Professional Documents
Culture Documents
MANUAL
ON
RUNOFF COMPUTATION
WITH
HEC-HMS
NOVEMBER 2009
Project for
Strengthening of Flood Management Function of DPWH
This Manual.........................................................................................................................1
Purposes of Runoff Analysis ...............................................................................................1
Overall Procedures of Runoff Analysis with HEC-HMS....................................................3
3.3
3.4
Required Data......................................................................................................................6
Physical Conditions of Sub-basins ......................................................................................7
3.2.1 Catchment Area of Sub-basins ...............................................................................7
3.2.2 Lag Time ................................................................................................................7
3.2.3 SCS Unit Hydrograph Type Selection....................................................................8
Precipitation.........................................................................................................................9
Physical Features of River Reaches...................................................................................12
4.2
4.3
4.4
4.5
4.6
4.7
1.
INTRODUCTION
1.1
This Manual
HEC-HMS (HEC-Hydrologic Modeling System) is the computer program for the runoff
analysis developed by the Hydrologic Engineering Center (HEC), US Army Crops of
Engineers.
The software can be downloaded on the HECs web-site free of charge along
refer to users manuals and technical references of HEC-HMS issued by HEC, for further
understanding of the software.
Runoff analysis methodologies which are convenient for ungauged river basins are employed
in this manual so as to help flood control planning of small to middle sized river basins where
observed precipitation and discharge data are often unavailable.
Nevertheless, in principle,
It should be
noted that HEC-HMS users should direct their best efforts to search available recorded data
for the calibration, before going for methods for ungauged basins introduced in this manual.
1.2
Some of runoff analysis methods like the Rational Formula provide only a peak
discharge, while other methods, such as the unit hydrograph and the storage function
methods, can produce temporal discharge distribution (hydrographs).
Rainfall
River Basin
Rainfall
(on the catchment Area)
Time
Runoff Analysis
(e.g. Rational Formula, Unit Hydrograph, etc.)
Rainfall
Q (m3/s)
Discharge
(Peak Q or Hydrograph)
Time
Figure 1.1
Two questions may arise here; why discharges are required, and why discharge has to be
derived by transforming rainfall, instead of utilising observed discharge data.
Why discharges are required? :
should be designed based on peak discharge and associated water levels, so that river
channels can accommodate design discharge.
such as dams and retarding basins, require inflow hydrographs for their planning and design.
Why discharge has to be derived by transforming rainfall, instead of utilising observed
discharge data? : Flood control measures should be planned and designed based on design
flood with a targeted probability.
and reliable for the frequency analysis to estimate design probable floods.
The following
Stream gauging stations are often not installed especially in middle to small sized
river basins.
Discharge (water level) observation tends to fail during large floods, because
gauges can be damaged by floods.
Observed discharge records often cannot represent natural runoff phenomena, because it
can be affected by storage effects on upstream by dams, retarding basins, natural
swamps, overflows, and others. Changes of river channel dimensions and watershed
conditions may also alter downstream discharge characteristics.
Precise discharge can hardly be measured when flood water overflows from a river
channel.
Rating curves (H-Q curves) which convert recorded water levels to discharges are often
not available or not reliable.
though it is essential especially after large floods which could change river cross section
shapes.
extrapolation due to the absence of discharge measurement data during high water, and
therefore, are often lost reliability.
In short, rainfall data, especially daily rainfall data, is often more available and reliable than
discharge data.
rainfall.
Then, design discharge distribution is determined based on resulted peak discharges from the
runoff analysis, as schematically described in the following figure.
S2
Runoff at downstream
end of S2 (m3/s)
Q2
S3
S1
Q3
Q1
Runoff at downstream
end of S1 (m3/s)
Cross Sections
Q2
Q3
Flow
Q1
Q1 : Design discharge
for this stretch
Figure 1.2
1.3
Data preparation
2)
HEC-HMS computation
3)
2.
Chapter 3
Chapter 4
Starting HEC-HMS
Running simulation
Viewing results
Chapter 5
This chapter introduces features of the river basin which was applied for a practice model in
this manual.
This chapter also explains how to translate an actual river basin conditions into
an analysis model.
2.1
This manual
applies the SCS unit hydrograph, which is synthetic and requires the limited number of
parameters.
The SCS unit hydrograph is useful for ungauged river basins, because its
parameters can basically be derived from basin physical characteristics, not by calibration
with observed discharge data.
unit hydrographs, such as the Clark and the Snyder unit hydrographs can also be appropriate,
when observed discharge data adequate for calibration are available.
HEC-HMS enables users to involve river routine in a model as mentioned earlier.
Among
The San Juan river basin presented in the following map is used for this practice.
A practice
model for this manual includes only upstream parts of the basin, consisting of five subbasins
(S-1 to S-5).
The subsequent figure illustrates a basin model diagram of the practice model
area.
C-7
C-8
C-9
C-10
Figure 2.1
S-1
C-7
S-2
S-4
S-8
Salapan
Creek
S-9
C-10
C-9
S-7
Mytunas
Creek
C-8
S-6
Mariablo
River
S-5
Diliman
Creek
Talayan
Creek
S-3
Legend
S-1
Sub-basin and ID
C-7
S-10
Pasig River
Figure 2.2
3.
3.1
Required Data
Model Diagram
The runoff analysis for this practice, which employs the SCS unit hydrograph and the
Muskingam-Conge methods, requires the following data as inputs.
(i)
(ii)
(iii)
Precipitation
3.2.1
The catchment area of each sub-basin can be measured on the NAMRIA 1/50,000 maps with
a planimeter or with GIS.
Sub- Basin
No.
Name of Creek
San Francisco River (Junction
with Dario River)
22.8
S-2
Dario River
10.4
S-3
2.1
S-4
Mariablo River
9.8
S-5
Talayan River
8.3
S-1
Total
Note :
Area
(km2)
53.4
Data in this table are prepared for exercise purposes, and may differ from
actual site conditions.
3.2.2
Lag Time
The lag time is defined as the time between the center of mass of excess rainfall to the time to
peak of the unit hydrograph.
equations.
The lag time should be determined based on analyses of observed rainfall and
discharge data, or on the calibration of the runoff analysis in nearby gauged areas.
It can be
L Lca
Lg = 0.6865 Ct
Where :
0.38
Lg :
Ct :
L:
length of water course from the downstream end of the subbasin to the
upstream sub-basin boundary (km)
Lca
S:
average basin slope (overall slope along longest water course from the
downstream to upstream ends of the subbasin)
The following table summarizes physical features of the sub-basins and computed lag times
for this practice model.
3.2.3
L
(km)
7.954
4.145
3.115
4.018
5.056
Highest
Elev.
(El.m)
48
30
10
32
19
Lowest
Elev.
(El.m)
10
10
4
4
6
Elev.
Diff.
(m)
38
20
6
28
13
Slope
S
0.004777
0.004826
0.001926
0.006969
0.002571
Lg
Lca
(km)
4.20
2.00
1.60
2.01
2.45
Ct
0.35
0.35
0.35
0.35
0.35
(hr)
2.52
1.48
1.45
1.37
1.94
(min)
150
90
90
80
120
Data in this table are prepared for exercise purposes, and may differ from actual conditions.
Two types of the SCS unit hydrographs are available in HEC-HMS ver. 3.3, the Standard
and the Delmarva types.
The Standard type is default and has widely been applied in the
Philippines and other countries. The Delvarva type of the SCS unit hydrograph is originally
developed for flat coastal plain areas in the US, and produces a hydrograph with flatter peak
and longer base than the standard type.
Standard Type :
Urban areas
Mixed areas of urban and rural
Rural areas with average slope steeper than 0.5 per cent
Delvarva Type :
Rural areas with average slope milder than 0.5 per cent
In this practice, the Standard type is applied to all sub-basins, because the sample basin is
urbanized.
8
Precipitation
Rainfall applied to the runoff analysis should be basin average rainfall, not point rainfall at a
certain rainfall gauging station.
This
method is useful for areas where RIDF curves are available, but recorded hourly rainfall data
are not available.
Reference
hydrology text books and other documents for further details and for other methodologies.
Using RIDF curves, a design hyetograph can be derived through the following steps.
(i)
Procedures of developing a hyetograph from a RIDF curve are schematically shown below.
R=
(C + T)
b1
d1
b2
b3
r (mm)
R (mm/hr)
d2
d3
d4
d6
d5
d7
....
1
....
Time (hr)
Time
2hrs
3hrs
(hr)
(a)
1
2
3
4
....
(min)
T (a')
60
120
180
240
....
Rainfall
Intensity
from Eq.
R
(mm/hr)
R (b)
(b1)
(b2)
(b3)
(b4)
....
24
1440
(b24)
Duration
T
Figure 3.1
Cum. Rain
for (a) hrs
(b)x(a)
(mm)
(c)
(c1)=(b1)x1
(c2)=(b2)x2
(c3)=(b3)x3
(c4)=(b4)x4
...
Hourly Rain
Position
Incremental
of (c)
(mm/hr)
(d)
(d1)=(c1)
(d2)=(c2)-(c1)
(d3)=(c3)-(c2)
(d4)=(c4)-(c3)
....
(c24)=(b24)x24 (d24)=(c24)-(c23)
13th (Center)
12th
14th
11th
....
1st
The curves at Port Area synoptic station are applied to this example.
are provided as RIDF curves for the 10 and 25-year probable floods at Port Area rainfall
station in Reference 5.
R=
6017.42
(89.62 + T )0.85
R=
26620
(184.31 + T )1.02
where :
(ii)
T:
Duration (min)
R:
Daily or hourly scale of basin rainfall with a particular probability becomes smaller than point
rainfall, because intensive rainfall unlikely extends an entire river basin.
converted to basin rainfall using an area reduction factor defined by the following Hortons
formula.
Po :
A:
The catchment are of this practice model is 53.4 km2 as shown in Table 3.1.
Hence, the
Effective rainfall (excess rainfall) should ideally be analysed based on volume of rainfall and
runoff recorded during actual floods in or around the objective river basin.
However, when
observed data are not available, effective rainfall needs to be estimated by different a method.
In the Philippines, significant rainfall which triggers major floods normally occurs after certain
amount of small to moderate rainfall.
flood emerges under such conditions, and therefore, minimal losses should be considered.
For this practice, no loss is taken.
The hyetographs derived through the above procedures are summarized in the following
tables, and illustrated in the subsequent charts.
10
(a')
min
60
120
180
240
300
360
420
480
540
600
660
720
780
840
900
960
1020
1080
1140
1200
1260
1320
1380
1440
(a')
min
60
120
180
240
300
360
420
480
540
600
660
720
780
840
900
960
1020
1080
1140
1200
1260
1320
1380
1440
11
80
80
70
70
60
60
50
50
Rainfall (mm/hr)
Rainfall (mm/hr)
40
30
40
30
20
20
10
10
0
1
11 13 15 17 19 21 23
11 13 15 17 19 21 23
Time (hr)
Time (hr)
Figure 3.2
3.4
Design Hyetograph
The following table summarizes the features of river reaches, which are required for the
Muskingum-Conge method.
River
Name of Creek
Reach
C-7
Note :
Length
(m)
Highest
(El.m)
Lowest
(El.m)
El.
Difference
(m)
Ave. Basin
Slope
3115
10
0.001926
Data in this table are prepared for exercise purposes, and may differ from actual conditions.
These can be
Shape :
Trapezoid
Bottom width :
30m
Side slope :
vertical distance.)
4.
Mannings n :
0.03
HEC-HMS COMPUTATION
This chapter describes how to operate HEC-HMS software in order to accomplish the runoff
analysis using data prepared in the previous chapter.
12
(ii)
Inputting data
(iii)
(iv)
(v)
4.1
4.1.1
Before starting HEC-HMS modelling, users should keep the following aspects in mind.
The formatting of dates and times is suggested to be set to English (United States).
Using other formatting may cause errors in time series data of HEC-HMS.
In order to
change the formatting, select Start (usually placed at the left bottom corner of the window
screen) Control Panel Regional and Language Options Region select
English (United States).
For storing HEC-HMS data sets, one folder for one project is recommended to be created
prior to starting modelling.
following reason.
A long path to the folder where HEC-HMS files are saved might cause unexpected
problems. (For example, a model cannot be opened.)
problems, moving the folder to the root directory (e.g. C: HEC-HMS_practice) could
solve them.
4.1.2
Installation Procedure
Use the
4.1.3
1)
2)
User Interface
The user interface of HEC-HMS ver. 3.3 consists of a menu bar, tool bar and four main panes
as shown in the following figure.
13
Figure 4.1
4.2
Starting HEC-HMS
4.2.1
The program can be started by selecting Start (usually placed at the left bottom corner of the
window screen) Programs HEC HEC-HMS HEC-HMS 3.3 menu item, or by
double clicking the HEC-HMS icon
empty Project Definition Window in Figure 4.2 appears when the program is started.
Figure 4.2
14
The
A Project stores all HEC-HMS data sets including information of basins and precipitation.
new project should be created to start modelling.
Name :
Description :
Location :
Click
on the right, and select path to the folder which HEC-HMS
files should be stored in. (e.g. c:HECHMS-practice)
Figure 4.3
Go to Tools Project Options to open the Project Option Window (Figure 4.4).
Unit System :
Metric
Loss :
Transform :
SCS UH
Baseflow :
Routine :
Muskingum-Cunge
Gain Loss:
Precipitation :
Specified Hyetograph
Snowmelt :
15
Figure 4.4
available, 0.05 m3/s/km2 can be applied. (See Technical Standard and Guidelines : Part 1
Planning)
4.3
4.3.1
The Basin Model of HEC-HMS is a place to store information of sub-basins and reaches
constituting a model.
In order to create a Basin Model, on the menu bar of the Project Definition Window, select
Components Basin Model Manager New.
SanJuanRiver for this example, then press Create.
16
Figure 4.5
After adding a new basin, close the Basin Model Manager Window by clicking
The basin model name appears on the Watershed Explorer pane as shown in the following
figure.
Watershed
Explorer
Figure 4.6
4.3.2
Desktop Pane
in the following table, and a table in page 31 of HEC-HMS Users Manual describes all
elements.
Element icons can be found on the tool bar above the Watershed Explorer (see
Figure 4.7).
SanJuanRiver for this practice, on the Watershed Explorer (see Figure 4.7).
17
Name
Subbasin
Descriptions
This is used to present physical subbasins in the modelled river
basin. Rainfall is transformed to runoff in the subbasin.
Precipitation losses and baseflow can also be considered.
Reach
Junction
Note : * Icons on tool bar above the Watershed Explorer. See Figure 4.7.
A HEC-HMS basin model for the SabJuanRiver model should be developed as in the
following figure based on the basin diagram in Figure 2.2, using five subbasin (S-1 to S-5),
one reach (C-7) and three junction (Junction-1 to Junction-3) elements.
Watershed
Explorer
Desktop Pane
Component
Editor
Figure 4.7
In order to develop a basin model map, elements should be added on the Desktop Pane firstly.
Then, they should be connected each other to formulate a flow network system though the
following procedures.
18
Add elements
On the tool bar, push and activate an icon of an element to be added (see Figure
(i)
4.7),
(ii)
On the Desktop Pane, move the mouse and click at a targeted position where the
desired element is to be added,
(iii)
Input a name (e.g. S-1) of the element (Subbasin, Reach or Junction), and then
press Create,
(iv)
(2)
Repeat (i) to (iii) to add all elements. (S-1 to S-5, C-7, and Junction-1 to Junction-3)
Connect elements
icon on the tool bar to activate it,
(i)
Click on the
(ii)
Click on the desired element (S-1 to S-5, C-7, or Junction-1 to Junction-3) on the
Watershed Explorer (or click the element icon on the Desktop Pane) to activate the
Component Editor,
(iii)
On the Component Editor, select the Subbasin tab for Subbasins, the Reach tab for
Reaches, or the Junction tab for Junctions,
(iv)
(v)
19
Figure 4.8
4.3.3
Then, data of each element (Subbasin and Reach) should be input with the following
procedures.
(i)
Click on the
(ii)
In order to activate the Element Data Input Window, click one of element names
(Subbasin or Reach) on the Watershed Explorer (or click the element icon on the
Desktop Pane).
Figure 4.9
(iii)
(iv)
20
Subbasin
Subbasin
Area
(km2) *1
Transform
Loss
method
Transform method
Baseflow
method
Graph
Type*3
Lag Time
(min) *2
S-1
22.8
---None---
---None---
Standard
150
S-2
10.4
---None---
---None---
Standard
90
S-3
2.1
---None---
---None---
Standard
90
S-4
9.8
---None---
---None---
Standard
80
S-5
8.3
---None---
---None---
Standard
120
Note :
*1: see Tables 3.1, *2: see Table 3.2, and *3: see Subsection 3.2.3
Table 4.3
Tab
Reach
Reach
Routing
Method
Loss/
Gain
method
Length
(m)
Slope
Man
ning
sn
Invert
(m)
Shape
Bottom
width
(m)
Side
slope
C-7
Musking
umConge
--None--
3115
0.001926
0.03
(empty)
Trapez
oid
30
Note :
After completing element data input, go to File Save, in order to save the data.
4.4
In order to make the HEC-HMS model recognize rainfall data, design hyetograph data (hourly
rainfall values) should be input in Time Series Data, firstly.
For this practice, hyetographs for 10-year rainfall and 25-year rainfall are used.
Hence, two
separate Time Series Data, named Rain-10y and Rain-25y respectively, should be prepared.
(i)
On the menu bar of the Project Definition Window, select Components Time-Series
Data Manager Select Data Type of Precipitation Gauges New.
Specify a
rainfall time-series data set name, Rain-10y for the first example, then press Create.
(ii)
(iii)
On the Watershed Explorer Pane, click a yellow icon under the Time-Series Data
Precipitation Gages Rain-10y folder to activate the Component Editor (see Figure
4.10).
21
Figure 4.10
Units :
Incremental Millimeters
Time Interval :
01Jan2000
Start Time :
00:00
End Date :
02Jan2000
End Time :
Table tab
Input the design hyetograph data in the following table.
Figure 4.11, the first cell of the Precipitation (MM) (01Jan2000, 00:00) cannot accept
data input.
22
Note :
25-year Rain
Hour
Rain
mm/hr
1
1.15
2
1.27
3
1.56
4
1.89
5
2.41
6
3.02
7
4.05
8
5.51
9
7.95
10
12.29
11
21.33
12
45.26
13
75.60
14
30.04
15
15.87
16
9.70
17
6.55
18
4.61
19
3.49
20
2.77
21
2.09
22
1.77
23
1.50
24
1.15
Total
262.83
Figure 4.11
(iv)
(v)
23
A Meteorologic Model relates Time Series Data containing design hydrographs with
subbasins.
For this practice, a separate Meteorologic Model should be prepared for 10-year
and 25-year probable rainfalls (e.g. Meteo-10y and Meteo-25y), through the following
procedures.
(i)
Meteo-10y for the first example, then press Create as in the following figure.
Figure 4.12
(ii)
(iii)
On the Watershed Explorer Pane, click the Meteo-10y icon under the Meteorologic
Models folder in order to activate the Component Editor.
.
Then, the following
Precipitation :
Specific Hyetograph
Evapotranspiration :
---None---
Snowmelt :
---None---
Unit System :
Metric
Basins tab
(iv)
Then, click the Specified Hyetograph icon under the Meteo-10y icon on the
Watershed Explorer, in order to input the following information.
Subbasins tab
For all Subbasins, select Rain-10y in cells of the Gage column as in the following
figure.
24
(v)
Meteo-25y, and Gages (Time Series Data) applied to subbasins should be Rain-25y.
Successful procedures create two Meteorologic Model icons (Meteo-10y and Meteo-25y) and
two Time-Series Data icons (Rain-10y and Rain-25y) on the Watershed Explorer as in the
following figure.
Figure 4.13
4.5
The Control Specifications define start and end times and the time interval of the simulation.
The two cases (10-year and 25-year) of this practice model can share one Control
Specifications setting.
Select Components Control Specifications Manager New on the menu bar of the
Project Definition Window.
The Control Specifications folder and the Control 1 icon are created as in the following
figure.
25
Figure 4.14
On the Watershed Explorer Pane, click the Control 1 icon under the Control
Specifications folder in order to activate the Control Specifications tab in Figure 4.15.
Then, the required information should be input as follows.
Figure 4.15
For this practice, the start date and time is set at the initial time of the design hyetograph.
The end date and time was determined to secure 24 hours of a simulation period sufficiently
long in consideration of the precipitation period (24 hours for this practice) and the time lag of
a hydrograph (delay of the presence of peak discharge from peak rainfall.)
The time interval needs to be shorter than 0.29 x Lag time (see Table 4.2), and should be a
divisor of the time interval of the hyetograph data (1 hour for this example case).
this practice model, 20 minutes should be applied.
4.6
Running Simulation
4.6.1
Hence, for
One
In order to create a new Simulation Run configuration, on the menu bar of the Project
Definition Window, select Compute Create Simulation Run.
Run name, TestRun10y for the first case, then press Next.
Basin Model :
SanJuanRiver
Meteorologic Model :
Meteo-10y
Control Specifications :
Control-1
A new TestRun10y icon is created on the Compute tab page of the Watershed Explorer
Pane. (see Figure 4.16)
Then, repeat the same procedures for the second case applying the following information.
TestRun25y
Basin Model :
SanJuanRiver
Meteorologic Model :
Meteo-25y
Control Specifications :
Control-1
With the completion of the above procedures, two Simulation Run icons are displayed on the
Watershed Explorer Pane as shown in the following figure.
Figure 4.16
Simulation Runs
Discharge, outflow values are multiplied by the ratio value specified in this page.
27
Ratio tab
4.6.2
Ratio Method :
No Ratio
Run Simulation
In order to select the simulation case, go to Compute Select Run TestRun10y (or
TestRun25y) on the menu bar of the Project Definition Window.
Then, to start simulation, select Compute Compute Run [TestRun10y] (or Compute Run
[TestRun25y] ) on the menu bar of the Project Definition Window, or click
on the tool
bar.
4.7
Results can be accessed on the Results tab page of the Watershed Explorer Pane.
In
order to view results, click one of result type icons, such as Graph and Summary Table
under the Simulation Results simulation run name (e.g. TestRun10y) element name (e.g.
S-1) folder.
Figure 4.17
By clicking icons of different elements and different result types on the Watershed Explorer
Pane, simulation results at different points can be presented with different forms on the
Desktop Pane.
28
Figure 4.18
Figure 4.19
Figure 4.20
29
5.
Simulation results by the software cannot be utilized for subsequent analyses without
evaluation.
The software can complete simulation without providing error messages, but a
a lag time for the SCS unit hydrograph, should be adjusted to explore a best fit of two
hydrographs.
1400
OBSERVED
CALCULATED
1200
Discharge (m3/s)
1000
800
600
400
200
0
11/1 12/1 13/1 14/1 15/1 16/1 17/1 18/1 19/1 20/1 21/1 22/1 23/1 24/1 25/1 26/1 27/1 28/1 29/1
Date
Figure 5.1
When observed data are not adequately available for the calibration, specific discharge is one
of convenient references for checking simulation results.
hydrograph derived by the HEC-HMS computation should not be too far from ones of
recorded discharges in adjacent areas.
example.
Figure 5.2
30
REFERENCES
1.
HEC, USACE, HEC-HMS Quick Start Guide ver. 3.3, September 2008
2.
3.
4.
5.
6.
7.
Lin, Steve S.T. and Perkins, William At, Technical Memorandum DER 270: Review of
Pre-developed Runoff Analysis Methods volume I, .Water Resources Division,
Resource Planning Department, south Florida Water Management District , April 1989
Retrieved Sep., 2009 from
http://www.sfwmd.gov/portal/page/portal/pg_grp_tech_pubs/portlet_tech_pubs/dre-270.
pdf
31
Attachment
Runoff Analysis Input Data Processing Form
-Developing Hourly Rainfall Hyetograph
by Alternating Block Method-
00Start
Practice
53.4
Notes :
- This form helps users to develop hourly rainfall hyetographs by the Alternating Block
Method .
-
Black ltr.
and
Blue ltr.
Black ltr.
and
Blue ltr.
- Values in
Blue ltr.
and
Blue ltr.
Black ltr.
References :
1 RIDF of Selected Synoptic PAGASA Station, Attachment 4.3 of "Specific Discharge
Curve, Rainfall Intensity Duration Curve, Isohyet of Probable 1-day Rainfall ", FCSEC,
March 2003
2 Iso-specific Coefficient, Attachment 4.4 of "Specific Discharge Curve, Rainfall Intensity
Duration Curve, Isohyet of Probable 1-day Rainfall ", FCSEC, March 2003
3 Isohyet of Probable 1-Day Rainfall, Attachment 4.5 of "Specific Discharge Curve, Rainfall
Intensity Duration Curve, Isohyet of Probable 1-day Rainfall ", FCSEC, March 2003
01StList
Station
Vigan
Laoag
Aparri
Tuguegarao
Iba
Dagupan City
Baguio City
Cabanatuan
Baler
Port Area
Tayabas
NAIA (MIA)
Science Garden
Ambulong
Infanta
Alabat
Daet
Legaspi
Virac
Coron
San Jose
Romblon
Roxas City
Masbate
Catarman
Catbalogan
Tacloban City
Guiuan
Puerto Prinsesa
Cuyo
Iloilo City
Dumaguete City
Tagbilaran
Mactan International Airport
Maasin
Surigao
Dipolog
Cagayan de Oro
Malaybalay
Davao City
Hinatuan
Zamboanga City
General Santos
Region
Ilocos Sur
Ilocos Norte
Cagayan
Cagayan
Zambales
Pangasinan
Benguet
Nueva Ecija
Quezon
Manila
Quezon
Pasay City
Quezon City
Batangas
Quezon
Quezon
Camarines Norte
City Albay
Rader Catanduanes
Occidental Mindoro
Romblon
Aklan
Masbate
Northern Samar
Western Samar
Layte
Eastern Samar
Palawan
Palawan
Iloilo
Negros Oriental
Boholl
Cebu
Southern Layte
Surigao del Norte
Zamboanga del Norte
Misamis Oriental
Bukidnon
Davao del Sur
Surigao del Sur
Zamboanga del Sur
02Methods
Example of Method 1
Runoff Analysis Input Data Processing Form
Developing Hourly Rainfall Hyetograph by Alternating Block Method
2. Coefficients for Rainfall Intensity-Duration-Frequency (RIDF) Curve
(1) Selection of Methods : Selection is OK.
Tick with "x" one of four methods accorting to your selection.
x Method 1: Apply FCSEC's RIDF curves at one of PAGASA synoptic stations on sheet "01StList"
Method 2: Manual input of coefficients for RDIF curves
Method 3: Develop RIDF curves based on iso-specific coefficient and isohyet of probable 1-day rain
Method 4: Manual input of hourly rainfall values (Go to Sheet "04Method4")
425 Name
Station ID*
Port Area
Formula
T (min)
Type 1 :
4860.10
27.70
1.02
5426.08
58.15
0.92
16524.97
74.85
1.24
17502.14
185.91
1.02
10
27293.72
107.26
1.32
6017.42
89.62
0.85
(C
25
48845.51
167.53
1.43
26620.00
184.31
1.02
Type 2 :
50
69763.09
219.71
1.49
35363.86
200.22
1.05
100
82036.77
236.28
1.51
49935.14
221.44
1.08
R =
R=
A
+T
(C + T )b
2
5
Formula
T (min)
Type 1 :
R =
10
(C
25
Type 2 :
50
R=
100
A
+T
A
(C + T )b
b (=log /(log24-log1))
(from Reference 3)
R (mm)
10
25
50
100
10
25
50
100
R
24
24
I t = I 24 =
24
t
t
A (=I24)
C (=24)
Formula
t (hr)
24
Type 3 :
24
10
24
25
C
R = A
t
24
50
24
A = I 24
100
24
C = 24
(2-4) Method 4 : Manual input of hourly rainfall values (Go to Sheet "04Method4")
Example of Method 1
03R25yr
Coefficients
184.31
24
Storm (Rainfall) Duration for Runoff Analysis (Select from "7", "13" or "24" hours)
Duration
(hour)
Intensity
1.02
Design Hyetograph
(Total Rain, Point Rainfall)
d=c*a
97.61
97.61
97.61
1.49
78.02
156.04
58.43
1.64
64.94
194.82
38.78
2.01
55.59
222.36
27.54
2.44
48.57
242.85
20.49
3.11
43.12
258.72
15.87
3.90
38.75
271.25
12.53
5.23
35.19
281.52
10.27
7.12
32.22
289.98
8.46
10.27
10
29.71
297.10
7.12
15.87
30
11
27.55
303.05
5.95
27.54
20
12
25.69
308.28
5.23
58.43
10
13
24.06
312.78
4.50
97.61
14
22.62
316.68
3.90
38.78
15
21.35
320.25
3.57
20.49
16
20.21
323.36
3.11
12.53
17
19.18
326.06
2.70
8.46
18
18.25
328.50
2.44
5.95
19
17.41
330.79
2.29
4.50
20
16.64
332.80
2.01
3.57
21
15.94
334.74
1.94
2.70
22
15.29
336.38
1.64
2.29
23
14.69
337.87
1.49
1.94
24
14.14
339.36
1.49
1.49
110
100
90
Total
80
Rainfall (mm/hr)
70
60
50
40
13
24
Time (hour)
339.36
Note : The above rainfall amount is the total rainfall, and losses are not considered.
An area reduction factor for Method 1 (and for Methods 2 and 4, according to conditions) are not considered yet
Example of Method 1
03R25yr
53.4
0.7745
0.7745
Manual Input
Time
Total Rain
Loss
24
(adjusted by fa)
Design Hyetograph
(Excess Rain, Basin Rainfall)
(%)
(hour)
(mm/hr)
(mm/hr)
(mm/hr)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Total
Max.
1.15
1.27
1.56
1.89
2.41
3.02
4.05
5.51
7.95
12.29
21.33
45.25
75.60
30.04
15.87
9.70
6.55
4.61
3.49
2.76
2.09
1.77
1.50
1.15
262.81
75.60
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.15
1.27
1.56
1.89
2.41
3.02
4.05
5.51
7.95
12.29
21.33
45.25
75.60
30.04
15.87
9.70
6.55
4.61
3.49
2.76
2.09
1.77
1.50
1.15
262.81
75.60
to total
0.44%
0.48%
0.59%
0.72%
0.92%
1.15%
1.54%
2.10%
3.02%
4.68%
8.12%
17.22%
28.77%
11.43%
6.04%
3.69%
2.49%
1.75%
1.33%
1.05%
0.80%
0.67%
0.57%
0.44%
100.0%
28.77%
80
70
60
50
Rainfall (mm/hr)
40
30
20
10
0
7
13
Time (hour)
24
02Methods
Example of Method 2
Runoff Analysis Input Data Processing Form
Developing Hourly Rainfall Hyetograph by Alternating Block Method
2. Coefficients for Rainfall Intensity-Duration-Frequency (RIDF) Curve
(1) Selection of Methods : Selection is OK.
Tick with "x" one of four methods accorting to your selection.
Method 1: Apply FCSEC's RIDF curves at one of PAGASA synoptic stations on sheet "01StList"
Station ID*
Name
Formula
T (min)
Type 1 :
R =
10
(C
25
Type 2 :
50
R=
100
A
+ T
(C + T )b
459.44
0.00
0.58
649.58
0.00
0.56
10
3532.97
89.00
0.77
(C
25
8073.72
133.50
0.85
Type 2 :
50
26845.54
216.66
1.00
100
27489.24
209.17
0.99
Formula
Type
Type
T (min)
Type 1 :
R =
R=
A
+T
A
(C + T )b
b (=log /(log24-log1))
(from Reference 3)
R (mm)
10
25
50
100
10
25
50
100
R
24
24
I t = I 24 =
24
t
t
A (=I24)
C (=24)
Formula
t (hr)
24
Type 3 :
24
10
24
25
C
R = A
t
24
50
24
A = I 24
100
24
C = 24
(2-4) Method 4 : Manual input of hourly rainfall values (Go to Sheet "04Method4")
Example of Method 2
03R25yr
Coefficients
---
8073.72
133.50
24
Storm (Rainfall) Duration for Runoff Analysis (Select from "7", "13" or "24" hours)
Duration
(hour)
Intensity
0.85
Design Hyetograph
(Total Rain, Point Rainfall)
d=c*a
91.92
91.92
91.92
3.52
73.06
146.12
54.20
3.96
60.99
182.97
36.85
4.33
52.56
210.24
27.27
4.85
46.31
231.55
21.31
5.49
70
41.47
248.82
17.27
6.51
60
37.62
263.34
14.52
7.66
34.47
275.76
12.42
9.54
31.84
286.56
10.80
12.42
10
29.61
296.10
9.54
17.27
11
27.70
304.70
8.60
27.27
12
26.03
312.36
7.66
54.20
10
13
24.57
319.41
7.05
91.92
14
23.28
325.92
6.51
36.85
15
22.13
331.95
6.03
21.31
16
21.09
337.44
5.49
14.52
17
20.15
342.55
5.11
10.80
18
19.30
347.40
4.85
8.60
19
18.53
352.07
4.67
7.05
20
17.82
356.40
4.33
6.03
21
17.16
360.36
3.96
5.11
22
16.56
364.32
3.96
4.67
23
16.00
368.00
3.68
3.96
24
15.48
371.52
3.52
3.68
100
90
Rainfall (mm/hr)
80
50
40
30
Total
20
13
24
Time (hour)
371.52
Note : The above rainfall amount is the total rainfall, and losses are not considered.
An area reduction factor for Method 1 (and for Methods 2 and 4, according to conditions) are not considered yet
Example of Method 2
03R25yr
53.4
0.7745
0.7745
Manual Input
Time
Total Rain
Loss
24
(adjusted by fa)
Design Hyetograph
(Excess Rain, Basin Rainfall)
(%)
(hour)
(mm/hr)
(mm/hr)
(mm/hr)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Total
Max.
2.73
3.07
3.35
3.76
4.25
5.04
5.93
7.39
9.62
13.38
21.12
41.98
71.19
28.54
16.50
11.25
8.36
6.66
5.46
4.67
3.96
3.62
3.07
2.85
287.75
71.19
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2.73
3.07
3.35
3.76
4.25
5.04
5.93
7.39
9.62
13.38
21.12
41.98
71.19
28.54
16.50
11.25
8.36
6.66
5.46
4.67
3.96
3.62
3.07
2.85
287.75
71.19
to total
0.95%
1.07%
1.16%
1.31%
1.48%
1.75%
2.06%
2.57%
3.34%
4.65%
7.34%
14.59%
24.74%
9.92%
5.73%
3.91%
2.91%
2.31%
1.90%
1.62%
1.38%
1.26%
1.07%
0.99%
100.0%
24.74%
80
70
60
50
Rainfall (mm/hr)
40
30
20
10
0
7
13
Time (hour)
24
02Methods
Example of Method 3
Runoff Analysis Input Data Processing Form
Developing Hourly Rainfall Hyetograph by Alternating Block Method
2. Coefficients for Rainfall Intensity-Duration-Frequency (RIDF) Curve
(1) Selection of Methods : Selection is OK.
Tick with "x" one of four methods accorting to your selection.
Method 1: Apply FCSEC's RIDF curves at one of PAGASA synoptic stations on sheet "01StList"
Method 2: Manual input of coefficients for RDIF curves
x Method 3: Develop RIDF curves based on iso-specific coefficient and isohyet of probable 1-day rain
Method 4: Manual input of hourly rainfall values (Go to Sheet "04Method4")
Station ID*
Name
Formula
T (min)
Type 1 :
R =
10
(C
25
Type 2 :
50
A
+ T
R=
(C + T )b
100
** : Short duration curves are not applicable to this form.
2
5
Formula
T (min)
Type 1 :
R =
10
(C
25
Type 2 :
50
A
+T
A
(C + T )b
R=
100
Location Interested
7.3
(from Reference 3)
R (mm)
0.626
10
25
50
100
155
230
270
330
365
400
10
25
50
100
6.458
9.583
R
24
24
I t = I 24 =
24
t
t
b (=log /(log24-log1))
Formula
Type
A (=I24)
C (=24)
6.458
24
0.626
Type 3 :
9.583
24
0.626
10
11.250
24
0.626
25
C
R = A
t
13.750
24
0.626
50
15.208
24
0.626
A = I 24
100
16.667
24
0.626
C = 24
2
5
Type
t (hr)
b
(2-4) Method 4 : Manual input of hourly rainfall values (Go to Sheet "04Method4")
Example of Method 3
03R25yr
Method 3: Develop RIDF curves based on iso-specific coefficient & isohyet of probable 1-day rain
Method 4: Manual input of hourly rainfall values (This sheet is not used. Go to Sheet "04Method4")
Coefficients
---
13.75
24.00
24
Storm (Rainfall) Duration for Runoff Analysis (Select from "7", "13" or "24" hours)
Duration
(hour)
Intensity
0.63
Design Hyetograph
(Total Rain, Point Rainfall)
d=c*a
101.82
101.82
101.82
5.24
65.79
131.58
29.76
5.28
50.96
152.88
21.30
5.73
42.51
170.04
17.16
6.11
36.94
184.70
14.66
6.65
32.93
197.58
12.88
7.35
29.88
209.16
11.58
8.08
27.47
219.76
10.60
9.11
25.51
229.59
9.83
10.60
10
23.87
238.70
9.11
12.88
30
11
22.48
247.28
8.58
17.16
20
12
21.28
255.36
8.08
29.76
10
13
20.23
262.99
7.63
101.82
14
19.31
270.34
7.35
21.30
15
18.49
277.35
7.01
14.66
16
17.75
284.00
6.65
11.58
17
17.09
290.53
6.53
9.83
18
16.48
296.64
6.11
8.58
19
15.93
302.67
6.03
7.63
20
15.42
308.40
5.73
7.01
21
14.96
314.16
5.76
6.53
22
14.52
319.44
5.28
6.03
23
14.12
324.76
5.32
5.76
24
13.75
330.00
5.24
5.32
110
100
90
Total
80
Rainfall (mm/hr)
70
60
50
40
13
24
Time (hour)
330.00
Note : The above rainfall amount is the total rainfall, and losses are not considered.
An area reduction factor for Method 1 (and for Methods 2 and 4, according to conditions) are not considered yet
Example of Method 3
03R25yr
53.4
0.7745
1.0000
Manual Input
Time
Total Rain
Loss
24
(adjusted by fa)
Design Hyetograph
(Excess Rain, Basin Rainfall)
(%)
(hour)
(mm/hr)
(mm/hr)
(mm/hr)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Total
Max.
5.24
5.28
5.73
6.11
6.65
7.35
8.08
9.11
10.60
12.88
17.16
29.76
101.82
21.30
14.66
11.58
9.83
8.58
7.63
7.01
6.53
6.03
5.76
5.32
330.00
101.82
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
5.24
5.28
5.73
6.11
6.65
7.35
8.08
9.11
10.60
12.88
17.16
29.76
101.82
21.30
14.66
11.58
9.83
8.58
7.63
7.01
6.53
6.03
5.76
5.32
330.00
101.82
to total
1.59%
1.60%
1.74%
1.85%
2.02%
2.23%
2.45%
2.76%
3.21%
3.90%
5.20%
9.02%
30.85%
6.45%
4.44%
3.51%
2.98%
2.60%
2.31%
2.12%
1.98%
1.83%
1.75%
1.61%
100.0%
30.85%
110
100
90
80
70
Rainfall (mm/hr)
60
50
40
30
20
10
0
7
13
Time (hour)
24
02Methods
Example of Method 4
Runoff Analysis Input Data Processing Form
Developing Hourly Rainfall Hyetograph by Alternating Block Method
2. Coefficients for Rainfall Intensity-Duration-Frequency (RIDF) Curve
(1) Selection of Methods : Selection is OK.
Tick with "x" one of four methods accorting to your selection.
Method 1: Apply FCSEC's RIDF curves at one of PAGASA synoptic stations on sheet "01StList"
Method 2: Manual input of coefficients for RDIF curves
Method 3: Develop RIDF curves based on iso-specific coefficient and isohyet of probable 1-day rain
Station ID*
Name
Formula
T (min)
Type 1 :
R =
10
(C
25
Type 2 :
50
R=
100
A
+ T
(C + T )b
2
5
Formula
T (min)
Type 1 :
R =
10
(C
25
Type 2 :
50
R=
100
A
+T
A
(C + T )b
b (=log /(log24-log1))
(from Reference 3)
R (mm)
10
25
50
100
10
25
50
100
R
24
24
I t = I 24 =
24
t
t
A (=I24)
C (=24)
Formula
t (hr)
24
Type 3 :
24
10
24
25
C
R = A
t
24
50
24
A = I 24
100
24
C = 24
(2-4) Method 4 : Manual input of hourly rainfall values (Go to Sheet "04Method4")
Example of Method 4
04Method4
Method 4: Manual input of hourly rainfall values (This sheet is not used. Go to Sheet "04Method4")
5
24
Storm (Rainfall) Duration for Runoff Analysis (Select from "7", "13" or "24" hours)
Hourly Rainfall Distribution
Time
Design Hyetograph
(Total Rain, PointRainfall)
(hour)
2.42
2.56
2.72
2.92
3.15
3.44
3.80
4.29
4.98
10
6.06
11
8.07
12
13.99
13
47.84
14
10.01
15
6.88
16
5.45
17
4.60
18
4.03
19
3.61
20
3.28
21
3.03
22
2.82
23
2.64
24
2.49
60
50
Total
Rainfall (mm/hr)
40
30
20
10
0
7
13
24
Time (hour)
155.04
Note : The above rainfall amount is the total rainfall, and losses are not considered.
An area reduction factor for Method 1 (and for Methods 2 and 4, according to conditions) are not considered yet
Example of Method 4
04Method4
C. A. (km ) *
Area Reduction Factor fa
Area Reduction Factor fa
Applied
53.4
0.7745
0.7745
24
Manual Input
Total Rain
Loss
Excess Rain
(adjusted by fa)
Design Hyetograph
(Excess Rain, Basin Rainfall)
(%)
(hour)
(mm/hr)
(mm/hr)
(mm/hr)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Total
Max.
1.88
1.98
2.11
2.26
2.44
2.66
2.94
3.32
3.86
4.69
6.25
10.83
37.05
7.75
5.33
4.22
3.56
3.12
2.79
2.54
2.34
2.18
2.04
1.93
120.07
37.05
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.88
1.98
2.11
2.26
2.44
2.66
2.94
3.32
3.86
4.69
6.25
10.83
37.05
7.75
5.33
4.22
3.56
3.12
2.79
2.54
2.34
2.18
2.04
1.93
120.07
37.05
to total
1.57%
1.65%
1.76%
1.88%
2.03%
2.22%
2.45%
2.77%
3.21%
3.91%
5.21%
9.02%
30.86%
6.45%
4.44%
3.51%
2.96%
2.60%
2.32%
2.12%
1.95%
1.82%
1.70%
1.61%
100.0%
30.86%
40
30
Rainfall (mm/hr)
Time
20
10
0
7
13
Time (hour)
24