Professional Documents
Culture Documents
the
achievements
of
professionals
who
specialise
in
construction
claims
www.instituteccp.com
Chronology and Database
When it is time to prepare the claim, much time can be saved if various records are collected
and recorded on a database. The time to start doing this is as soon as an event occurs which
is likely to result in a claim. It then becomes a fairly easy job as correspondence, minutes
and the like are reviewed on a daily basis, to copy and file relevant documents separately
and to add them to the database. An example of a simple spreadsheet database is shown
below.
JOHNSON CONSTRUCTION GROUP
ANDY HEWITT
Construction Contracts and
Claims Consultant
Date
Type
Ref.
From
To
Subject
08-Jul-09
Letter
0306
JCG
APS
18-Jul-09
44
JCG
ENGR
25-Sep-10
Mat
App
Test
C1194
APS
JCG
Test Certificate
14-Oct-10
Letter
2053
ENGR
JCG
16-Oct-10
Letter
001
JCG
APS
Waterproofing Type 1
17-Oct-10
Letter
2196
JCG
ENGR
17-Oct-10
Letter
2061
ENGR
JCG
25-Oct-10
1194
APS
JCG
01-Nov-10
Letter
2114
ENGR
JCG
02-Nov-10
Letter
2264
JCG
ENGR
03-Nov-10
Letter
2123
ENGR
JCG
06-Nov-10
Letter
2280
JCG
ENGR
Contents
Letter of intent
Product and subcontractor
approval
Test Certificate 2A Underpass
Bridge
Waterproofing under
investigation. Instructed not to
lay until approved. APS to
provide requested information
Request technical clarifications.
Enclosing mix designs
Conf of verbal instructions.
Proceed with sub-grade where
waterproofing completed
Letter of undertaking required
from APS
Re Meeting 12 Oct. required
RSA mix design to confirm
compatibility. Pointing out
conflicts in dwgs and request
clarification
Repeat request for APS to
provide undertaking of product
performance
Request instructions re use of
RSA and RSA specification
Query why RSA is required.
Repeat request for performance
undertaking
Repeat request instructions re
use of RSA and RSA
specification
Date
Type
Ref.
From
To
Subject
06-Nov-10
Letter
2136
ENGR
JCG
11-Dec-10
Letter
2239
ENGR
JCG
19-Dec-10
Letter
2435
JCG
ENGR
20-Dec-10
Letter
2438
JCG
ENGR
20-Dec-10
Letter
2439
JCG
ENGR
04-Jan-11
Letter
2496
JCG
ENGR
04-Jan-11
Letter
2497
JCG
ENGR
05-Jan-11
Letter
2299
ENGR
JCG
05-Jan-11
Letter
2300
ENGR
JCG
Contents
Request information on use of
RSA and performance
undertaking. Confirm spec for
RSA provided by email
Not following claim procedure
Not relevant to waterproofing
Following claim procedure. Reconfirm notice of claim
Confirm instructions deleting
waterproofing. Notice of claim
Reserve rights to claim
Notice of claim
Rejection of claim. Allege
delivered mats not notified
previously
Rejection of delay claim
One of the best ways to write a claim narrative, particularly in the case of an extension of
time claim, is by way of a chronology. This will help to demonstrate cause and effect and will
also tell the story in a logical way and automatically lead the reviewer to a logical
conclusion. When sorted into chronological order, the records in such a database will form
an excellent starting point from which to start the claim narrative.
Such records and the database will be invaluable information to a claims consultant or to a
colleague who is not project-based, who may be brought in to prepare the claim.
The
database can also be used as an invaluable working tool while preparing the claim, for
example, significant events may be highlighted to establish when a certain event occurred
and the sort and filter functions in Microsoft Excel may be used to good effect.
This paper was provided by FICCP, Andy Hewitt.
If you have a paper or article to be considered for inclusion in the ICCP Knowledge Centre
and blog, please do let us know via hello@instituteccp.com.
Find out more about becoming an Associate, Member, Fellow or Corporate Member of
the ICCP at www.instituteccp.com