CONSTRUCTION PLANNING & SCHEDULING:HUKM PATHOLOGY

N
o
1

2
3

ACTIVITY

TESTS INVOLVED

Preliminaries
I.
Site Office &
Hoarding
Site Clearing and Grubbing
Site Investigation

ESTIMATED
DURATION (Days)
2

3
a)Field Exploration

Soil Sampling
JKR Probe
Soil Investigation
Works Schedule
Groundwater
Level
Measurement
Piloting

b)Laboratory Testing

Earthwork
Platform Level:32,35,37 m
Volume of Cut=6482.85 m3
Volume of Fill=5824.17 m3

Turfing(31080m2)

Groundwork and Foundation


I.
Formwork and
Piling(Pad Footing)

Building Works(by Floor)


A )FABRICATION
STORAGE

Classification Test
(BS1377:1990)

Excavation
Compaction

Cube Test

48
*Waiting Period for hardening of
Concrete

B)BLOK A
I.
Formwork
Beam
Slab
Columns
II.
III.
IV.
V.
VI.
VII.
VIII.
IX.
X.

Cube Test
Inspection for detailing

Reinforcement Work
Concreting
Stairs
Brickwall
Roofing
Perimeter Drain
Plumbing Work
Sanitary Piping
Toilet Fittings

b) BLOK B
I.

II.
III.
IV.
V.
VI.
VII.
VIII.
IX.

Formwork
Beam
Slab
Columns
Reinforcement Work
Concreting
Brickwall
Roofing
Perimeter Drain
Plumbing Work
Sanitary Piping
Toilet Fittings

c)GUARD HOUSE AND


RUMAH SAMPAH

Infrastructure Works
I.
Road
II.
Parking
III.
Drainage
IV. Sewerage and
Manhole

*Upon finishing the structural


work

30

10

11
12
13
14

V. Water Reticulation
Internal Works
I.
Plumbing Installation
II.
Sanitary Appliances
III.
Electrical Installation
IV. Fire Protection
Installation
V. Air Conditioning
Installation
VI.
Lift and Conveyor
Installation
VII.
Communication
Installation
FINISHES
I.
Floor finishes
II.
Wall and ceiling
finishes
III.
Skirting and
architraves
IV. External rendering
V. Window Frames
VI.
Glass and Glazing
VII.
Doors
VIII.
Hardware
IX.
Window Cills
X.
Roof Lights
Inspection and Testing
Commissioning
Work Rectified Date
Handover

22