Professional Documents
Culture Documents
Proposed by:
PT. ITS KEMITRAAN
o Haryo Dwito Armono, PhD
o Sujantoko, MT
o Sholihin, MT
September 2013
I. INTRODUCTION
a. Background
The development and activities along coastal areas (such as harbor extension and developments, port
channel dredging, reclamation, construction of coastal protection, etc) will impact the natural stability of
the shoreline. The effect of the development varies in each coasts, depend on the wind and wave
climate, tidal range, sediment materials, geographical location as well as geological condition. A proper
planning is essential to ensure the development of coastal areas have small influence to the surrounding
area, nevertheless improve the environment of coastal areas.
The development of coastal areas for waterfront cities has been growing rapidly in Indonesia. PT Karya
Unggulan Gemilang (KUG - LIPPO Group) planned to develop coastal areas in Ambon Gulf. The
development including coastal reclamation / beach nourishment and construction of coastal protection
structures in the boundary of reclamation land. KUG has started construction of Phase 1 (1.2 Ha)
reclamation as part of a larger reclamation project (total 64 Ha) at Ambon Bay. This is the proposal by
PT ITS Kemitraan (ITSK) to review a design of coastal structures (bundwall) initially developed by PT
KUG
b. Purpose of Study
As stated in te Term of Reference, the purpose of the study is to analysis of structural design on
reclamation of 1.2 Ha in the bay Ambon Reclamation project to minimize the reclamation construction
cost and to ensure that the coastal works is reasonable to construct
c. Area of Study
The study cover the area in the vicinity of Waai Ruhu river or Merah Putih Bridge as shown in the figure
below. Detailed location will be provided by LIPPO Group (the project owner).
d. Scope of Works
The owner (KUG) seek the professional engineering services of ITSK for the following works:
Design Optimization
In Design Optimization, we will redesign the coastal protection structure if the analysis shows the
previously design of coastal protecting structures (bundwall) is inadequate. The redesign is based on
the current Soil Condition and data, redesign Reclamation Level Design, and Slope Stability analysis.
Coastal Protections Structure will also be redesign includes the selection of Armour units and
Structure Stability.
In the design review and proposed design the following aspect will also be considered:
A. Soil Condition. The condition of existing soil affects the reclamation project. The thickness of
soft clay (soil) will give the degree of settlement and time of consolidation. Soft soil also
influences the stability of embankment slope and coastal protection structures. The elevation of
reclamation level should consider the soil condition.
B. Bathymetric condition. Coastal reclamation also need to consider the depth of the reclaimed
coastal area. Deep bathymetric area will cost more, as the need of fill material is increase. The
thickness of reclamation fill will also bring the high settlement rate and likely of sliding.
C. Coastal Protection Structure. Filled area of reclamation must be protected from incoming wave
as well as to hold the embankment of soil. Coastal protection structure will be costly for high
reclamation level on soft soil.
To give a best design, a model either numerical of physical model is needed. The model in used to give
aid in the process of seeking the best design. The model is used to minimize the uncertainties that will
be occur in the design process. Kamphuis(2000) shows the design process in coastal engineering practice
usually follows the following chart:
Post-
Preliminary Modelling Design Project
Implementation
Design Implementation
Monitoring
Approval
Due to the limited time given by the owner, only numerical model will be performed in this study. A
numerical model can be used to check the integrity of structural designed by the owner previously.
The slope stability software will also be used to analyze the stability of coastal protection structures.
Figure 3 shows the typical results of slope stability analysis using GEO Slope.
g. Time of Study
Time allocate for structural design study work less than one months starting from authorization
of work in Letter of Intent (LOI).
h. Bill of Quantity
The following experts is needed for the proposed study:
A. Coastal Engineer also act as TEAM LEADER
B. Geotechnical Engineer 1 person
C. Technical Assitant 2 persons
D. CAD operator 1 person
Total cost of the proposed study is Rp 237.050.000, (Two hundred thirty seven million fifty thousand
rupiahs) including 10% Value Added Tax as shown in detail as follows:
Description Quantity Rate (Rp) Cost (Rp)
A. DIRECT LABOR
A.1 Senior/ Expert
1 Lead Engineer & Coastal Engineer 1 MM 30.000.000 30.000.000
2 Geotechnical Engineer 1 MM 25.000.000 25.000.000
A.2 Engineer / supporting
1 Asistant Engineer 1 Coastal / Structure 1 MM 3.000.000 3.000.000
2 Asistant Engineer 2 Geotechnic 1 MM 3.000.000 3.000.000
2 CAD Operator 1 persons 1 MM 2.500.000 2.500.000
SUB TOTAL A 63.500.000
B. ANALYSIS STRUCTURE
1 Analysis of soil mechanics & Hydrodynamics wave, tide, setlement 1 LS 50.000.000
2 Analysis of structure stability 1 LS 80.000.000
SUB TOTAL B 130.000.000
C. SUPPORTING
1 Report 1 LS 5.000.000 5.000.000
2 Supplies: paper, Toner, Ink, Copy 1 LS 3.000.000 3.000.000
3 Comunication & Internet conection 1 LS 2.000.000 2.000.000
4 Meeting 2 times:
Transportation & Airport Tax 3 persons x 2 trips x 2 times meeting 12 MT 750.000 9.000.000
Taxi & Meal 2 LS 1.500.000 3.000.000
SUB TOTAL C 22.000.000
TOTAL A + B + C (before Tax) 215.500.000
PPN 10 % 21.550.000
T O T A L after TAX 237.050.000