MANDATORY SPARE PARTS

SECTION A.4.2
(ELECTRICAL)
COKE HANDLING SYSTEM PACKAGE
A307-0ID-16-50-SL-7000 Rev. A
INTEGRATED REFINERY EXPANSION PROJECT
Page 3 of 3
BPCL-KR

Sl. No

PART DESCRIPTION

7.0

HV induction motors & MV induction motors


37 kW & above (one set of spare for each
rating & type)

7.1.

Bearing (DE & NDE)

7.2.

Terminal studs/bushing assembly

QUANTITY REQUIRED

One each
One set each

NOTES:
1. The word TYPE means the Make, Model no., Type, Range, Size/ Length, Rating, Material
as applicable.
2. The terminology used under 'Item Description' is the commonly used name of the part and
may vary from manufacturer to manufacturer.
3. Mandatory spares as indicated above do not cover commissioning spares.
4. Mandatory spares as indicated above do not cover two year O&M spares.
5. Mandatory spares shall be applicable for electrical items of sub-packages as per mandatory
spares philosophy specified elsewhere in the bid document.

Format No. EIL 1641-1924


1
Page 1108 Rev.
of 3134

Copyright EIL All rights reserved