You are on page 1of 124

4.

Specification - Landscaping
Prepared by Michael Smith and Associates
Landscape Architecture and Urban Design
In conjunction with:
STORM Consulting Pty Ltd
Martin Butcher Lighting Design

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

19

1.

PRELIMINARIES

1.1 Scope
The landscape works are to be carried out in accordance with this
Specification, Plans, Details and Bill of Quantities. This Specification will be
read in accordance with Specification sections and drawing notes from the
Engineer (STORM Consulting) and the separate Specification from the
Lighting Designer (Martin Butcher Lighting Designs).
Any found conflict between the Specification, Drawings and Details or Instruction
will
be brought to the Superintendents attention for clarification prior to tender closing.
The works include the supply and construction of all work, materials and
equipment necessary for the proper completion and establishment of works
shown or implied in the Specification and associated drawings and documents.
The works for the Greeves Street, St Kilda Streetscape Upgrade will include
but not be limited to, the following:

Set out, earthworks and excavation/filling;


Erection of fencing to the works site to prevent public access;
Excavation and removal of existing gravel surfacing;
Removal of several sections of existing bluestone kerb and channel that have
become displaced along the street. Salvage and securely store to avoid theft;
Removal and disposal of section of existing road surface;
Excavation and removal of existing brick speed humps;
Removal and disposal of existing tufting plants, low shrubs, ground covers and
mulch to existing garden beds;
Protection of existing underground services and confirm by using an
underground
detection firm to prove location;
Removal and disposal of existing grassed surface and soil to sections of the
nature strip;
Protection of existing trees to be retained;
Protection of existing assets including grassed areas, road surfaces and existing
path surfaces;
Protection of private property gates, fences, paths and plants;
Supply and construction of a bluestone pitcher edge to new garden bed areas.
Bluestone pitchers available from Councils Depot;
Supply and construction of asphalt surfacing;
Re-setting of the removed bluestone kerb and channel;
Preparation of planting areas, supply of topsoil and mulch;
Supply and planting of shrubs and groundcovers;

Thinning of canopy of existing eight Desert Ash trees;


Preparation of grassed areas, supply of topsoil, preparation of topsoil, supply and
installation of instant turf;
Relocation of two existing litter bins from Carlisle and Inkerman Streets;
Contract No: 1799
Title: Greeves Street, Streetscape Upgrade
20
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Repairs and miscellaneous items;

Maintenance and Establishment, Construction Defects Liability and


maintenance
on all supplied and constructed items above.
Carry out the following works in accordance with Specification sections and
drawing notes by STORM Consultancy Pty Ltd and Martin Butcher Lighting Design:
Removal of one existing side entry pit;
Supply and installation one new side entry
pit; Upgrading of two existing side entry
pits;
Supply and construction of 12 timber garden light posts;
Cabling, electrical works and supply and connection of Distribution boards;
1.2 Protection of existing and new works
The Contractor is responsible for the protection of existing public assets and the
new works during construction and making good any damages during
construction.
The Contractor is required to take photographs or videotape legibly the existing
site to ensure queries as to the nature of the existing site, prior to
commencement of works, can be confirmed.
1.3 Construction Management Plan
The Contractor is to prepare a Construction Management Plan within 7 days
of receipt of the Letter of Acceptance. The plan is to be submitted for approval by
the Superintendent. The plan will include the following:
Proposed location of storage for plant and
materials; Proposed access routes and vehicles
for access; Storm water and sediment control;
Waste and materials management;
Traffic management Plan, to the satisfaction of the City of Port Phillip.
1.4 Site for Works
This project involves landscape works (and coordinated Drainage and
Lighting
works) at Greeves Street, St Kilda Streetscape Upgrade (Melway Reference 2P
D7
and D8).
1.5 Inspection of Site

Contractors must undertake a mandatory visit to the site prior to tendering


to ascertain for themselves the actual extent of work to be undertaken, the
nature of and the difficulties associated with the works. The client will not consider
any claim whatsoever on account of failure to do so.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
21
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

1.6 Site Access, Vehicle Control and Noise Control


Site access to Greeves Street, St Kilda is to be from adjoining streets
Inkerman Street (2P D7) and Carlisle Street (2P D9). The northern half of
Greeves Street is one way south bound from Inkerman Street to the Vale
Street intersection The Contractor should make themselves familiar with the
access points and consider the transport and loading / unloading of plant and
materials. Avoid using Blanche and Vale Streets for access. Access to the site
will be discussed in detail at the tender stage and confirmed with the successful
contractor.
Plant and equipment must be capable of being maneuvered on site without
damage to the site, works and adjacent areas.
The Contractor is to work solely within the confines of the immediate Greeves
Street
corridor. Vehicles, machinery and materials are not to access or be stored to
the
areas beyond the Greeves Street corridor. Any private or public assets damaged
beyond the Greeves Street corridor are to be reinstated by the Contractor
following
completion of construction and horticultural work. Soil disturbance within the
Greeves
Street corridor should be limited to areas of new works and the Contractor
should
avoid disturbance and compaction around root zones of trees. Upon completion
of
works the Contractor is responsible for making good and reinstating any areas
of
ground within the Greeves Street corridor which have been disturbed during
the
works.
The Contractor is to undertake all works in accordance with EPA noise regulations
in a residential area.
1.7 Provision for Traffic as per City of Port Phillip Requirements
1.7.1 Definitions
Work Zone
The length of roadway within the Contract limit of the Works
as
specified.
Work Area
The specific area where work is being carried out, as defined in
the
Contract.

Side Track
A temporary roadway constructed within the road reserve to carry
traffic around the Works or Work Zone.
Traffic Detour
A detour of traffic away from the Work Zone or the Works via
alternative roads or streets.
1.7.2

General

This Clause covers requirements where the Contractor is


solely responsible for traffic management.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
22
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Unless specified otherwise, the Contractor is to make provisions


for
traffic, including pedestrian, in accordance with this section and the
relevant
parts
of
the
VicRoads
Worksite
Traffic
Management
(Roadworks Signing) Code of Practice, hereinafter referred to as the
Code, or Australian Standard AS 1742.3 - Manual of Uniform Traffic
Control devices. The Contractor is to make such provision for traffic
notwithstanding anything contained in the General Conditions of
Contract and without derogating in any way from the
Contractors
obligations pursuant to the General Conditions of Contract and
in
particular from the Contractors obligations pursuant to
Clause
Protection of People and Property of the General Conditions
of
Contract.
The Contractor is to submit, within 7 days of receipt of the Letter
of Acceptance, a Traffic Management Plan providing details of
the proposed provisions for traffic to be provided during the
Contract for approval by the Superintendent. Works shall not
commence until approval by the Superintendent has been granted.
Works will not commence or continue at any location until all
appropriate signs and devices such as lamps, barricades, traffic
control apparatus and the like are in place, side tracks have been
constructed where required and line marking completed where
required.
At all times when the Contractors employees are on site, the
Contractor is to render immediate assistance without charge to any
person whose lawful passage through a work area may be
obstructed or made difficult by or as a result of the Contractors
operations.
Unless otherwise approved, when work is not being performed on the
site, traffic will not be carried through that works zone or works area
on side tracks, detours or part widths of the existing pavement.
1.7.3 Care of Areas Used by Traffic
Both during and at the end of each days work, the Contractor is to be
responsible for ensuring that the pavement and shoulders used by

traffic
within the Work Area, and all other areas within the Work Zone where
the Contractor has undertaken work, are in a safe and trafficable
condition.
The Contractor is to immediately remove any material that has fallen
on
any travelled path, or road leading to/from the work site, as a result
of
the transportation of materials or other. The Contractor is to
immediately remove any material stored or deposited near the
travelled
path that could constitute a hazard to traffic. Any soiling of
adjacent
road pavements, caused by vehicles or equipment engaged in these
activities are to be immediately cleaned off by the Contractor to the
satisfaction of the Superintendent. The Contractor is to bear all
costs
incurred in complying with this clause.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
23
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

1.7.4 Signs and Devices


Unless otherwise specified, the Contractor is to supply signs
and devices required to complete the work covered by this section.
Signs and devices are to comply with the relevant sections of the
Code together with the following additional requirements:
a)

Pavement markers are to comply with the requirement of AS 1906,


Retroreflective Materials and Devices for Road Traffic
Control Purposes, Part 3 - Raised Pavement Markers
(Retroreflective and Non Retroreflective). The adhesives used
to fasten them to the pavement are to comply with the
requirements of Section 853 of Vicroads Standard
Specifications.

b)

Retroreflective sheeting used on any sign or device is to comply


with the requirements of AS 1906, Retroreflective Materials
and Devices for Road Traffic Control Purposes, Part 1 Retroreflective Materials, for Class 2 material, except that
the coefficient of luminous intensity will not be less than 50%
of the values given in Table 2.2 of AS 1906 Part 1, for each
designated colour when tested in the cleaned condition.

c)

Dirty, illegible, damaged or faded signs are not to be used if there


is any doubt that the message or intent of the sign is unclear or
confusing to road users. The Contractor is to clean, replace or
renew all signs as required to ensure legibility and
luminous
intensity.

1.7.5 Storage of Plant and Equipment


When not in use, the Contractor will be responsible for the safe
storage of plant and equipment clear of the travelled path.
Wherever possible, plant and equipment is to be stored not less
than 3 m from the edge of the traffic path. If it is not possible to
provide such clearance, the plant and equipment is to be moved from
the Works area to a suitable storage site or be protected by suitable
signs, lights and devices.
1.7.6 Access to Side Roads and Abutting Property
Construction operations are to be conducted in such a manner as

to
minimise inconvenience to abutting property owners.
Unless
otherwise
specified, access to properties and side roads is to be maintained at
all
times wherever practicable other than when the works present a
traffic
hazard or the work would suffer damage as a result of the passage of
traffic.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
24
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Where the Contractor proposes to restrict access to abutting


properties
as a result of the Contractors operations, the Contractor is to
provide
a
minimum of 24 hours notice to the affected property owner/occupier.
Access will not be denied to any abutting property outside
the customary working hours.
1.7.7 Construction Operations Affecting Traffic
General
Unless otherwise specified, the Contractor is to conduct the
operations
as to minimise obstruction and inconvenience to the public, and will
not
have under construction any greater length or amount of work than
can
be managed properly with due regard to the convenience of the
public.
Any intermingling of construction plant with traffic is to be kept
to a minimum at all times.
Unless specified otherwise, the Contractor is to:
a)

provide a minimum safe working width for the Contractors


construction plant plus an absolute minimum clearance to
the edge of traffic path of 1.2 m;

b)
not

provide a minimum one way clear travel path width of traffic of


less than 3.5 m for one-way operation and 7 m for twoway
operation;

c)

not work on any part of a carriageway during peak traffic flows


unless such work in conducted that it does not cause any
additional delays to traffic than if the work was not done;

d)

locate the longitudinal joint(s) for pavement construction and/or


cold planing works at either the traffic lane line(s) or at the
centre of the traffic lane(s).

Earthworks and Pavement Construction


Unless otherwise approved by the Superintendent, earthworks
and pavement construction are to proceed only in areas clear of
travelled paths and footpaths.

Where construction is being carried out over part of the


carriageway width, the following conditions are to apply:
a)

steps or batters within 1.5 m of the travelled path of the


carriageway are to be delineated as specified in the Code.
Where
the step or batter forms a drop in level of more than 200 mm at
a
slope steeper than 1 in 6, barricades will be used in addition to
delineation.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
25
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

b)

where the level difference in the form of a step or batter of less


than 80 mm and is between the travelled paths, such step or
batter is to be removed before the close of work each day and
the full width of carriageway made available to traffic
overnight. The removal of such step or batter will be
effected by shaping to a cross-fall not steeper then 1 in 10.

c)
all

Unless otherwise specified, prior to the close of work each day


steps between layers of unbound pavement material being
placed are to be tapered to a slope not steeper than 1 in 10.

Footpaths and Pedestrian Walkways


Unless otherwise specified, temporary footpaths or pedestrian
walkways
within the work zone are to be not less than 1.5 m wide, are to have a
firm, even and free draining surface and are to be free from steps and
obstructions.
1.7.8 Side Tracks, Detours and Road Closures
Side Tracks
Traffic will not be diverted on to any side track until permission to
use such side track has been given by the Superintendent.
Detours
Unless otherwise specified, traffic will not be detoured on to
roads outside the work zones.
Road Closures
Refer to VicRoads Traffic Management Note No. 10 Procedure
for Planning Road Closures.
1.8 Traffic Management Plan
1.8.1

General

Good planning and notification of road and lane closures are to result
in
minimal interruption to traffic on the route. It is to also result in
better
co-ordination with other events, avoiding situations (for example)
where
traffic is blocked or constrained on adjacent routes at the same time.
1.8.2 Traffic Management Plan
All procedures for any road closures must be included in the Traffic

Management Plan. The amount of detail included in the plan


is
dependent on the likely impact on traffic of the closure of the road
or
section of road. The plan must take into account the available
traffic
capacity, possible alternative routes, and time of day when the
closure
can best be undertaken, traffic signal changes, need for publicity and
other issues.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
26
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

1.8.3 Notification
For works on VicRoads declared roads, at least two weeks notice
before
the road closure is to take place, the Traffic Control
and
Communications Centre (TCCC) is to be advised by creating a
Work/Event Report on the Real Time Traffic Information Database.
This
provides adequate time for the road closure to be included in the
VicRoads Roadworks bulletin. On the day or night of the works, the
Contractor must notify the Superintendent and the TCCC
of
implementation time and completion of the closure, advise of
the
expected duration and any adverse impacts on traffic. Details of
each
closure for all major works must then be entered by the TCCC staff in
the Real Time Traffic Information Database.
A letter drop is to take place to all commercial and residential
premises
adjacent to, or affected by, any significant works explaining why
the
works are required and detailing the closures, their times and
duration.
Advance notification of impending works is to be provided by use
of
Variable Message Signs (VMS) at strategic locations in advance of
the
work site, at least 7 days prior to the closures. At the time of
closure,
signs including VMS (where appropriate) are to be located at points
that
allow motorists to take alternative routes in accordance with the
Traffic
Management Plan.
1.8.4 Monitoring During Closure
Wet weather, incidents on adjacent routes, or unforeseen events may
result in a decrease in the available traffic capacity in the area
resulting
in longer delays. The Superintendent is to ensure that the closure
and

the traffic operations are regularly reviewed and that consideration


is
given to taking remedial action where necessary if the traffic delays
are
greater than 10 minutes.
Any change to the closure is to be checked against the provisions of
the Code and the TCCC should be notified.
1.8.5 Restoration
Prior to the issue of the Final Certificate, unless otherwise
specified,
detours and side tracks used or constructed during the Contract are
to
be restored to the condition existing at the time of commencement of
the
work under the Contract. Where the Contractor is responsible for the
restoration of detours and side tracks the Contractor is to produce
from
the local authorities or landowners concerned clearances in
writing
stating that such detours and side tracks have been restored to their
satisfaction.
1.8.6 Use and Care of Roads
The Contractor will be responsible for repair of damage caused to
any
roads, bridges or other structures by transporting material under the
Contract. If requested by the Superintendent, the Contractor is to

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
27
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

submit clearances from municipal and


concerned before the Final Certificate is issued.

other

authorities

In respect of repair of damage to roads, the Contractor will be


deemed when tendering:
a)

to have inspected the roads used for transport;

b)

to have acquired, by consultation with the municipal or other


authorities concerned, knowledge of the roads and any existing
or
likely restrictions upon their use which could affect the transport
proposals;

c)
the

to have assessed the possibility and extent of any damage to


roads which may be caused by the transport under the Contract;

d)

to have made due allowance for the effects of such restrictions


and for the cost of rectification of such damage in accordance
with the requirements of the authorities concerned.

1.9 Storage and Site Cleanliness


The Contractor is to keep the site free from rubbish, debris or any other
deleterious material at all times. All unused or removed rubbish and debris is to be
removed from the site and disposed to a legal point of discharge at the
Contractors expense. Where the rubbish is a hazard or is remaining after three
days the Superintendent will arrange for the removal of the debris at the
Contractors expense.
1.10 Works Program
The Contractor will commence works in accordance with the
Contract Commencement date as stated within the Letter of Acceptance. The
Contractor is to prepare and lodge a complete works program, outlining stages and
completion times, to the Superintendent within 7 days of receipt of the Letter of
Acceptance for approval by the Superintendent.
1.11 Supervision/ Inspections and Samples
The Contractor will make the site available to the Superintendent at all times
for inspections of the works, and give a minimum of 48 hours notice to
the Superintendent for inspections. The Contractor or their representative
must be present at all inspections.
Inspections and samples will include, but not be limited to, the following:

Prior to commencement of demolition, i.e. marking out/pegging etc;


Completion of demolition and commencement of set out for new
works; Midway through excavation, earthworks and trimming;
Completion of earthworks;
Setout of bluestone kerbs and edgings;

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
28
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Laying of new sub bases and surfaces for asphalt


surface; Sub base preparation for kerb and channels;
Set out of lighting;
Installation of lighting;
Topsoil and mulch spread and leveling for garden
beds; Set out of plants;

Midway through planting of trees, shrubs and


groundcovers; Maintenance and establishment.
The Contractor will construct, supply or submit samples of the following surfaces
and
materials for the approval by the Superintendent not less than 1 week prior
to
delivery to site.

Mulch for garden


beds;
Imported fill
soil;
Imported topsoil for planting beds.
1.12 Hours of Work
The Contractor is to undertake all works between 7 a.m. - 5.30 p.m. on
weekdays. No work shall be permitted on weekends, unless for emergency
reasons. Any works undertaken outside of normal Monday to Friday working
hours much be approved prior in writing by the Superintendent.
1.13 Services
The Contractor is responsible prior to commencing works, for checking the location
of existing services and utilities with Council that may affect the works of this
Contract. The Contractor will notify the Superintendent of any conflict
between existing services and proposed works prior to commencing any works.
The Contractor will be responsible for any damage caused by any works
or operations under this Contract. The Contractor is also responsible for any
damage caused by the works in this contract and any fault that may develop in
any service due to works under the control of the Contractor.
The Contractor is to advise the Superintendent of any such damage or fault and is
to make their own arrangements with the various authorities or service agents,
which may be necessary. The Contractor will have no claim against the client for
any loss or delay occasioned by any such damage or defects.
It is the responsibility of the Contractor to contact Dial Before You Dig to
obtain
current and correct underground services information at the time of

demolition,
excavation and construction. Any modifications to existing underground services
and
associated infrastructure (pits, meters, valves etc) must be approved by the
Superintendent and the relevant Service Authority.
Provide services
where
necessary for construction. Notify the Superintendent of any conflicts with
services
immediately.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
29
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

1.14 Materials
The Contractor is to place orders for delivery of all materials, plants, supplies,
etc., with ample time to ensure that suppliers guarantee delivery at times to
accord with the construction program.
The Contractor must allow for supply of materials from any available source
to enable completion within the specified time. No cost adjustment will be made
for the use of imported materials if the Contractor finds it necessary to augment
or replace local supplies with imported material.
All materials liable to deteriorate by exposure to the weather will be kept under
cover and the Contractor will be held responsible for loss or deterioration
occurring in the course of loading, unloading, transit or storage no matter what the
cause.
1.15 Protection of works
General
The Contractor is responsible for ensuring the safety of the site and the
General
Public by paraweb fencing around each area and other safety protective
measures
as per clauses 1.7 and 1.8 of works as it occur, to the satisfaction of the
Superintendent. Signage advising unauthorised entry to the site works areas is
not
permitted is to be provided at regular intervals. The Contractor will ensure the
safety
and security of the works site.
The Contractor is responsible for the protection of private residential assets,
including but not limited to fences, gates, pathways and vegetation. Any damage
to private property must be reported to the Superintendent immediately and
arrangements made to repair/replace with the Superintendent and property
owner at no cost to the Council or the property owner/occupier.
The Contractor will be responsible for the control and clean up of all
associated
works that produce waste material, including dust and slurry. The Contractor
will
control all grinding, cutting and associated works are controlled in a manner to
stop
the travel of waste, including dust and slurry, into new structures or over the
general
area.
The Contractor will, at their expense, as soon as the progress of the works
permits,
repair and restore any structure, service or public asset damaged in any way to
the
same or better condition in which it was in prior to the damage to the satisfaction

of
the Superintendent.
All roads, all surfaces, garden beds, channels, paths or other places used
in conjunction with the work will be kept free of unnecessary obstruction whilst the
work is proceeding and left in a tidy condition upon completion and reinstated
to their previous condition prior to contract works.
Any damage to property must be reported to the Superintendent immediately.
1.16 Soil and Waste in Drains
The Contractor is to cover all relevant culverts and drains during soilmoving
operations and operations where mobile waste is produced. The Contractor will
avoid

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
30
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

soil and other deleterious materials entering pits or drains during the Contract.
The
Contractor will remove (not by washing down the pipe) any material which enters
the
pits.
Allow for any works necessary to effectively control erosion and siltation on the
site for the duration of the contract period.
1.17 Water Supply
The Contractor is responsible for the supply of water on-site as necessary
to undertake the work included as part of the contract.
1.18 Electricity Supply
The Contractor is responsible for the supply of electricity on site, if required by
the Contractor, by means of a site generator.
1.19 Sanitary Accommodation
The Contractor is responsible for the provision of sanitary accommodation to
comply to Health and Safety regulations.
1.20 Practical Completion
The Contractor will ensure that all works excluding "Maintenance and
Establishment Period" are completed prior to the date for Practical Completion.
For the purposes of issuance of the Certificate of Practical Completion, all plants
and grassed areas will show signs of healthy vigorous growth.
Any certificates of warranty will be handed over to the Superintendent at
Practical Completion.
1.21 Maintenance and Establishment Period- Horticultural Works
The Contractor will maintain the horticultural works for a period of twenty-six
(26) weeks following the date of issue of the Certificate of Practical Completion
by the Superintendent. Practical completion will be given when the instant turf
thatch is firmly rooted into the site soil.
At the conclusion of the Maintenance and Establishment Period all plants
and grassed areas will show signs of healthy vigorous growth.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
31
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

2.

SET OUT AND EARTH WORKS

2.1 The Site


Greeves Street, St Kilda Streetscape Upgrade (Melway reference 2P D7 and D8)
Inspection Point: The Contractor and Superintendent will inspect the Site as
per
schedule.
2.2

Drawings

The following drawings form part of the contract documents:


Landscape Drawings:
L1: Demolition Plan
L2: Demolition Plan
L3: Set Out Plan
L4: Set Out Plan
L5: Planting Plan
L6: Planting Plan
L7: Detailed Planting
Plans L8: Details
Drainage Drawings:
1317-00-C01 (Cover sheet)
1317-00-P02 (Kerb, Pit and Lintel Details- Pit
11)
1317-00-P03 (Kerb, Pit and Lintel Details- Pit
14)
1317-00-P04 (Kerb, Pit and Lintel Details- Pit
15)
Lighting Drawings:
MSL 105-E01
MSL 105-E02
2.3 Setting out of Greeves Street Streetscape Upgrade
The Contractor is to be responsible for the setting out of all works and the
accuracy
of lines and levels. The Contractor is to provide all necessary equipment to set
out
the works and have the equipment available to the Superintendent to check
the
levels and set out.
2.4

Demolition

The Contractor is responsible for the careful demolition of all-existing surfaces,


the
removal and disposal of existing shrubs / tufting plants (including root systems)
and
miscellaneous items as shown on the drawings and directed by the
Superintendent.
The Contractor shall contact Dial-Before-You-Dig prior to commencement of
demolition works.
Saw cuts shall be used in existing pavement surfaces to be demolished
when adjoining surfaces are to remain.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
32
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

It is the Contractors responsibility to make their own assessment of the nature of


the ground and the difficulties likely to be encountered during all demolition,
excavation and filling works required under the Contract.
All demolished material (unless nominated for delivery to Councils depot)
and excess material is to be removed from the site on a continuous basis
at the Contractors expense to a legal point of discharge.
All bluestone pitchers removed for the re-setting of existing sections of kerb
and
channel are to be cleaned, salvaged and stored in a secure place to avoid theft
of
pitchers for re-use. Organise re-setting of bluestone pitchers as soon as demolition
is
completed to reduce the time of inconvenience to residents and businesses.
Two No. existing litter bins are to be relocated from Inkerman and Carlisle Streets
to new locations as per Set Out Plan L3 and L4.
2.5 Recyclable Materials
Dispose of salvaged brick, bituminous materials of size greater than 50 mm and
other recyclable materials at approved recycling establishments.
2.6 Fill Material
a) Fill material for Roads and paved surfaces
All additional materials required due to over-excavation, disposal or a shortfall
of suitable excavated material is to be imported at the Contractors expense.
Filling material is to be Class 2 FCR, compacted in layers not exceeding
150mm, using a machine type approved by the Superintendent.
The Contractor is to remove any fill or soil deemed unsuitable for its intended
use
from the site at the Contractors cost. Any required imported fill is to be to the
satisfaction of the Superintendent, with a sample being approved prior to
delivery.
b) Fill material for nature strips and garden areas
All site topsoil to be removed and sub-soil cultivated to areas of garden beds
and grassed areas. Imported clean topsoil is to be free from all
extraneous and deleterious material, is to be used subject to the approval of
the Superintendent. Spread imported fill material to achieve levels on
the plan. Contact the Superintendent upon completion of excavation and
completion of filling so that inspections may be carried out, (refer
Supervision/Inspections and Samples clause in Section 1 of this Specification).

Fill material to be a grey black medium textured - sandy loam free of


pests, diseases, organic matter and debris, ph range 5.5 - 7.
The Contractor is to remove any fill or soil deemed unsuitable for its intended
use
from the site at the Contractors cost. Any required imported fill is to be to the
satisfaction of the Superintendent, with a sample being approved prior to
delivery.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
33
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

2.7 Sub- Grade Preparation


The Contractor is to notify the Superintendent at the completion of Subgrade preparation to arrange an inspection prior to sub-base preparation.
Sub-bases are to be clear of all material containing humus and vegetable matter.
Fill any soft spots with 5% cement stabilized Class 2 Fine Crushed Rock.
Sub-grades are to form a smooth and continuous finish with no inconsistent rises
or depressions causing water to pond.
All compaction is to be as required in AS 1289 TestE2.1/E2.2 and test rolled in
accordance with AS 3798.
Sub-bases are to be uniform in consolidation with no soft spots. Any soft, wet
or unsuitable areas are to be removed and replaced with an approved material
and consolidated to not less than the standard requirement as per clause 2.6.
Request approval by the Superintendent of any treatment to eradicate soft
spots prior to formation of grades and works over the treated areas.
2.8

De-watering

During earthworks and excavation, the Contractor is to provide drainage such that
all
excavation and filling will be free draining to low points clear of the works at all
times.
Drain or pump water from low points to prevent damage to the works due
to
inundation, flooding, ponding or other causes. The Contractor is to do all
things
necessary to divert any water, which interferes with progress of the works, and
to
keep areas free from water during excavation and filling. Sufficient pumps,
wellpoints or other equipment are to be provided by the Contractor for keeping
trenches
and excavations dewatered during the works at no additional cost to the council.
Existing drainage lines and structures may be utilised by the Contractor in
draining
the site. Before breaking into any lines or structures, the Contractor must obtain
prior
approval from the Superintendent in writing. Should such approval be
given,
restitution of the structure to a condition at least equivalent to that before
the
breaking occurred is to be undertaken by the Contractor at their expense.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
34
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

3.

ASHPHALT SURFACING

3.1 Extent of Works


The works to be performed under this part of this Specification include the supply
of all labour, tools and materials necessary for the construction of the asphalt
surface to the three speed hump points.
Refer to the Traffic Management Section and the Program documenting the
Contractors responsibility in working with Council on advising residents of the
works program in demolition, preparation and asphalting.
Inspection Point: The Contractor will give 24 hours notice to the Superintendent,
as per schedule, of intention to:
Set out of new surfaces
Trimming, excavation and sub-grade compaction for the new surfaces;

Base preparation for the asphalt speed humps and for the re-set
bluestone
pitcher kerb and channels;

Drainage Pits and their


replacement;
First section test
and approval;
All pavements abutting different finishes will have the appropriate backfill
material and finish to edge, i.e. Bluestone pitchers, existing road surfaces, etc.
3.2 Base Preparation
On excavation compact site soil to 98% MMDD. Remove any soft spots and
cover with Geofabric layer. Depth to be 480mm.
There are to be 3 layers of crushed rock (a) Supply and spread a 150mm layer
base
layer of 40mm N.D. FCR compacted to 95% of the Standard Maximum Dry
Density.
(b) Supply and spread a 150mm mid layer of 20mm Class 3 FCR compacted to
95%
of the Standard Maximum Dry Density. (c) Supply and spread a 150mm top layer
of
20mm Class 2 FCR compacted to 98% of the Standard Maximum Dry Density.
Crushed rock to be clean and free of debris.
Undertake as per Set Out Plans L3 and L4. Refer to detail C L8.
3.3 Surface
Supply and spread a 30mm compacted layer of 10mm Nom. Size Type T
asphalt. Asphalt is to be placed in accordance with the Drawings and this

Specification. All asphalt to be machine laid where possible and conform to


levels and profiles, matching and extending those existing.
All material and workmanship is to conform to the current VicRoads Specification
"Materials and Construction for Asphalt Surfacing and Base".
Spreading is to be carried out in a competent and careful manner. Tools are to be
kept clean at all times by using diesel fuel or kerosene. Raking is to be kept to
an absolute minimum.
Contract No: 1799
Title: Greeves Street, Streetscape Upgrade
35
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Asphalt is to be between 170oC -180oC when leaving the supplier and should be a
minimum 165oC when delivered to site and should not be accepted otherwise.
No
asphalt is to be placed when the ambient temperature is less than 10C or when
cold
winds chill the asphalt to an extent that spreading and compacting are
adversely
affected.
After the final compaction, no part of the finished asphalt work is to have a density
of less than 97% of the laboratory compacted density.
The finished surface of new pavement is to match existing surface levels
as approved by the Superintendent. The asphalt surface is to be finished true to
grade, levels and profile, and must not vary more than + or - 5mm from the
testing edge when tested with a 3 metre long straight-edge and profile
template. The finished surface of all pavements is to be free draining and
must not pond water. Deficient areas are to be made good to the satisfaction of
the Superintendent.
Undertake as per Set Out Plans L3 and L4. Refer to detail C L8.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
36
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

4.

KERB AND CHANNEL RE-SETTING AND NEW BLUESTONE KERB


EDGING

4.1 Extent of Works


The work performed in this part of the Specification includes the supply of all
labour, tools and materials necessary for the supply and re-setting of portions to
the existing bluestone pitcher kerb and channel and new bluestone pitcher
edging to the new garden bed as per Set Out Plans L3 and L4 and Details A L8
and B L8. There are seven short lengths of bluestone kerb and channel requiring
re-setting.
New Bluestone Pitcher edging to garden beds:
-Council will supply bluestone pitchers from Councils Depot on the day
the
Contractor advises they are ready for the pitchers. Contractor to pre-arrange
the
delivery by Council. Bluestone is to be set in place on the day of delivery to
minimise
the risk of theft.
4.2 Removal
Confirm with Superintendent the precise extent of each of the 7N o sections
existing bluestone kerb and channel as shown on the Demolition Plans L1 and
L2 and Set Out Plans L3 and L4.
Carefully remove the bluestone pitchers in order not to damage or
mark/scratch individual pitchers.
Erect barrier fencing to prevent pedestrian or vehicle entry into the exposed
trenches along the kerb channels and the road section, and retain barrier fencing
until the resetting is completed and the concrete has cured. Refer to clauses
1.9 and 1.10 concerning pedestrian and vehicle management.
4.3 Base Preparation for Bluestone Pitcher Kerb and Channel
On excavation compact site soil to 95% MMDD. Remove any soft spots and fill with
a 75mm compacted layer of Class 2 FCR.
Supply and spread 75mm compacted layer of Class 2 FCR. Crushed rock is to
be clean and free of debris.
4.4 Re-setting of Bluestone Pitcher Kerb and Channel
All concrete is to be placed in daylight. Concrete is to conform to AS 1379 and
have
a minimum 28-day compressive strength of 25MPA when tested in compliance
with
AS 1012.

Place concrete bedding to a depth of 100mm over the compacted Class 2 FCR
and set salvaged bluestone pitchers to match on site levels at a maximum of
30mm spacings. Fill joints with Mortar mix 16% cement, 16% Stone dust, 67%
blended washed sand and 1% lime; Readymix Bluestone Grout or equal
approved. Excess mortar to be removed from the surface of the bluestone.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
37
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

4.5

New Bluestone Pitcher Edging to one garden bed

To the one section of garden edge to the south west garden bed (garden bed E)
of the Blanche Street intersection, install a new bluestone pitcher edge.
Council to supply new bluestone pitchers.
On excavation compact site soil to 95% MMDD. Remove any soft spots and fill with
a 75mm compacted layer of Class 2 FCR.
Supply and spread 75mm compacted layer of Class 2 FCR. Crushed rock is to
be clean and free of debris.
All concrete is to be placed in daylight. Concrete is to conform to AS 1379 and
have
a minimum 28-day compressive strength of 25MPA when tested in compliance
with
AS 1012.
Place concrete bedding to a depth of 100mm over the compacted Class 2 FCR
and set new bluestone pitchers to match on site levels at a maximum of 30mm
spacings. Fill joints with Mortar mix 16% cement, 16% Stone dust, 67% blended
washed sand and 1% lime; Readymix Bluestone Grout or equal approved.
Excess mortar to be removed from the surface of the bluestone.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
38
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

5.
5.1

STORMWATER PIT REMEDIATION


Preliminary and General

This technical specification covers the works required to upgrade the lintels of
the stormwater pits 11, 14 and 15 on Greeves Street, St Kilda, as shown on
Michael Smith and Associates Drawing No. L4. This Specification is to be read in
conjunction with the following associated Storm Consultings drawings:
DRAWING NO:
1317-00-C01
1317-00-P02
1317-00-P03
1317-00-P04
5.2

TITLE:
Coversheet
Kerb, pit and lintel details - pit 11
Kerb, pit and lintel details - pit 14
Kerb, pit and lintel details - pit 15

Stormwater Pit Remediation Scope

The contractor is to supply all plant, material and labour to carry out the
following
works:
5.2.1 Pit 11 and 15:
Retain existing concrete pits and remove existing concrete lintels,
pit lids and covers. Saw cut and remove the existing concrete kerb
and channel and adjacent bluestone edging (road side of kerb and
channel). The approximate extent of the cutting is shown in sheet
P02 Detail 01 and sheet P04 Detail 03. In addition the roadside wall
of each pit shall be saw cut and lowered by a sufficient amount so as
to allow a minimum 150 mm vertical opening when the lintel is
replaced.
Reinstate Pits 11 and 15 with Rocla Vic roads 1800 mm wide lintel
and
Rocla RCA 1200 x 750 pit lid and cover. The new lintels are to be
with
a minimum of 150 mm compacted (95% standard compactive
effort)
crushed rock under the lintel pillars either side of the pits. The lintel is
to
then be backfilled around the sides and back with concrete to
provide
support. The pit lid frame is to be fitted onto the existing pit by
bedding
in mortar. The pit lids have been intentionally oversized and
any
overhang beyond the pit wall is to be backfilled with concrete to
prevent
future cracking of the lids edges.
The inside of the lintels is to be shaped with concrete infill to

transition
from the lintel width (1500 mm) to the pit width (assumed to be 900
mm). The concrete infill surface is to be with a smooth trowelled finish.
The removed sections of kerb and adjacent bluestone edge are to be
reinstated with a poured concrete channel/apron which is to be of
a
minimum thickness of 300 mm on the road side as shown Section D
and
F. Steel reinforcing within the concrete channel/apron are to
comprise
of a single layer of SL92 mesh placed with a minimum cover of 75
mm
(measured from the top surface). In addition to the reinforcing mesh,
the
concrete kerb/apron is to be tied to the existing concrete pit
and
adjacent channel with D12 started bars on minimum 200 mm centres.
The starter bars are to be embedded a minimum of 75 mm into
existing

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
39
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

concrete (and secured with suitable adhesive compound, such


as chemset). The starter bars are to be bent at a suitable angle to
extend a minimum of 200 mm into the new concrete, the bars must
be tied to the reinforcing mesh. The poured concrete channel is to
be shaped to concentrate and grade flows toward the lintel/pit
opening. The lintel opening is to be at least 150 mm high (measured
between the concrete channel/apron and the lintel soffit). The poured
concrete channel/apron surface is to be left with a smooth trowelled
finish.
5.2.2 Pit 14:
Break out and remove the existing brick pit, lintel and lid and cover.
Saw cut and remove the existing concrete kerb and channel and
one line of bluestone edging (road side of kerb and channel). The
approximate extent of the concrete cutting is shown in sheet P03
Detail 02.
All new pits, including access covers, gully grates and frames
complying with AS:3996, are to be constructed to the details
shown
on
the drawings and to the requirements of the
manufacturers. Inlet and outlet pipes are to be cored from the
precast pits (cored hole size equal to the pipe diameter plus 50 mm).
The pipes penetrations through the pit walls shall be sealed with
epoxy mortar.
The new Pit 14 is to comprise a Rocla Precast RKO 600 x 900 pit and
riser to match existing depth of stormwater pipe (Contractor to
confirm).
The new pit is to be installed as per the manufactures specification
with
pit lid and cover to suit (shown as Rocla RCA 1200 x 750) and Rocla
1800 mm lintel.
Notwithstanding the manufactures specifications the pit is to be
placed on a minimum of 150 mm compacted crushed rock. The lintel
and lid are to be installed in the same manner as for Pits 11 and 15.
5.3

Minor Concrete Work


5.3.1 Scope
The work to be executed under this work section consists of the
supply and placement of concrete and ancillary requirements like
excavation, preparation of foundations, forming up, placement of
reinforcement, core hole in precast units and backfilling for work
shown on the drawings but not having individual specifications.
These works include drainage pits and other supplementary

structures, footings and works of a similar nature.


All concrete must have a minimum 28 day compressive strength of
32MPa and all unformed surfaces shall have a smooth towelled
finish. All concrete work must comply with the below standards.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
40
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

5.4

Referenced Standards

THE FOLLOWING DOCUMENTS REFERRED TO IN THIS WORKSECTION


SHALL BE DEEMED AS THE LATEST EDITION OF THE AUSTRALIAN
STANDARDS, INCLUDING AMENDMENTS AND SUPPLEMENTS.
AS 1012
AS 1012.1
AS 1012.3.1

METHODS OF TESTING CONCRETE


AMPLING FRESH CONCRETE
DETERMINATION OF PROPERTIES RELATED TO THE
CONSISTENCY OF CONCRETESLUMP TEST
AS 1012.8.1 METHOD OF MAKING AND CURING CONCRETE
COMPRESSION
AND INDIRECT TENSILE TEST SPECIMENS
AS 1012.9 DETERMINATION OF THE COMPRESSIVE STRENGTH
OF
CONCRETE SPECIMENS
AS 1012.14 METHOD FOR SECURING AND TESTING CORES FROM
STRENGTH
AS 1141
AS 1141.14
AS 1141.21
AS 1141.23
AS 1141.24

HARDENED CONCRETE FOR COMPRESSIVE

METHODS FOR TESTING AND SAMPLING AGGREGATES


PARTICLE SHAPE BY PROPORTIONAL CALLIPER
AGGREGATE CRUSHING VALUE
LOS ANGELES VALUE
AGGREGATE SOUNDNESSEVALUATION BY EXPOSURE TO
SODIUM SULPHATE SOLUTION
AS 1289
METHODS OF TESTING SOILS FOR ENGINEERING
PURPOSES AS 1289.3.3.1 SOIL CLASSIFICATION TESTSCALCULATION
OF THE
PLASTICITY INDEX OF A SOIL
AS 1289.5.4.1 SOIL COMPACTION AND DENSITY TESTSCOMPACTION
CONTROL TESTDRY DENSITY RATIO,
MOISTURE
VARIATION AND MOISTURE RATIO
AS 1379
SPECIFICATION AND SUPPLY OF CONCRETE
AS 1478
CHEMICAL ADMIXTURES FOR CONCRETE, MORTAR AND
GROUT
AS 1478.1 ADMIXTURES FOR CONCRETE
AS 1554
STRUCTURAL STEEL WELDING
AS 1554.3
WELDING OF REINFORCING STEEL
AS 2082
TIMBERHARDWOODVISUALLY STRESS-GRADED FOR
STRUCTURAL PURPOSES
AS 2758
AGGREGATES AND ROCK FOR ENGINEERING PURPOSES
AS 2758.1
CONCRETE AGGREGATES
AS 3600
CONCRETE STRUCTURES
AS 3610
FORMWORK FOR CONCRETE
AS 3799
LIQUID MEMBRANE-FORMING CURING COMPOUNDS FOR
CONCRETE
AS 3972
PORTLAND AND BLENDED CEMENTS
AS/NZS 1859 (VARIOUS) RECONSTITUTED WOOD-BASED
PANELS AS/NZS 2271 PLYWOOD AND BLOCKBOARD FOR
EXTERIOR USE AS/NZS 4671 STEEL REINFORCING MATERIALS

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
41
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

6.
6.1

CULTIVATION AND SOILS


Extent of Works

The Contractor is to grade to final levels and re-cultivate to garden beds to areas
on the Planting Plans L5, L6, L7 shown as planted.
6.2

Site Trimming

Herbicide spray all grassed or weed infested nature strips to be converted to


garden
bed using approved herbicide and to the manufacturers application and
protection
instructions. Dont spray on a windy day and the Contractor is to take measures
to
prevent spray drift affecting plants within residential and commercial properties.
On
die-back of grass, remove existing grass thatch and topsoil to 100mm depth prior
to
cultivation of all areas to be planted. Site topsoil is to be savaged and stockpiled
for
reuse as topsoil and fill soil.
6.3

Garden Bed Preparation

Prior to spreading imported topsoil to all new garden beds and grassed
areas, remove any debris and grass root thatch, cultivate site soil and fill material
to a depth of 150mm by mechanical means. Supply and spread gypsum evenly
over all garden bed areas at a rate of 1kg/m 2. Allow fallow period of seven
(7) days prior to spreading imported topsoil.
6.4

Fill Material for Garden Bed Mounds and Areas where Required

Imported fill is to be a light brown - grey clay loam (pH range 6-7). Clay soil of
heavy yellow or white clay or fill soil of varying loam contents and or soil
containing building rubble, debris and organic matter will not be accepted. Prior
to ordering fill material, the Contractor is to supply the Superintendent with a
sample of the imported fill material proposed for use for approval.
Prior to ordering fill material the Contractor is to supply the Superintendent with a
2kg sample of the imported fill soil proposed for use for approval by the
Superintendent. This will be retained by the Superintendent as a reference sample.
6.5

Topsoil for Garden Beds

Spread imported topsoil to a lightly rolled depth of 100mm depth to all new
garden bed areas over 150mm depth of cultivated site soil.
Imported top soil is to be a 50/50 mix of grey/brown medium textured loam and
black sandy loam. Lightly roll the topsoil spread to grassed areas and garden beds
to finish topsoil as gently haunched at 25mm above adjoining footpaths and

kerblines to allow for soil settlement. Supply 1kg sample of imported top soil
intended for use to Superintendent for approval prior to ordering.
Should the ground become over compacted due to machinery working over
surface, the Superintendent may require re-cultivation of compacted ground prior
to planting. Such re-cultivation is to be at the Contractors expense.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
42
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

6.6

Preparation

Imported top soil is to be graded to a smooth surface to ensure free


surface
drainage. No clods larger than 50mm diameter are to be left. Cultivate surface soil
to
a fine friable tilth by mechanical means. Grade surface to adjoining
footpaths,
bluestone pitcher and plinth edges. The surface is to be free of depressions
and
undulations with the variance being no greater than 50mm over a 5 metre
length.
Gently haunch the topsoil above adjoining footpaths and bluestone kerbs. In case
of
adverse weather conditions the work may be suspended at the direction of
the
Superintendent. To areas of grass to be reinstated, cultivate the site soil to a depth
of
75mm by mechanical means and when soil is in a friable condition, to then
place
instant turf.
6.7

Final Grading

Garden beds are to be finished to form a gently crowned profile and are to
finish
25mm above adjacent concrete edges and grassed areas. During the fallow
period,
lightly hose the prepared surface to aid settlement. Fill any areas of subsidence
with
stockpiled topsoil to maintain grades and tolerances. To areas of grass at the time
of
turfing, cultivate the turf bed to a depth of 25mm by raking soil in transverse
directions to give a loose surface. Soil surface for instant turf of nature strips is
to
finish as a lightly rolled layer flush to the adjoining paths and
bluestone
edges/kerbing.
6.8

Fertiliser

Spread Pivot 900 fertiliser at 30gms/m2 to cultivated areas and rake in to the topsoil.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
43
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

7.
7.1

PLANTING
Extent of Works

The Contractor is to provide plant material from an approved


nursery/supplier, fertilisers, stakes and labour to plant plants and deciduous trees
as per the Planting Plans L5, L6, and L7.
7.2

Plant Material

Plants are to be healthy, well-grown specimens, free of pest and diseases. Plants
are to be delivered to the site in such a manner as to prevent damage in transit.
The Superintendent is to inspect plant material on delivery to site and sign off
approval. Any specimens which are not in accordance with the plant schedule or
are not well grown, free of pests and diseases may be rejected.
7.3

Plant Sizes

Plant materials are to be supplied in the following minimum sizes:


Shrubs
- 100mm container
Groundcovers/Succulents
- 100mm container
Deciduous Trees (Advanced Specimens) - 2.7metres high, 50mm trunk
calliper
700mm diameter container
7.4

Setting Out

The Contractor is to set out the plant material in accordance with the planting
plans and obtain the on-site approval of the Superintendent prior to planting.
Planting in large areas may be staged to ensure plants are not on-site and
in containers for longer than 24 hours.
7.5

Planting Conditions

Planting is not be carried out if the soil is very wet and waterlogged, or during
periods of adverse or extreme weather or windy conditions.
7.6

Planting Procedure for Shrubs, Ground Covers and Succulents

fertiliser

Thoroughly soak the plant before planting.


Over excavate each plant hole by at least three times the pot diameter
and pot height.
If the soil is very dry, fill with water and allow to drain completely.
Fertilise at the rate of 25gm of slow release, long life Osmocote
or similar) per 100mm diameter pot. Place fertiliser in the bottom of
the

hole and cover with soil to ensure there is no contact between the
roots
and fertiliser.
Place the plant into the hole and backfill with approved garden soil free
from weeds, stones, clods of subsoil and other extraneous matter.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
44
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019


soil

Plants are to be set plumb and level with the adjacent soil - ensure no
is placed against the stem of the root crown.
Form a bowl around the plant to hold at least 1 litre of water.
Spread mulch evenly over bowl.

The plant label is to be removed from the trunk of the plant and left visible in
the adjacent earth.
7.7

Planting Procedure for Deciduous Trees

Minimum size is not to be less than 2.7metres in height (soil level to top growth)
and 50mm diameter trunk caliper.

Thoroughly moisten plant roots before planting and soak all containergrown stock.

Dig hole of a sufficient size, with domed bottom to take root ball without
restricting the root diameter. Minimum diameter 400mm.

If the soil is very dry fill with water and allow to drain completely.

Cut back any damaged roots to healthy tissue.

Fertilise at the rate of 50gms of slow release, long life Osmocote


fertiliser
(or similar) per tree. Place fertiliser in the bottom of the hole and
cover
with soil to ensure there is no contact between the roots and fertiliser.
Planting: Place plant in hole. Gently cover the roots with imported topsoil
in 150mm layers and compact around the perimeter of the hole with
foot
to ensure no air pockets and root ends bend downwards. Ensure
roots
are not pressed against the bottom of the hole due to filling with soil
too
quickly or lumpy soil.

Staking: Allow to provide two (2) 2500x50x50mm hardwood stakes


per
tree, set to a minimum of 500mm apart to avoid root damage.
Drive stakes 500mm into the ground. Use approved flexible webbing
ties tied in a figure 8 configuration. Monitor tree stability in prevailing
winds before staking advanced trees.

Form a bowl around trunk to hold at least 6 litres of water. Spread


mulch
evenly over bowl.

Remove the plant label from the trunk of the plant and either tie to the
tree

guard, tree stake or leave visible in adjacent granitic sand.


7.8

Garden Mulch

After planting plants the Contractor will supply and spread shredded pine
wood
mulch to an average depth of 75mm (+/- 10mm) to all planting bed areas
after
planting. Mulch slither sizes to vary from 125mm to 25mm in length and 3 to 10mm
in
width and be of an even range of sizes. Mulch level to finish above adjacent
paved
surfaces.
Mulch is to be free from soil clods, rocks and all other non-organic matter.
Provide
a
sample of mulch for approval by the Superintendent prior to supply and delivery
to
the site.
Contract No: 1799
Title: Greeves Street, Streetscape Upgrade
45
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Keep mulch away from tree trunks to avoid rotting at ground level. Apply
mulch regularly to maintain mulch level as specified.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
46
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

8.
8.1

NEW GRASSED AREAS


Extents of works

The Contractor is to prepare the topsoil for Turf Type Tall Fescue instant turf
planting
to nature strip areas as shown on the Set Out Plans L3 and L4 and Details F L8
and
G L8.
8.2

Turf Type Tall Fescue turf laying

Lay Turf Type Tall Fescue instant turf to the specifications and instructions of the
turf
supplier.
8.3

Satisfactory growth

Maintain the turf bed in a weed free state and keep moist. The Superintendent is
to
give written notification when satisfactory establishment has taken place, upon
which
Practical Completion and the 26 week horticultural maintenance period will
commence.
Satisfactory establishment is defined as when the turf is unable to be lifted
clear from the underlying imported topsoil soil. Any areas of turf that
require replacement due to death or poor establishment are to be replaced by the
Contractor at no additional
charge to the contract.
8.4

Practical completion

Upon satisfactory growth of the Turf Type Tall Fescue turf as per clause 9.3,
the
Certificate of Practical Completion may be applied for. Upon receipt of Notice
of
Practical Completion, the contractor is to cut the grass using a cylinder
mower.
Immediately after the first cut, spread approved fertiliser to turf suppliers
directions. The fertiliser must not be spread on wet grass and is to be evenly
spread over the entire grass surface and thoroughly watered after application.
8.5

Mowing

Allow for mowing during the maintenance period. The initial cut is to take place
when grass is 50mm high and be cut to a height of 30mm, second and subsequent
cuts are to be done when the grass reaches 50mm in height.
8.6

Weed control

Inspect grass on a weekly basis and if weeds become apparent, remove weed
growth by cultivation. Selective herbicides may be used at the Contractors
direction. Ensure that weed spraying is carried out on a calm day and protect all
trees, shrubs and ground covers from spray drift damage.
8.7

Watering

Water grass regularly to ensure a dense sward of grass is established.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
47
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

9.
9.1

ESTABLISHMENT, DEFECTS, LIABILITY AND MAINTENANCE


General

The Practical Completion Certificate is given when all construction works


are
practically complete to the satisfaction of the Superintendent, garden beds and
plants
show successful establishment and the instant turf has firmly rooted into the
imported
topsoil layer. Any bare areas of reinstated grass may require re-turfing and
aftercare
and Practical Completion will be withheld until the defined percentage is achieved.
The Maintenance and Establishment Period commences at the issue of the
Practical
Completion Certificate. The Contractor is to maintain the horticultural works for
the
period of twenty-six (26) weeks following the issue of the Practical Completion
Certificate.
9.2

Maintenance

Maintenance includes the care of the Contract areas by accepted


construction
practices, as well as rectifying any defects that become apparent in the Contract
area
under normal use. This will include but not be limited to, the following items
where
and as required:
Re-spreading or topping up of mulch, relaying depressions in paved areas, refixing furniture, maintaining site neatly and tidily.
Any soil subsidence or erosion, which may occur after the soil filling and
preparation operations, is to be made good.
All mulched surfaces are to be maintained in a clean and tidy condition and
be reinstated if necessary, as specified.
9.3

Garden Beds

Garden beds are to be maintained weed-free, mulch kept topped up to the


specified depth and maintained clear of plant stems. Control any plant
chlorosis/yellowing with appropriate fertilisers.
Any weeds are to be removed by hand and disposed of to a legal point of discharge.
9.4

Plant Replacement

Replace any plants which fail to thrive or survive within 2 weeks of such

condition becoming evident.


9.5

Watering

Grassed areas, trees and garden bed areas are to be watered regularly by tanker
or
similar means so as to ensure continuous healthy growth. The minimum
acceptable
requirement for trees and shrubs is 10 litres of water during each period of one
week.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
48
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

9.6

Reporting

During the Maintenance and Establishment period, the site is to be regularly and
routinely attended at weekly intervals or more often as required. Each attendance
is to be marked by reporting to the Superintendent.
9.7

Final Completion

At the end of the Maintenance and Establishment Period, pavements, fixtures and
associated works are to be in first class condition to hand over to the
Proprietor. Pavements and fixtures are to be stable, clean, and structurally and
visually sound. The period may be extended until a satisfactory standard is
reached.
Request an inspection and report by the Superintendent one (1) week prior to
the end of the Maintenance and Establishment Period. Any defects are to be
rectified before the Maintenance and Establishment Period is deemed to be
complete.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
49
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

5. Specification - Lighting
UNMETERED PUBLIC FEATURE LIGHTING &
ASSOCIATED
ELECTRICAL
SERVICES

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
50
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

1.
1.1

WORKING INSTRUCTIONS
Drawings

The following Public Lighting and Associated electrical services drawings shall
form part of the Contract:
Drawing No.

Title

MSL105-E01

Greeves Street, St Kilda, Streetscape Upgrade Project


- Metered Featured Public Lighting Layout

MSLl105-E02

Greeves Street, St Kilda, Streetscape Upgrade Project


- Metered Featured Public Lighting Layout

1.2

Operating and Maintenance Instructions and Manuals

Provide operating and maintenance instructions and manuals in accordance with


the following specification:Operating and Maintenance Manuals - General
THREE (3) COPIES of the manual are required.
The data to be provided in the manuals shall include manufacturer's
literature,
diagrams, illustrations and drawing and test reports covering commissioning and
works tests.
A draft of the proposed manual shall be provided for the approval of
the Superintendent not later than one week prior to the due date for physical
completion of the work under the Contract.
Presentation
Manuals shall be of International A4 size, with stiff plastic covers. The binding
shall be of the loose leaf Type with all pages machine punched and shall permit
pages to lie flat and enable easy insertion and removal of pages.
Good quality, durable printing paper shall be used for text, printed on one side
only. Drawings shall be folded in their length to fit covers.
1.3

As Installed Drawings

On completion of the works, provide as-installed drawings detailing the


complete
works.
Supply a set of prints in each manual, and one (1) set of CAD disks.

All drawings shall be prepared using the computer aided drafting system
AUTOCAD
latest Release, Application CAD software and shall be supplied with .DXF, .DWG
&
.PDF format files. All computer drawings shall be compiled and saved on CDROM.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
51
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

1.4

Fees and Permits

The Contractor shall immediately upon entering into a contract make all
applications for permits and or certificates required by any authority having
jurisdiction over this contract and pay all associated fees including all on-site
inspection fees.
1.5

Materials, Workmanship and Sundries

All materials, fittings, accessories and apparatus shall be new and unused of
first grade design and manufacture, and shall comply with the relevant S.A.A.
document. The workmanship shall be of a high standard throughout.
The Contractor must submit to the Superintendent prior to commencing
installation,
samples of all accessories, fittings and apparatus which it is proposed to employ
in
the work, and only such times as have been approved may be installed. Failure
to
comply with this provision may result in the unconditional rejection of such
items
when inspected on site.
Any rejected materials, accessories or apparatus shall be removed from the
site within twenty-four (24) hours.
1.6

Setting Out, Cutting Away and Making Good

Thoroughly check the relevant dimensions on the drawings and confirm by


site measurements which will take precedence over other figures.
The setting out shall be confirmed on-site with the Superintendent at
the commencement of the contract and prior to any on-site works being performed.
The Electrical Contractor shall set out, at the earliest opportunity the position
and
sizes of all penetrations, recesses, etc, necessary for the accommodation of the
work
included in this Contract, and shall arrange to cut away for and make good
after,
such work.
1.7

Coordination

The Electrical Contractor shall be responsible for checking and co-ordination of


work under the Lighting and Electrical Services Works package.
1.8

Scaffolding, Hoisting and Lifting

Provide all cranage, lifting, hoisting, protection, hoarding, scaffolding and the
like

associated with the works of the Contract to the requirements of the


Workcover
Victoria, Electrical Distribution Business (Citipower) and any other relevant
Authority.
1.9

Tests

Carry out complete commissioning and testing.


All testing and commissioning work shall be carried out by qualified persons.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
52
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

1.10 Inspection of Site


The Electrical Contractor warrants that before tendering, the Electrical Contractor
inspected the site and is conversant with all visible existing conditions in
and
surrounding the site and with conditions of access to and use of the site for
building
purposes and has noted anything likely to affect the performance of the
contract
which such an inspection should have reasonably disclosed including work
below
overhead power lines.
1.11

Site Noise Control and Disruption

Comply with all statutory requirements relating to noise levels on site.


Take all necessary precautions to prevent nuisance from noise and vibration.
Cutting, drilling, digging, demolition and like activities shall be planned and
conducted in such a way as to cause as little inconvenience as possible to
occupants of adjacent areas and the public.
All compressors and other stationery engines shall be of the silenced type
and silence jackhammers shall be used where such breaking equipment is
necessary or called for. Operation of equipment shall be closely supervised
to ensure that silencers are always in place.
1.12

Codes and Standards

Notwithstanding that stated herein, the entire electrical services installation shall
fully
comply with the regulation of the following Authorities having jurisdiction over
such
works:
-

Victoria Building Regulations incorporating Building Code of Australia

Insurance Council of Australia (ICA)

Electricity Distribution Business (CitiPower)

Workcover Victoria

Together with all relevant Australian Standards and all Amendments to


those Standards.
1.13

Alternatives

The manufacturer and model numbers specified herein or on the drawings


indicate the preferred type of equipment and the design intent. The Electrical
Contractor may propose alternatives where noted with proof that they are

"equal". Acceptable "equal" proposal shall include submission of proof for


a)

Identical construction details

b)

Identical materials specification

c)

Identical technical performance

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
53
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Submit proof to Superintendent for approval if alternative is proposed.


The submission shall include:
a)

Appropriate technical literature

b)

Any initial and running cost savings

c)

Technical calculations

Where an item of equipment other than that specified or detailed in the


drawing,
which requires any redesign of the system, drawings showing the layout of
the
equipment and such redesign as required therefore shall be prepared to
the
satisfaction of the Superintendent at the Electrical Contractor's own expense.
Where
such approved deviation necessitates a different quantity and arrangement
of
materials and equipment from that originally specified or indicated on the
Drawings,
additional materials and equipment required by the system shall be provided at
no
additional cost.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
54
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

2.

SCOPE OF WORK - ELECTRICAL CONTRACT

The scope of work covered by the Lighting & Associated Electrical


Services documents and to be performed by the Electrical Contractor
includes the manufacture, supply, installation, testing, commissioning
and subsequent maintenance during the Defects liability period of the work
specified herein and shown on the accompanying drawings.
The Electrical Contractor shall be responsible for the provision of all
manufactured items, materials, labour, cartage, tools, plant, appliances and
fixings necessary for the proper execution of the works, including all minor and
incidental works.
1. 1100 MOCS Call, location and service location testing on site of all
Underground Services along the route of proposed trenches.
2. Conduct of formal CitiPower NO GO ZONE ASSESSMENT prior to
starting works on site to establish all safe working procedures
for works taking place near live network electrical assets.
3. Liaison with CitiPower and provision of Citipower pole mounted
Fused
Mains Junction Box and Enclosure Main Switchboard including a 2
Amp Circuit breaker together with co-ordination of the
unmetered
supply connections (4 No) for underground power supply to the new
Main Distribution Pillars, MDP-Carlisle, Vale, Blanche & Inkerman
and
payment of truck appointment fees to make connection. Note the
Drg
shows an approximate location only with exact supply points to be
confirmed.
4. new Main Distribution Board Pillars MDP-Carlisle, Vale, Blanche &
Inkerman as shown and specified including production of a drafted
shop drawing for approval. Pillars shall include Main
Distribution
Board and Public Lighting Controls as shown and shall also
include
Energy Retail Meter panels to suit possible future metering
additions
in case Council decide at a later date to convert to metered supply.
5. (Item Deleted - no new item)
6. Supply and installation of New Timber Light Posts Type TL1 and
TL2 including attendance during concrete pouring to locate
conduit into Posts.

7. Supply & Installation of Type U S1and S2 luminaires and wiring at


Light Posts. Works to also include all associated LED power
supplies and controls.
8. Night Trial during Construction to pinpoint placement and setouts of
Timber Light Post and orientation of luminaires .
9. External Feature Lighting Controls as detailed.
10. New Timber Light Post Foundations for Type TL1 and TL2 Light
Posts as detailed on the Landscape Architectural Drawings.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
55
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

11. Provision of luminaire samples for approval and swatches to


confirm
paint colours for Pillars.
12. Excavation, backfilling and reinstatement to suit the
proposed
Underground conduit and pit installation works.
13. Supply and Installation of Cat A underground PVC conduits and
draw
wires to supply Lighting & Power including Marker Tapes
14. Electrical Pits as shown.
15. Supply & Installation of Public Light and Power circuit wiring.
16. Engagement of a specialist company to accurately record to
CitiPower
approved record standards, the underground services laid
or
discovered to include precise offset measurements from
permanent
site features such as kerbing and entry into the MOCS system to
form
a permanent site record of works undertaken.
17. Testing and Commissioning including setup and functional check of
Public Lighting Controls.
18. Provision of Operating and Maintenance Manuals (3 sets) including
an
as-built drawing and CAD disk.
19. Removal of all rubbish and debris from the site associated with
the
works on a daily basis.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
56
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

3.

WORK BY OTHERS

Principal
1. (Item deleted).
2. Supply Connection Charge for the New Public Lighting Supply
levied
on 1st Customer Billing Accounts by the Energy Retailer for each
new
Electricity Meter..
4.

GENERAL ELECTRICAL REQUIREMENTS

Execute all work in accordance with the attached specification and drawings,
current rules and regulations and Australian Standards, the following in particular:

Building Code of Australia including Victorian Amendments

AS3000 SAA Wiring Rules

Wiring Regulations

Service and Installation Rules - Code of Practice for the Connection of

Electrical
Installations to Supply Mains.

AS3008 - Selection of Cables for A.C. Voltages up to 0.6/1kV

AS3439.1 - Low Voltage Switchgear and Controlgear Assemblies

Materials
New materials shall be supplied, unless otherwise specified on drawings.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
57
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

5.
5.1

ELECTRICITY SUPPLY AND METERING


Alternatives

Electricity Supply shall be new at supply points as shown.


Unmetered supply charges levied by Citipower will be the responsibility of
the
Principal.
Supply shall be taken at 240 V 50 Hz Single Phase and neutral.
Provide underground service conduit from Main Distribution Pillars to each
supply pole. Provide all works on supply pole to run mains up each supply pole
including cable guarding, a new Fused Mains Junction Box and enclosure
style Main switchboard mounted at 4 metres including a 2 Amp Circuit Breaker
as the Main Switch all to Citipower requirements and verified with Citipower
Connections Technical Advisor, Mr Terry Long 1300 132 894.
5.2

Metering

Arrange for each supply to be made as an unmetered connection of supply.


Confer with the Electricity Distribution Business to confirm requirements
for connection and allow for all materials and labour requirements.
Work shall include Liaison, and follow-up with the Electricity Distribution Business
on behalf of the Principal.
Complete all paperwork required by Citipower to effect connection with the
Principal and lodge on the Principals behalf.
Follow up during construction to obtain connection in good time for the
works
program.
Supply and install a meter panel in each Pillar to allow the possible future
conversion
to a metered supply in compliance with current Service & installation
Rules
requirements.
5.3

No Go Zone Assessment

The Contractor shall independently ascertain full details from the MOCS 1100
Call Service concerning the assets on site and carry out a site services location
survey using cable detection equipment to ensure assets are correctly pinpointed.
Upon award of contract and prior to any site works commencing directly arrange
with
CitiPower to have a NO GO ZONE ASSESSMENT carried out on proposed works

procedures and comply with all required provisions without variation to the contract.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
58
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

6.
6.1

MAIN SWITCHBOARD PILLARS (4 NO)


General Requirements

Supply & Install new Main Switchboard Distribution pillars (MSPs) fabricated only
by an approved manufacturer.
Each pillar shall be identical, free standing, totally enclosed, weatherproof, metal
clad, air break and dust vermin proofed type.
Each pillar shall be front connected and conform with AS 3439 and AS 1939 - IP65.
Provide switchgear, busbars, cables, supports, fixings, lugs, glands, gland plates,
terminals, nameplates, labels and all accessories necessary for the work. Use
nonflammable, non-hygroscopic and non-tracking materials.
Operating handles of switchgear shall not be higher than 2000mm and lower
than 375mm above finished floor level.
Fabricate cubicles as shown using folded and welded sections and bracings.
Ground flush all welds in normally visible areas.
Provide a channel frame as shown which shall be incorporated in the base of
each pillar to provide rigidity and support for lifting. Provide each pillar with a
suitable concrete plinth and bolt to this concrete plinth to approval.
The metalwork shall be clean, free from scale and blemishes, and given
internally and externally a corrosion inhibiting treatment, followed by a first
undercoat and a final coat. Colours shall be internal WHITE, external a selected
colour which shall be confirmed by the Superintendent at the time of shop drawing
approval.
Provide adequate ventilation to limit temperature rise to the requirements of
this specification and AS3439.
Ventilation louvres shall not be installed on front of switchboard.
Fit lockable doors to front for maintenance, inspection and testing.
Fit sponge neoprene gaskets around doors for dust-proofing.
Door and panel handles, hinges and fastenings shall be stainless steel.
Fit a door restraint arm at base of pillar to allow door to be secured open
against wind conditions.
Control sections of the switchboard shall be compartmentalised from the
power
sections.
2
Control and monitoring cables shall be multi-stranded minimum 2.5mm 0.6/1KV
V75
grade.
Colour code wiring in accordance with AS2067 and identify them by moulded
ferrules at both ends.
Terminate incoming and outgoing cables on insertion or tunnel type rail-mounted
terminal blocks.

Lace and loom cables and wires using ties, cleats, trays and ducts as
appropriate. Provide bushes to prevent chafing of cables.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
59
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Label all pillar apparatus and controls. Labels shall be polycarbonate,


engraved black lettering on white and all labels shall be mechanically fixed. The
pillar shall be fitted with a main label with 10mm high letters, in a position on inside
of Door.
Provide a rating plate to provide all information prescribed in AS 3439 and
include details of the rating plate on the submitted shop drawing. The plate shall
be located inside of door and in any case shall note manufacturer, date of
manufacture, fault rating capacity and form of construction.
Electrical equipment shall not be connected to the pillar until the equipment has
been tested to be safe for connections. Temporary final circuit connections
shall be provided with earth leakage protection.
A spares holder shall be provided inside the door of the pillar.
6.2

Shop Drawings

Prepare a professionally drafted shop drawing for approval by CitiPower


and Superintendent showing the proposed pillars.
Shop drawing shall include plans, elevations, sections, details and schematic
wiring diagrams to show the make up of each pillar, manufacturers of equipment
and all details necessary to provide a proper record of the installation.
6.3

Distribution Board

As listed provide a new Metalclad Load Centre style Main Switchboard at each
pillar. Fit fault current limiters as shown
The Distribution Board shall be a fully enclosed unit complete with Door and
Lock and not just a chassis and front escutcheon.
Miniature circuit breakers shall comply with AS3111.
Select fault interrupting capacity in accordance with the prospective fault
levels indicated on drawings.
In any case the minimum fault interrupting capacity shall be 6 kA. The utilisation
of current limiting fuses are acceptable.
Use the same manufacture of miniature circuit breakers throughout the
installation. MCBs shall be DIN style.
Circuit labelling and schedule shall be affixed to the inside of distribution boards.
New Labels shall be manufactured and be of engraved laminated plastic, Traffolyte
or
equal. Identification labels shall be 10mm high letters.
Electrical equipment and accessories shall not be connected to the distribution
board circuit breakers until they have been tested to be in safe operational order.
All
temporary connections for construction use or site tests shall be provided with
earth leakage protection. Electrical loading shall be balanced as evenly as
possible across the three phases during commissioning.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
60
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

6.4

Residual Current Circuit Breakers

The residual current devices (RCD's) shall be current operated circuit breaker type
in compliance with AS3190 and be fitted to the Public Lighting and power outlet
circuits as individual circuit breakers..
The circuit breakers shall provide 2 pole switching for single phase circuits and 4
pole switching for 3 phase circuits.
The RCD's and MCB's for final sub-circuit protection shall be one integral unit.
Single phase RCD protected circuit breakers shall only occupy a single pole
space. And 3 Phase RCD breakers 4 spaces maximum
The sensitivity shall be 30 mA.
6.5

Lighting Switches and GPOs

Provide GPOs as shown in the Distribution Pillars wired to a separate 20A MCB
on the corresponding Distribution Board.
GPO's shall generally be rated for 10 amp capacity unless otherwise indicated
on
drawings.
Each outlet shall be numbered with circular tags, indicating the circuit
number. Outlets shall be IP rated IP56 minimum
6.6

Lighting Control

Provide a New Daylight Sensor and Timeclock control circuit at each pillar
complete with manual bypass switch for routine testing to operate a contactor for
control of the Metered Public Feature Lighting and any future circuits.
Locate the PE Cell behind a windowed polycarbonate cutout within the Pillar to
one
side.
The opening shall be made weatherproof via polycarbonate window sheet
and maintain the IP rating specified for the Pillar.
6.7

Daylight Sensor

The daylight sensor shall be a photoelectric device contained within a


weatherproof and vandal-resistant enclosure, designed for outdoor operation and
rated for 10 Amp. 240 volt minimum. The relay shall switch lighting ON in
diminished lighting levels, and OFF in increased lighting levels. The switching
threshold value shall be of good stability, with built-in ON-OFF time delay of
approximately 30 seconds.
6.8

Timeclocks

The time clocks shall be single channel switching only not multi-channel.

Timeclocks shall have 24-hour 7-day cycles and automatic winter / summer time
switch over and integral manual override switch.
Time shall be set and adjustable by mechanical dials or by push button with
liquid
crystal display. The rating of each relay contact shall be minimum 2.5A Inductive
at

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
61
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

250V. The clock shall be protected by an IP20 plastic case. The time clock shall
be
quartz crystal operated. A minimum of 3 years running reserve shall be provided.
Timeclocks shall be NHP Grasslin Talento Digital Model 371.
Confirm operational setting times with the Superintendent during shop
drawing
approval.
6.9

Contractors

Contactors shall comply with AS1029 for mechanical duty Class 0.3 and making
and
breaking Category AC3. They shall be double break, non-sticking, chatter-free
and
shall operate without audible hums. They shall close satisfactorily at 80% and hold
in
satisfactorily at 65% of nominal voltage. Auxiliary contacts shall be rated at
minimum
10 Amps, 240V.
6.10

Relays

Relays shall be electro-mechanical plug-in type complying with AS1431. They


shall
have self-cleaning silver contacts and shall be enclosed in dust-proof clear
plastic
cases. The rating of the relay contacts shall match that of circuit breaker device.
The relays shall close satisfactorily at 80% and hold in satisfactorily at 65% of
nominal voltage.
6.11

Control Switches

Control switches shall be rotary type providing a positive wiping action


when operated, and designed for panel mounting. They shall be double break and
rated at a minimum of 16 Amp inductive at 0.8pf. Do not use circuit breakers for
switches. A manual bypass switch shall be provided for the Public Lighting
circuit per specification requirements listed above.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
62
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

7.
7.1

CABLING AND WIRING SYSTEMS


PVC/PVC Cabling

The cabling installation shall comply with AS3008 and AS3000..


PVC insulated and PVC sheathed (PVCPVC) cables shall comply with AS3147, of
0.6/1KV, V75 grade.
XLPE insulated and PVC sheathed (XLPEPVC) cables where
applicable shall comply with AS3198, of 0.6/1kV R90 grade.
Use multi-core cables with copper conductors and colour code, each core
using
standard approved colours. Preserve the uniformity of phase colours
throughout
the
installation.
Run cables straight and true, parallel with, or perpendicular to the main
axes
of
the
site.
Rate the cable to match the rating of the circuit protective device and equipment.
Each circuit shall incorporate an insulated earthing conductor of
appropriate size in accordance with AS3000.
Clip or saddle cables to approved supporting systems.
7.2

PVC Wiring

Use T.P.I. (PVC insulated) cables where wiring is enclosed within either steel
or PVC conduits, otherwise use TPS cables.
TPS and TPI cables shall comply with AS3147.
The cabling installation shall comply with AS3008 and AS3000. Joints in
cables will not be permitted.
Run cables straight and true, parallel with, or perpendicular to the main
axis of the site and pathways.
Apply derating in accordance with AS3008 as appropriate.
Rate the cable to match the rating of the circuit protective device and equipment.
7.3
Wiring Methods
External underground wiring
minimum

TPS in UPVC conduits with 600mm


cover to top of conduits.

Posts Internal
supporting

TPS installed clipped into timber

channel.
Power cable sizes shall have a minimum size as follows:
Lighting sub-circuits
Power sub-circuits
Single earthing conductor

6 sq mm
2.5 sq mm
2.5 sq mm

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
63
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Space circuits in accordance with AS3008 so that derating factors need not
be
applied.
Through joints in cables will not be acceptable.
7.4

Conduits

General
The minimum diameter of conduit used for Underground Public Lighting shall be
32 Dia UPVC Heavy Duty
Rigid Category A, Electrical Orange to AS 2053. Sharp edges shall be smoothed
prior to drawing-in wires.
General
The minimum diameter of conduit used shall be 32 mm external. Install drawin boxes in accessible positions.
Terminate conduits in switch and outlet boxes of the same material as the
conduits. Sharp edges shall be smoothed prior to drawing-in wires.
P.V.C. Conduit
PVC conduit shall be rigid, high impact, heavy or light duty as specified,
complying with AS2053.
Form sets using an internal bending spring. Use jointing cement to all
conduit connections.
Steel Conduit
Steel conduit using screwed fittings shall be used.
Treat threaded joints on metal conduits with aluminium paint or other
rust preventative to ensure good electrical continuity.
Make sets using a standard proprietary bender of proportional size to the
conduit being used. Any sets which do not retain substantially circular section or
which open seams, joints or welds will not be accepted.
Flexible Conduit
Use flexible conduit for final connection to items of fixed power equipment.
Flexible
conduit shall comprise helical wound, interlocking, flexible galvanised metal
tubing
having a close fitting PVC outer sleeve. Terminate using galvanised
screwed
adaptors of the same manufacture as the flexible conduit. Ensure that the flexible
conduit is of adequate length to avoid any strain on the conduit or terminations
under
all conditions of use.

7.5

Concealment of Wiring and Conduits

All wiring and conduits shall be generally be run concealed underground.


If the Electrical Contractor considers that a section of the wiring cannot be
concealed,
advise the Superintendent, who will issue a direction as to the installation of that

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
64
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

particular section of the wiring. There shall be no marring of constructed


finishes without express approval of the Superintendent.
7.6

Alignment of Equipment

Generally equipment shall be aligned Install conduits truly vertical or horizontal


and parallel to the main axis of buildings, pathways and site structures.
The location of equipment shown on the electrical layout drawings is
diagrammatic
only.
Confirm on site with the Superintendent the actual position required, prior
to installation of any work.
7.7

General Safety Precautions

All exposed or loose cable ends shall be protected with tape to prevent potential
risk to causing eye damage.
During installation all cables shall be rolled up to above head height to
prevent potential risk to causing eye damage.
Do not terminate cables onto circuit breakers of live switchboards until load end of
cable is permanently terminated and until the electrical equipment has
been
insulation tested. Do not connect cables to circuit breakers and tape the breaker
in
the OFF position.
Ensure that cables are not positioned to enable them to come into contact with
sharp edges of building elements.
7.8

Underground Cabling Installation

The underground cabling installation shall include:


a)

Liaison with the Distribution Business (CitiPower)

b)
Co-ordination with other in-ground services such as gas,
sewer,
stormwater, fire mains, water supply, service road lighting, irrigation
lines and telephone services, prior to digging, trenching or coring,
c)

Laying of sand-beds for all underground conduiting,

d)

Provision of lighting pits shown

e)

Supply and installation of Cat.A PVC conduits to accommodate the


underground cabling.
PVC conduits to be sealed to prevent
water seepage into conduits.

f)
the

Supply and installation of Electricity marker tapes continuously above


centre line of electrical conduits.

g)
call

Asset recording of position of underground services and input to 1100


system records using a specialist company approved to conduct works to
the Authorities Recording standards.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
65
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Provide temporary fencing, barriers and night lighting as appropriate to


prevent accidents. Generally trenching and backfill should be completed as
quickly as possible to ensure trench integrity, personnel safety and to prevent
obstruction to other activities on site.
Necessary precautions with due regard to the terrain and weather forecasts shall
be taken to prevent flooding and cave-in of exposed trenches.
Underground cables shall be installed in unbroken lengths between
termination
points. Exposed underground conduits shall be protected with metal or
concrete
cover slabs.
In each underground conduit a 4mm polyethylene draw rope shall be provided
for both used and unused conduits.
Where conduits rise above ground they shall be sealed with an expanding foam
or weak concrete slurry to prevent moisture and vermin entry.
7.9

Underground Cable Trenches and Conduits

The Electrical Sub-Contractor shall be fully responsible for the provision


including
laying and marking of all conduits associated with the public lighting supply
services.
Conduct all trenching, backfilling and surface reinstatement.
All trenching shall conform with the minimum requirements of this
specification section as setout hereafter as well as other specification
requirements of the authorities concerned.
Supply and install underground cable conduits for the enclosure of mains and
final
circuit cables. Cable conduits shall be laid 600mm (to top of conduits) below
pavements and final finished ground levels. Cable conduits shall be Rigid PVC
for
Category A underground system. Liaise with the Superintendent for exact routes
and
locations of cable conduit runs. Lay continuous heavy duty orange
polyethylene
marker tapes 300mm above and aligned with conduits on centre of run.
Trenches should be provided with a grade away from structures. Ensure that the
underground cable and conduit installation does not interfere with other
services including existing services on the site. Make good any damage to
other services during the cable conduit installation to the original conditions to
approval without variation to the contract price.

Trenches shall be constructed in straight runs and sides, with a smooth and even
bottom free from stones and other projections. Trenching in existing continuous
hard surface eg concrete. asphalt, bitumen, etc., shall be neatly saw-cut and
reinstated at completion by the Head Contractor.
Liaise with the Principal and the Distribution Business in trenching works. Arrange
for and pay costs associated with Distribution Business inspections of the cable
and conduit installation while trenches are open.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
66
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Backfilling over conduits shall use clean existing material free of organic matter
and rocks. Apply in maximum 300mm layers and compact to approval. Complete
backfill using approved top soil.
All excess spoil shall be removed from site.
Do not backfill excavations of the cable and conduit installation until the
relevant
construction or services installation works have been inspected, tested
where
appropriate, and approved by the Superintendent or Superintendents
appointed
representative and the Distribution Business where their services are involved.
Materials to be used for backfilling shall conform to one of the following types:
a)

Selected material excavated from site being free from organic matter, topsoil,
rubbish, debris, lumps or balls of clay and from rock with a
maximum dimension in excess of 100mm,

b)

Approved imported, granular material such as salamander, clean quarry


waste, granitic sand or clean road-making gravel, any such material to be
free of particles with a maximum dimension of 100mm, and

c)

First class backfilling consisting of material of quality not lower than Class 2A
crushed rock.

Filling materials shall be placed in horizontal layers of not more than 200mm
loose thickness and each layer tamped and/or watered then compacted as
appropriate to the required density before the following layer is placed.
The compacted density of the material when tested shall not be less than:
a)
For non-spanning slab on ground areas of building:
100% standard maximum dry density
b)

For areas covered by pavements:


95% standard maximum dry density

c)

For all other areas:


90% standard maximum dry density

The standard maximum dry density for the material shall be that obtained
in accordance with AS1289.
When services pipes are not required to be encased in concrete, initial filling of
the
same material as specified for pipe bedding, or 7mm nominal size fine crushed
rock,
shall be carefully packed around all pipes and fittings by placing and compacting
in
150mm layers until the filling material reaches at least 150mm above the tops of

the
pipes.
The materials shall be carefully packed by manual ramming only, to a level at
least
300mm above tops of pipes taking particular care to avoid damage and
displacement
of services components and jointing seals. Mechanical rammers may be used in
all
other locations.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
67
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

In order to avoid displacement of and damage to services components, the


material shall not be dropped into place from a height of more than 1 metre
unrestricted fall before the surface of compacted filling has reached a level of at
least 150mm above the tops of the pipes.
After initial backfilling trench excavations shall be backfilled as follows:
a)

BACKFILLING UNDER PAVEMENT


First class backfilling shall be used under pavements and any future
pavements. The trench shall be backfilled and compacted until level with
the underside of pavements and to the surface level for future
construction.
Approved imported granular material may be used as an alternative
material subject to specific authorisation of the Superintendent.

b)

BACKFILLING FOR OTHER AREAS


Selected material won from site shall be used for backfilling in areas other
than under buildings, pavements and surface drains. Filling material shall
be placed in layers not exceeding 200mm loose thickness and each layer
compacted before the following layer is placed.
In grassed areas, the turf sods which were removed and stored during
excavation works shall be set firmly in position with tops flush with the
adjacent turf surfaces, using good quality topsoil or sandy loam as bedding
as a filling around all sides of sods.

In other unpaved areas excluding garden beds, topsoils shall be placed and
packed to fill the excavation and finished with a slight mound to allow for
settlement.
In garden beds, the top of the excavations shall be filled with topsoil and mulch
to match existing strata and intending finished ground level.
7.10 Cable Locations
Engage a Specialist company approved by the Distribution Business to carry out
all service records of installed Underground Services in Public Areas to ensure
the records are prepared to a standard suitable for entry onto the MOCS system
for 1100 Call location by the Distribution Business and arrange for this to occur..
Mark the location of all electrical services conduits installed under this
contract through the installation of electrical marker tapes in durable polyethylene
inscribed Electricity. Lay above the centre line of each service conduit run in
accordance with the Trench Detail shown on the Drawings.
Cable marker tapes shall be high quality acid and alkali resistant polyethylene film
250mm wide in accordance with AS 2645 with inscriptions facing up.
Service record the location of all underground services laid or discovered to

Include precise offset from permanent site features such as kerbing. Include
attendance and laying of Electrical marker tape during backfilling for all trenches.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
68
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Lay surface cable markers at intervals not exceeding 30m of straight run, at
each change of direction, at each road crossing marking on kerb of road/path
edge each side.. Cable Markers shall be submitted for approved.
7.11

Underground Cable Pits

Confirm the exact setout of all cable pits.


Lighting (LP) Cable Service Pits shall be circular approved utility style Lighting
and Service Pits with Concrete lid 450 dia nominal to withstand the traffic
load and submitted for approval.
Note that all pits shall be able to withstand vehicular maintenance traffic.
Provide concrete collars around pit to reinforce design where necessary to
provide this capacity.
Polymer concrete (Polycrete) pits and / or lids are unacceptable for use with any pit
Pits constructed or finished with in-situ concrete shall be finished to a suitable
high quality exposed aggregate finish to approval.
All

Pit

Lids

shall

be

either

purchased

complete

with

the

wording
Electrici
ty prominently inscribed in the lid or alternatively labelled with non-trip cable
markers displaying the same wording securely fixed to the Pit Lid to approval
At Electrical turning pits offset install conduits to maximise bending radius for
draw-in operations.
Provide a gravel base and drainage hole in each pit.
Seal all conduit openings around and internally to ensure moisture and vermin
proof construction.
7.12

Tree Protection Guidelines

a)

TREE PROTECTION ZONES (TPZ)

All trees shall be protected from damage during the works.


A tree protection zone shall be established within the dripline of all tree trunks.
Install temporary fencing (star picket with para-webbing or similar approved)
to clearly mark tree protection zones.
In tree protection zones:

no fuel, oil or chemicals shall be allowed or stored.

servicing and re-fuelling of equipment and vehicles is prohibited

No storage of any materials, equipment or temporary buildings should take


place
b)

TRENCHING, EXCAVATION & BORING WORKS

Prior to commencement of any excavation or boring works, the locations of


all conduit routes and poles shall be marked on site for confirmation by

the superintendent.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
69
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

No trenching shall occur within the TPZ unless otherwise approved in writing by
the superintendent.
For all required underground cabling within TPZ, directional boring shall be utilised.
Extreme care shall be taken when excavating footings for light posts..
For footings within TPZ, hand digging only will be
unless otherwise approved in writing by the superintendent.

allowed,

For footings outside the TPZ, augers may be utilised, however


Superintendents arborist must be in attendance to monitor the works.

the

Where any roots greater than 40mm diameter are encountered, Contact
the Superintendent for instruction and direction

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
70
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

8.
8.1

GENERAL INSTALLATION REQUIREMENTS


Cutting Away, Chasing and Making Good

Advise the Superintendent with drawings where necessary, the locations and sizes
of all openings, conduits, inserts, etc. required for the installation of electrical
services. Supply and install conduits, inserts and fittings required.
8.2

Fixings and Anchors

Wooden plugs shall not be used for fixing anywhere on this site.
Fixings into masonry or concrete for lightweight items may use at least two
plastic
plugs .
Items heavier than one kilogram shall be fixed on to masonry or concrete with two
or
more metal expansion devices of the "Loxin" or similar type of adequate size.
The
expansion anchor shall be properly set before attempting to hold the item with
the
anchor.
8.3

Corrosion Protection

All small metallic parts shall be plated or of non-corroding material. Where


small parts are visible, such as switchboard hinges, they shall be stainless steel.
Other small items shall be galvanised, cadmium plated or passivated. All
external ferrous items exposed to weather shall be stainless steel or hot dip
galvanised.
Ferrous brackets or steelwork located out of doors shall be hot dip galvanised.
The metal shall be properly cleaned and prepared, then as a minimum shall
be primed and painted with two finishing coats.
Aluminium brackets and other items shall be anodised.
8.4

Earthing

The earthing system shall be to the requirements of the Distribution Business and
as specified in AS3000 SAA Wiring Rules.
Earth all metal enclosures, including Light Post metalwork, and pillars.
Bonding Conductors shall terminate as a common link block thence to the
Main Switchboard Main Earth Bar.
Conduct an earth impedance test to verify effectiveness of earthing.
Bond also, sheathing of cables, metal conduits, where applicable, and all parts
of a metallic system forming part of a wiring system, using earth clips, conductors
or other approved means.

Comply strictly with AS3000 relating to types, sizes, installation and connection of
all earth conductors.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
71
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

8.5

General Safety Requirements

Means of personnel access and equipment hoisting shall be secure to prevent


falling.
Bolted connections are preferred to site welding. Provide Firm and adequate
supports and means of fixing for the light fittings and conduits to prevent
support structure failure.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
72
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

9.
9.1

LIGHTING
Luminaires - General

Luminaires and Light Posts of the same type shall be identical and be of the types
shown on the drawings.
Luminaires shall be complete with lamps, starters, ballasts, diffusers,
suspensions and fixing brackets.
Ballasts shall be quiet in operation. Power factor correction capacitors shall
be
provided to maintain a minimum value of 0.90 lagging. Internal wiring shall
use
o
105 C PVC insulated conductors.
Lamp holders shall be manufactured from high temperature polycarbonate.
Provide an approved earth stud complete with washers and lock nuts on
each
luminaire.
Luminaires shall be glanded where wiring enters.
Metalware shall generally be powder coated.
Lamps shall all have matching colour temperature..
Upon completion of the installation, the luminaire and lighting equipment shall be
in first class operating order and free from defects in condition and finish. At time of
final inspection, all luminaires and equipment shall be clean, fully lamped,
and be complete with required lenses, reflectors, glare shields and other
components necessary for the function of the luminaires.
Any parts damaged prior to the final inspection shall be replaced by the
Electrical
Contractor prior to inspection. Replace or make good all defects revealed by
final
inspection.
9.2

Type U, S1 and S2 Feature Luminaries

Trial setout and aim luminaires at night trial and set at final commissioning
Provide brackets and supports for efficient neat installation such that luminaires
are neatly and securely mounted in a vandal resistant manner within the
support structure so as to be rendered least conspicuous both from an
appearance and vandalism protection viewpoint.
All brackets and fixings shall consider the method of wiring entry and be
concealed out of normal line of sight. No exposed connections will be permitted.
9.3

Lighting Night Trial

Include to conduct a night trial duration 2-3 hours over a single evening
during construction when construction is sufficiently advanced to allow the
instruction of final setout and aiming.
Bring a single post of each type fully equipped with luminaires and complete
with
temporary flex and plug and site leads to enable trialling of optimum setout
positions.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
73
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

10. LIGHT POSTS AND FOUNDATION


10.1

General

Supply & install New Light Posts as shown complete with all foundation
supports. All Posts shall be erected true.
The following procedure shall be carried out:
a)
b)
c)

Prepare detailed shop drawing for the Type TL1 & TL2 Timber Light Posts
including Luminaires.
Submit and obtain approval.
Fabricate and Deliver the posts and Luminaires specified.

10.2 Light Post Foundations


The Electrical Contractor shall be responsible for providing suitable concrete
post foundations suited to installation at the project site and shall include all
costs associated with their correct provision.
The Electrical Contractor shall provide in accordance with details contained on
the landscape architectural drawings.
Note that Foundation arrangements shown on Electrical Services drawings
show general pole and wiring installation requirements only and do not
purport to document size and depth of foundations or any other aspect of
the structural adequacy requirements.
The Electrical Contractor shall include to co-ordinate the provision of conduit
entries and orientation of posts to ensure that posts are erected with the correct
orientation of pole mounted luminaires. Carefully check the setup to ensure
luminaires when finally installed onto the poles obtain the correct alignment.
10.3

Timber Light Post Construction

Refer to the Landscape Drawings for details of Post Timber grade and
protective treatments required.
Design to suit the Luminaire arrangements shown and provide brackets to match
the luminaire mounting fixing and cable entries.
Bracketing and fixing shall be mechanically strong to maintain the luminaire in
the mounted position.
10.4 Access Panels
Provide access panels at the base of each timber pole. Access panel size shall
be nominated on the shop drawings.

The access panels shall be fully lockable as shown.


All power supplies and electrical apparatus shall be further enclosed via an
IP65 enclosure within each access panel.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
74
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

10.5

Delivery and Off Loading

Works shall include Freight & Off-loading.


10.6 Paint Finish
Paint exposed metalwork at each Timber Light Post using a selected external
coastal paint specification finish to be confirmed at time of shop drawing
submission by the Superintendent.
10.7

Shop Drawings

The following shop drawings shall be submitted as a minimum:

Shop Drawing Detail of each Timber Light Post Type including Luminaire in

proposed assembled condition.


Shop Drawing Schematic

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
75
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

11. ELECTRICAL ACCESSORIES


Switch and power outlet plates internally shall have high impact ABS, of
identical appearance and colour, generally surface mounted type.
Outlets shall be equal to Clipsal IP 56 rated and series grey switched socket
outlets with current rating as shown.
Each outlet shall be numbered with circular tags, indicating the circuit number.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
76
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

12. TESTING AND COMMISSIONING


12.1

Scope

This section sets out the testing and commissioning requirements of the
services
installed.
Test all systems and equipment as required by this specification.
Carry out preliminary testing, checking, control setting, etc. prior to notification
that the work has reached the state of Practical Completion. Provide during this
period a skilled operator to operate the system.
Give forty-eight (48) hours notice in writing prior to any sectional or complete tests
on any tests called for by this specification being executed. Provide all
necessary testing apparatus and be responsible for all costs associated with the
testing.
Test and demonstrate operational readiness of the following systems:

Metered Public Lighting & Controls

Each system shall be tested as specified in the respective section for the
system herein and the associated Standards.
All electrical Installation testing shall be carried out in accordance with AS3017.
Include copy of all testing notes and reports in the operating and
maintenance
manuals.
12.2

Electrical Inspection

Provide for the Electrical Services Installation prescribed and non-prescribed


works
to be inspected by a registered Electrical Inspector to be approved at time of
Tender
submission.
A full report shall be prepared and provided to the Lighting Consultant.
The Contractor shall make all applications and pay all fees as required.
There shall include but not limited to prescribed and non prescribed
inspections, truck appointments etc.
12.3

Certification

Perform at appropriate times during the currency of site work, all tests required
by Government and Local Authorities who may from time to time have jurisdiction
over the work, and obtain the necessary certificates of approval. Lodge all
these certificates of approval.
At the time of Practical Completion, and as a condition thereof, provide Certificates

of
Compliance for all works carried out under this contract and the Electrical
Inspection
Report.
Carry out all tests, obtain the necessary certificates of approval of the following:

The Certificate of Electrical Safety


Independent Electrical Inspection as setout herein.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
77
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Pole foundation structural certification.

All certificates shall be included in the Maintenance manual.


12.4

Earthing

Check that all earthing provided is installed and tested to the requirements
of AS3000 and AS3017.
12.5 Lighting
Check and clean all luminaires.
Verify by test all luminaires are fully functional
Set dim levels via switch dim control to each Type S1 & S2 luminaire as directed.
12.6

Main Switchboard Pillars

Test as specified in AS 3439. In any case carry out insulation tests.


Check that all circuit breakers function correctly and RCD Devices are
fully operational.
Check all Lighting Controls are functional and time clocks are programmed
to principals time settings
Check that all operating handles and other loose items have been supplied and
are in the correct storage positions.
Touch up cabinet scratches and polish off any dirty
marks. Vacuum out and refit any removed covers.
12.7 Wiring
At installation completion, remove any temporary cable bridges, secure all
cables, check all earth connections and check the security of all terminations. Tidy
up cabling and secure with wire ties.
12.8

Labelling, Padlocks and Keys

Clear and professionally signwritten or printed labels shall be provided on all line
equipment in areas if energised prior to practical completion.
Check that all labels required have been provided. All labels shall be screw fixed
traffolyte.
Supply & Fit the Principals approved Power Industry Padlocks to MSP
Pillars.
Hand over keys (2 sets) and any specified spare items to the
Superintendent.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
78
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

13. DEMONSTRATION AND TRAINING


The Electrical Contractor shall, prior to the issue of the notice of completion,
spend
sufficient time with the Principal or his appointed representative to show the
location
of all items which require maintenance and/or adjustment during the life of
the
installation. They shall also explain the operation of each item and system to
the
Principal and show where that item and system reference information is located in
the maintenance manual.
Allow for demonstration and training of the following systems:
System

Hours

Metered Public Lighting & Power

14. SERVICE AND MAINTENANCE


Carry out service and maintenance inclusive of lamp replacement for the full
duration of the maintenance contract (12 months).
The Electrical Contractor shall include to effect lamp replacement within 48 hours
of written notification to do so being issued by the Superintendent during the
service & maintenance period.

15.
15.1

WARRANTIES
General

Make good any defects caused by faulty workmanship and/or materials during the
Defects Liability Period upon notice to do so.
This shall extend to al lamps which fail within the 12 months defects liability period.
15.2

Time Warranties For Workmanship and Materials

The time warranties for the work commence at the agreed date of
Practical
Completion given to the Contractor for the completion of each phase of the works.
Warrant the respective portion of the works completed in each phase for a period
of
52 weeks from the date of Practical Completion.

In the event of inclusion of equipment normally covered by a lesser time


warranty, allow for and include the cost of extending such warranty.
15.3

Equipment Warranties

Warrant that the performance of all items of equipment used in the works are not
less
than those specified when operating under the specified conditions and that
such
equipment can be installed with adequate clearances for operation and
maintenance.
Replace any items of equipment, not meeting the requirements, at the sole cost
of the Contractor.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
79
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

Note:
Period

Replacement and/or repair of equipment during the Defects Liability


may result in the Defects Liability Period being extended for the
respective
items.

Contract No: 1799


Title: Greeves Street, Streetscape Upgrade
80
PORT PHILLIP CITY COUNCIL - amended and reproduced under copyright Licence 1204-c019

You might also like