Exercise 1

You are project manager that has been handed the following Work Breakdown Structure. As a project manager you must do the following:
1) Prepare a project network diagram.
2) Calculate the scheduling times (forward and reverse passes) and total float for each activity.
3) Identify critical path activities.

Activity

Immediate Predecessor

Duration (Days)

A
B
C
D
E
F
G
H
I
J

A
B
B
C
D,E
F,G
H,I

2
3
4
1
2
5
7
2
3
1

Exercise 1 Solution

Exercise 2
You are project manager that has been handed the following Work Breakdown Structure. As a project manager you must do the following:
1) Prepare a project network diagram.
2) Calculate the scheduling times (forward and reverse passes) and total float for each activity.
3) Identify critical path activities.

Activity

Immediate Predecessor

Duration (Days)

A
B
C
D
E
F
G
H
I
J
K
L
M

B,E
C
C
C
G
A
A
I,D,F
K,H
L,J

18
3
1
4
6
8
6
11
5
22
7
9
5

Exercise 2 Solution

Exercise 3
You are project manager that has been handed the following Work Breakdown Structure. As a project manager you must do the following:
1) Prepare a project network diagram.
2) Calculate the scheduling times (forward and reverse passes) and total float for each activity.
3) Identify critical path activities.

Activity

Immediate Predecessor

Duration (Days)

A
B
C
D
E
F
G
H
I
J
K
L

A
A
B
B
B
F
D,E
C
I
H
G,J,K

7
10
12
3
8
7
2
5
13
6
14
5

Exercise 3 Solution

Exercise 4
You are project manager that has been handed the following Work Breakdown Structure. As a project manager you must do the following:
1) Prepare a project network diagram.
2) Calculate the scheduling times (forward and reverse passes) and total float for each activity.
3) Identify critical path activities.

Activity

Immediate Predecessor

Duration (Days)

A
B
C
D
E
F
G
H
I

A
A
D,E
C
B,C
F,G,H

8
10
8
10
16
17
18
14
9

Exercise 4 Solution