?
73
1 day?
74
Waves Avenue
1 day?
75
Lagoon Circle
1 day?
76
1 day?
77
Bay Circle
1 day?
78
1 day?
79
Block A
5 days
Wed 06/15/11
Tue 06/21/11
80
Block B
5 days
Wed 06/22/11
Tue 06/28/11 79
81
Block C
6 days
82
Block D
6 days
Thu 07/07/11
Thu 07/14/11 81
83
Block E
7 days
Fri 07/15/11
Mon 07/25/11 82
84
Block F
7 days
85
Block G
7 days
Thu 08/04/11
86
Block H
6 days
87
Block I
5 days
Tue 08/23/11
Mon 08/29/11 86
88
Block J
9 days
Tue 08/30/11
Fri 09/09/11 87
89
CAST FOUNDATION
1 day?
90
8 days
Thu 09/01/11
Mon 09/12/11 79
91
8 days
Tue 09/13/11
Thu 09/22/11 90
92
8 days
Fri 09/23/11
Tue 10/04/11 91
93
9 days
Wed 10/05/11
Mon 10/17/11 92
94
11 days
Tue 10/18/11
Mon 10/31/11 93
95
11 days
96
11 days
97
9 days
98
17 days
Thu 12/15/11
Fri 01/06/12 97
99
22 days
Mon 01/09/12
Tue 02/07/12 98
100
1 day?
101
8 days
Thu 09/08/11
Mon 09/19/11
102
8 days
Tue 09/20/11
Thu 09/29/11
103
8 days
Fri 09/30/11
Start
Finish
Predec
Thu 12/01/11 95
127
128
129
130
131
132
133
134
135
Appendix O Interview Questions to the National Housing Trust and National Water
Commission.
136
137