You are on page 1of 928

DETAILED UNIT PRICE ANALYSIS

Item No./Description : 100(1) Clearing & Grubbing (with Stripping)


Unit of Measurement : ha
Output per hour : 0.05

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Dump Truck (12 cu. yd) 2


b. Payloader (1.50 cu.m.) 1
c. Bulldozer, D6H SERIES II PSDS/DD 1

(Hauling Distance - within three (3) km.)

Assumed 150mm cut

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.05 ha
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 100(3)a Individual Removal of Trees (small a, 150mm up to


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Dump Truck (12 cu. yd) 1
c. Chain Saw 1
Minor Tools (5% of Labor Cost)

* Boom Truck - if necessary for trimming in Urban Areas

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Rope, 1" dia. - 5 uses m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 100(3)b Individual Removal of Trees (small b, above 300mm


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Dump Truck (12 cu. yd) 1
c. Chain Saw 1
Minor Tools (5% of Labor Cost)

* Boom Truck - if necessary for trimming in Urban Areas

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Rope, 1" dia. - 5 uses m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 100(4)a Individual Removal of Trees (large a, above 500mm


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Dump Truck (12 cu. yd) 1
c. Chain Saw 1
Minor Tools (5% of Labor Cost)

* Boom Truck - if necessary for trimming in Urban Areas

Sub - Total for B


C. Total (A + B)
D. Output per hour = 01. ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Rope, 1" dia. - 5 uses m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 100(4)b Individual Removal of Trees (large b, above 750 up to


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Dump Truck (12 cu. yd) 1
c. Chain Saw 1
Minor Tools (5% of Labor Cost)

* Boom Truck - if necessary for trimming in Urban Areas

Sub - Total for B


C. Total (A + B)
D. Output per hour = 01. ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Rope, 1" dia. - 5 uses m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(1) Removal of Structures and Obstruction


Unit of Measurement : ls
Output per hour : 1.00

Designation No. of Person

A. Labor

See derivation for Item Nos. 101(1)a to 101(1)d

Sub - Total for A

Name and Capacity No of Units

B. Equipment

See derivation for Item Nos. 101(1)a to 101(1)d

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
See derivation for Item Nos. 101(1)a to 101(1)d

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(1)a Removal of Concrete Bridge Structures


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1


b. Jackhammer 2
c. Air Compressor (356 - 450 cfm) 1
d. Dump Truck (12 cu.yd.) 1
e. Payloader (1.50 cu.m.) 1
f. Truck Mounted Crane (31 - 35 mt) 1
g. Cutting Outfit 1

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Oxy/Acytelene set
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(1)b Removal of Steel Bridge Structures


Unit of Measurement : kg.
Output per hour : 1,000.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Truck Mounted Crane (31 - 35 mt) 1


b. Service Truck/Cargo Truck (2 - 5 mt) 1
c. Welding Machine (300A), Gas/Diesel Driven 1
d. Cutting Outfit 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1000.0000 kg
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Oxy/Acytelene set
b. Welding Rod kg.
c. Rope 1" dia. m.
* Include shoring materials if needed based on actual field
condition

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(1)c Removal of Stone Masonry Lined Drainage Structures


Unit of Measurement : cu.m.
Output per hour : 10.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1


b. Backhoe (0.80 cu.m.) - for loading 1
c. Dump Truck (12 cu. yd) 1

* Disposal area (within three (3) km.)


Sub - Total for B
C. Total (A + B)
D. Output per hour = 10.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(1)d Removal of Concrete Drainage Structures


Unit of Measurement : cu.m.
Output per hour : 2.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1


b. Backhoe (0.80 cu.m.) - for loading 1
c. Dump Truck (12 cu. yd) 1
d. Cutting Outfit 1

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Oxy/Acetylene set
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(2)a Removal of RCPC (24" dia.) - 610mm dia.


Unit of Measurement : ea
Output per hour : 6.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
Minor Tools (10 % of Labor Cost)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(2)b Removal of RCPC (30" dia.) - 760mm dia.


Unit of Measurement : ea
Output per hour : 5.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
Minor Tools (10 % of Labor Cost)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(2)c Removal of RCPC (36" dia.) - 910mm dia


Unit of Measurement : ea
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
Minor Tools (10 % of Labor Cost)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(2)d Removal of RCPC (42" dia.) - 1070mm dia.


Unit of Measurement : ea
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
Minor Tools (10 % of Labor Cost)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(2)e Removal of RCPC (48" dia.) - 1220mm dia


Unit of Measurement : ea
Output per hour : 3.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
Minor Tools (10 % of Labor Cost)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(2)f Removal of RCPC (60" dia.) - 1520mm dia.


Unit of Measurement : ea
Output per hour : 2.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
Minor Tools (10 % of Labor Cost)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/As
Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1


b. Cargo Truck (2 - 5 mt) 1
Minor Tools (10% of Labor Cost)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.)


Unit of Measurement : sq.m.
Output per hour : 40.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1


b. Payloader (1.50 cu.m.), LX80-2C 1
c. Dump Truck (12 cu. yd) 1
Minor Tools (10% of Labor Cost)

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 40.00 sq.m.
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(3)a.2 Removal of Existing PCC Pavement, 0.23m thk. (for R
Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1


b. Payloader (1.50 cu.m.), LX80-2C 1
c. Dump Truck (12 cu. yd) 1
d. Concrete Saw (7.5 Hp), 14" Blade 1
Minor Tools (10% of Labor Cost)

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 30.00000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Concrete Saw (diamond blade 14") pc.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(3)b Removal of Existing Asphalt Pavement (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 60.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1


b. Payloader (1.50 cu.m.), LX80-2C 1
c. Dump Truck (12 cu. yd) 1
Minor Tools (10% of Labor Cost)

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 60.00000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(3)c Removal of Sidewalk (100mm thk)


Unit of Measurement : sq.m.
Output per hour : 75.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1


b. Backhoe (0.80 cu.m.) 1
c. Dump Truck (12 cu. yd) 1

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 75.00000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(4)a Removal of Curb


Unit of Measurement : m.
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1


b. Backhoe (0.80 cu.m.) 1
c. Dump Truck (12 cu. yd) 1

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 101(4)b Removal of Curb & Gutter


Unit of Measurement : m
Output per hour : 30.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Pavement (0.80 cu.m.) 1


b. Backhoe (0.80 cu.m.) 1
c. Dump Truck (12 cu. yd) 1

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 30.00000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 102(1) Roadway Excavation (Unsuitable)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Dump Truck (12 cu. yd) 2


b. Backhoe (0.80 cu.m.) 1
c. Payloader (1.50 cu.m.) at disposal site 1
Minor Tools (10% of Labor Cost)

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 102(2)a Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 60.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1


b. Payloader (1.50 cu.m.) 1
c. Payloader (1.50 cu.m.) - at disposal area 1
d. Dump Truck (12 cu.yd.) 2

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 60.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,420.00 2,840.00


1.00 1,733.00 1,733.00
1.00 3,379.00 3,379.00

7,952.00
8,099.36

161,987.20

Quantity Unit Cost Amount


0.00
161,987.20
9% of G 14,578.85
8% of G 12,958.98
5% of (G + H + I) 9,476.25
(G + H + I + J) 199,001.28
ILED UNIT PRICE ANALYSIS (DUPA)

of Trees (small a, 150mm up to 300mm )

No. of Hours Hourly Rate Amount

0.33 69.42 22.91


0.33 50.18 16.56
0.33 38.97 25.72

65.19

No. of Hours Hourly Rate Amount

0.25 1,537.00 384.25


0.17 1,420.00 241.40
0.17 75.36 12.81
3.26

641.72
706.91

706.91

Quantity Unit Cost Amount

20.00 3.50 14.00


14.00
720.91
9% of G 64.88
8% of G 57.67
5% of (G + H + I) 42.17
(G + H + I + J) 885.64
ILED UNIT PRICE ANALYSIS (DUPA)

of Trees (small b, above 300mm up to 500mm )

No. of Hours Hourly Rate Amount

0.67 69.42 46.51


0.67 50.18 33.62
0.67 38.97 52.22

132.35

No. of Hours Hourly Rate Amount

0.50 1,537.00 768.50


0.33 1,420.00 468.60
0.33 75.36 24.87
6.62

1,268.59
1,400.94

1,400.94

Quantity Unit Cost Amount

20.00 3.50 14.00


14.00
1,414.94
9% of G 127.34
8% of G 113.20
5% of (G + H + I) 82.77
(G + H + I + J) 1,738.25
ILED UNIT PRICE ANALYSIS (DUPA)

of Trees (large a, above 500mm up to 750mm )

No. of Hours Hourly Rate Amount

3.33 69.42 231.17


3.33 50.18 167.10
3.33 38.97 259.54

657.81

No. of Hours Hourly Rate Amount

2.50 1,537.00 3,842.50


1.67 1,420.00 2,371.40
1.67 75.36 125.85
32.89

6,372.64
7,030.45

7,030.45

Quantity Unit Cost Amount

20.00 3.50 14.00


14.00
7,044.45
9% of G 634.00
8% of G 563.56
5% of (G + H + I) 412.10
(G + H + I + J) 8,654.11
ILED UNIT PRICE ANALYSIS (DUPA)

of Trees (large b, above 750 up to 900mm )

No. of Hours Hourly Rate Amount

6.67 69.42 463.03


6.67 50.18 334.70
6.67 38.97 519.86

1,317.59

No. of Hours Hourly Rate Amount

5.00 1,537.00 7,685.00


3.33 1,420.00 4,728.60
3.33 75.36 250.95
65.88

12,730.43
14,048.02

14,048.02

Quantity Unit Cost Amount

20.00 3.50 14.00


14.00
14,062.02
9% of G 1,265.58
8% of G 1,124.96
5% of (G + H + I) 822.63
(G + H + I + J) 17,275.19
ILED UNIT PRICE ANALYSIS (DUPA)

es and Obstruction

No. of Hours Hourly Rate Amount

0
0
0

0.00

No. of Hours Hourly Rate Amount

0.00
0.00
0.00

0.00
0.00

0.00

Quantity Unit Cost Amount


0.00
0.00
9% of G 0.00
8% of G 0.00
5% of (G + H + I) 0.00
(G + H + I + J) 0.00
ILED UNIT PRICE ANALYSIS (DUPA)

e Bridge Structures

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

0.50 1,998.10 999.05


1.00 150.00 300.00
1.00 965.00 965.00
0.125 1,420.00 177.50
0.125 1,733.00 216.63
0.25 1,861.00 465.25
1.00 45.45 45.45

3,168.88
3,494.54

3,494.54

Quantity Unit Cost Amount

0.10 2,500.00 250.00


250.00
3,744.54
9% of G 337.01
8% of G 299.56
5% of (G + H + I) 219.06
(G + H + I + J) 4,600.16
ILED UNIT PRICE ANALYSIS (DUPA)

dge Structures

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 1,861.00 1,861.00


1.00 783.00 783.00
1.00 371.00 371.00
1.00 45.45 45.45
32.57

3,093.02
3,418.68

3.42

Quantity Unit Cost Amount

0.00025 2,500.00 0.63


0.002 90.00 0.18
0.05 3.50 0.18
0.98
4.40
9% of G 0.40
8% of G 0.35
5% of (G + H + I) 0.26
(G + H + I + J) 5.40
ILED UNIT PRICE ANALYSIS (DUPA)

asonry Lined Drainage Structures

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

0.50 1,998.10 999.05


0.50 1,537.00 768.50
1.00 1,420.00 1,420.00
3,187.55
3,334.91

333.49

Quantity Unit Cost Amount

0.00
333.49
9% of G 30.01
8% of G 26.68
5% of (G + H + I) 19.51
(G + H + I + J) 409.69
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 50.18
1.00 38.97 77.94

197.54

No. of Hours Hourly Rate Amount

0.50 1,998.10 999.05


0.25 1,537.00 384.25
0.50 1,420.00 710.00
1.00 45.45 45.45

2,138.75
2,336.29

1,168.15

Quantity Unit Cost Amount

0.10 2,500.00 250.00


250.00
1,418.15
9% of G 127.63
8% of G 113.45
5% of (G + H + I) 82.96
(G + H + I + J) 1,742.19
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,537.00 1,537.00


0.50 1,017.90 508.95
14.74

2,060.69
2,208.05

368.01

Quantity Unit Cost Amount


0.00
368.01
9% of G 33.12
8% of G 29.44
5% of (G + H + I) 21.53
(G + H + I + J) 452.10
ILED UNIT PRICE ANALYSIS (DUPA)

30" dia.) - 760mm dia.

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1 1,537.00 1,537.00
0.50 1,017.90 508.95
14.74

2,060.69
2,208.05

441.61

Quantity Unit Cost Amount


0.00
441.61
9% of G 39.74
8% of G 35.33
5% of (G + H + I) 25.83
(G + H + I + J) 542.52
ILED UNIT PRICE ANALYSIS (DUPA)

36" dia.) - 910mm dia

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,537.00 1,537.00


0.50 1,017.90 508.95
14.74

2,060.69
2,208.05

552.01

Quantity Unit Cost Amount


0.00
552.01
9% of G 49.68
8% of G 44.16
5% of (G + H + I) 32.29
(G + H + I + J) 678.15
ILED UNIT PRICE ANALYSIS (DUPA)

42" dia.) - 1070mm dia.

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,537.00 1,537.00


0.50 1,017.90 508.95
14.74

2,060.69
2,208.05

552.01

Quantity Unit Cost Amount


0.00
552.01
9% of G 49.68
8% of G 44.16
5% of (G + H + I) 32.29
(G + H + I + J) 678.15
ILED UNIT PRICE ANALYSIS (DUPA)

48" dia.) - 1220mm dia

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,537.00 1,537.00


0.50 1,017.90 508.95
14.74

2,060.69
2,208.05

736.02

Quantity Unit Cost Amount


0.00
736.02
9% of G 66.24
8% of G 58.88
5% of (G + H + I) 43.06
(G + H + I + J) 904.19
ILED UNIT PRICE ANALYSIS (DUPA)

60" dia.) - 1520mm dia.

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,537.00 1,537.00


0.50 1,017.90 508.95
14.74

2,060.69
2,208.05

1,104.02

Quantity Unit Cost Amount


0.00
1,104.02
9% of G 99.36
8% of G 88.32
5% of (G + H + I) 64.59
(G + H + I + J) 1,356.29
ILED UNIT PRICE ANALYSIS (DUPA)

her than Pipe Culverts (PVC/GI/Asbestos, up to 200mm ), L=10 ft.

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 922.00 922.00


0.50 783.00 391.50
14.74

1,328.24
1,475.60

737.80

Quantity Unit Cost Amount


0.00
737.80
9% of G 66.40
8% of G 59.02
5% of (G + H + I) 43.16
(G + H + I + J) 906.38
ILED UNIT PRICE ANALYSIS (DUPA)

Concrete Pavement (0.23m thk.)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,998.10 1,998.10


1.00 1,733.00 1,733.00
0.50 1,420.00 710.00
14.74

4,455.84
4,603.20

115.08

Quantity Unit Cost Amount


0.00
115.08
9% of G 10.36
8% of G 9.21
5% of (G + H + I) 6.73
(G + H + I + J) 141.38
ILED UNIT PRICE ANALYSIS (DUPA)

PCC Pavement, 0.23m thk. (for Reblocking at intermittent section)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,998.10 1,998.10


1.00 1,733.00 1,733.00
0.50 1,420.00 710.00
0.50 32.63 16.32
14.74

4,472.15
4,619.51

153.98

Quantity Unit Cost Amount

0.00015 8,000.00 1.20


1.20
155.18
9% of G 13.97
8% of G 12.41
5% of (G + H + I) 9.08
(G + H + I + J) 190.64
ILED UNIT PRICE ANALYSIS (DUPA)

Asphalt Pavement (100mm thk.)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,733.00 1,733.00
0.50 1,420.00 710.00
14.74

4,630.74
4,778.10

79.63

Quantity Unit Cost Amount


0.00
79.63
9% of G 7.17
8% of G 6.37
5% of (G + H + I) 4.66
(G + H + I + J) 97.83
ILED UNIT PRICE ANALYSIS (DUPA)

k (100mm thk)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 1,998.10 1,998.10


1.00 1,537.00 1,537.00
0.50 1,420.00 710.00

4,245.10
4,392.46

58.57

Quantity Unit Cost Amount


0.00
58.57
9% of G 5.27
8% of G 4.69
5% of (G + H + I) 3.43
(G + H + I + J) 71.95
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

0.50 1,998.10 999.05


0.50 1,537.00 768.50
0.50 1,420.00 710.00

2,477.55
2,624.91

52.50

Quantity Unit Cost Amount


0.00
52.50
9% of G 4.72
8% of G 4.20
5% of (G + H + I) 3.07
(G + H + I + J) 64.49
ILED UNIT PRICE ANALYSIS (DUPA)

Gutter

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

0.50 1,998.10 999.05


0.50 1,537.00 768.50
0.50 1,420.00 710.00

2,477.55
2,624.91

87.50

Quantity Unit Cost Amount


0.00
87.50
9% of G 7.87
8% of G 7.00
5% of (G + H + I) 5.12
(G + H + I + J) 107.49
ILED UNIT PRICE ANALYSIS (DUPA)

n (Unsuitable)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 116.91

186.33

No. of Hours Hourly Rate Amount

1.00 1,420.00 2,840.00


1.00 1,537.00 1,537.00
0.10 1,733.00 173.30
18.63

4,568.93
4,755.26

237.76

Quantity Unit Cost Amount


0.00
237.76
9% of G 21.40
8% of G 19.02
5% of (G + H + I) 13.91
(G + H + I + J) 292.09
ILED UNIT PRICE ANALYSIS (DUPA)

n (Surplus Common)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 3,379.00 3,379.00


1.00 1,733.00 1,733.00
0.25 1,733.00 433.25
1.00 1,420.00 2,840.00

8,385.25
8,532.61

142.21

Quantity Unit Cost Amount


0.00
142.21
9% of G 12.80
8% of G 11.38
5% of (G + H + I) 8.32
(G + H + I + J) 174.71
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 102(2)b Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 80.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1


b. Payloader (1.50 cu.m.) 1
c. Payloader (1.50 cu.m.) - at disposal area 1
d. Dump Truck (12 cu.yd.) 3
e. Backhoe (0.80 cu.m.) 1

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 80.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (D

Item No./Description : 102(3)a Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 56.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Bulldozer w/ Ripper, D6H SERIES II PSDS/DD 1


b. Payloader (1.50 cu.m.) 1
c. Payloader (1.50 cu.m.) - at disposal area 1
d. Dump Truck (12 cu.yd.) 2
e. Backhoe (0.80 cu.m.) w/ attachment 1

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 56.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 102(3)b Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 42.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Bulldozer w/ Ripper, D6H SERIES II PSDS/DD 1


b. Payloader (1.50 cu.m.) 1
c. Payloader (1.50 cu.m.) - at disposal area 1
d. Dump Truck (12 cu.yd.) 2

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 42.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting


Unit of Measurement : cu.m.
Output per hour : 4.20

Designation No. of Person

A. Labor
a. Construction Foreman (Drilling) 1
b. Skilled Labor 2
c. Unskilled Labor 4
a. Construction Foreman (Blasting) 1
b. Skilled Labor 1
c. Unskilled Labor 2
a. Construction Foreman (Disposal) 1
b Unskilled Labor 2
Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Payloader (1.50 cu.m.) 1
c. Payloader (1.50 cu.m.) - at disposal area 1
d. Dump Truck (12 cu.yd.) 1
e. Pneumatic Drilling Machine 2
f. Air Compressor (161 - 185 cfm) 1
(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.2000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Dynamite kg.
b. Detonation Cord m.
c. Detonator pc.
d. Ammonium Sulfate kg.
e. Blasting Cap pc.
f. Safety Fuse m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (T


Unit of Measurement : cu.m.
Output per hour : 1.65

Designation No. of Person

A. Labor
a. Construction Foreman (Drilling) 1
b. Skilled Labor 2
c. Unskilled Labor 4
a. Construction Foreman (Blasting) 1
b. Skilled Labor 1
c. Unskilled Labor 2
a. Construction Foreman (Disposal) 1
b Unskilled Labor 2
Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Backhoe w/ Chipping Hammer (0.80 cu.m.) 1
c. Dump Truck (12 cu. yd) 1
d. Pneumatic Drilling Machine 2
e. Air Compressor (161 - 185 cfm) 1
f. Payloader (1.50 cu.m.) 1
g. Payloader (1.50 cu.m.) - at disposal area 1
h. Water Truck/Pump (16000L) 1

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.65 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Dynamite kg.
b. Detonation Cord m.
c. Detonator pc.
d. Ammonium Sulfate kg.
e. Blasting Cap pc.
f. Safety Fuse m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 102(4) Roadway Excavation (Surplus Unclassified)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1


b. Payloader (1.50 cu.m.) 1
c. Payloader (1.50 cu.m.) - at disposal area 1
d. Dump Truck (12 cu. yd) 2

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(1)a Structure Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Dump Truck (12 cu. yd) 2


b. Backhoe (0.80 cu.m.) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(1)b Structure Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Dump Truck (12 cu. yd) 2


b. Backhoe (0.80 cu.m.) 1
c. Backhoe w/ Breaker (0.80 cu.m.) 1
Minor Tools (10% of Labor Cost )

Sub - Total for B


C. Total (A + B)
D. Output per hour = 14.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(1)c Structure Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Dump Truck (12 cu. yd) 1


b. Backhoe (0.80 cu.m.) 1
c. Backhoe w/ Breaker (0.80 cu.m.) 1
Minor Tools (10% of Labor Cost)
Sub - Total for B
C. Total (A + B)
D. Output per hour = 4.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(2)a Bridge Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

b. Backhoe (0.80 cu.m.) 1


b. Dump Truck (12 cu. yd) 2
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(2)b Bridge Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Backhoe w/ Breaker (0.80 cu.m.) 1
c. Dump Truck (12 cu.yd.) 2
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 14.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(2)c Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Backhoe w/ Breaker (0.80 cu.m.) 1
c. Dump Truck (12 cu. yd) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(2)d Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 1.50

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Jack Hammer 2
b. Air Compressor (356 - 450 cfm) 1
c. Backhoe (0.80 cu.m.) 1
d. Dump Truck (12 cu. yd) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.500 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(3) Foundation Fill


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Plate Compactor (5 Hp) 1


b. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Filling Materials cu.m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(4) Excavation ordered below Plan Elevation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Dump Truck (12 cu. yd) 2


b. Backhoe (0.80 cu.m.) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20. cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(5)a Shoring


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person

A. Labor

Note:
*) The component quantity of items of work involved such as item 404/405/509 shall be based
actual design of the shoring.
**) Costing of this item shall be based on the standard Detailed Unit Price Analysis (DUPA) of ite
as processed component pay item.

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.0000 l.s
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials/Processed Component Pay Item

a. 404 - Reinforcing Steel Bar kg.


b. 405 - Structural Concrete cu.m.
c. 509 - Steel Sheet Pile l.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(5)b Cribbing/Cofferdamming


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Crawler Crane (36 - 40 mt) 1


b. Vibro Hammer (Hydraulic Operated) 1
c. Welding Machine (300 A, Gas/Diesel Driven 1
d. Cutting Outfit 1
e. Water Pump, 100mm suction diameter 1

Sub - Total for B


C. Total (A + B)
D. Output = 1.0000 l.s
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Steel Sheet Pile kg.


b. Walling, Bracing, Diagonal, etc. kg.
Miscellaneous (1% of Materials Cost)
Note:
a.) The assume dimesion of area to be provided with cofferdam is 12m x 12m square with
Steel Sheet Piles depth of 9m at 48 kg./m.
b.) The quantity of component materials requirement may vary depending on the actual
design of Cribbing/Cofferdamming.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 103(6) Pipe Culvert and Drain Excavation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Dump Truck (12 cu. yd) 2


b. Backhoe (0.80 cu.m.) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 104(1)a Embankment (from Borrow)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Common Borrow (w/ 25% Shrinkage Factor) cu.m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 104(1)b Embankment from Roadway Excavation


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person

A. Labor
For Excavation Work:
a. Construction Foreman 1
b. Unskilled Labor 2

Spreading and Compaction:


a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment
For Excavation Work:
a. Bulldozer, D6H SERIES II PSDS/DD 1
b. Payloader (1.50 cu.m.) 1
c. Dump Truck (12 cu.yd.) 2

Spreading and Compaction:


a. Motorized Road Grader (140 hp), G710A 1
b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 104(2) Selected Borrow for topping , case 1


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 104(3) Selected Borrow for topping , case 2


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 104(4) Earth Berm


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Plate Compactor (5 Hp) 1


b.Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Filling Materials cu.m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 105(1) Subgrade Preparation (Common Material)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 300.00000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 105(2) Subgrade Preparation (Existing Pavement)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 300.00000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 105(3) Subgrade Preparation (Unsuitable Material)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1
Sub - Total for B
C. Total (A + B)
D. Output per hour = 300.00000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)

n (Surplus Common)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 3,379.00 3,379.00


1.00 1,733.00 1,733.00
0.30 1,733.00 519.90
1.00 1,420.00 4,260.00
1.00 1,537.00 1,537.00

11,428.90
11,576.26

144.70

Quantity Unit Cost Amount


0.00
144.70
9% of G 13.02
8% of G 11.58
5% of (G + H + I) 8.47
(G + H + I + J) 177.77
AILED UNIT PRICE ANALYSIS (DUPA)

n (Surplus Soft Rock)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 3,885.85 3,885.85


1.00 1,733.00 1,733.00
0.25 1,733.00 433.25
1.00 1,420.00 2,840.00
1.00 1,537.00 1,537.00

10,429.10
10,576.46

188.87

Quantity Unit Cost Amount


0.00
188.87
9% of G 17.00
8% of G 15.11
5% of (G + H + I) 11.05
(G + H + I + J) 232.02
ILED UNIT PRICE ANALYSIS (DUPA)

n (Surplus Soft Rock)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 3,885.85 3,885.85


1.00 1,733.00 1,733.00
0.20 1,733.00 346.60
1.00 1,420.00 2,840.00

8,805.45
8,952.81

213.16

Quantity Unit Cost Amount


0.00
213.16
9% of G 19.18
8% of G 17.05
5% of (G + H + I) 12.47
(G + H + I + J) 261.87
ILED UNIT PRICE ANALYSIS (DUPA)

n (Surplus Hard Rock) - Blasting

No. of Hours Hourly Rate Amount

0.40 69.42 27.768


0.40 50.18 40.144
0.40 38.97 62.352
0.20 69.42 13.884
0.20 50.18 10.036
0.20 38.97 15.588
0.40 69.42 27.768
0.40 38.97 31.176
228.72

No. of Hours Hourly Rate Amount

0.20 1,537.00 307.40


0.15 1,733.00 259.95
0.05 1,733.00 86.65
0.40 1,420.00 568.00
0.40 170.00 136.00
0.40 502.00 200.80

1,558.80
1,787.52

425.60

Quantity Unit Cost Amount

0.40 280.00 112.00


2.00 80.00 160.00
0.15 260.00 39.00
0.20 75.00 15.00
0.40 45.00 18.00
0.10 40.00 4.00

348.00
773.60
9% of G 69.62
8% of G 61.89
5% of (G + H + I) 45.26
(G + H + I + J) 950.37
ILED UNIT PRICE ANALYSIS (DUPA)

n (Surplus Hard Rock) - Blasting (Tunnel Excavation)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88
1.00 69.42 69.42
1.00 50.18 50.18
1.00 38.97 77.94
0.50 69.42 34.71
0.50 38.97 38.97
596.88

No. of Hours Hourly Rate Amount

0.50 1,537.00 768.50


0.10 1,998.10 199.81
0.50 1,420.00 710.00
1.00 170.00 340.00
1.00 502.00 502.00
0.20 1,733.00 346.60
0.03 1,733.00 51.99
0.05 2,450.00 122.50

3,041.40
3,638.28

2,205.02

Quantity Unit Cost Amount

2.00 280.00 560.00


1.40 80.00 112.00
2.00 260.00 520.00
1.00 75.00 75.00
0.45 45.00 20.25
0.10 40.00 4.00

1,291.25
3,496.27
9% of G 314.66
8% of G 279.70
5% of (G + H + I) 204.53
(G + H + I + J) 4,295.17
ILED UNIT PRICE ANALYSIS (DUPA)

n (Surplus Unclassified)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 3,379.00 3,379.00


1.00 1,733.00 1,733.00
0.20 1,733.00 346.60
1.00 1,420.00 2,840.00

8,298.60
8,445.96

168.92

Quantity Unit Cost Amount


0.00
168.92
9% of G 15.20
8% of G 13.51
5% of (G + H + I) 9.88
(G + H + I + J) 207.52
ILED UNIT PRICE ANALYSIS (DUPA)

(Common Soil)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 116.91

186.33

No. of Hours Hourly Rate Amount

1.00 1,420.00 2,840.00


1.00 1,537.00 1,537.00
18.63

4,395.63
4,581.96

229.10

Quantity Unit Cost Amount


0.00
229.10
9% of G 20.62
8% of G 18.33
5% of (G + H + I) 13.40
(G + H + I + J) 281.45
ILED UNIT PRICE ANALYSIS (DUPA)

(Soft Rock)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 116.91

186.33

No. of Hours Hourly Rate Amount

1.00 1,420.00 2,840.00


0.50 1,537.00 768.50
0.50 1,998.10 999.05
18.63

4,626.18
4,812.51

343.75

Quantity Unit Cost Amount


0.00
343.75
9% of G 30.94
8% of G 27.50
5% of (G + H + I) 20.11
(G + H + I + J) 422.30
ILED UNIT PRICE ANALYSIS (DUPA)

(Solid Rock)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 116.91

186.33

No. of Hours Hourly Rate Amount

1.00 1,420.00 1,420.00


0.25 1,537.00 384.25
0.75 1,998.10 1,498.58
18.63
3,321.46
3,507.79

876.95

Quantity Unit Cost Amount

0.00
876.95
9% of G 78.93
8% of G 70.16
5% of (G + H + I) 51.30
(G + H + I + J) 1,077.33
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 50.18
1.00 38.97 77.94

197.54

No. of Hours Hourly Rate Amount

1.00 1,537.00 1,537.00


1.00 1,420.00 2,840.00
19.75

4,396.75
4,594.29

229.71

Quantity Unit Cost Amount


0.00
229.71
9% of G 20.67
8% of G 18.38
5% of (G + H + I) 13.44
(G + H + I + J) 282.20
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 50.18
1.00 38.97 77.94

197.54

No. of Hours Hourly Rate Amount

0.50 1,537.00 768.50


0.50 1,998.10 999.05
1.00 1,420.00 2,840.00
19.75

4,627.30
4,824.84

344.63

Quantity Unit Cost Amount


0.00
344.63
9% of G 31.02
8% of G 27.57
5% of (G + H + I) 20.16
(G + H + I + J) 423.38
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 50.18
1.00 38.97 77.94

197.54

No. of Hours Hourly Rate Amount

0.50 1,537.00 768.50


1.00 1,998.10 1,998.10
0.50 1,420.00 710.00
19.75

3,496.35
3,693.89

923.47

Quantity Unit Cost Amount


0.00
923.47
9% of G 83.11
8% of G 73.88
5% of (G + H + I) 54.02
(G + H + I + J) 1,134.49
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 50.18
1.00 38.97 77.94

197.54

No. of Hours Hourly Rate Amount

1.00 150.00 300.00


1.00 965.00 965.00
0.15 1,537.00 230.55
0.15 1,420.00 213.00
19.75

1,728.30
1,925.84

1,283.90

Quantity Unit Cost Amount


0.00
1,283.90
9% of G 115.55
8% of G 102.71
5% of (G + H + I) 75.11
(G + H + I + J) 1,577.27
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 155.88

225.30

No. of Hours Hourly Rate Amount

1.00 123.00 123.00


0.01 2,450.00 24.50
22.53

170.03
395.33

316.26

Quantity Unit Cost Amount

1.15 465.00 534.75


534.75
851.01
9% of G 76.59
8% of G 68.08
5% of (G + H + I) 49.78
(G + H + I + J) 1,045.47
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 116.91

186.33

No. of Hours Hourly Rate Amount

1.00 1,420.00 2,840.00


1.00 1,537.00 1,537.00
18.63

4,395.63
4,581.96

229.10

Quantity Unit Cost Amount


0.00
229.10
9% of G 20.62
8% of G 18.33
5% of (G + H + I) 13.40
(G + H + I + J) 281.45
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

item 404/405/509 shall be based on the

d Unit Price Analysis (DUPA) of item 404/405/509

No. of Hours Hourly Rate Amount

Quantity Unit Cost Amount

*
*
*
9% of G
8% of G
5% of (G + H + I)
(G + H + I + J)
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

160 69.42 11,107.20


160 50.18 16,057.60
160 38.97 24,940.80

52,105.60

No. of Hours Hourly Rate Amount

160.00 1,902.00 304,320.00


160.00 2,123.00 339,680.00
40.00 371.00 14,840.00
40.00 45.45 1,818.00
160.00 266.25 42,600.00

703,258.00
755,363.60

755,363.60

Quantity Unit Cost Amount

69,120.00 48.00 3,317,760.00


7,323.77 48.00 351,540.96
36,693.01
dam is 12m x 12m square with

ary depending on the actual

3,705,993.97
4,461,357.57
9% of G 401,522.18
8% of G 356,908.61
5% of (G + H + I) 260,989.42
(G + H + I + J) 5,480,777.77
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 116.91

186.33

No. of Hours Hourly Rate Amount

1.00 1,420.00 2,840.00


1.00 1,537.00 1,537.00
18.63

4,395.63
4,581.96

229.10

Quantity Unit Cost Amount


0.00
229.10
9% of G 20.62
8% of G 18.33
5% of (G + H + I) 13.40
(G + H + I + J) 281.45
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
4,778.86

95.58

Quantity Unit Cost Amount

1.25 160.00 200.00


200.00
295.58
9% of G 26.60
8% of G 23.65
5% of (G + H + I) 17.29
(G + H + I + J) 363.12
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

0.83 69.42 57.62


0.83 38.97 64.69

1.00 69.42 69.42


1.00 38.97 77.94

269.67

No. of Hours Hourly Rate Amount

0.83 3,379.00 2,804.57


0.83 1,733.00 1,438.39
0.83 1,420.00 2,357.20

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

11,231.66
11,501.33

230.03

Quantity Unit Cost Amount


0.00
230.03
9% of G 20.70
8% of G 18.40
5% of (G + H + I) 13.46
(G + H + I + J) 282.59
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
4,778.86

95.58

Quantity Unit Cost Amount

1.25 420.00 525.00


525.00
620.58
9% of G 55.85
8% of G 49.65
5% of (G + H + I) 36.30
(G + H + I + J) 762.38
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
4,778.86

95.58

Quantity Unit Cost Amount

1.25 420.00 525.00


525.00
620.58
9% of G 55.85
8% of G 49.65
5% of (G + H + I) 36.30
(G + H + I + J) 762.38
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 155.88

225.30

No. of Hours Hourly Rate Amount

1.00 123.00 123.00


0.01 2,450.00 24.50
22.53

170.03
395.33

316.26

Quantity Unit Cost Amount

1.25 420.00 525.00


525.00
841.26
9% of G 75.71
8% of G 67.30
5% of (G + H + I) 49.21
(G + H + I + J) 1,033.49
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
4,778.86

15.93

Quantity Unit Cost Amount


0.00
15.93
9% of G 1.43
8% of G 1.27
5% of (G + H + I) 0.93
(G + H + I + J) 19.57
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
4,778.86

15.93

Quantity Unit Cost Amount


0.00
15.93
9% of G 1.43
8% of G 1.27
5% of (G + H + I) 0.93
(G + H + I + J) 19.57
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50
4,631.50
4,778.86

15.93

Quantity Unit Cost Amount

0.00
15.93
9% of G 1.43
8% of G 1.27
5% of (G + H + I) 0.93
(G + H + I + J) 19.57
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 200 Aggregate Subbase Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Aggregate Subbase Course cu.m.


(w/ 15% Shrinkage Factor)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 200(1) Aggregate Subbase Course (for Intermittent Reblockin


Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Plate Compactor (5 Hp) 1
d. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 40.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Aggregate Subbase Course cu.m.


(w/ 15% Shrinkage Factor)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 201 Aggregate Base Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Aggregate Base Course cu.m.


(w/ 15% Shrinkage Factor)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 201(1) Aggregate Base Course (for Reblocking)


Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
a. Plate Compactor (5 Hp) 1
d. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 40.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Aggregate Base Course cu.m.


(w/ 15% Shrinkage Factor)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 202 Crushed Aggregate Base Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Crushed Aggregate Base Course cu.m.


(w/ 15% Shrinkage Factor)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)

Course

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
4,778.86

95.58

Quantity Unit Cost Amount

1.15 350.00 402.50


402.50
498.08
9% of G 44.83
8% of G 39.85
5% of (G + H + I) 29.14
(G + H + I + J) 611.89
ILED UNIT PRICE ANALYSIS (DUPA)

Course (for Intermittent Reblocking)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 123.00 30.75
0.25 2,450.00 612.50

4,662.25
4,809.61

120.24

Quantity Unit Cost Amount

1.15 580.00 667.00


667.00
787.24
9% of G 70.85
8% of G 62.98
5% of (G + H + I) 46.05
(G + H + I + J) 967.12
ILED UNIT PRICE ANALYSIS (DUPA)

urse

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
4,778.86

95.58

Quantity Unit Cost Amount

1.15 650.00 747.50


747.50
843.08
9% of G 75.88
8% of G 67.45
5% of (G + H + I) 49.32
(G + H + I + J) 1,035.72
ILED UNIT PRICE ANALYSIS (DUPA)

urse (for Reblocking)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 123.00 30.75
0.25 2,450.00 612.50

4,662.25
4,809.61

120.24

Quantity Unit Cost Amount

1.15 650.00 747.50


747.50
867.74
9% of G 78.10
8% of G 69.42
5% of (G + H + I) 50.76
(G + H + I + J) 1,066.02
ILED UNIT PRICE ANALYSIS (DUPA)

Base Course

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 77.94

147.36

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
4,778.86

95.58

Quantity Unit Cost Amount

1.15 700.00 805.00


805.00
900.58
9% of G 81.05
8% of G 72.05
5% of (G + H + I) 52.68
(G + H + I + J) 1,106.36
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 203 Lime Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 10

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Hydrated Lime, Type N (Normal) bag


b. Aggregate Base Course cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 204 Portland Cement Stabilized Road Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 10

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Aggregate Base Course cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 205 Asphalt Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 10

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1
d. Asphalt Distributor, 10 ft. wide (5 ton) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Emulsified Asphalt SS-1 m.t.


b. Aggregate Base Course cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 206 Portland Cement Treated Plant Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Concrete Batching Plant (30 cu.m.) 1


b. Dump Truck (12 cu.yd.) 3
c. Motorized Road Grader (140 hp), G710A 1
d. Vibratory Roller (10 m.t.), SD100DC 1
e. Payloader (1.50 cu.m.), LX80-2C 1
f. Water Truck/Pump (16000L) 1
g. Asphalt Distributor, 10 ft. wide (5 ton) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Aggregate Base Course cu.m.
c. MC 70 Cut-back Asphalt m.t.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)

d Mix Base Course

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 389.70

459.12

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
5,090.62

339.37

Quantity Unit Cost Amount

2.80 180.00 504.00


1.15 650.00 747.50
1,251.50
1,590.87
9% of G 143.18
8% of G 127.27
5% of (G + H + I) 93.07
(G + H + I + J) 1,954.39
ILED UNIT PRICE ANALYSIS (DUPA)

abilized Road Mix Base Course

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 389.70

459.12

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50
5,090.62

339.37

Quantity Unit Cost Amount

3.00 220.00 660.00


1.15 650.00 747.50
1,407.50
1,746.87
9% of G 157.22
8% of G 139.75
5% of (G + H + I) 102.19
(G + H + I + J) 2,146.04
ILED UNIT PRICE ANALYSIS (DUPA)

oad Mix Base Course

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 389.70

459.12

No. of Hours Hourly Rate Amount

1.00 2,173.00 2,173.00


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50
1.00 936.00 936.00

5,567.50
6,026.62

401.77

Quantity Unit Cost Amount

0.07 44,000.00 3,080.00


1.15 650.00 747.50
3,827.50
4,229.27
9% of G 380.63
8% of G 338.34
5% of (G + H + I) 247.41
(G + H + I + J) 5,195.66
ILED UNIT PRICE ANALYSIS (DUPA)

eated Plant Mix Base Course

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

0.50 1,759.50 879.75


0.50 1,352.00 2,028.00
0.50 2,173.00 1,086.50
0.50 1,846.00 923.00
0.50 1,733.00 866.50
0.25 2,450.00 612.50
0.10 936.00 93.60

6,489.85
6,815.51

454.37

Quantity Unit Cost Amount

3.00 220.00 660.00


1.15 650.00 747.50
0.0075 40,300.00 302.25
1,709.75
2,164.12
9% of G 194.77
8% of G 173.13
5% of (G + H + I) 126.60
(G + H + I + J) 2,658.62
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 300(1) Gravel Surface Course (Uncrushed)


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Uncrushed Aggregate Surface Course cu.m.


(w/ 15% Shrinkage Factor)

241+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 300(2) Crushed Aggregate Surface Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1


b. Vibratory Roller (10 m.t.), SD100DC 1
c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Crushed Aggregate Surface Course cu.m.


(w/ 15% Shrinkage Factor)

243+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 301(1) Bituminous Prime Coat (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. MC 70 Cut-back Asphalt m.t.


(w/ 5% wastage)

245+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 301(2) Bituminous Prime Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. RC 70 Cut-back Asphalt m.t.


(w/ 5% wastage)

247+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 302(1) Bituminous Tack Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. RC 70 Cut-back Asphalt m.t.


(w/ 5% wastage)

249+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 302(2) Bituminous Tack Coat (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Emulsified Asphalt SS-1 m.t.


(w/ 5% wastage)

251+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 303(1) Bituminous Seal Coat (Cover Aggregate)


Unit of Measurement : m.t.
Output per hour : 16.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 20

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Tandem Steel Roller (10.1 m.t.), CC421 1


b. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.0000 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cover Aggregate m.t.


(w/ 15% Shrinkage Factor)

Note: 1.60 m.t./cu.m.

253+32
using unit wt. of 1,600 kg./m

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 303(2) Bituminous Seal Coat (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. MC Cut-back Asphalt m.t.


(w/ 5% Wastage)

255+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 303(3) Bituminous Seal Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. RC 70 Cut-back Asphalt m.t.


(w/ 5% Wastage)

257+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Gr


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t.


(w/ 5% Wastage)

259+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 304(1) Bituminous Surface Treatment (Aggregate Grading)


Unit of Measurement : m.t.
Output per hour : 16.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 20

Sub - Total for A

Name and Capacity No of Units

B. Equipment

b. Vibratory Roller (10 m.t.), SD100DC 1


c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.0000 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Aggregates m.t.
(w/ 15% Shrinkage Factor)

261+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penet


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t.


(w/ 5% Wastage)

263+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 304(3) Bituminous Surface Treatment (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. MC Cut-back Asphalt m.t.


(w/ 5% Wastage)

265+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 304(4) Bituminous Surface Treatment (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. RC 70 Cut-back Asphalt m.t.


(w/ 5% Wastage)

267+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 304(5) Bituminous Surface Treatment (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Emulsified Asphalt SS-1 m.t.


(w/ 5% wastage)

269+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 305(1) Bituminous Penetration Macadam Pavement (Aggrega


Unit of Measurement : m.t.
Output per hour : 16.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 20

Sub - Total for A

Name and Capacity No of Units

B. Equipment

b. Vibratory Roller (10 m.t.), SD100DC 1


c. Water Truck/Pump (16000L) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.0000 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Aggregates m.t.
(w/ 15% Shrinkage Factor)

271+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 305(2) Bituminous Penetration Macadam Pavement (Asphalt


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Asphalt Cement (w/ 5% Wastage) m.t.

273+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 305(3) Bituminous Penetration Macadam Pavement (RC Cut-


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. RC 70 Cut-back Asphalt m.t.


(w/ 5% Wastage)

275+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 305(4) Bituminous Penetration Macadam Pavement (Emulsifi


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1


b. Power Broom (20 m. wide) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.300 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Emulsified Asphalt SS-1 m.t.


(w/ 5% wastage)

277+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 306(a) Bituminous Road Mix Surface Course


Unit of Measurement : m.t.
Output per hour : 12.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader w/ Scarifier (140 hp), G710A 1


b. Tandem Steel Roller (10.1 m.t.), CC421 1
c. Pneumatic Tire Roller (10 m.t.) 1
d. Asphalt Distributor, 10 ft. wide (5 ton) 1
e. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.0000 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Crushed Gravel m.t.


b. MC Cut-back Asphalt (7%) m.t.
c. Hydrated Lime (0.75%) bag

279+32
0.0575(2.335)(1.05) = 0.141
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 306(b) Bituminous Road Mix Surface Course


Unit of Measurement : m.t.
Output per hour : 12.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader w/ Scarifier (140 hp), G710A 1


b. Tandem Steel Roller (10.1 m.t.), CC421 1
c. Pneumatic Tire Roller (10 m.t.) 1
d. Asphalt Distributor, 10 ft. wide (5 ton) 1
e. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.0000 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Crushed Gravel m.t.


b. Emulsified Asphalt (10%) m.t.
c. Hydrated Lime (0.75%) bag

281+32
0.08(2.335)(1.05) = 0.196
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 306(1) Aggregates for Bituminous Road Mix Surface Course
Unit of Measurement : m.t.
Output per hour : 12.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 3

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Motorized Road Grader w/ Scarifier (140 hp), G710A 1


b. Tandem Steel Roller (10.1 m.t.), CC421 1
c. Pneumatic Tire Roller (10 m.t.) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.0000 m.t
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Crushed Gravel m.t.

283+32
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

) Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 77.94 b. Skilled Labor
c. Unskilled Labor

147.36 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 2,173.00 2,173.00 a. Asphalt Distributor, 10 f


1.00 1,846.00 1,846.00
0.25 2,450.00 612.50

4,631.50 S
4,778.86 C.
D. Output per hour = 1.0000
95.58 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.15 700.00 805.00 a. MC Cut-back Asphalt

285+32
805.00 S
900.58 G. Direct Unit Cost (E + F)
9% of G 81.05 H. Overhead, Contingencies
8% of G 72.05 I. Contractor's Profit (CP)
5% of (G + H + I) 52.68 J. Value Added Tax (VAT)
(G + H + I + J) 1,106.36 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman
1.00 69.42 69.42 b. Skilled Labor
1.00 38.97 77.94 c. Unskilled Labor
a. Batching Plant Enginee
b. Mechanical Engineer
c. Electrical Engineer
d. Unskilled Laboratory Te
e. Unskilled Labor
147.36 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 2,173.00 2,173.00 a. Asphalt Paver (80 Hp),


1.00 1,846.00 1,846.00 b. Pneumatic Tire Roller (1
0.25 2,450.00 612.50 c. Tandem Steel Roller (10
d. Dump Truck (12 cu.yd.)
e. Asphalt Batch Plant ( 60
f. Water Truck/Pump (160
g. Payloader (1.50 cu.m.),
Minor Tools (10% of Labor

4,631.50 S
4,778.86 C.
D. Output per hour = 171.300
95.58 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.15 750.00 862.50 a. Bituminous Material (8%


b. Aggregates, Sand (79%
c. Aggregates, 3/8 (19%)
d. Mineral Filler (7%)

287+32
e. Diesel

862.50 S
958.08 G. Direct Unit Cost (E + F)
9% of G 86.23 H. Overhead, Contingencies
8% of G 76.65 I. Contractor's Profit (CP)
5% of (G + H + I) 56.05 J. Value Added Tax (VAT)
(G + H + I + J) 1,177.00 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

ck Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman
1.00 69.42 69.42 b. Skilled Labor
1.00 38.97 116.91 c. Unskilled Labor
a. Batching Plant Enginee
b. Mechanical Engineer
c. Electrical Engineer
d. Unskilled Laboratory Te
e. Unskilled Labor
186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Asphalt Paver (80 Hp),


1.00 130.54 130.54 b. Pneumatic Tire Roller (1
c. Tandem Steel Roller (10
d. Dump Truck (12 cu.yd.)
e. Asphalt Batch Plant ( 60
f. Water Truck/Pump (160
g. Payloader (1.50 cu.m.),
Minor Tools (10% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 171.300
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 40,300.00 42,315.00 a. Emulsified Asphalt (10%


b. Aggregates, Sand (79%
c. Aggregates, 3/8 (19%)
d. Mineral Filler (7%)

289+32
e. Diesel

42,315.00 S
46,491.23 G. Direct Unit Cost (E + F)
9% of G 4,184.21 H. Overhead, Contingencies
8% of G 3,719.30 I. Contractor's Profit (CP)
5% of (G + H + I) 2,719.74 J. Value Added Tax (VAT)
(G + H + I + J) 57,114.48 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

ck Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman
1.00 69.42 69.42 b. Skilled Labor
1.00 38.97 116.91 c. Unskilled Labor
a. Batching Plant Enginee
b. Mechanical Engineer
c. Electrical Engineer
d. Unskilled Laboratory Te
e. Unskilled Labor
186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Asphalt Paver (80 Hp),


1.00 130.54 130.54 b. Pneumatic Tire Roller (1
c. Tandem Steel Roller (10
d. Dump Truck (12 cu.yd.)
e. Asphalt Batch Plant ( 60
f. Water Truck/Pump (160
g. Payloader (1.50 cu.m.),
Minor Tools (10% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 171.300
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 41,575.00 43,653.75 a. MC - 70 Cut-back Asph


b. Aggregates, Sand (79%
c. Aggregates, 3/8 (19%)
d. Mineral Filler (7%)

291+32
e. Diesel

43,653.75 S
47,829.98 G. Direct Unit Cost (E + F)
9% of G 4,304.70 H. Overhead, Contingencies
8% of G 3,826.40 I. Contractor's Profit (CP)
5% of (G + H + I) 2,798.05 J. Value Added Tax (VAT)
(G + H + I + J) 58,759.13 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

k Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman
1.00 69.42 69.42 b. Skilled Labor
1.00 38.97 116.91 c. Unskilled Labor
a. Batching Plant Enginee
b. Mechanical Engineer
c. Electrical Engineer
d. Unskilled Laboratory Te
e. Unskilled Labor
186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Dump Truck (12 cu. yd)


1.00 130.54 130.54 b. Asphalt Batch Plant ( 60
c. Water Truck/Pump (160
d. Payloader (1.50 cu.m.),
Minor Tools (10% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 171.300
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 41,575.00 43,653.75 a. MC - 70 Cut-back Asph


b. Aggregates, Sand (79%
c. Aggregates, 3/8 (19%)
d. Mineral Filler (7%)

293+32
e. Diesel

43,653.75 S
47,829.98 G. Direct Unit Cost (E + F)
9% of G 4,304.70 H. Overhead, Contingencies
8% of G 3,826.40 I. Contractor's Profit (CP)
5% of (G + H + I) 2,798.05 J. Value Added Tax (VAT)
(G + H + I + J) 58,759.13 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

sphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Asphalt Paver (80 Hp),


1.00 130.54 130.54 b. Pneumatic Tire Roller (1
c. Tandem Steel Roller (10
d. Water Truck/Pump (160
Minor Tools (10% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 285.51
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 44,000.00 46,200.00 a. Bituminous Concrete Su


thickness = 30mm (w/ 5%

295+32
46,200.00 S
50,376.23 G. Direct Unit Cost (E + F)
9% of G 4,533.86 H. Overhead, Contingencies
8% of G 4,030.10 I. Contractor's Profit (CP)
5% of (G + H + I) 2,947.01 J. Value Added Tax (VAT)
(G + H + I + J) 61,887.20 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

gate) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 779.40 b. Skilled Labor
c. Unskilled Labor

848.82 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 1,652.00 1,652.00 a. Asphalt Paver (80 Hp),


0.25 2,450.00 612.50 b. Pneumatic Tire Roller (1
c. Tandem Steel Roller (10
c. Water Truck/Pump (160
Minor Tools (10% of Labor

2,264.50 S
3,113.32 C.
D. Output per hour = 214.13
194.58 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.15 406.25 467.19 a. Bituminous Concrete Su


thickness = 40mm (w/ 5%

297+32
467.19 S
661.77 G. Direct Unit Cost (E + F)
9% of G 59.56 H. Overhead, Contingencies
8% of G 52.94 I. Contractor's Profit (CP)
5% of (G + H + I) 38.71 J. Value Added Tax (VAT)
(G + H + I + J) 812.98 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

k Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Asphalt Paver (80 Hp),


1.00 130.54 130.54 b. Pneumatic Tire Roller (1
c. Tandem Steel Roller (10
c. Water Truck/Pump (160
Minor Tools (10% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 171.300
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 40,300.00 42,315.00 a. Bituminous Concrete Su


thickness = 50mm (w/ 5%

299+32
42,315.00 S
46,491.23 G. Direct Unit Cost (E + F)
9% of G 4,184.21 H. Overhead, Contingencies
8% of G 3,719.30 I. Contractor's Profit (CP)
5% of (G + H + I) 2,719.74 J. Value Added Tax (VAT)
(G + H + I + J) 57,114.48 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

k Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman
1.00 69.42 69.42 b. Skilled Labor
1.00 38.97 116.91 c. Unskilled Labor
a. Batching Plant Enginee
b. Mechanical Engineer
c. Electrical Engineer
d. Unskilled Laboratory Te
e. Unskilled Labor
186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Asphalt Paver (80 Hp),


1.00 130.54 130.54 b. Pneumatic Tire Roller (1
c. Tandem Steel Roller (10
d. Dump Truck (12 cu.yd.)
e. Asphalt Batch Plant ( 60
f. Water Truck/Pump (160
g. Payloader (1.50 cu.m.),
Minor Tools (10% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 285.51
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 41,575.00 43,653.75 a. Asphalt Cement (8%)


b. Aggregates, Sand (79%
c. Aggregates, 3/8 (19%)
d. Mineral Filler (7%)

301+32
e. Diesel

43,653.75 S
47,829.98 G. Direct Unit Cost (E + F)
9% of G 4,304.70 H. Overhead, Contingencies
8% of G 3,826.40 I. Contractor's Profit (CP)
5% of (G + H + I) 2,798.05 J. Value Added Tax (VAT)
(G + H + I + J) 58,759.13 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

ment Penetration Grade 120-150) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman
1.00 69.42 69.42 b. Skilled Labor
1.00 38.97 116.91 c. Unskilled Labor
a. Batching Plant Enginee
b. Mechanical Engineer
c. Electrical Engineer
d. Unskilled Laboratory Te
e. Unskilled Labor
186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Asphalt Paver (80 Hp),


1.00 130.54 130.54 b. Pneumatic Tire Roller (1
c. Tandem Steel Roller (10
d. Dump Truck (12 cu.yd.)
e. Asphalt Batch Plant ( 60
f. Water Truck/Pump (160
g. Payloader (1.50 cu.m.),
Minor Tools (10% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 214.13
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 50,775.00 53,313.75 a. Asphalt Cement (8%)


b. Aggregates, Sand (79%
c. Aggregates, 3/8 (19%)
d. Mineral Filler (7%)

303+32
e. Diesel

53,313.75 S
57,489.98 G. Direct Unit Cost (E + F)
9% of G 5,174.10 H. Overhead, Contingencies
8% of G 4,599.20 I. Contractor's Profit (CP)
5% of (G + H + I) 3,363.16 J. Value Added Tax (VAT)
(G + H + I + J) 70,626.44 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

regate Grading) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman
1.00 69.42 69.42 b. Skilled Labor
1.00 38.97 779.40 c. Unskilled Labor
a. Batching Plant Enginee
b. Mechanical Engineer
c. Electrical Engineer
d. Unskilled Laboratory Te
e. Unskilled Labor
848.82 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 1,846.00 1,846.00 a. Asphalt Paver (80 Hp),


0.25 2,450.00 612.50 b. Pneumatic Tire Roller (1
c. Tandem Steel Roller (10
d. Dump Truck (12 cu.yd.)
e. Asphalt Batch Plant ( 60
f. Water Truck/Pump (160
g. Payloader (1.50 cu.m.),
Minor Tools (10% of Labor

2,458.50 S
3,307.32 C.
D. Output per hour = 171.300
206.71 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.15 406.25 467.19 a. Asphalt Cement (8%)


b. Aggregates, Sand (79%
c. Aggregates, 3/8 (19%)
d. Mineral Filler (7%)

305+32
e. Diesel

467.19 S
673.90 G. Direct Unit Cost (E + F)
9% of G 60.65 H. Overhead, Contingencies
8% of G 53.91 I. Contractor's Profit (CP)
5% of (G + H + I) 39.42 J. Value Added Tax (VAT)
(G + H + I + J) 827.88 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

halt Cement Penetration Grade 120-150) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Transit Mixer (5 cu.m.)


1.00 130.54 130.54 b. Concrete Vibrator
c. Concrete Batching Plan
d. Payloader (1.50 cu.m.),
e. Concrete Screeder (5.5
f. Water Truck/Pump (160
g. Concrete Saw (7.5 Hp),
h. Bar Cutter, Single Phas
Minor Tools (5% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 107.33
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 50,775.00 53,313.75 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

307+32
e. Sand
f. Gravel
g. Cement
h. Concrete Saw (diamond
i. Pipe Sleeve, 1" dia.
j. Grease/Tar

53,313.75 S
57,489.98 G. Direct Unit Cost (E + F)
9% of G 5,174.10 H. Overhead, Contingencies
8% of G 4,599.20 I. Contractor's Profit (CP)
5% of (G + H + I) 3,363.16 J. Value Added Tax (VAT)
(G + H + I + J) 70,626.44 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

Cut-back Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Concrete Vibrator


1.00 130.54 130.54 b. Concrete Screeder (5.5
c. Concrete Saw (7.5 Hp),
d. Bar Cutter, Single Phas
Minor Tools (5% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 107.33
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 40,300.00 42,315.00 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

309+32
e. Ready Mix Concrete, 35
f. Concrete Saw (diamond
g. Pipe Sleeve, 1" dia.
h. Grease/Tar

42,315.00 S
46,491.23 G. Direct Unit Cost (E + F)
9% of G 4,184.21 H. Overhead, Contingencies
8% of G 3,719.30 I. Contractor's Profit (CP)
5% of (G + H + I) 2,719.74 J. Value Added Tax (VAT)
(G + H + I + J) 57,114.48 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

Cut-back Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Transit Mixer (5 cu.m.)


1.00 130.54 130.54 b. Concrete Vibrator
c. Concrete Batching Plan
d. Payloader (1.50 cu.m.),
e. Concrete Screeder (5.5
f. Water Truck/Pump (160
g. Concrete Saw (7.5 Hp),
h. Bar Cutter, Single Phas
Minor Tools (5% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 80.500
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 41,575.00 43,653.75 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

311+32
e. Sand
f. Gravel
g. Cement
h. Concrete Saw (diamond
i. Pipe Sleeve, 1 1/2" dia.
j. Grease/Tar

43,653.75 S
47,829.98 G. Direct Unit Cost (E + F)
9% of G 4,304.70 H. Overhead, Contingencies
8% of G 3,826.40 I. Contractor's Profit (CP)
5% of (G + H + I) 2,798.05 J. Value Added Tax (VAT)
(G + H + I + J) 58,759.13 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

ulsified Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Concrete Vibrator


1.00 130.54 130.54 b. Concrete Screeder (5.5
c. Concrete Saw (7.5 Hp),
d. Bar Cutter, Single Phas
Minor Tools (5% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 80.5 sq
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 44,000.00 46,200.00 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

313+32
e. Ready Mix Concrete, 35
f. Concrete Saw (diamond
g. Pipe Sleeve, 1" dia.
h. Grease/Tar

46,200.00 S
50,376.23 G. Direct Unit Cost (E + F)
9% of G 4,533.86 H. Overhead, Contingencies
8% of G 4,030.10 I. Contractor's Profit (CP)
5% of (G + H + I) 2,947.01 J. Value Added Tax (VAT)
(G + H + I + J) 61,887.20 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

Pavement (Aggregates) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 779.40 b. Skilled Labor
c. Unskilled Labor

848.82 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 1,846.00 1,846.00 a. Transit Mixer (5 cu.m.)


0.25 2,450.00 612.50 b. Concrete Vibrator
c. Concrete Batching Plan
d. Payloader (1.50 cu.m.),
e. Concrete Screeder (5.5
f. Water Truck/Pump (160
g. Concrete Saw (7.5 Hp),
h. Bar Cutter, Single Phas
Minor Tools (5% of Labor

2,458.50 S
3,307.32 C.
D. Output per hour = 70.0000
206.71 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.15 406.25 467.19 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

315+32
e. Sand
f. Gravel
g. Cement
h. Concrete Saw (diamond
i. Pipe Sleeve, 2" dia.
j. Grease/Tar

467.19 S
673.90 G. Direct Unit Cost (E + F)
9% of G 60.65 H. Overhead, Contingencies
8% of G 53.91 I. Contractor's Profit (CP)
5% of (G + H + I) 39.42 J. Value Added Tax (VAT)
(G + H + I + J) 827.88 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

Pavement (Asphalt Cement) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Concrete Vibrator


1.00 130.54 130.54 b. Concrete Screeder (5.5
c. Concrete Saw (7.5 Hp),
d. Bar Cutter, Single Phas
Minor Tools (5% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 70. sq.m
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 50,775.00 53,313.75 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

317+32
e. Ready Mix Concrete, 35
f. Concrete Saw (diamond
g. Pipe Sleeve, 1" dia.
h. Grease/Tar

53,313.75 S
57,489.98 G. Direct Unit Cost (E + F)
9% of G 5,174.10 H. Overhead, Contingencies
8% of G 4,599.20 I. Contractor's Profit (CP)
5% of (G + H + I) 3,363.16 J. Value Added Tax (VAT)
(G + H + I + J) 70,626.44 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

Pavement (RC Cut-back Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Transit Mixer (5 cu.m.)


1.00 130.54 130.54 b. Concrete Vibrator
c. Concrete Batching Plan
d. Payloader (1.50 cu.m.),
e. Concrete Screeder (5.5
f. Water Truck/Pump (160
g. Concrete Saw (7.5 Hp),
h. Bar Cutter, Single Phas
Minor Tools (5% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 64.400
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 41,575.00 43,653.75 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

319+32
e. Sand
f. Gravel
g. Cement
h. Concrete Saw (diamond
i. Pipe Sleeve, 2" dia.
j. Grease/Tar

43,653.75 S
47,829.98 G. Direct Unit Cost (E + F)
9% of G 4,304.70 H. Overhead, Contingencies
8% of G 3,826.40 I. Contractor's Profit (CP)
5% of (G + H + I) 2,798.05 J. Value Added Tax (VAT)
(G + H + I + J) 58,759.13 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

Pavement (Emulsified Asphalt) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 116.91 b. Skilled Labor
c. Unskilled Labor

186.33 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 936.00 936.00 a. Concrete Vibrator


1.00 130.54 130.54 b. Concrete Screeder (5.5
c. Concrete Saw (7.5 Hp),
d. Bar Cutter, Single Phas
Minor Tools (5% of Labor

1,066.54 S
1,252.87 C.
D. Output per hour = 64.4 sq
4,176.23 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.05 44,000.00 46,200.00 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

321+32
e. Ready Mix Concrete, 35
f. Concrete Saw (diamond
g. Pipe Sleeve, 1" dia.
h. Grease/Tar

46,200.00 S
50,376.23 G. Direct Unit Cost (E + F)
9% of G 4,533.86 H. Overhead, Contingencies
8% of G 4,030.10 I. Contractor's Profit (CP)
5% of (G + H + I) 2,947.01 J. Value Added Tax (VAT)
(G + H + I + J) 61,887.20 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

se Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 116.91 c. Unskilled Labor

236.51 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 2,824.90 2,824.90 a. Transit Mixer (5 cu.m.)


1.00 1,652.00 1,652.00 b. Concrete Vibrator
1.00 561.00 561.00 c. Concrete Batching Plan
1.00 936.00 936.00 d. Payloader (1.50 cu.m.),
0.25 2,450.00 612.50 e. Concrete Screeder (5.5
23.65 f. Water Truck/Pump (160
g. Concrete Saw (7.5 Hp),
h. Bar Cutter, Single Phas
Minor Tools (5% of Labor

6,610.05 S
6,846.56 C.
D. Output per hour = 57.500
570.55 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.15 406.25 467.19 a. Reinforcing Steel Bar


0.07 40,300.00 2,821.00 b. Curing Compound
0.30 180.00 54.00 c. Asphalt Sealant
d. Steel Forms (Rental)

323+32
e. Sand
f. Gravel
g. Cement
h. Concrete Saw (diamond
i. Pipe Sleeve, 2" dia.
j. Grease/Tar

3,342.19 S
3,912.73 G. Direct Unit Cost (E + F)
9% of G 352.15 H. Overhead, Contingencies
8% of G 313.02 I. Contractor's Profit (CP)
5% of (G + H + I) 228.89 J. Value Added Tax (VAT)
(G + H + I + J) 4,806.79 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

se Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 116.91 c. Unskilled Labor

236.51 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 2,824.90 2,824.90 a. Concrete Vibrator


1.00 1,652.00 1,652.00 b. Concrete Screeder (5.5
1.00 561.00 561.00 c. Concrete Saw (7.5 Hp),
1.00 936.00 936.00 d. Bar Cutter, Single Phas
0.25 2,450.00 612.50 Minor Tools (5% of Labor
23.65

6,610.05 S
6,846.56 C.
D. Output per hour = 57.5 sq
570.55 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.15 406.25 467.19 a. Reinforcing Steel Bar


0.10 44,000.00 4,400.00 b. Curing Compound
0.30 180.00 54.00 c. Asphalt Sealant
d. Steel Forms (Rental)

325+32
e. Ready Mix Concrete, 35
f. Concrete Saw (diamond
g. Pipe Sleeve, 1" dia.
h. Grease/Tar

4,921.19 S
5,491.73 G. Direct Unit Cost (E + F)
9% of G 494.26 H. Overhead, Contingencies
8% of G 439.34 I. Contractor's Profit (CP)
5% of (G + H + I) 321.27 J. Value Added Tax (VAT)
(G + H + I + J) 6,746.60 K. Total Unit Cost

928-5
RICE ANALYSIS (DUPA)

x Surface Course Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 116.91 c. Unskilled Labor

236.51 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 2,824.90 2,824.90 a. Transit Mixer (5 cu.m.)


1.00 1,652.00 1,652.00 b. Concrete Vibrator
1.00 561.00 561.00 c. Concrete Batching Plan
0.25 2,450.00 612.50 d. Payloader (1.50 cu.m.),
23.65 e. Concrete Screeder (5.5
f. Water Truck/Pump (160
g. Concrete Saw (7.5 Hp),
h. Bar Cutter, Single Phas
Minor Tools (5% of Labor

5,674.05 S
5,910.56 C.
D. Output per hour = 53.67 s
492.55 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.15 406.25 467.19 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

327+32
e. Sand
f. Gravel
g. Cement
h. Concrete Saw (diamond
i. Pipe Sleeve, 2" dia.
j. Grease/Tar

467.19 S
959.73 G. Direct Unit Cost (E + F)
9% of G 86.38 H. Overhead, Contingencies
8% of G 76.78 I. Contractor's Profit (CP)
5% of (G + H + I) 56.14 J. Value Added Tax (VAT)
(G + H + I + J) 1,179.03 K. Total Unit Cost

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 306(2) Bituminous Material for Bituminous Road Mix Surface Course


: m.t.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 3 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

utor, 10 ft. wide (5 tons) 1 1.00 936.00

Sub - Total for B


Total (A + B)
= 1.0000 m.t

Name and Specification Unit Quantity Unit Cost

m.t. 1.05 40,300.00

329+32
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 307 Bituminous Plant Mix Surface Course-General (50mm thk.)


: sq.m.
: 171.30

Designation No. of Person No. of Hours Hourly Rate

Laying & 1 1.00 69.42


Compaction 4 1.00 50.18
8 1.00 38.97
Engineer Batching/ 1 1.00
Mixing 1 1.00
operation 1 1.00
ratory Technician 1 1.00
4 1.00
Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
12 cu.yd.) 2 1.00 1,420.00
Plant ( 60-80 TPH) 1 1.00 4,286.63
ump (16000L) 1 1.00 2,450.00
0 cu.m.), LX80-2C 1 1.00 1,733.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 171.300 sq.m

Name and Specification Unit Quantity Unit Cost

aterial (8%) m.t 0.00981 44,000.00


and (79%) cu.m. 0.041 650.00
8 (19%) cu.m. 0.010 650.00
bag 0.130 240.56

331+32
L 1.165 240.56

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 308(a) Cold Asphalt Plant Mix (50mm thk.)


: sq.m.
: 171.30

Designation No. of Person No. of Hours Hourly Rate

Laying & 1 1.00 69.42


Compaction 4 1.00 50.18
8 1.00 38.97
Engineer Batching/ 1 1.00
Mixing 1 1.00
operation 1 1.00
ratory Technician 1 1.00
4 1.00
Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
12 cu.yd.) 2 1.00 1,420.00
Plant ( 60-80 TPH) 1 1.00 4,286.63
ump (16000L) 1 1.00 2,450.00
0 cu.m.), LX80-2C 1 1.00 1,733.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 171.300 sq.m

Name and Specification Unit Quantity Unit Cost

halt (10%) m.t 0.01226 44,000.00


and (79%) cu.m. 0.041 650.00
8 (19%) cu.m. 0.01 650.00
bag 0.13 240.56

333+32
L 1.165 240.56

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 308(b) Cold Asphalt Plant Mix (50mm thk.)


: sq.m.
: 171.30

Designation No. of Person No. of Hours Hourly Rate

Laying & 1 1.00 69.42


Compaction 4 1.00 50.18
8 1.00 38.97
Engineer Batching/ 1 1.00
Mixing 1 1.00
operation 1 1.00
ratory Technician 1 1.00
4 1.00
Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
12 cu.yd.) 2 1.00 1,420.00
Plant ( 60-80 TPH) 1 1.00 4,286.63
ump (16000L) 1 1.00 2,450.00
0 cu.m.), LX80-2C 1 1.00 1,733.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 171.300 sq.m

Name and Specification Unit Quantity Unit Cost

ack Asphalt (7%) m.t 0.00858 40,300.00


and (79%) cu.m. 0.0488 650.00
cu.m. 0.01 650.00
bag 0.13 240.56

335+32
L 1.165 240.56

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 309 Bituminous Plant Mix (Stockpile Maintenance Mixture)


: sq.m.
: 171.30

Designation No. of Person No. of Hours Hourly Rate

Laying & 1 1.00 69.42


Compaction 4 1.00 50.18
8 1.00 38.97
Engineer Batching/ 1 1.00
Mixing 1 1.00
operation 1 1.00
ratory Technician 1 1.00
4 1.00
Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

12 cu. yd) 2 1.00 1,420.00


Plant ( 60-80 TPH) 1 1.00 4,286.63
ump (16000L) 1 1.00 2,450.00
0 cu.m.), LX80-2C 1 1.00 1,733.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 171.300 sq.m

Name and Specification Unit Quantity Unit Cost

ack Asphalt (10%) m.t 0.01226 40,300.00


and (79%) cu.m. 0.041 650.00
cu.m. 0.01 650.00
bag 0.13 240.56

337+32
L 1.165 240.56

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 310(a.1) Bituminous Concrete Surface Course (30mm thk.)


: sq.m.
: 285.51

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 8 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
ump (16000L) 1 1.00 2,450.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 285.51 sq.m

Name and Specification Unit Quantity Unit Cost

ncrete Surface Course m.t. 0.074 4,500.00


m (w/ 5% wastage)

339+32
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 310(a.2) Bituminous Concrete Surface Course (40mm thk.)


: sq.m.
: 214.13

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 8 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
ump (16000L) 1 1.00 2,450.00
% of Labor Cost )

Sub - Total for B


Total (A + B)
= 214.13 sq.m

Name and Specification Unit Quantity Unit Cost

ncrete Surface Course m.t. 0.098 4,500.00


m (w/ 5% wastage)

341+32
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 310(a.3) Bituminous Concrete Surface Course (50mm thk.)


: sq.m.
: 171.30

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 8 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
ump (16000L) 1 1.00 2,450.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 171.300 sq.m

Name and Specification Unit Quantity Unit Cost

ncrete Surface Course m.t. 0.123 4,500.00


m (w/ 5% wastage)

343+32
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 310(b.1) Bituminous Concrete Surface Course (30mm thk.)


: sq.m.
: 285.51

Designation No. of Person No. of Hours Hourly Rate

Laying & 1 1.00 69.42


Compaction 4 1.00 50.18
8 1.00 38.97
Engineer Batching/ 1 1.00
Mixing 1 1.00
operation 1 1.00
ratory Technician 1 1.00
4 1.00
Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
12 cu.yd.) 2 1.00 1,420.00
Plant ( 60-80 TPH) 1 1.00 4,286.63
ump (16000L) 1 1.00 2,450.00
0 cu.m.), LX80-2C 1 1.00 1,733.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 285.51 sq.m

Name and Specification Unit Quantity Unit Cost

m.t 0.00588 40,300.00


and (79%) cu.m. 0.025 650.00
cu.m. 0.006 650.00
bag 0.078 240.56

345+32
L 0.699 240.56

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 310(b.2) Bituminous Concrete Surface Course (40mm thk.)


: sq.m.
: 214.13

Designation No. of Person No. of Hours Hourly Rate

Laying & 1 1.00 69.42


Compaction 4 1.00 50.18
8 1.00 38.97
Engineer Batching/ 1 1.00
Mixing 1 1.00
operation 1 1.00
ratory Technician 1 1.00
4 1.00
Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
12 cu.yd.) 2 1.00 1,420.00
Plant ( 60-80 TPH) 1 1.00 4,286.63
ump (16000L) 1 1.00 2,450.00
0 cu.m.), LX80-2C 1 1.00 1,733.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 214.13 sq.m

Name and Specification Unit Quantity Unit Cost

m.t 0.00785 40,300.00


and (79%) cu.m. 0.033 650.00
cu.m. 0.008 650.00
bag 0.104 240.56

347+32
L 0.932 240.56

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 310(b.3) Bituminous Concrete Surface Course (50mm thk.)


: sq.m.
: 171.30

Designation No. of Person No. of Hours Hourly Rate

Laying & 1 1.00 69.42


Compaction 4 1.00 50.18
8 1.00 38.97
Engineer Batching/ 1 1.00
Mixing 1 1.00
operation 1 1.00
ratory Technician 1 1.00
4 1.00
Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

(80 Hp), NF220BIIVDM 1 1.00 1,833.00


e Roller (10 m.t.) 1 1.00 561.00
Roller (10.1 m.t.), CC421 1 1.00 1,652.00
12 cu.yd.) 2 1.00 1,420.00
Plant ( 60-80 TPH) 1 1.00 4,286.63
ump (16000L) 1 1.00 2,450.00
0 cu.m.), LX80-2C 1 1.00 1,733.00
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 171.300 sq.m

Name and Specification Unit Quantity Unit Cost

m.t 0.00981 40,300.00


and (79%) cu.m. 0.041 650.00
cu.m. 0.01 650.00
bag 0.13 240.56

349+32
L 1.165 240.56

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.


: sq.m.
: 107.33

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

5 cu.m.) 4 1.00 1,318.00


2 1.00 91.25
hing Plant (30 cu.m.) 1 1.00 1,759.50
0 cu.m.), LX80-2C 1 1.00 1,733.00
eder (5.5 Hp) 1 1.00 545.00
ump (16000L) 1 1.00 2,450.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 107.33 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.33 40.00


L 0.29 28.00
L 0.12 44.00
m 0.46 50.00

351+32
cu.m. 0.0825 850.00
cu.m. 0.15 650.00
bag 1.43 220.00
(diamond blade 14" dia) pc. 0.00015 8,000.00
m 0.0078 34.33
L 0.0015 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.1.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.


: sq.m.
: 107.33

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

2 1.00 91.25
eder (5.5 Hp) 1 1.00 545.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 107.33 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.33 40.00


L 0.29 28.00
L 0.12 44.00
m 0.46 50.00

353+32
ncrete, 3500 psi cu.m. 0.15 850.00
(diamond blade 14" dia) pc. 0.00015 8,000.00
m 0.0078 34.33
L 0.0015 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200mm thk.


: sq.m.
: 80.50

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

5 cu.m.) 4 1.00 1,318.00


2 1.00 91.25
hing Plant (30 cu.m.) 1 1.00 1,759.50
0 cu.m.), LX80-2C 1 1.00 1,733.00
eder (5.5 Hp) 1 1.00 545.00
ump (16000L) 1 1.00 2,450.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 80.500 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.39 36.00


L 0.29 75.00
L 0.12 50.00
m 0.46 56.00

355+32
cu.m. 0.11 500.00
cu.m. 0.20 600.00
bag 1.90 240.00
(diamond blade 14" dia) pc. 0.00015 8,000.00
1/2" dia. m 0.0086 97.00
L 0.0056 210.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.2.1 PCC Pavement (Plain) - Conventional Method, 200mm thk.


: sq.m.
: 80.50

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

2 1.00 91.25
eder (5.5 Hp) 1 1.00 545.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 80.5 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.39 40.00


L 0.29 28.00
L 0.12 44.00
m 0.46 50.00

357+32
ncrete, 3500 psi cu.m. 0.2 850.00
(diamond blade 14" dia) pc. 0.00015 8,000.00
m 0.0086 34.33
L 0.0056 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk.


: sq.m.
: 70.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

5 cu.m.) 4 1.00 1,318.00


2 1.00 91.25
hing Plant (30 cu.m.) 1 1.00 1,759.50
0 cu.m.), LX80-2C 1 1.00 1,733.00
eder (5.5 Hp) 1 1.00 545.00
ump (16000L) 1 1.00 2,450.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 70.0000 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.43 40.00


L 0.29 28.00
L 0.12 44.00
m 0.46 50.00

359+32
cu.m. 0.1265 850.00
cu.m. 0.23 650.00
bag 2.19 220.00
(diamond blade 14") pc. 0.00015 8,000.00
m 0.0071 97.00
L 0.0087 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.3.1 PCC Pavement (Plain) - Conventional Method, 230mm thk.


: sq.m.
: 70.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

2 1.00 91.25
eder (5.5 Hp) 1 1.00 545.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 70. sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.43 40.00


L 0.29 28.00
L 0.12 44.00
m 0.46 50.00

361+32
ncrete, 3500 psi cu.m. 0.23 850.00
(diamond blade 14" dia) pc. 0.00015 8,000.00
m 0.0071 34.33
L 0.0087 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250mm thk.


: sq.m.
: 64.40

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

5 cu.m.) 4 1.00 1,318.00


2 1.00 91.25
hing Plant (30 cu.m.) 1 1.00 1,759.50
0 cu.m.), LX80-2C 1 1.00 1,733.00
eder (5.5 Hp) 1 1.00 545.00
ump (16000L) 1 1.00 2,450.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 64.400 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.45 40.00


L 0.29 28.00
L 0.15 44.00
m 0.46 50.00

363+32
cu.m. 0.1375 850.00
cu.m. 0.25 650.00
bag 2.38 220.00
(diamond blade 14") pc. 0.00015 8,000.00
m 0.0078 97.00
L 0.0095 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.4.1 PCC Pavement (Plain) - Conventional Method, 250mm thk.


: sq.m.
: 64.40

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

2 1.00 91.25
eder (5.5 Hp) 1 1.00 545.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 64.4 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.45 40.00


L 0.29 28.00
L 0.15 44.00
m 0.46 50.00

365+32
ncrete, 3500 psi cu.m. 0.25 850.00
(diamond blade 14" dia) pc. 0.00015 8,000.00
m 0.0078 34.33
L 0.0095 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280mm thk.


: sq.m.
: 57.50

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

5 cu.m.) 4 1.00 1,318.00


2 1.00 91.25
hing Plant (30 cu.m.) 1 1.00 1,759.50
0 cu.m.), LX80-2C 1 1.00 1,733.00
eder (5.5 Hp) 1 1.00 545.00
ump (16000L) 1 1.00 2,450.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 57.500 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.50 40.00


L 0.29 28.00
L 0.17 44.00
m 0.46 50.00

367+32
cu.m. 0.154 850.00
cu.m. 0.28 650.00
bag 2.66 220.00
(diamond blade 14") pc. 0.00015 8,000.00
m 0.0078 97.00
L 0.0078 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.5.1 PCC Pavement (Plain) - Conventional Method, 280mm thk.


: sq.m.
: 57.50

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

2 1.00 91.25
eder (5.5 Hp) 1 1.00 545.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 57.5 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.50 40.00


L 0.29 28.00
L 0.17 44.00
m 0.46 50.00

369+32
ncrete, 3500 psi cu.m. 0.28 850.00
(diamond blade 14" dia) pc. 0.00015 8,000.00
m 0.0078 34.33
L 0.0078 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300mm thk.


: sq.m.
: 53.67

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
4 1.00 50.18
r 12 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

5 cu.m.) 4 1.00 1,318.00


2 1.00 91.25
hing Plant (30 cu.m.) 1 1.00 1,759.50
0 cu.m.), LX80-2C 1 1.00 1,733.00
eder (5.5 Hp) 1 1.00 545.00
ump (16000L) 1 1.00 2,450.00
(7.5 Hp), 14" Blade 1 1.00 32.63
gle Phase 1 0.10 219.75
of Labor Cost)

Sub - Total for B


Total (A + B)
= 53.67 sq.m

Name and Specification Unit Quantity Unit Cost

kg. 0.55 40.00


L 0.29 28.00
L 0.18 44.00
m 0.46 50.00

371+32
cu.m. 0.165 850.00
cu.m. 0.30 650.00
bag 2.85 220.00
(diamond blade 14") pc. 0.00015 8,000.00
m 0.0094 97.00
L 0.0094 300.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)

928-5
DETAILE

Item No./Description : 311(1)a.6.1 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 53.67

Amount Designation

A. Labor

69.42 a. Construction Foreman


50.18 b. Skilled Labor
116.91 c. Unskilled Labor

236.51 Sub - Total for A

Amount Name and Capacity

B. Equipment

936.00 a. Concrete Vibrator


b. Concrete Screeder (5.5 Hp)
c. Concrete Saw (7.5 Hp), 14" Blade
d. Bar Cutter, Single Phase
Minor Tools (5% of Labor Cost)

936.00 Sub - Total for B


1,172.51 C. Total (A + B)
D. Output per hour = 53.67 sq.m
1,172.51 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

42,315.00 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Steel Forms (Rental)

373+32
e. Ready Mix Concrete, 3500 psi
f. Concrete Saw (diamond blade 14" dia)
g. Pipe Sleeve, 1" dia.
h. Grease/Tar

42,315.00 Sub - Total for F


43,487.51 G. Direct Unit Cost (E + F)
3,913.88 H. Overhead, Contingencies & Miscellaneous (OCM)
3,479.00 I. Contractor's Profit (CP)
2,544.02 J. Value Added Tax (VAT)
53,424.41 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)b.1 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 90.00

Amount Designation

A. Labor
69.42
200.72 a. Construction Foreman
311.76 b. Skilled Labor
0.00 c. Unskilled Labor
0.00
0.00
0.00
0.00
581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. Concrete Batching Plant (30 cu.m.)


561.00 b. Concrete Paver, COM, III, FOUR-TRACK
1,652.00 c. Transit Mixer (5 cu.m.)
2,840.00 d. Payloader (1.50 cu.m.), LX80-2C
4,286.63 e. Water Truck/Pump (16000L)
2,450.00 f. Concrete Saw (7.5 Hp), 14" Blade
1,733.00 g. Concrete Vibrator
58.19 h. Bar Cutter, Single Phase

15,413.82 Sub - Total for B


15,995.72 C. Total (A + B)
D. Output per hour = 90.0000 sq.m
93.38 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

431.64 a. Reinforcing Steel Bar


26.65 b. Curing Compound
6.50 c. Asphalt Sealant
31.27 d. Sand

375+32
280.25 e. Gravel
f. Cement
g. Concrete Saw (diamond blade 14")
h. Pipe Sleeve, 2" dia.
i. Grease/Tar

776.32 Sub - Total for F


869.69 G. Direct Unit Cost (E + F)
78.27 H. Overhead, Contingencies & Miscellaneous (OCM)
69.58 I. Contractor's Profit (CP)
50.88 J. Value Added Tax (VAT)
1,068.42 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)b.1.1 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 100.00

Amount Designation

A. Labor
69.42
200.72 a. Construction Foreman
311.76 b. Skilled Labor
0.00 c. Unskilled Labor
0.00
0.00
0.00
0.00
581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. Concrete Paver, COM, III, FOUR-TRACK


561.00 b. Concrete Screeder (5.5 Hp)
1,652.00 d. Concrete Vibrator
2,840.00 d. Bar Cutter, Single Phase
4,286.63
2,450.00
1,733.00
58.19

15,413.82 Sub - Total for B


15,995.72 C. Total (A + B)
D. Output per hour = 100.0000 sq.m
93.38 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

539.44 a. Reinforcing Steel Bar


26.65 b. Curing Compound
6.50 c. Asphalt Sealant
31.27 d. Ready Mix Concrete, 3500 psi

377+32
280.25 e. Concrete Saw (diamond blade 14" dia)
f. Pipe Sleeve, 1" dia.
g. Grease/Tar

884.12 Sub - Total for F


977.49 G. Direct Unit Cost (E + F)
87.97 H. Overhead, Contingencies & Miscellaneous (OCM)
78.20 I. Contractor's Profit (CP)
57.18 J. Value Added Tax (VAT)
1,200.85 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)b.2 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 82.80

Amount Designation

A. Labor
69.42
200.72 a. Construction Foreman
311.76 b. Skilled Labor
0.00 c. Unskilled Labor
0.00
0.00
0.00
0.00
581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. Concrete Batching Plant (30 cu.m.)


561.00 b. Concrete Paver, COM, III, FOUR-TRACK
1,652.00 c. Transit Mixer (5 cu.m.)
2,840.00 d. Payloader (1.50 cu.m.), LX80-2C
4,286.63 e. Water Truck/Pump (16000L)
2,450.00 f. Concrete Saw (7.5 Hp), 14" Blade
1,733.00 g. Concrete Vibrator
58.19 h. Bar Cutter, Single Phase

15,413.82 Sub - Total for B


15,995.72 C. Total (A + B)
D. Output per hour = 82.800 sq.m
93.38 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

345.77 a. Reinforcing Steel Bar


31.72 b. Curing Compound
6.50 c. Asphalt Sealant
31.27 d. Sand

379+32
280.25 e. Gravel
f. Cement
g. Concrete Saw (diamond blade 14")
h. Pipe Sleeve, 2" dia.
i. Grease/Tar

695.52 Sub - Total for F


788.90 G. Direct Unit Cost (E + F)
71.00 H. Overhead, Contingencies & Miscellaneous (OCM)
63.11 I. Contractor's Profit (CP)
46.15 J. Value Added Tax (VAT)
969.16 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)b.2.1 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 100.00

Amount Designation

A. Labor
69.42
200.72 a. Construction Foreman
311.76 b. Skilled Labor
0.00 c. Unskilled Labor
0.00
0.00
0.00
0.00
581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

2,840.00 a. Concrete Paver, COM, III, FOUR-TRACK


4,286.63 b. Concrete Screeder (5.5 Hp)
2,450.00 d. Concrete Vibrator
1,733.00 d. Bar Cutter, Single Phase
58.19

11,367.82 Sub - Total for B


11,949.72 C. Total (A + B)
D. Output per hour = 100.0000 sq.m
69.76 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

494.08 a. Reinforcing Steel Bar


26.65 b. Curing Compound
6.50 c. Asphalt Sealant
31.27 d. Ready Mix Concrete, 3500 psi

381+32
280.25 e. Concrete Saw (diamond blade 14" dia)
f. Pipe Sleeve, 1" dia.
g. Grease/Tar

838.75 Sub - Total for F


908.51 G. Direct Unit Cost (E + F)
81.77 H. Overhead, Contingencies & Miscellaneous (OCM)
72.68 I. Contractor's Profit (CP)
53.15 J. Value Added Tax (VAT)
1,116.11 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)b.3 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 73.93

Amount Designation

A. Labor

69.42 a. Construction Foreman


200.72 b. Skilled Labor
311.76 c. Unskilled Labor

581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. Concrete Batching Plant (30 cu.m.)


561.00 b. Concrete Paver, COM, III, FOUR-TRACK
1,652.00 c. Transit Mixer (5 cu.m.)
2,450.00 d. Payloader (1.50 cu.m.), LX80-2C
58.19 e. Water Truck/Pump (16000L)
f. Concrete Saw (7.5 Hp), 14" Blade
g. Concrete Vibrator
h. Bar Cutter, Single Phase

6,554.19 Sub - Total for B


7,136.09 C. Total (A + B)
D. Output per hour = 73.93 sq.m
24.99 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

333.00 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Sand

383+32
e. Gravel
f. Cement
g. Concrete Saw (diamond blade 14")
h. Pipe Sleeve, 2" dia.
i. Grease/Tar

333.00 Sub - Total for F


357.99 G. Direct Unit Cost (E + F)
32.22 H. Overhead, Contingencies & Miscellaneous (OCM)
28.64 I. Contractor's Profit (CP)
20.94 J. Value Added Tax (VAT)
439.80 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)b.3.1 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 100.00

Amount Designation

A. Labor

69.42 a. Construction Foreman


200.72 b. Skilled Labor
311.76 c. Unskilled Labor

581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. Concrete Paver, COM, III, FOUR-TRACK


561.00 b. Concrete Screeder (5.5 Hp)
1,652.00 d. Concrete Vibrator
2,450.00 d. Bar Cutter, Single Phase
58.19

6,554.19 Sub - Total for B


7,136.09 C. Total (A + B)
D. Output per hour = 100.0000 sq.m
33.33 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

441.00 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Ready Mix Concrete, 3500 psi

385+32
e. Concrete Saw (diamond blade 14" dia)
f. Pipe Sleeve, 1" dia.
g. Grease/Tar

441.00 Sub - Total for F


474.33 G. Direct Unit Cost (E + F)
42.69 H. Overhead, Contingencies & Miscellaneous (OCM)
37.95 I. Contractor's Profit (CP)
27.75 J. Value Added Tax (VAT)
582.71 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)b.4 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 69.00

Amount Designation

A. Labor

69.42 a. Construction Foreman


200.72 b. Skilled Labor
311.76 c. Unskilled Labor

581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. Concrete Batching Plant (30 cu.m.)


561.00 b. Concrete Paver, COM, III, FOUR-TRACK
1,652.00 c. Transit Mixer (5 cu.m.)
2,450.00 d. Payloader (1.50 cu.m.), LX80-2C
58.19 e. Water Truck/Pump (16000L)
f. Concrete Saw (7.5 Hp), 14" Blade
g. Concrete Vibrator
h. Bar Cutter, Single Phase

6,554.19 Sub - Total for B


7,136.09 C. Total (A + B)
D. Output per hour = 69.0000 sq.m
41.66 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

553.50 a. Reinforcing Steel Bar


b. Curing Compound
c. Asphalt Sealant
d. Sand

387+32
e. Gravel
f. Cement
g. Concrete Saw (diamond blade 14")
h. Pipe Sleeve, 2" dia.
i. Grease/Tar

553.50 Sub - Total for F


595.16 G. Direct Unit Cost (E + F)
53.56 H. Overhead, Contingencies & Miscellaneous (OCM)
47.61 I. Contractor's Profit (CP)
34.82 J. Value Added Tax (VAT)
731.15 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)b.4.1 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 100.00

Amount Designation

A. Labor
69.42
200.72 a. Construction Foreman
311.76 b. Skilled Labor
0.00 c. Unskilled Labor
0.00
0.00
0.00
0.00
512.48 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. Concrete Paver, COM, III, FOUR-TRACK


561.00 b. Concrete Screeder (5.5 Hp)
1,652.00 d. Concrete Vibrator
2,840.00 d. Bar Cutter, Single Phase
4,286.63
2,450.00
1,733.00
51.25

15,406.88 Sub - Total for B


15,919.36 C. Total (A + B)
D. Output per hour = 100.0000 sq.m
55.76 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

236.96 a. Reinforcing Steel Bar


16.25 b. Curing Compound
3.90 c. Asphalt Sealant
18.76 d. Ready Mix Concrete, 3500 psi

389+32
168.15 e. Concrete Saw (diamond blade 14" dia)
f. Pipe Sleeve, 1" dia.
g. Grease/Tar

444.03 Sub - Total for F


499.79 G. Direct Unit Cost (E + F)
44.98 H. Overhead, Contingencies & Miscellaneous (OCM)
39.98 I. Contractor's Profit (CP)
29.24 J. Value Added Tax (VAT)
613.99 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)c PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 12.00

Amount Designation

A. Labor
69.42
200.72 a. Construction Foreman
311.76 b. Skilled Labor
0.00 c. Unskilled Labor
0.00
0.00
0.00
0.00
581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. One Bagger Mixer


561.00 b. Water Truck/Pump (16000L)
1,652.00 c. Concrete Vibrator
2,840.00 d. Bar Cutter, Single Phase
4,286.63 e. Concrete Saw (7.5 Hp), 14" Blade
2,450.00 Minor Tools (5% of Labor Cost )
1,733.00
58.19

15,413.82 Sub - Total for B


15,995.72 C. Total (A + B)
D. Output per hour = 12.0000 sq.m
74.70 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

316.36 a. Reinforcing Steel Bar


21.45 b. Curing Compound
5.20 c. Asphalt Sealant
25.02 d. Steel Forms (Rental)

391+32
224.20 e. Sand
f. Gravel
g. Cement
h. Concrete Saw (diamond blade 14")
i. Pipe Sleeve, 1" dia.
j. Grease/Tar

592.23 Sub - Total for F


666.93 G. Direct Unit Cost (E + F)
60.02 H. Overhead, Contingencies & Miscellaneous (OCM)
53.35 I. Contractor's Profit (CP)
39.02 J. Value Added Tax (VAT)
819.32 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(1)c.1 PCC Pavement (Plain) -


Unit of Measurement : sq.m.
Output per hour : 12.00

Amount Designation

A. Labor
69.42
200.72 a. Construction Foreman
311.76 b. Skilled Labor
0.00 c. Unskilled Labor
0.00
0.00
0.00
0.00
581.90 Sub - Total for A

Amount Name and Capacity

B. Equipment

1,833.00 a. Concrete Vibrator


561.00 b. Concrete Saw (7.5 Hp), 14" Blade
1,652.00 c. Bar Cutter, Single Phase
2,840.00 Minor Tools (5% of Labor Cost)
4,286.63
2,450.00
1,733.00
58.19

15,413.82 Sub - Total for B


15,995.72 C. Total (A + B)
D. Output per hour = 12. sq.m
93.38 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

395.34 a. Reinforcing Steel Bar


26.65 b. Curing Compound
6.50 c. Asphalt Sealant
31.27 d. Steel Forms (Rental)

393+32
280.25 e. Ready Mix Concrete, 3500 psi
f. Concrete Saw (diamond blade 14" dia)
g. Pipe Sleeve, 1" dia.
h. Grease/Tar

740.02 Sub - Total for F


833.40 G. Direct Unit Cost (E + F)
75.01 H. Overhead, Contingencies & Miscellaneous (OCM)
66.67 I. Contractor's Profit (CP)
48.75 J. Value Added Tax (VAT)
1,023.83 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(2) PCC Pavement (Reinforc


Unit of Measurement : sq.m.
Output per hour : 6.00

Amount Designation

A. Labor

69.42 a. Construction Foreman


200.72 b. Skilled Labor
467.64 c. Unskilled Labor

737.78 Sub - Total for A

Amount Name and Capacity

B. Equipment

5,272.00 a. Concrete Batching Plant (30 cu.m.)


182.50 b. Concrete Screeder (5.5 Hp)
1,759.50 c. Transit Mixer (5 cu.m.)
1,733.00 d. Payloader (1.50 cu.m.), LX80-2C
545.00 e. Water Truck/Pump (16000L)
2,450.00 f. Concrete Vibrator
32.63 g. Bar Cutter, Single Phase
21.98 h. Bar Bender
36.89 Minor Tools (5% of Labor)

12,033.49 Sub - Total for B


12,771.27 C. Total (A + B)
D. Output per hour = 6.0000 sq.m
118.99 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

13.20 a. Reinforcing Steel Bar


8.12 b. Curing Compound
5.28 c. Asphalt Sealant
23.00 d. Steel Forms (Rental)

395+32
70.13 e. Sand
97.50 f. Gravel
314.60 g. Cement
1.20 h. # 16 GI Tie Wire (2% of RSB)
0.27
0.45

533.74 Sub - Total for F


652.73 G. Direct Unit Cost (E + F)
58.75 H. Overhead, Contingencies & Miscellaneous (OCM)
52.22 I. Contractor's Profit (CP)
38.18 J. Value Added Tax (VAT)
801.88 K. Total Unit Cost

928-5
DETAILE

Item No./Description : 311(2)1 PCC Pavement (Reinforc


Unit of Measurement : sq.m.
Output per hour : 6.00

Amount Designation

A. Labor

69.42 a. Construction Foreman


200.72 b. Skilled Labor
467.64 c. Unskilled Labor

737.78 Sub - Total for A

Amount Name and Capacity

B. Equipment

182.50 a. Concrete Vibrator


545.00 b. Concrete Saw (7.5 Hp), 14" Blade
32.63 c. Bar Cutter, Single Phase
21.98 d. Bar Bender
36.89 Minor Tools (5% of Labor Cost)

818.99 Sub - Total for B


1,556.77 C. Total (A + B)
D. Output per hour = 6. sq.m
14.50 E. Direct Unit Cost (C D)

Amount Name and Specification

F. Materials

13.20 a. Reinforcing Steel Bar


8.12 b. Curing Compound
5.28 c. Asphalt Sealant
23.00 d. Steel Forms (Rental)

397+32
127.50 e. Ready Mix Concrete, 3500 psi
1.20 f. # 16 GI Tie Wire (2% of RSB)
0.27
0.45

179.02 Sub - Total for F


193.52 G. Direct Unit Cost (E + F)
17.42 H. Overhead, Contingencies & Miscellaneous (OCM)
15.48 I. Contractor's Profit (CP)
11.32 J. Value Added Tax (VAT)
237.74 K. Total Unit Cost

928-5
Amount

69.42
200.72
467.64

737.78

Amount

5,272.00
182.50
1,759.50
1,733.00
545.00
2,450.00
32.63
21.98
36.89

12,033.49
12,771.27

158.65

Amount

14.04
21.75
6.00
25.76

399+32
55.00
120.00
456.00
1.20
0.83
1.18

701.76
860.41
77.44
68.83
50.33
1,057.01

928-5
Amount

69.42
200.72
467.64

737.78

Amount

182.50
545.00
32.63
21.98
36.89

818.99
1,556.77

19.34

Amount

15.60
8.12
5.28
23.00

401+32
170.00
1.20
0.30
1.68

225.18
244.51
22.01
19.56
14.30
300.39

928-5
Amount

69.42
200.72
467.64

737.78

Amount

5,272.00
182.50
1,759.50
1,733.00
545.00
2,450.00
32.63
21.98
36.89

12,033.49
12,771.27

182.45

Amount

17.20
8.12
5.28
23.00

403+32
107.53
149.50
481.80
1.20
0.69
2.61

796.92
979.37
88.14
78.35
57.29
1,203.16

928-5
Amount

69.42
200.72
467.64

737.78

Amount

182.50
545.00
32.63
21.98
36.89

818.99
1,556.77

22.24

Amount

17.20
8.12
5.28
23.00

405+32
195.50
1.20
0.24
2.61

253.15
275.39
24.79
22.03
16.11
338.32

928-5
Amount

69.42
200.72
467.64

737.78

Amount

5,272.00
182.50
1,759.50
1,733.00
545.00
2,450.00
32.63
21.98
36.89

12,033.49
12,771.27

198.31

Amount

18.00
8.12
6.60
23.00

407+32
116.88
162.50
523.60
1.20
0.76
2.85

863.50
1,061.81
95.56
84.95
62.12
1,304.44

928-5
Amount

69.42
200.72
467.64

737.78

Amount

182.50
545.00
32.63
21.98
36.89

818.99
1,556.77

24.17

Amount

18.00
8.12
6.60
23.00

409+32
212.50
1.20
0.27
2.85

272.54
296.71
26.70
23.74
17.36
364.51

928-5
Amount

69.42
200.72
467.64

737.78

Amount

5,272.00
182.50
1,759.50
1,733.00
545.00
2,450.00
32.63
21.98
36.89

12,033.49
12,771.27

222.11

Amount

20.00
8.12
7.48
23.00

411+32
130.90
182.00
585.20
1.20
0.76
2.34

961.00
1,183.11
106.48
94.65
69.21
1,453.45

928-5
Amount

69.42
200.72
467.64

737.78

Amount

182.50
545.00
32.63
21.98
36.89

818.99
1,556.77

27.07

Amount

20.00
8.12
7.48
23.00

413+32
238.00
1.20
0.27
2.34

300.41
327.48
29.47
26.20
19.16
402.31

928-5
Amount

69.42
200.72
467.64

737.78

Amount

5,272.00
182.50
1,759.50
1,733.00
545.00
2,450.00
32.63
21.98
36.89

12,033.49
12,771.27

237.96

Amount

22.00
8.12
7.92
23.00

415+32
140.25
195.00
627.00
1.20
0.91
2.82

1,028.22
1,266.18
113.96
101.29
74.07
1,555.50

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Conventional Method, 300mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
12 1.00 38.97 467.64

737.78

No of Units No. of Hours Hourly Rate Amount

2 1.00 91.25 182.50


1 1.00 545.00 545.00
1 1.00 32.63 32.63
1 0.10 219.75 21.98
36.89

818.99
1,556.77

29.01

Unit Quantity Unit Cost Amount

kg. 0.55 40.00 22.00


L 0.29 28.00 8.12
L 0.18 44.00 7.92
m 0.46 50.00 23.00

417+32
cu.m. 0.3 850.00 255.00
pc. 0.00015 8,000.00 1.20
m 0.0094 34.33 0.32
L 0.0094 300.00 2.82

320.38
349.39
9% of G 31.45
8% of G 27.95
5% of (G + H + I) 20.44
(G + H + I + J) 429.22

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Using Concrete Paver, 230mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
10 1.00 38.97 389.70

659.84

No of Units No. of Hours Hourly Rate Amount

1 1.00 1,759.50 1,759.50


1 1.00 6,765.00 6,765.00
4 1.00 1,318.00 5,272.00
1 1.00 1,733.00 1,733.00
1 1.00 2,450.00 2,450.00
1 1.00 32.63 32.63
1 0.10 91.25 9.13
1 0.10 219.75 21.98

18,043.23
18,703.07

207.81

Unit Quantity Unit Cost Amount

kg. 0.43 40.00 17.20


L 0.29 28.00 8.12
L 0.12 44.00 5.28
cu.m. 0.1265 850.00 107.53

419+32
cu.m. 0.23 650.00 149.50
bag 2.19 220.00 481.80
pc. 0.00015 8,000.00 1.20
m 0.0071 97.00 0.69
L 0.0087 300.00 2.61

773.92
981.74
9% of G 88.36
8% of G 78.54
5% of (G + H + I) 57.43
(G + H + I + J) 1,206.06

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Using Concrete Paver, 230mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
10 1.00 38.97 389.70

659.84

No of Units No. of Hours Hourly Rate Amount

1 1.00 6,765.00 6,765.00


1 1.00 545.00 545.00
1 0.10 91.25 9.13
1 0.10 219.75 21.98

7,341.10
8,000.94

80.01

Unit Quantity Unit Cost Amount

kg. 0.43 40.00 17.20


L 0.29 28.00 8.12
L 0.12 44.00 5.28
cu.m. 0.23 850.00 195.50

421+32
pc. 0.00015 8,000.00 1.20
m 0.0071 34.33 0.24
L 0.0087 300.00 2.61

230.15
310.16
9% of G 27.91
8% of G 24.81
5% of (G + H + I) 18.14
(G + H + I + J) 381.04

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Using Concrete Paver, 250mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
10 1.00 38.97 389.70

659.84

No of Units No. of Hours Hourly Rate Amount

1 1.00 1,759.50 1,759.50


1 1.00 6,765.00 6,765.00
4 1.00 1,318.00 5,272.00
1 1.00 1,733.00 1,733.00
1 1.00 2,450.00 2,450.00
1 1.00 32.63 32.63
1 0.10 91.25 9.13
1 0.10 219.75 21.98

18,043.23
18,703.07

225.88

Unit Quantity Unit Cost Amount

kg. 0.45 40.00 18.00


L 0.29 28.00 8.12
L 0.15 44.00 6.60
cu.m. 0.1375 850.00 116.88

423+32
cu.m. 0.25 650.00 162.50
bag 2.38 220.00 523.60
pc. 0.00015 8,000.00 1.20
m 0.0078 97.00 0.76
L 0.0095 300.00 2.85

840.50
1,066.38
9% of G 95.97
8% of G 85.31
5% of (G + H + I) 62.38
(G + H + I + J) 1,310.05

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Using Concrete Paver, 250mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
10 1.00 38.97 389.70

659.84

No of Units No. of Hours Hourly Rate Amount

1 1.00 6,765.00 6,765.00


1 1.00 545.00 545.00
1 0.10 91.25 9.13
1 0.10 219.75 21.98

7,341.10
8,000.94

80.01

Unit Quantity Unit Cost Amount

kg. 0.45 40.00 18.00


L 0.29 28.00 8.12
L 0.15 44.00 6.60
cu.m. 0.25 850.00 212.50

425+32
pc. 0.00015 8,000.00 1.20
m 0.0078 34.33 0.27
L 0.0095 300.00 2.85

249.54
329.55
9% of G 29.66
8% of G 26.36
5% of (G + H + I) 19.28
(G + H + I + J) 404.85

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Using Concrete Paver, 280mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
10 1.00 38.97 389.70

659.84

No of Units No. of Hours Hourly Rate Amount

1 1.00 1,759.50 1,759.50


1 1.00 6,765.00 6,765.00
4 1.00 1,318.00 5,272.00
1 1.00 1,733.00 1,733.00
1 1.00 2,450.00 2,450.00
1 1.00 32.63 32.63
1 0.10 91.25 9.13
1 0.10 219.75 21.98

18,043.23
18,703.07

252.98

Unit Quantity Unit Cost Amount

kg. 0.50 40.00 20.00


L 0.29 28.00 8.12
L 0.17 44.00 7.48
cu.m. 0.154 850.00 130.90

427+32
cu.m. 0.28 650.00 182.00
bag 2.66 220.00 585.20
pc. 0.00015 8,000.00 1.20
m 0.0078 97.00 0.76
L 0.0078 300.00 2.34

938.00
1,190.98
9% of G 107.19
8% of G 95.28
5% of (G + H + I) 69.67
(G + H + I + J) 1,463.12

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Using Concrete Paver, 280mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
10 1.00 38.97 389.70

659.84

No of Units No. of Hours Hourly Rate Amount

1 1.00 6,765.00 6,765.00


1 1.00 545.00 545.00
1 0.10 91.25 9.13
1 0.10 219.75 21.98

7,341.10
8,000.94

80.01

Unit Quantity Unit Cost Amount

kg. 0.50 40.00 20.00


L 0.29 28.00 8.12
L 0.17 44.00 7.48
cu.m. 0.28 850.00 238.00

429+32
pc. 0.00015 8,000.00 1.20
m 0.0078 34.33 0.27
L 0.0078 300.00 2.34

277.41
357.42
9% of G 32.17
8% of G 28.59
5% of (G + H + I) 20.91
(G + H + I + J) 439.09

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Using Concrete Paver, 300mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
10 1.00 38.97 389.70

659.84

No of Units No. of Hours Hourly Rate Amount

1 1.00 1,759.50 1,759.50


1 1.00 6,765.00 6,765.00
4 1.00 1,318.00 5,272.00
1 1.00 1,733.00 1,733.00
1 1.00 2,450.00 2,450.00
1 1.00 32.63 32.63
1 0.10 91.25 9.13
1 0.10 219.75 21.98

18,043.23
18,703.07

271.06

Unit Quantity Unit Cost Amount

kg. 0.55 40.00 22.00


L 0.29 28.00 8.12
L 0.18 44.00 7.92
cu.m. 0.165 850.00 140.25

431+32
cu.m. 0.30 650.00 195.00
bag 2.85 220.00 627.00
pc. 0.00015 8,000.00 1.20
m 0.0094 97.00 0.91
L 0.0094 300.00 2.82

1,005.22
1,276.28
9% of G 114.87
8% of G 102.10
5% of (G + H + I) 74.66
(G + H + I + J) 1,567.91

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Using Concrete Paver, 300mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
10 1.00 38.97 389.70

659.84

No of Units No. of Hours Hourly Rate Amount

1 1.00 6,765.00 6,765.00


1 1.00 545.00 545.00
1 0.10 91.25 9.13
1 0.10 219.75 21.98

7,341.10
8,000.94

80.01

Unit Quantity Unit Cost Amount

kg. 0.55 40.00 22.00


L 0.29 28.00 8.12
L 0.18 44.00 7.92
cu.m. 0.3 850.00 255.00

433+32
pc. 0.00015 8,000.00 1.20
m 0.94 34.33 32.27
L 0.94 300.00 282.00

608.51
688.52
9% of G 61.97
8% of G 55.08
5% of (G + H + I) 40.28
(G + H + I + J) 845.85

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Conventional Method, 150mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


8 1.00 50.18 401.44
16 1.00 38.97 623.52

1,094.38

No of Units No. of Hours Hourly Rate Amount

1 1.00 172.00 172.00


1 0.05 2,450.00 122.50
2 1.00 91.25 182.50
1 0.05 219.75 10.99
1 0.10 32.63 3.26
54.72

545.97
1,640.35

136.70

Unit Quantity Unit Cost Amount

kg. 0.33 40.00 13.20


L 0.29 28.00 8.12
L 0.12 44.00 5.28
m 0.46 50.00 23.00

435+32
cu.m. 0.0825 850.00 70.13
cu.m. 0.15 650.00 97.50
bag 1.43 220.00 314.60
pc. 0.00015 8,000.00 1.20
m 0.0078 34.33 0.27
L 0.0015 300.00 0.45

533.74
670.44
9% of G 60.34
8% of G 53.64
5% of (G + H + I) 39.22
(G + H + I + J) 823.63

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Plain) - Conventional Method, 150mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


8 1.00 50.18 401.44
16 1.00 38.97 623.52

1,094.38

No of Units No. of Hours Hourly Rate Amount

2 1.00 91.25 182.50


1 0.05 32.63 1.63
1 0.10 219.75 21.98
54.72

260.83
1,355.21

112.93

Unit Quantity Unit Cost Amount

kg. 0.33 40.00 13.20


L 0.29 28.00 8.12
L 0.12 44.00 5.28
m 0.46 50.00 23.00

437+32
cu.m. 0.15 850.00 127.50
pc. 0.00015 8,000.00 1.20
m 0.0078 34.33 0.27
L 0.0015 300.00 0.45

179.02
291.95
9% of G 26.28
8% of G 23.36
5% of (G + H + I) 17.08
(G + H + I + J) 358.66

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Reinforced), 300mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
12 1.00 38.97 467.64

737.78

No of Units No. of Hours Hourly Rate Amount

1 0.10 1,759.50 175.95


1 0.10 545.00 54.50
2 0.10 1,318.00 263.60
1 0.10 1,733.00 173.30
1 0.10 2,450.00 245.00
1 0.10 91.25 9.13
1 0.25 219.75 54.94
1 0.25 351.50 87.88
36.89

1,101.18
1,838.96

306.49

Unit Quantity Unit Cost Amount

kg. 54.21 40.00 2,168.40


L 0.29 28.00 8.12
L 0.18 44.00 7.92
m 0.46 50.00 23.00

439+32
cu.m. 0.1650 850.00 140.25
cu.m. 0.30 650.00 195.00
bag 2.85 220.00 627.00
kg. 1.084 47.00 50.95

3,220.64
3,527.13
9% of G 317.44
8% of G 282.17
5% of (G + H + I) 206.34
(G + H + I + J) 4,333.08

928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)

vement (Reinforced), 300mm thk.

No. of Person No. of Hours Hourly Rate Amount

1 1.00 69.42 69.42


4 1.00 50.18 200.72
12 1.00 38.97 467.64

737.78

No of Units No. of Hours Hourly Rate Amount

1 0.10 91.25 9.13


1 0.10 32.63 3.26
1 0.25 219.75 54.94
1 0.25 351.50 87.88
36.89

192.09
929.87

154.98

Unit Quantity Unit Cost Amount

kg. 54.21 40.00 2,168.40


L 0.29 28.00 8.12
L 0.18 44.00 7.92
m 0.46 50.00 23.00

441+32
cu.m. 0.30 850.00 255.00
kg. 1.084 47.00 50.95

2,513.39
2,668.37
9% of G 240.15
8% of G 213.47
5% of (G + H + I) 156.10
(G + H + I + J) 3,278.09

928-5
443+32
928-5
445+32
928-5
447+32
928-5
449+32
928-5
451+32
928-5
453+32
928-5
455+32
928-5
457+32
928-5
459+32
928-5
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 404 Reinforcing Steel Bar, Grade 40 (Minor Structures)


Unit of Measurement : kg.
Output per hour : 180.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Bar Cutter 1
b. Bar Bender 1
c. Cargo Truck (9 - 10 mt) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 180.00000 kg
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Tie Wire (2% of RSB) kg.


b. Reinforcing Steel Bar, Grade 40 kg.
(w/ 5% Wastage)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 405 Structural Concrete Class A (Minor Structures)


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 4
c. Unskilled Labor 8

Installation/Removal of Formworks
b. Skilled Labor 4
c. Unskilled Labor 8
Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Concrete Vibrator 1
c. Water Truck/Pump (16000L) 1
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.4000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Lumber, Good - 4 uses bd.ft.


b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc.
c. Assorted CWN (1kg./100 bd.ft. of Lumber) kg.
d. Cement bag
e. Sand cu.m.
f. Gravel cu.m.

Note:
*Quantities for lumber, plywood and CWN are dependent on the
type of minor structure.
The above-computed quantities are based on box culvert.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)

r, Grade 40 (Minor Structures)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

0.50 219.75 109.88


0.50 351.50 175.75
0.15 1,212.00 181.80

467.43
948.97

5.27

Quantity Unit Cost Amount

0.021 47.00 0.99


1.05 40.00 42.00
42.99
48.26
9% of G 4.34
8% of G 3.86
5% of (G + H + I) 2.82
(G + H + I + J) 59.29
ILED UNIT PRICE ANALYSIS (DUPA)

Class A (Minor Structures)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 200.72
1.00 38.97 311.76

1.00 50.18 200.72


1.00 38.97 311.76
1,094.38

No. of Hours Hourly Rate Amount

1.00 172.00 172.00


1.00 91.25 91.25
0.10 2,450.00 245.00
54.72

562.97
1,657.35

1,183.82

Quantity Unit Cost Amount

* 70.0000 40.00 700.00


* 1.600 700.00 280.00
* 0.700 68.00 47.60
9.50 220.00 2,090.00
0.50 850.00 425.00
1.00 650.00 650.00

4,192.60
5,376.42
9% of G 483.88
8% of G 430.11
5% of (G + H + I) 314.52
(G + H + I + J) 6,604.93
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 500(1)a Pipe Culverts, 610mm dia. (24" )


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. R.C. Pipes (610mm dia.) pc.
d. Sand Bedding/Selected Sandy Soil cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 500(1)b Pipe Culverts, 760mm dia. (30" )


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. R.C. Pipes (760mm dia.) pc.
d. Sand Bedding/Selected Sandy Soil cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 500(1)c Pipe Culverts, 910mm dia. (36" )


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. R.C. Pipes (910mm dia.) pc.
d. Sand Bedding/Selected Sandy Soil cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 500(1)d Pipe Culverts, 1070mm dia. (42" )


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. R.C. Pipes (1070mm dia.) pc.
d. Sand Bedding/Selected Sandy Soil cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 500(1)e Pipe Culverts, 1220mm dia. (48" )


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. R.C. Pipes (1220mm dia.) pc.
d. Sand Bedding/Selected Sandy Soil cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 500(1)f Pipe Culverts, 1520mm dia. (60" )


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. R.C. Pipes (1520mm dia.) pc.
d. Sand Bedding/Selected Sandy Soil cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 501(1) Underdrain


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Plate Compactor (5 Hp) 1


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Coarse Aggregates cu.m.


b. Fine Aggregates cu.m.
c. Filter Cloth sq.m.
d. 150 mm. dia. Concrete Perforated Pipe pc.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 501(2) Blind Drain


Unit of Measurement : m
Output per hour : 1.25

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Coarse Aggregates cu.m.


b. Fine Aggregates cu.m.
c. Filter Cloth sq.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 501(3) Granular Backfill filter material for Underdrains


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Plate Compactor (5 Hp) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Coarse Aggregates (Granular Backfill Materials) cu.m.


(w/ 15% Shrinkage Factor)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (D

Item No./Description : 502 Manhole/Catch Basin/Inlet


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person

A. Labor Item No. Description

502(1)a Manhole (610mm dia RCPC)


502(1)b Manhole (760mm dia RCPC)
502(1)c Manhole (910mm dia RCPC)
502(1)d Manhole (1070mm dia RCPC)
502(1)e Manhole (1220mm dia RCPC)
502(2)a Inlet, Type I
502(2)b Inlet, Type I-A
502(3)a.1 Catch Basin (Single Barrel 610 mm dia RCPC)
502(3)a.2 Catch
SubBasin
- Total(Single
for A Barrel 760 mm dia RCPC)
502(3)a.3 Catch Basin (Single Barrel 910 mm dia RCPC)
502(3)a.4 Catch
NameBasin (Single Barrel 1070mm dia RCPC)
and Capacity No of Units
502(3)a.5 Catch Basin (Single Barrel 1220mm dia RCPC)
B. Equipment
502(3)b.1 Catch Basin (Double Barrel 610 mm dia RCPC)
502(3)b.2 Catch Basin (Double Barrel 910 mm dia RCPC)
502(3)b.3 Catch Basin (DoubleBarrel 1220 mm dia RCPC)
502(7) Adjusting Manhole, Type I-A
502(8) Adjusting Inlet, Type I and Type I-A
502(9)a Adjusting Catch Basin (Single Barrel, 610mm dia.)
502(9)b Adjusting Catch Basin (Double Barrel, 610mm dia.)

These pay items are variable in dimensions based on the actual consdition which
standard estimate should be based on the standard Detailed unit Analysis (DUPA

Further, these items with unit of measure as "each" in the Blue Book is recomme
component items such as Items 103(3) - Foundation Fill, 404 - Reinforcing Steel B
(Minor Structures) in the Summarry of quantities in the preparation of design plan
These pay items are variable in dimensions based on the actual consdition which
standard estimate should be based on the standard Detailed unit Analysis (DUPA

Further, these items with unit of measure as "each" in the Blue Book is recomme
component items such as Items 103(3) - Foundation Fill, 404 - Reinforcing Steel B
(Minor Structures) in the Summarry of quantities in the preparation of design plan

Sub - Total for B


C. Total (A + B)
D. Output = 1.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials/Processed Component Pay Item

a. 103(3) - Foundation Fill cu.m.


b. 404 - Reinforcing Steel Bar kg.
c. 405 - Structural Concrete cu.m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 502(4) Concrete Covers


Unit of Measurement : ea.
Output : 5.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Bar Cutter 1
c. Concrete Vibrator 1
c. Welding Machine (300 A, Gas/Diesel Driven 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 5.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

Dimension: 1.29m x 0.57m x 0.20m w/ Flat Bar Frame


a. Portland Cement bag
b. Sand cu.m.
c. Gravel cu.m.
d. Reinforcing Steel Bar kg.
e. #16 GI Tie Wire (2% of RSB) kg.
f. 6mm thk. Steel Plate kg.
g. 16mm thk. Steel Plate kg.
h. 1/2" Ordinary Plywood - 2 uses pc.
i. 16mm dia. U-bolt & Knot set
j. Welding Rod (1 kg./2000 kg. of Steel) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 502(5) Metal Frames and Gratings


Unit of Measurement : pair
Output : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 1

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.0000 pair
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. 410mmx660mmx60mm, C.I. Cover with Frame set


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 502(6) Metal Frames and Covers (Circular)


Unit of Measurement : pair
Output : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 1

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.0000 pair
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. 580mm dia. C.I. Manhole Cover with Frame set


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 503(a) Drainage Steel Grating with Frame (675mm x 975mm
Unit of Measurement : set
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 1

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Bar Cutter 1
b. Welding Machine (300 A, Gas/Diesel Driven 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 set
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. 65mm x 5mm Flat Bar kg.


b. 6mm dia. x 975mm Twisted Cross Rod kg.
c. 75mm x 75mm x 9mm Angle Bar kg.
d. Welding Rod (1 kg./2000 kg. of Steel) kg.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 503(b) Drainage Steel Grating with Frame (715mm x 2000mm
Unit of Measurement : set
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 1

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Bar Cutter 1
b. Welding Machine (300 A, Gas/Diesel Driven 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 set
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. 65mm x 5mm Flat Bar kg.


b. 6mm dia. x 975mm Twisted Cross Rod kg.
c. 75mm x 75mm x 9mm Angle Bar kg.
d. Welding Rod (1 kg./2000 kg. of Steel) kg.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pip


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pip


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pip


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pip


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pip


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Boom Truck (2 - 5 mt) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(2)a Removing, Cleaning and Re-laying Salvaged Culvert P


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Sand Bedding cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(2)b Removing, Cleaning and Re-laying Salvaged Culvert P


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Sand Bedding cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(2)c Removing, Cleaning and Re-laying Salvaged Culvert P


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Sand Bedding cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(2)d Removing, Cleaning and Re-laying Salvaged Culvert P


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Sand Bedding cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(2)e Removing, Cleaning and Re-laying Salvaged Culvert P


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (0.80 cu.m.) 1


b. Plate Compactor (5 Hp) 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Sand Bedding cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610mm dia.) - Half Silt
Unit of Measurement : m
Output per hour : 8.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (2 - 5 mt) 1


b. Steel Wheel w/ Nylon Rope 1
c. Improvised Bamboo with Bucket 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 8.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(3)b Cleaning Culvert Pipe in place (760mm dia.) - Half Silt
Unit of Measurement : m
Output per hour : 5.25

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

c. Cargo Truck (9 - 10 mt) 1


b. Steel Wheel w/ Nylon Rope 1
c. Improvised Bamboo with Bucket 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.2500 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)

m dia. (24" )

No. of Hours Hourly Rate Amount

0.44 69.42 30.54


0.44 50.18 44.16
0.44 38.97 68.59

143.29

No. of Hours Hourly Rate Amount

0.22 1,537.00 338.14


0.22 123.00 27.06
14.33

379.53
522.82

522.82

Quantity Unit Cost Amount

0.774 240.00 185.76


0.044 500.00 22.00
1.00 1,000.00 1,000.00
0.088 500.00 44.00
1,251.76
1,774.58
9% of G 159.71
8% of G 141.97
5% of (G + H + I) 103.81
(G + H + I + J) 2,180.07
ILED UNIT PRICE ANALYSIS (DUPA)

m dia. (30" )

No. of Hours Hourly Rate Amount

0.50 69.42 34.71


0.50 50.18 50.18
0.50 38.97 77.94

162.83

No. of Hours Hourly Rate Amount

0.25 1,537.00 384.25


0.25 123.00 30.75
16.28

431.28
594.11

594.11

Quantity Unit Cost Amount

0.918 220.00 201.96


0.052 850.00 44.20
1.00 1,750.00 1,750.00
0.108 850.00 91.80
2,087.96
2,682.07
9% of G 241.39
8% of G 214.57
5% of (G + H + I) 156.90
(G + H + I + J) 3,294.93
ILED UNIT PRICE ANALYSIS (DUPA)

m dia. (36" )

No. of Hours Hourly Rate Amount

0.57 69.42 39.57


0.57 50.18 57.21
0.57 38.97 88.85

185.63

No. of Hours Hourly Rate Amount

0.29 1,537.00 445.73


0.29 123.00 35.67
18.56

499.96
685.59

685.59

Quantity Unit Cost Amount

1.080 220.00 237.60


0.061 850.00 51.85
1.00 2,170.00 2,170.00
0.128 850.00 108.80
2,568.25
3,253.84
9% of G 292.85
8% of G 260.31
5% of (G + H + I) 190.35
(G + H + I + J) 3,997.34
ILED UNIT PRICE ANALYSIS (DUPA)

mm dia. (42" )

No. of Hours Hourly Rate Amount

0.67 69.42 46.51


0.67 50.18 67.24
0.67 38.97 104.44

218.19

No. of Hours Hourly Rate Amount

0.33 1,537.00 507.21


0.33 123.00 40.59
21.82

569.62
787.81

787.81

Quantity Unit Cost Amount

1.242 220.00 273.24


0.070 850.00 59.50
1.00 2,900.00 2,900.00
0.149 850.00 126.65
3,359.39
4,147.20
9% of G 373.25
8% of G 331.78
5% of (G + H + I) 242.61
(G + H + I + J) 5,094.84
ILED UNIT PRICE ANALYSIS (DUPA)

mm dia. (48" )

No. of Hours Hourly Rate Amount

0.80 69.42 55.54


0.80 50.18 80.29
0.80 38.97 124.70

260.53

No. of Hours Hourly Rate Amount

0.40 1,537.00 614.80


0.40 123.00 49.20
26.05

690.05
950.58

950.58

Quantity Unit Cost Amount

1.404 220.00 308.88


0.080 850.00 68.00
1.00 3,800.00 3,800.00
0.170 850.00 144.50
4,321.38
5,271.96
9% of G 474.48
8% of G 421.76
5% of (G + H + I) 308.41
(G + H + I + J) 6,476.60
ILED UNIT PRICE ANALYSIS (DUPA)

mm dia. (60" )

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

0.50 1,537.00 768.50


0.50 123.00 61.50
32.57

862.57
1,188.23

1,188.23

Quantity Unit Cost Amount

1.710 220.00 376.20


0.097 850.00 82.45
1.00 6,175.00 6,175.00
0.210 850.00 178.50
6,812.15
8,000.38
9% of G 720.03
8% of G 640.03
5% of (G + H + I) 468.02
(G + H + I + J) 9,828.46
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

0.80 69.42 55.54


0.80 38.97 124.70

180.24

No. of Hours Hourly Rate Amount

0.40 123.00 49.20


18.02

67.22
247.46

247.46

Quantity Unit Cost Amount

0.20 900.00 180.00


0.39 850.00 331.50
2.00 275.00 550.00
1.05 230.00 241.50
1,303.00
1,550.46
9% of G 139.54
8% of G 124.04
5% of (G + H + I) 90.70
(G + H + I + J) 1,904.75
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 155.88

225.30

No. of Hours Hourly Rate Amount

22.53

22.53
247.83

198.26

Quantity Unit Cost Amount

0.22 900.00 198.00


0.39 850.00 331.50
2.00 275.00 550.00
1,079.50
1,277.76
9% of G 115.00
8% of G 102.22
5% of (G + H + I) 74.75
(G + H + I + J) 1,569.73
ILED UNIT PRICE ANALYSIS (DUPA)

r material for Underdrains

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 155.88

225.30

No. of Hours Hourly Rate Amount

1.00 123.00 123.00


22.53

145.53
370.83

296.66

Quantity Unit Cost Amount

1.15 900.00 1,035.00


1,035.00
1,331.66
9% of G 119.85
8% of G 106.53
5% of (G + H + I) 77.90
(G + H + I + J) 1,635.95
AILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

RCPC)
RCPC)
RCPC)
RCPC) No. of Hours Hourly Rate Amount
RCPC)
RCPC)
RCPC)
RCPC)

0mm dia.)
10mm dia.)

on the actual consdition which combines component items , hence


d Detailed unit Analysis (DUPA).

in the Blue Book is recommended to be broken down seperately by


n Fill, 404 - Reinforcing Steel Bar and 405 - Structural Concrete Class A
the preparation of design plans
on the actual consdition which combines component items , hence
d Detailed unit Analysis (DUPA).

in the Blue Book is recommended to be broken down seperately by


n Fill, 404 - Reinforcing Steel Bar and 405 - Structural Concrete Class A
the preparation of design plans

Direct Unit
Quantity Direct Cost
Cost

9% of G
8% of G
5% of (G + H + I)
(G + H + I + J)
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

0.50 172.00 86.00


0.50 219.75 109.88
0.50 148.88 74.44
0.25 371.00 92.75
0.05 2,450.00 122.50
32.57

518.13
843.79

168.76

Quantity Unit Cost Amount

1.43 220.00 314.60


0.075 850.00 63.75
0.15 650.00 97.50
46.46 40.00 1,858.40
0.93 47.00 43.71
73.58 48.00 3,531.84
2.97 48.00 71.28
0.33 620.00 102.30
2.00 250.00 250.00
0.04 90.00 1.80

6,335.18
6,503.94
9% of G 585.35
8% of G 520.32
5% of (G + H + I) 380.48
(G + H + I + J) 7,990.09
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

0.50 69.42 34.71


0.50 50.18 25.09
0.50 38.97 19.49

79.29

No. of Hours Hourly Rate Amount

7.93

7.93
87.21

87.21

Quantity Unit Cost Amount

1.00 4,700.00 4,700.00


4,700.00
4,787.21
9% of G 430.85
8% of G 382.98
5% of (G + H + I) 280.05
(G + H + I + J) 5,881.09
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

0.50 69.42 34.71


0.50 50.18 25.09
0.50 38.97 19.49

79.29

No. of Hours Hourly Rate Amount

7.93

7.93
87.21

87.21

Quantity Unit Cost Amount

1.00 5,700.00 5,700.00


5,700.00
5,787.21
9% of G 520.85
8% of G 462.98
5% of (G + H + I) 338.55
(G + H + I + J) 7,109.59
ILED UNIT PRICE ANALYSIS (DUPA)

ng with Frame (675mm x 975mm Sump Grating)

No. of Hours Hourly Rate Amount

4.00 69.42 277.68


4.00 50.18 200.72
4.00 38.97 155.88

634.28

No. of Hours Hourly Rate Amount

2.00 219.75 439.50


4.00 371.00 1,484.00

1,923.50
2,557.78

2,557.78

Quantity Unit Cost Amount

62.557 48.00 3,002.74


1.244 48.00 59.71
38.36 48.00 1,841.28
0.051 90.00 4.59
4,908.32
7,466.10
9% of G 671.95
8% of G 597.29
5% of (G + H + I) 436.77
(G + H + I + J) 9,172.10
ILED UNIT PRICE ANALYSIS (DUPA)

ng with Frame (715mm x 2000mm Trench Grating)

No. of Hours Hourly Rate Amount

8.00 69.42 555.36


8.00 50.18 401.44
8.00 38.97 311.76

1,268.56

No. of Hours Hourly Rate Amount

4.00 219.75 879.00


8.00 371.00 2,968.00

3,847.00
5,115.56

5,115.56

Quantity Unit Cost Amount

127.066 48.00 6,099.17


3.174 48.00 152.35
41.64 48.00 1,998.72
0.086 90.00 7.74
8,257.98
13,373.54
9% of G 1,203.62
8% of G 1,069.88
5% of (G + H + I) 782.35
(G + H + I + J) 16,429.39
ILED UNIT PRICE ANALYSIS (DUPA)

, Stockpiling Salvaged Culvert Pipe (24" dia) - 610mm

No. of Hours Hourly Rate Amount

0.33 69.42 22.91


0.33 50.18 33.12
0.33 38.97 51.44

107.47

No. of Hours Hourly Rate Amount

0.17 1,537.00 261.29


0.17 1,017.90 173.04
0.08 2,450.00 196.00
10.75

641.08
748.55

748.55

Quantity Unit Cost Amount


0.00
748.55
9% of G 67.37
8% of G 59.88
5% of (G + H + I) 43.79
(G + H + I + J) 919.59
ILED UNIT PRICE ANALYSIS (DUPA)

, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm

No. of Hours Hourly Rate Amount

0.40 69.42 27.77


0.40 50.18 40.14
0.40 38.97 62.35

130.26

No. of Hours Hourly Rate Amount

0.20 1,537.00 307.40


0.20 1,017.90 203.58
0.10 2,450.00 245.00
13.03

769.01
899.27

899.27

Quantity Unit Cost Amount


0.00
899.27
9% of G 80.93
8% of G 71.94
5% of (G + H + I) 52.61
(G + H + I + J) 1,104.75
ILED UNIT PRICE ANALYSIS (DUPA)

, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm

No. of Hours Hourly Rate Amount

0.50 69.42 34.71


0.50 50.18 50.18
0.50 38.97 77.94

162.83

No. of Hours Hourly Rate Amount

0.25 1,537.00 384.25


0.25 1,017.90 254.48
0.13 2,450.00 318.50
16.28

973.51
1,136.34

1,136.34

Quantity Unit Cost Amount


0.00
1,136.34
9% of G 102.27
8% of G 90.91
5% of (G + H + I) 66.48
(G + H + I + J) 1,395.99
ILED UNIT PRICE ANALYSIS (DUPA)

, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm

No. of Hours Hourly Rate Amount

0.50 69.42 34.71


0.50 50.18 50.18
0.50 38.97 77.94

162.83

No. of Hours Hourly Rate Amount

0.25 1,537.00 384.25


0.25 1,017.90 254.48
0.13 2,450.00 318.50
16.28

973.51
1,136.34

1,136.34

Quantity Unit Cost Amount


0.00
1,136.34
9% of G 102.27
8% of G 90.91
5% of (G + H + I) 66.48
(G + H + I + J) 1,395.99
ILED UNIT PRICE ANALYSIS (DUPA)

, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm

No. of Hours Hourly Rate Amount

0.67 69.42 46.51


0.67 50.18 67.24
0.67 38.97 104.44

218.19

No. of Hours Hourly Rate Amount

0.33 1,537.00 507.21


0.33 1,017.90 335.91
0.17 2,450.00 416.50
21.82

1,281.44
1,499.63

1,499.63

Quantity Unit Cost Amount


0.00
1,499.63
9% of G 134.97
8% of G 119.97
5% of (G + H + I) 87.73
(G + H + I + J) 1,842.29
ILED UNIT PRICE ANALYSIS (DUPA)

and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm

No. of Hours Hourly Rate Amount

0.67 69.42 46.51


0.67 50.18 67.24
0.67 38.97 104.44

218.19

No. of Hours Hourly Rate Amount

0.40 1,537.00 614.80


0.33 123.00 40.59
0.10 2,450.00 245.00
21.82

922.21
1,140.40

1,140.40

Quantity Unit Cost Amount

0.774 220.00 170.28


0.044 850.00 37.40
0.088 850.00 74.80
282.48
1,422.88
9% of G 128.06
8% of G 113.83
5% of (G + H + I) 83.24
(G + H + I + J) 1,748.01
ILED UNIT PRICE ANALYSIS (DUPA)

and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm

No. of Hours Hourly Rate Amount

0.80 69.42 55.54


0.80 50.18 80.29
0.80 38.97 124.70

260.53

No. of Hours Hourly Rate Amount

0.48 1,537.00 737.76


0.40 123.00 49.20
0.12 2,450.00 294.00
26.05

1,107.01
1,367.54

1,367.54

Quantity Unit Cost Amount

0.918 220.00 201.96


0.052 850.00 44.20
0.108 850.00 91.80
337.96
1,705.50
9% of G 153.50
8% of G 136.44
5% of (G + H + I) 99.77
(G + H + I + J) 2,095.21
ILED UNIT PRICE ANALYSIS (DUPA)

and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

0.60 1,537.00 922.20


0.50 123.00 61.50
0.15 2,450.00 367.50
32.57

1,383.77
1,709.43

1,709.43

Quantity Unit Cost Amount

1.080 220.00 237.60


0.061 850.00 51.85
0.128 850.00 108.80
398.25
2,107.68
9% of G 189.69
8% of G 168.61
5% of (G + H + I) 123.30
(G + H + I + J) 2,589.28
ILED UNIT PRICE ANALYSIS (DUPA)

and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

0.60 1,537.00 922.20


0.50 123.00 61.50
0.15 2,450.00 367.50
32.57

1,383.77
1,709.43

1,709.43

Quantity Unit Cost Amount

1.242 220.00 273.24


0.070 850.00 59.50
0.149 850.00 126.65
459.39
2,168.82
9% of G 195.19
8% of G 173.51
5% of (G + H + I) 126.88
(G + H + I + J) 2,664.39
ILED UNIT PRICE ANALYSIS (DUPA)

and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm

No. of Hours Hourly Rate Amount

1.33 69.42 92.33


1.33 50.18 133.48
1.33 38.97 207.32

433.13

No. of Hours Hourly Rate Amount

0.80 1,537.00 1,229.60


0.67 123.00 82.41
0.20 2,450.00 490.00
43.31

1,845.32
2,278.45

2,278.45

Quantity Unit Cost Amount

1.404 220.00 308.88


0.080 850.00 68.00
0.170 850.00 144.50
521.38
2,799.83
9% of G 251.98
8% of G 223.99
5% of (G + H + I) 163.79
(G + H + I + J) 3,439.59
ILED UNIT PRICE ANALYSIS (DUPA)

e in place (610mm dia.) - Half Silted

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 783.00 783.00


1.00 300.00 300.00
1.00 200.00 200.00
32.57

1,315.57
1,641.23

205.15

Quantity Unit Cost Amount


0.00
205.15
9% of G 18.46
8% of G 16.41
5% of (G + H + I) 12.00
(G + H + I + J) 252.03
ILED UNIT PRICE ANALYSIS (DUPA)

e in place (760mm dia.) - Half Silted

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 1,212.00 1,212.00


1.00 300.00 300.00
1.00 200.00 200.00
32.57

1,744.57
2,070.23

394.33

Quantity Unit Cost Amount


0.00
394.33
9% of G 35.49
8% of G 31.55
5% of (G + H + I) 23.07
(G + H + I + J) 484.43
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910mm dia.) - Half Silt
Unit of Measurement : m
Output per hour : 3.75

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

c. Cargo Truck (9 - 10 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.7500 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070mm dia.) - Half Si
Unit of Measurement : m
Output per hour : 2.75

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

c. Cargo Truck (9 - 10 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.75 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220mm dia.) - Half Si
Unit of Measurement : m
Output per hour : 2.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

c. Cargo Truck (9 - 10 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520mm dia.) - Half Si
Unit of Measurement : m
Output per hour : 1.50

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

c. Cargo Truck (9 - 10 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.5000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 504(4) Reconditioning Drainage Structures


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

c. Cargo Truck (9 - 10 mt) 1


b. Bamboo with Bucket - 4 uses 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

* If some repair is needed, component materials required and


corresponding man-hour will be added to DUPA
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(1) Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.50

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.50 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Boulders (15 - 25 kg.) cu.m.


Miscellaneous (1% of Materials Cost)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(2) Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1


Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Boulders (30 - 70 kg.) cu.m.


Miscellaneous (1% of Materials Cost)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(3) Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1


Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Boulders (50 - 100 kg.) cu.m.


Miscellaneous (1% of Materials Cost)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(4) Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1


Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.75 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Boulders (100 - 200 kg.) cu.m.


Miscellaneous (1% of Materials Cost)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(5) Grouted Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


c. Water Truck/Pump (16000L) 1
Minor Tools (5% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per hour = 1.25 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel Fill cu.m.
d. Weep Holes (PVC) m
e. Filter Cloth sq.m.
f. Boulders (15 - 25 kg.) cu.m.
Miscellaneous (1% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(6) Grouted Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Water Truck/Pump (16000L) 1
c. Backhoe (Wheel Type 0.28 cu.m.) 1
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel Fill cu.m.
d. Weep Holes (PVC) m
e. Filter Cloth sq.m.
f. Boulders (30 - 70 kg.) cu.m.
Miscellaneous (1% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(7) Grouted Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Water Truck/Pump (16000L) 1
c. Backhoe (Wheel Type 0.28 cu.m.) 1
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.75 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel Fill cu.m.
d. Weep Holes (PVC) m
e. Filter Cloth sq.m.
f. Boulders (60 - 100 kg.) cu.m.
Miscellaneous (1% of Materials)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(8) Grouted Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.50

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Water Truck/Pump (16000L) 1
c. Backhoe (Wheel Type 0.28 cu.m.) 1
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.50 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel Fill cu.m.
d. Weep Holes (PVC) m
e. Filter Cloth sq.m.
f. Boulders (100 - 200 kg.) cu.m.
Miscellaneous (1% of Materials)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 505(9) Filter Layer of Granular Material


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Granular Materials cu.m.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 506 Stone Masonry


Unit of Measurement : cu.m.
Output per hour : 1.60

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Water Truck/Pump (16000L) 1
c. Backhoe (Wheel Type 0.28 cu.m.) 1
Minor Tools (10% Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour =1.6000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel Fill cu.m.
d. Weep Holes (PVC) m
e. Filter Cloth sq.m.
f. Boulders cu.m.
Miscellaneous (1% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 507 Rubble Concrete


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Water Truck/Pump (16000L) 1
c. Backhoe (Wheel Type 0.28 cu.m.) 1
Minor Tools (10% Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.400 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel Fill cu.m.
d. Weep Holes (PVC) m
e. Filter Cloth sq.m.
f. Boulders cu.m.
g. Gravel cu.m.
Miscellaneous (2% of Materials)
Note:
60% Boulder
50% Class "B" Concrete (w/ side forms only)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 508 Hand Laid Rock Embankment


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.125 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Boulders cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 509(a) Timber Sheet Pile


Unit of Measurement : m.
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1


b. Drop Hammer (15 T) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Timber Sheet Piles, ave. dia. 395mm bd.ft.


b. Coco Log - 2 uses m.
c. Lumber (Falsework) - 4 uses bd.ft.
d. Nail/Spike (1 kg./100 bd.ft. of Lumber) kg.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 509(b) Steel Sheet Pile (Slope Protection)


Unit of Measurement : m
Output per hour : 10.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Crawler Crane (36 - 40 T) 1


b. Vibro Hammer (Hydraulic Operated) 1
c. Welding Machine (300 A, Gas/Diesel Driven 1
d. Cutting Outfit 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.0000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Steel Sheet Piles (48 kg./m.) kg.


Miscellaneous (3% of Materials Cost)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven - 0.50 m x 0
Unit of Measurement : m
Output per hour : 1.38

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 6
c. Unskilled Labor 6

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1


b. Diesel Hammer (K25 or equivalent) 1
c. One Bagger Mixer 1
d. Concrete Vibrator 1
e. Water Truck/Pump (16000L) 1
f. Bar Cutter, Single Phase 1
f. Bar Bender 1
g. Drop Hammer 1
h. Jack Hammer 2
i. Air Compressor (356 - 450 cfm) 1
j. Plate Compactor (5 Hp) 1
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.3800 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
a. Coco Log kg.
b. Reinforcing Steel Bar bag
c. Cement cu.m.
d. Sand cu.m.
e. Gravel pc.
f. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc.
g. Lumber, 2' x 2' - 4 uses bd.ft.
h. # 16 GI Tie Wire (2% of RSB) kg.
i. Spike (1 kg/100 bd.ft of Lumber kg.
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.
Casting Bed
a. Ready Mix Concrete cu.m
b. Coco Lumber - 4 uses bd.ft.
c. Base Course cu.m
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 510(1) Bed Course Granular Material


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Plate Compactor 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.2500 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Aggregate Subbase Course cu.m.


(w/ 15% Shrinkage Factor)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 510(2) Concrete Slope Protection


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 4
c. Unskilled Labor 8
Installation of Formworks & Rebars
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


c. Water Truck/Pump (16000L) 1
a. Backhoe (Wheel Type 0.28 cu.m.) 1
b. Concrete Vibrator 1
h. Bar Cutter, Single Phase 1
b. Bar Bender 1
Minor Tools (10% Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.0000 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Weep Holes (PVC) m
d. Filter Cloth sq.m.
e. Gravel cu.m.
f. Granular Filter cu.m.
f. Reinforcing Steel Bar kg.
g. Marine Plywood 1/2" x 4' x 8' - 4 uses pc.
h. Lumber - 4 uses bd.ft.
i. #16 GI Tie Wire (2% of RSB) kg.
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
* Note: RSB quantity is variable based on approved plan.
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 511(1) Gabions


Unit of Measurement : cu.m.
Output per hour : 2.50

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the quantity is variable.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.500 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Gabion Wire Mesh (1 x 1 x 2) pc.


(w/ complete accessories)
b. Boulders cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 511(2) Mattresses


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the quantity is variable.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.125 cu.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Mattresses (6 x 2 x 0.3 ) pc.


(w/ complete accessories)
b. Boulders cu.m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 511(3) Filter Cloth


Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (9 - 10 mt) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 100.0000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Filter Cloth sq.m.


Miscellaneous (5% of Materials Cost)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)

e in place (910mm dia.) - Half Silted

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 1,212.00 1,212.00


32.57

1,244.57
1,570.23

418.73

Quantity Unit Cost Amount


0.00
418.73
9% of G 37.69
8% of G 33.50
5% of (G + H + I) 24.50
(G + H + I + J) 514.41
ILED UNIT PRICE ANALYSIS (DUPA)

e in place (1070mm dia.) - Half Silted

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 1,212.00 1,212.00


32.57

1,244.57
1,570.23

570.99

Quantity Unit Cost Amount


0.00
570.99
9% of G 51.39
8% of G 45.68
5% of (G + H + I) 33.40
(G + H + I + J) 701.46
ILED UNIT PRICE ANALYSIS (DUPA)

e in place (1220mm dia.) - Half Silted

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 1,212.00 1,212.00


32.57

1,244.57
1,570.23

785.11

Quantity Unit Cost Amount


0.00
785.11
9% of G 70.66
8% of G 62.81
5% of (G + H + I) 45.93
(G + H + I + J) 964.51
ILED UNIT PRICE ANALYSIS (DUPA)

e in place (1520mm dia.) - Half Silted

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 1,212.00 1,212.00


32.57

1,244.57
1,570.23

1,046.82

Quantity Unit Cost Amount


0.00
1,046.82
9% of G 94.21
8% of G 83.75
5% of (G + H + I) 61.24
(G + H + I + J) 1,286.02
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

0.50 69.42 34.71


0.50 50.18 25.09
0.50 38.97 38.97

98.77

No. of Hours Hourly Rate Amount

0.25 1,212.00 303.00


0.50 200.00 25.00
9.88

337.88
436.65

436.65

Quantity Unit Cost Amount


0.00
436.65
9% of G 39.30
8% of G 34.93
5% of (G + H + I) 25.54
(G + H + I + J) 536.42
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

24.08

24.08
505.62

337.08

Quantity Unit Cost Amount

1.05 920.00 966.00


9.66
975.66
1,312.74
9% of G 118.15
8% of G 105.02
5% of (G + H + I) 76.80
(G + H + I + J) 1,612.70
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

0.50 922.00 461.00


16.28

477.28
802.94

642.35

Quantity Unit Cost Amount

1.05 810.00 850.50


8.51
859.01
1,501.36
9% of G 135.12
8% of G 120.11
5% of (G + H + I) 87.83
(G + H + I + J) 1,844.42
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

0.75 922.00 691.50


16.28

707.78
1,033.44

1,033.44

Quantity Unit Cost Amount

1.05 740.00 777.00


7.77
784.77
1,818.21
9% of G 163.64
8% of G 145.46
5% of (G + H + I) 106.37
(G + H + I + J) 2,233.67
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 922.00 922.00


16.28

938.28
1,263.94

1,685.26

Quantity Unit Cost Amount

1.05 650.00 682.50


6.83
689.33
2,374.58
9% of G 213.71
8% of G 189.97
5% of (G + H + I) 138.91
(G + H + I + J) 2,917.17
ILED UNIT PRICE ANALYSIS (DUPA)

ss A)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

1.00 172.00 172.00


0.05 2,450.00 122.50
24.08
318.58
800.12

640.09

Quantity Unit Cost Amount

3.00 220.00 660.00


0.25 850.00 212.50
0.015 650.00 9.75
0.30 144.67 43.40
0.015 275.00 4.13
1.05 920.00 966.00
18.96

1,914.73
2,554.83
9% of G 229.93
8% of G 204.39
5% of (G + H + I) 149.46
(G + H + I + J) 3,138.61
ILED UNIT PRICE ANALYSIS (DUPA)

ss B)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 172.00 172.00


0.05 2,450.00 122.50
0.50 922.00 461.00
16.28

771.78
1,097.44

1,097.44

Quantity Unit Cost Amount

2.50 220.00 550.00


0.21 850.00 178.50
0.015 650.00 9.75
0.30 144.67 43.40
0.015 275.00 4.13
1.05 810.00 850.50
16.36

1,652.64
2,750.08
9% of G 247.51
8% of G 220.01
5% of (G + H + I) 160.88
(G + H + I + J) 3,378.48
ILED UNIT PRICE ANALYSIS (DUPA)

ss C)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 172.00 172.00


0.05 2,450.00 122.50
0.75 922.00 691.50
16.28

1,002.28
1,327.94

1,770.59

Quantity Unit Cost Amount

2.20 220.00 484.00


0.18 850.00 153.00
0.015 650.00 9.75
0.30 144.67 43.40
0.015 275.00 4.13
1.05 730.00 766.50
14.61

1,475.38
3,245.97
9% of G 292.14
8% of G 259.68
5% of (G + H + I) 189.89
(G + H + I + J) 3,987.68
ILED UNIT PRICE ANALYSIS (DUPA)

ss D)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 172.00 172.00


0.05 2,450.00 122.50
1.00 922.00 922.00
16.28

1,232.78
1,558.44

3,116.89

Quantity Unit Cost Amount

1.80 220.00 396.00


0.15 850.00 127.50
0.015 650.00 9.75
0.30 144.67 43.40
0.015 275.00 4.13
1.05 650.00 682.50
12.63

1,275.91
4,392.79
9% of G 395.35
8% of G 351.42
5% of (G + H + I) 256.98
(G + H + I + J) 5,396.55
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 50.18
1.00 38.97 77.94

197.54

No. of Hours Hourly Rate Amount

19.75

19.75
217.29

217.29

Quantity Unit Cost Amount

1.05 900.00 945.00


945.00
1,162.29
9% of G 104.61
8% of G 92.98
5% of (G + H + I) 67.99
(G + H + I + J) 1,427.88
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

1.00 172.00 172.00


0.05 2,450.00 122.50
0.10 922.00 92.20
48.15

434.85
916.39

572.75

Quantity Unit Cost Amount

5.50 240.00 1,320.00


0.30 500.00 150.00
0.02 600.00 12.00
0.30 195.00 58.50
0.015 160.00 2.40
1.05 560.00 588.00
21.31

2,152.21
2,724.96
9% of G 245.25
8% of G 218.00
5% of (G + H + I) 159.41
(G + H + I + J) 3,347.61
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

1.00 172.00 172.00


0.05 2,450.00 122.50
0.10 922.00 92.20
48.15

434.85
916.39

654.57

Quantity Unit Cost Amount

4.20 220.00 924.00


0.2625 850.00 223.13
0.02 650.00 13.00
0.30 144.67 43.40
0.015 275.00 4.13
0.63 810.00 510.30
0.525 650.00 341.25
36.72

2,095.92
2,750.49
9% of G 247.54
8% of G 220.04
5% of (G + H + I) 160.90
(G + H + I + J) 3,378.98
ILED UNIT PRICE ANALYSIS (DUPA)

bankment

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

48.15

48.15
529.69

169.50

Quantity Unit Cost Amount

1.05 920.00 966.00


966.00
1,135.50
9% of G 102.20
8% of G 90.84
5% of (G + H + I) 66.43
(G + H + I + J) 1,394.96
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 50.18
1.00 38.97 77.94

197.54

No. of Hours Hourly Rate Amount

1.00 2,606.00 2,606.00


1.00 200.00 200.00
19.75

2,825.75
3,023.29

755.82

Quantity Unit Cost Amount

52.25 40.00 2,090.00


1.00 350.00 175.00
16.00 40.00 160.00
0.16 68.00 10.88
2,435.88
3,191.70
9% of G 287.25
8% of G 255.34
5% of (G + H + I) 186.71
(G + H + I + J) 3,921.01
ILED UNIT PRICE ANALYSIS (DUPA)

pe Protection)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 155.88

325.66

No. of Hours Hourly Rate Amount

1.00 1,902.00 1,902.00


1.00 2,123.00 2,123.00
0.25 371.00 92.75
0.25 45.45 11.36

4,129.11
4,454.77

445.48

Quantity Unit Cost Amount

48.00 48.00 2,304.00


69.12
2,373.12
2,818.60
9% of G 253.67
8% of G 225.49
5% of (G + H + I) 164.89
(G + H + I + J) 3,462.65
ILED UNIT PRICE ANALYSIS (DUPA)

furnished and driven - 0.50 m x 0.35 m

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 301.08
1.00 38.97 233.82

604.32

No. of Hours Hourly Rate Amount

0.23 2,606.00 599.38


0.13 150.00 19.50
0.15 172.00 25.80
0.15 91.25 13.69
0.01 2,450.00 24.50
0.20 219.75 43.95
0.20 351.50 70.30
0.13 200.00 26.00
0.01 150.00 3.00
0.01 965.00 9.65
0.01 123.00 1.23
30.22

867.21
1,471.53

1,066.33

Quantity Unit Cost Amount

0.71 40.00 28.40


41.64 220.00 9,160.80
1.66 850.00 1,411.00
0.09 650.00 58.50
0.18 700.00 126.00
0.24 700.00 42.00
18.59 40.00 185.90
0.83 47.00 39.01
0.06 68.00 4.08
0.19 68.00 12.92

0.03 2,840.00 85.20


1.50 20.00 7.50
0.03 530.00 15.90
11,161.31
12,227.64
9% of G 1,100.49
8% of G 978.21
5% of (G + H + I) 715.32
(G + H + I + J) 15,021.65
ILED UNIT PRICE ANALYSIS (DUPA)

r Material

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 38.97 155.88

225.30

No. of Hours Hourly Rate Amount

1.00 123.00 123.00


22.53

145.53
370.83

296.66

Quantity Unit Cost Amount

1.15 580.00 667.00


667.00
963.66
9% of G 86.73
8% of G 77.09
5% of (G + H + I) 56.37
(G + H + I + J) 1,183.86
ILED UNIT PRICE ANALYSIS (DUPA)

ection

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 200.72
1.00 38.97 311.76

1.00 50.18 100.36


1.00 38.97 155.88

838.14

No. of Hours Hourly Rate Amount

1.00 172.00 172.00


0.05 2,450.00 122.50
0.10 922.00 92.20
0.50 91.25 45.63
0.05 219.75 10.99
0.05 351.50 17.58
83.81

544.70
1,382.84

1,382.84

Quantity Unit Cost Amount

8.40 220.00 1,848.00


0.50 850.00 425.00
0.21 144.67 30.38
0.015 275.00 4.13
1.00 650.00 650.00
0.016 650.00 10.40
* 26.03 40.00 1,041.20
0.48 700.00 84.00
18.76 40.00 187.60
0.521 47.00 24.49
0.188 68.00 12.78

4,317.98
5,700.82
9% of G 513.07
8% of G 456.07
5% of (G + H + I) 333.50
(G + H + I + J) 7,003.46
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

0.00
481.54

192.62

Quantity Unit Cost Amount

0.50 2,900.00 1,450.00

1.05 920.00 966.00


2,416.00
2,608.62
9% of G 234.78
8% of G 208.69
5% of (G + H + I) 152.60
(G + H + I + J) 3,204.68
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

0.00
481.54

154.09

Quantity Unit Cost Amount

0.28 5,000.00 1,400.00

1.05 920.00 966.00


2,366.00
2,520.09
9% of G 226.81
8% of G 201.61
5% of (G + H + I) 147.43
(G + H + I + J) 3,095.93
ILED UNIT PRICE ANALYSIS (DUPA)

No. of Hours Hourly Rate Amount

1.00 69.42 69.42


1.00 50.18 100.36
1.00 38.97 311.76

481.54

No. of Hours Hourly Rate Amount

0.25 1,212.00 303.00

303.00
784.54

7.85

Quantity Unit Cost Amount

1.05 275.00 288.75


14.44
303.19
311.03
9% of G 27.99
8% of G 24.88
5% of (G + H + I) 18.20
(G + H + I + J) 382.10
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 600(1) Concrete Curb (Cast in place) - 0.45m x 0.15/0.20m


Unit of Measurement : m.
Output per hour : 17.50

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 4
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Concrete Vibrator 1
b. One Bagger Mixer 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 17.500 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel cu.m.
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc.
e. Form Lumber - 4 uses bd.ft.
f. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 600(2) Concrete Gutter (Cast in place) - 0.50m x 0.15m


Unit of Measurement : m.
Output per hour : 17.50

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 4
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Concrete Vibrator 1
b. One Bagger Mixer 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 17.500 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel cu.m.
d. Good Lumber - 4 uses bd.ft.
e. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.
f. Reinforcing Steel Bar kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 600(3) Concrete Curb and Gutter, Type A (Cast in place) - Na
Unit of Measurement : m
Output per hour : 10.30

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 4
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Concrete Vibrator 1
b. One Bagger Mixer 1
c. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.300 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel cu.m.
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc.
e. Form Lumber - 4 uses bd.ft.
f. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.
Miscellaneous (2% of Materials)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 600(4) Concrete Curb (Precast)


Unit of Measurement : pc.
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 1

Sub - Total for A

Name and Capacity No of Units

B. Equipment

b. Boom Truck (2 - 5 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.0000 pc
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Fabricated Concrete Curb m


Miscellaneous (5% of materials)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 600(5) Concrete Gutter (Precast)


Unit of Measurement : pc.
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 1

Sub - Total for A

Name and Capacity No of Units

B. Equipment

b. Boom Truck (2 - 5 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.0000 pc
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Fabricated Concrete Gutter m


Miscellaneous (5% of materials)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 600(6) Concrete Curb and Gutter (Precast)


Unit of Measurement : pc.
Output per hour : 3.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 1

Sub - Total for A

Name and Capacity No of Units

B. Equipment

b. Boom Truck (2 - 5 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.0000 pc
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Fabricated Concrete Curb and Gutter m


Miscellaneous (5% of materials)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 601(a) Sidewalk (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 161.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 4
c. Unskilled Labor 12

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Transit Mixer (5 cu.m.) 4


b. Concrete Vibrator 2
c. Concrete Batching Plant (30 cu.m.) 1
d. Payloader (1.50 cu.m.), LX80-2C 1
e. Concrete Screeder (5.5 Hp) 1
f. Water Truck/Pump (16000L) 1
g. Concrete Saw (7.5 Hp), 14" Blade 1
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 161.0000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Curing Compound L
b. Asphalt Sealant L
c. Forms m
d. Sand cu.m.
e. Gravel cu.m.
f. Cement bag

Note : Bed Course excluded

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 601(b) Sidewalk (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 20.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 4
c. Unskilled Labor 12

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Water Truck/Pump (16000L) 2
c. Concrete Vibrator 1
d. Concrete Saw (7.5 Hp), 14" Blade 1
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.0000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Curing Compound L
b. Asphalt Sealant L
c. Forms m
d. Sand cu.m.
e. Gravel cu.m.
f. Cement bag

Note : Bed Course excluded

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 602(1)a Right-of-Way Monument


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Concrete Vibrator 1
b. Cargo Truck (9 - 10 mt) 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Concrete Class "A" cu.m.


b. Reinforcing Steel Bar, Grade 40 kg.
c. Plywood, 1/2" x 4' x 8' - 4 uses pc.
d. Form Lumber, Good - 4 uses bd.ft.
e. Reflectorized Paint, Marker L
f. # 16 Tie Wire (2% of RSB) kg.
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 602(1)b Right-of-Way Monument (Precast)


Unit of Measurement : ea.
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

b. Cargo Truck (9 - 10 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Fabricated Right-of-Way Monument ea.


(delivered at site)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 602(2)a Maintenance Marker Post


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Concrete Vibrator 1
b. Cargo Truck (9 - 10 mt) 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Concrete Class "A" cu.m.


b. Reinforcing Steel Bar, Grade 40 kg.
c. Plywood, 1/2" x 4' x 8' - 4 uses pc.
d. Form Lumber, Good - 4 uses bd.ft.
e. Reflectorized Paint, Marker L
f. # 16 Tie Wire (2% of RSB) kg.
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 602(2)b Maintenance Marker Post (Precast)


Unit of Measurement : ea.
Output per hour : 4.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

b. Cargo Truck (9 - 10 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Fabricated Maintenance Marker Post ea.


(delivered at site)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 602(3)a Kilometer Post


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (9 - 10 mt) 1


b. Concrete Vibrator 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Concrete Class "A" cu.m.


b. Reinforcing Steel Bar kg.
c. Plywood 1/2" x 4' x 8' - 2 uses pc.
d. Lumber - 2 uses bd.ft.
e. Portland Cement bag
f. Pebble cu.m.
g. Reflectorized Paint, Marker L
h. # 16 Tie Wire (2% of RSB) kg.
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 602(3)b Kilometer Post (Precast)


Unit of Measurement : ea.
Output : 2.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (9 - 10 mt) 1


b. Concrete Vibrator 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 2.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Fabricated Kilometer Post ea.


b. Concrete Class "A" cu.m.
c. Reflectorized Paint, Marker lit.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 602(4) Guide Post


Unit of Measurement : ea.
Output per hour : 50.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.0000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Guide Post (Portable) ea.


b. Post Reflector ea.
Miscellaneous (5% of Materials)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 603(1) Cable Wire Guardrail


Unit of Measurement : m
Output per hour : 1.15

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 8

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Concrete Vibrator 1
c. Water Truck/Pump (16000L) 1
d. Cargo Truck (2 - 5 mt) 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.15 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel cu.m.
d. Guardrail Post set
e. Galvanized Wire Rope (1.21 kg./m) kg.
f. Check Rope set
g. Hook Bolt ea.
h. Anchor Bracket unit
i. Wire Mesh sq.m.
j. Tension Fittings set
Miscellaneous (5% of Materials)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
* Tentative Canvass Price
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 603(3)a Metal Guardrails (Metal Beam) including Concrete Pos
Unit of Measurement : m
Output per hour : 4.20

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Concrete Vibrator 1
c. Water Truck/Pump (16000L) 1
d. Cargo Truck (9 - 10 mt) 1
Minor Tools (5 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.2000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel cu.m.
d. Metal Beam Guardrail m
e. Plywood Marine, 1/2" thk. x 4' x 8' - 4 uses pc.
f. Lumber - 4 uses bd.ft.
g. Reinforcing Steel Bars, Grade 40 kg.
h. Tie Wire (2% of RSB) kg.
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.
j. Bolt, Nut & Washer 5/8" dia. x 9" pc.
k. Bolt, Nut & Washer 5/8" dia. x 1" pc.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 603(3)b Metal Beam End Piece


Unit of Measurement : ea.
Output per hour : 6.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (9 - 10 mt) 1


Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Metal Guardrail End Piece ea.


Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 603(4) Guardrail (Timber)


Unit of Measurement : m
Output per hour : 5.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 4

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (9 - 10 mt) 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.00000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Lumber, 8" x 8" x 5.5' Treated Post (Tanguile) bd.ft.


b. Lumber, 3" x 8" Plank (Tanguile) - Untreated bd.ft.
c. Carriage Bolt, 1/2" x 12" pc.
Miscellaneous (5% of Materials)
Note: Exclude Excavation Works

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 604(1) Fencing (Barbed Wire)


Unit of Measurement : m
Output per hour : 18.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Welding Machine (300 A, Gas/Diesel Driven 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 18.00000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. 3-Strand Galvanized Barbed Wire, Ga 12.5 m


b. 50mmx50mmx6m Angle Bar kg.
c. Ga. 9 Twisted Wire Fastener pc.
Miscellaneous (2% of Materials, Welding Rod & etc.)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 604(2) Fencing (Chain Link Fence Fabric) - Type I


Unit of Measurement : m
Output per hour : 6.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Welding Machine (300 A, Gas/Diesel Driven 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00000 m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cyclone Wire 8' Ga 10 m


b. 38mm x 38mm x 4mm Angle Bar kg
c. Welding Rod (1 kg/2000 kf of Steel kg
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 604(3) Fencing (Post) - Type I


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. One Bagger Mixer 1


b. Bar Cutter, Single Phase 1
c. Bar Bender 1
d. Water Truck/Pump (16000L) 1
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Cement bag
b. Sand cu.m.
c. Gravel cu.m.
d. Reinforcing Steel Bar kg.
e. # 16 Tie Wire (2% of RSB) kg.
f. Plywood 1/4' x 4' x 8' - 2 uses pc.
g. Lumber - 2 uses bd.ft.
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 604(4) Fencing (Gates) - (Height 3m. & Length 4.24m.)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Welding Machine (300 A, Gas/Diesel Driven 1


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. 50 mm. G.I. Pipe, Schedule 40 pc.


b. Cyclone Wire Galvanized 10' Gauge 10 m
c. 6mm dia. Plain Bar kg.
Miscellaneous (3% of Material Cost, Gate Lock, Hinge & etc.)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 605(1)a Danger/Warning Signs (60cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (2 - 5 mt) 1


Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Gravel cu.m.
d. Form Lumber, Good - 4 uses bd.ft.
e. 3" G.I. Pipe m.
f. Plate kg.
g. Bolts, 5mm pc.
h. Sign Face, 3mm thk. Aluminum Sheet pc.
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 605(1)b Danger/Warning Signs (90cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (2 - 5 mt) 1


Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Gravel cu.m.
d. Form Lumber, Good - 4 uses bd.ft.
e. 3" G.I. Pipe m.
f. Plate kg.
g. Bolts, 5mm pc.
h. Sign Face, 3mm thk. Aluminum Sheet pc.
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 605(2)a Regulatory Signs (60cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (2 - 5 mt) 1


Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Gravel cu.m.
d. Form Lumber, Good - 4 uses bd.ft.
e. 3" G.I. Pipe m.
f. Plate kg.
g. Bolts, 5mm pc.
h. Sign Face, 3mm thk. Aluminum Sheet pc.
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : 605(2)b Regulatory Signs (90cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Labor 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Cargo Truck (2 - 5 mt) 1


Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00000 ea
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

a. Portland Cement bag


b. Sand cu.m.
c. Gravel cu.m.
d. Form Lumber, Good - 4 uses bd.ft.
e. 3" G.I. Pipe m.
f. Plate kg.
g. Bolts, 5mm pc.
h. Sign Face, 3mm thk. Aluminum Sheet pc.
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
RICE ANALYSIS (DUPA)

5m x 0.15/0.20m Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 200.72 b. Skilled Labor
1.00 38.97 311.76 c. Unskilled Labor

581.90 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 91.25 91.25 a. Cargo Truck (2 - 5 mt)


1.00 172.00 172.00 Minor Tools (10 % of Labo
0.05 2,450.00 122.50
58.19

443.94 S
1,025.84 C.
D. Output per hour = 1.00000
58.62 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.72 220.00 158.40 a. Portland Cement


0.04 850.00 34.00 b. Sand
0.08 650.00 52.00 c. Gravel
0.28 700.00 49.00 d. Form Lumber, Good - 4
12.16 40.00 121.60 e. 3" G.I. Pipe
0.12 68.00 8.16 f. Plate
g. Bolts, 5mm
h. Sign Face, 3mm thk. Al
i. Assorted CWN (1 kg./10

423.16 S
481.78 G. Direct Unit Cost (E + F)
9% of G 43.36 H. Overhead, Contingencies
8% of G 38.54 I. Contractor's Profit (CP)
5% of (G + H + I) 28.18 J. Value Added Tax (VAT)
(G + H + I + J) 591.87 K. Total Unit Cost
RICE ANALYSIS (DUPA)

50m x 0.15m Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 200.72 b. Skilled Labor
1.00 38.97 311.76 c. Unskilled Labor

581.90 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 91.25 91.25 a. Cargo Truck (2 - 5 mt)


1.00 172.00 172.00 Minor Tools (10 % of Labo
0.05 2,450.00 122.50
58.19

443.94 S
1,025.84 C.
D. Output per hour = 1.00000
58.62 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.72 220.00 158.40 a. Portland Cement


0.04 850.00 34.00 b. Sand
0.08 650.00 52.00 c. Gravel
3.28 40.00 32.80 d. Form Lumber, Good - 4
0.03 68.00 2.04 e. 3" G.I. Pipe
0.84 37.00 31.08 f. Plate
g. Bolts, 5mm
h. Sign Face, 3mm thk. Al
i. Assorted CWN (1 kg./10

310.32 S
368.94 G. Direct Unit Cost (E + F)
9% of G 33.20 H. Overhead, Contingencies
8% of G 29.52 I. Contractor's Profit (CP)
5% of (G + H + I) 21.58 J. Value Added Tax (VAT)
(G + H + I + J) 453.24 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Cast in place) - National Road Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 200.72 b. Skilled Labor
1.00 38.97 311.76 c. Unskilled Labor

581.90 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 91.25 91.25 a. Cargo Truck (2 - 5 mt)


1.00 172.00 172.00 Minor Tools (10 % of Labo
0.05 2,450.00 122.50
58.19

443.94 S
1,025.84 C.
D. Output per hour = 1.00000
99.60 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.29 220.00 283.80 a. Portland Cement


0.07 850.00 59.50 b. Sand
0.14 650.00 91.00 c. Gravel
0.24 700.00 42.00 d. Form Lumber, Good - 4
11.47 40.00 114.70 e. 3" G.I. Pipe
0.11 68.00 7.48 f. Plate
11.97 g. Bolts, 5mm
h. Sign Face, 3mm thk. Al
i. Assorted CWN (1 kg./10

610.45 S
710.05 G. Direct Unit Cost (E + F)
9% of G 63.90 H. Overhead, Contingencies
8% of G 56.80 I. Contractor's Profit (CP)
5% of (G + H + I) 41.54 J. Value Added Tax (VAT)
(G + H + I + J) 872.29 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 38.97 c. Unskilled Labor

158.57 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.50 1,017.90 508.95 a. Cargo Truck (2 - 5 mt)


15.86 Minor Tools (10 % of Labo

524.81 S
683.38 C.
D. Output per hour = 1.00000
170.84 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 690.00 690.00 a. Portland Cement


34.50 b. Sand
c. Gravel
d. Form Lumber, Good - 4
e. 3" G.I. Pipe
f. Plate
g. Bolts, 5mm
h. Sign Face, 3mm thk. Al
i. Assorted CWN (1 kg./10

724.50 S
895.34 G. Direct Unit Cost (E + F)
9% of G 80.58 H. Overhead, Contingencies
8% of G 71.63 I. Contractor's Profit (CP)
5% of (G + H + I) 52.38 J. Value Added Tax (VAT)
(G + H + I + J) 1,099.93 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 38.97 c. Unskilled Labor

158.57 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.50 1,017.90 508.95 a. Cargo Truck (2 - 5 mt)


15.86 Minor Tools (10 % of Labo

524.81 S
683.38 C.
D. Output per hour = 1.00000
170.84 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 680.00 680.00 a. Portland Cement


34.00 b. Sand
c. Gravel
d. Form Lumber, Good - 4
e. 3" G.I. Pipe
f. Plate
g. Bolts, 5mm
h. Sign Face, 3mm thk. Al
i. Assorted CWN (1 kg./10

714.00 S
884.84 G. Direct Unit Cost (E + F)
9% of G 79.64 H. Overhead, Contingencies
8% of G 70.79 I. Contractor's Profit (CP)
5% of (G + H + I) 51.76 J. Value Added Tax (VAT)
(G + H + I + J) 1,087.03 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 38.97 c. Unskilled Labor

158.57 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.50 1,017.90 508.95 a. Cargo Truck (2 - 5 mt)


15.86 Minor Tools (10 % of Labo

524.81 S
683.38 C.
D. Output per hour = 1.00000
227.79 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 1,750.00 1,750.00 a. Portland Cement


87.50 b. Sand
c. Gravel
d. Form Lumber, Good - 4
e. 3" G.I. Pipe
f. Plate
g. Bolts, 5mm
h. Sign Face, 3mm thk. Al
i. Assorted CWN (1 kg./10

1,837.50 S
2,065.29 G. Direct Unit Cost (E + F)
9% of G 185.88 H. Overhead, Contingencies
8% of G 165.22 I. Contractor's Profit (CP)
5% of (G + H + I) 120.82 J. Value Added Tax (VAT)
(G + H + I + J) 2,537.21 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 200.72 b. Skilled Labor
1.00 38.97 467.64 c. Unskilled Labor

737.78 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 1,318.00 5,272.00 a. Cargo Truck (2 - 5 mt)


1.00 91.25 182.50 Minor Tools (5% of Labor)
1.00 1,759.50 1,759.50
1.00 1,733.00 1,733.00
1.00 545.00 545.00
1.00 2,450.00 2,450.00
1.00 32.63 32.63
36.89

12,011.52 S
12,749.30 C.
D. Output per hour = 10.0000
79.19 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.29 28.00 8.12 a. Pavement Markings (W


0.12 44.00 5.28 Miscellaneous (5% of abo
0.46 250.00 115.00
0.055 850.00 46.75
0.10 650.00 65.00
0.95 220.00 209.00

449.15 S
528.34 G. Direct Unit Cost (E + F)
9% of G 47.55 H. Overhead, Contingencies
8% of G 42.27 I. Contractor's Profit (CP)
5% of (G + H + I) 30.91 J. Value Added Tax (VAT)
(G + H + I + J) 649.06 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 200.72 b. Skilled Labor
1.00 38.97 467.64 c. Unskilled Labor

737.78 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 172.00 172.00 a. Cargo Truck (2 - 5 mt)


1.00 2,450.00 4,900.00 Minor Tools (10% of Lab
0.125 91.25 11.41
1.00 32.63 32.63
36.89

5,152.93 S
5,890.71 C.
D. Output per hour = 10.0000
294.54 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.29 28.00 8.12 a. Reflectorized Traffic Pa


0.12 44.00 5.28 Miscellaneous (5% of abo
0.46 250.00 115.00
0.055 850.00 46.75
0.10 650.00 65.00
0.95 220.00 209.00

449.15 S
743.69 G. Direct Unit Cost (E + F)
9% of G 66.93 H. Overhead, Contingencies
8% of G 59.49 I. Contractor's Profit (CP)
5% of (G + H + I) 43.51 J. Value Added Tax (VAT)
(G + H + I + J) 913.62 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 77.94 c. Unskilled Labor

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.20 91.25 18.25 a. Cargo Truck (2 - 5 mt)


0.05 1,212.00 60.60 Minor Tools (10% of Lab
19.75

98.60 S
296.14 C.
D. Output per hour = 10.0000
148.07 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.03 3,538.78 106.16 a. Reflectorized Traffic Pa


7.15 40.00 286.00 Miscellaneous (5% of abo
0.22 700.00 38.50
13.53 40.00 135.30
0.10 475.00 47.50
0.14 47.00 6.58
0.14 68.00 9.52

629.56 S
777.64 G. Direct Unit Cost (E + F)
9% of G 69.99 H. Overhead, Contingencies
8% of G 62.21 I. Contractor's Profit (CP)
5% of (G + H + I) 45.49 J. Value Added Tax (VAT)
(G + H + I + J) 955.33 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Unskilled Labor
1.00 38.97 77.94

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.05 1,212.00 60.60 a. Diamond Drill, CP-8 wit


19.75 b. Cargo Truck (2 - 5 mt)
c. Air Compressor (15 - 35
Minor Tools (5% of Labor)

80.35 S
277.89 C.
D. Output per hour = 10.0000
69.47 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 3,320.00 3,320.00 a. Reflective Stud Catchey


180mm x 140mm (type
b. Concrete Epoxy A & B
3,320.00 S
3,389.47 G. Direct Unit Cost (E + F)
9% of G 305.05 H. Overhead, Contingencies
8% of G 271.16 I. Contractor's Profit (CP)
5% of (G + H + I) 198.28 J. Value Added Tax (VAT)
(G + H + I + J) 4,163.97 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Unskilled Labor
1.00 38.97 77.94

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.20 91.25 18.25 a. Diamond Drill, CP-8 wit


0.05 1,212.00 60.60 b. Cargo Truck (2 - 5 mt)
19.75 c. Air Compressor (15 - 35
Minor Tools (5% of Labor)

98.60 S
296.14 C.
D. Output per hour = 10.0000
148.07 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.03 3,400.00 102.00 a. Reflective Stud Catchey


7.15 40.00 286.00 100mm x 100mm (type
0.22 700.00 38.50 b. Concrete Epoxy A & B
13.53 40.00 135.30
0.10 475.00 47.50
0.14 47.00 6.58
0.14 68.00 9.52

625.40 S
773.47 G. Direct Unit Cost (E + F)
9% of G 69.61 H. Overhead, Contingencies
8% of G 61.88 I. Contractor's Profit (CP)
5% of (G + H + I) 45.25 J. Value Added Tax (VAT)
(G + H + I + J) 950.21 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 77.94 c. Unskilled Labor

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.05 1,212.00 60.60 a. Plate Compactor (5 hp)


19.75 Minor Tools (10% of Labor

80.35 S
277.89 C.
D. Output per hour = 1.25 cu
69.47 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 1,650.00 1,650.00 a. Topsoil


1,650.00 S
1,719.47 G. Direct Unit Cost (E + F)
9% of G 154.75 H. Overhead, Contingencies
8% of G 137.56 I. Contractor's Profit (CP)
5% of (G + H + I) 100.59 J. Value Added Tax (VAT)
(G + H + I + J) 2,112.37 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.50 69.42 104.13 a. Construction Foreman


1.50 50.18 75.27 b. Skilled Labor
1.50 38.97 116.91 c. Unskilled Labor

296.31 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.50 1,212.00 606.00 a. Plate Compactor (5 hp)


0.10 91.25 9.13 Minor Tools (10% of Labor
29.63

644.76 S
941.07 C.
D. Output per hour = 1.25 cu
941.07 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.184 3,400.00 625.60


7.59 40.00 303.60
0.604 700.00 211.40
7.15 20.00 71.50
0.775 220.00 170.50
0.044 900.00 39.60
0.20 475.00 95.00
0.14 47.00 6.58
0.07 68.00 4.76

1,528.54 S
2,469.61 G. Direct Unit Cost (E + F)
9% of G 222.26 H. Overhead, Contingencies
8% of G 197.57 I. Contractor's Profit (CP)
5% of (G + H + I) 144.47 J. Value Added Tax (VAT)
(G + H + I + J) 3,033.91 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.50 69.42 104.13 a. Construction Foreman


1.50 50.18 75.27 b. Skilled Labor
1.50 38.97 116.91 c. Unskilled Labor

296.31 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.50 1,212.00 606.00 a. Water Truck/Pump (160


0.05 91.25 4.56 Minor Tools (10% of Labor
29.63

640.19 S
936.50 C.
D. Output per hour = 35.0000
468.25 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 4,150.00 4,150.00 a. Sprigs


0.095 3,400.00 323.00 b. Fertilizer
0.20 475.00 95.00
4,568.00 S
5,036.25 G. Direct Unit Cost (E + F)
9% of G 453.26 H. Overhead, Contingencies
8% of G 402.90 I. Contractor's Profit (CP)
5% of (G + H + I) 294.62 J. Value Added Tax (VAT)
(G + H + I + J) 6,187.04 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 38.97 77.94 b. Unskilled Labor

147.36 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

14.74 a. Water Truck/Pump (160


Minor Tools (10% of Labor

14.74 S
162.10 C.
D. Output per hour = 25.0000
3.24 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 1,240.00 1,240.00 a. Sods


1.00 85.00 85.00
66.25
1,391.25 S
1,394.49 G. Direct Unit Cost (E + F)
9% of G 125.50 H. Overhead, Contingencies
8% of G 111.56 I. Contractor's Profit (CP)
5% of (G + H + I) 81.58 J. Value Added Tax (VAT)
(G + H + I + J) 1,713.13 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 100.36 b. Skilled Labor
1.00 38.97 311.76 c. Unskilled Labor

481.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 172.00 172.00 a. Cargo Truck (9 - 10 mt)


0.25 91.25 22.81 b. Backhoe (0.80 cu.m.)
0.10 2,450.00 245.00 c. Water Truck/Pump (160
0.25 783.00 195.75 Minor Tools (10% of Labor
48.15
Note: Includes watering fo

683.72 S
1,165.26 C.
D. Output per hour = 1.00000
1,013.27 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

4.18 220.00 919.60 a. Trees (Delivered at Site


0.22 850.00 187.00 b. Fertilizers
0.43 650.00 279.50 c. Bamboo Pole
0.27 *1,800.00 486.00 d. Polyethylene Sheets
4.92 186.44 917.28 e. Tie Wire
0.22 *750.00 165.00
0.33 *350.00 115.50
0.11 *1,200.00 132.00
0.11 *295.00 32.45
0.65 *1,000.00 650.00
194.22

4,078.55
5,091.82 S
9% of G 458.26 G. Direct Unit Cost (E + F)
8% of G 407.35 H. Overhead, Contingencies
5% of (G + H + I) 297.87 I. Contractor's Profit (CP)
(G + H + I + J) 6,255.30 J. Value Added Tax (VAT)
K. Total Unit Cost
RICE ANALYSIS (DUPA)

uding Concrete Post Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 100.36 b. Skilled Labor
1.00 38.97 155.88 c. Unskilled Labor

325.66 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.50 172.00 86.00 a. Cargo Truck (9 - 10 mt)


0.50 91.25 45.63 b. Backhoe (0.80 cu.m.)
0.05 2,450.00 122.50 c. Water Truck/Pump (160
0.25 1,212.00 303.00 Minor Tools (10% of Labor
16.28

573.41 S
899.07 C.
D. Output per hour = 1.00000
214.06 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.33 220.00 72.60 a. Fertilizers


0.018 850.00 15.30 b. Bamboo Pole
0.036 650.00 23.40 c. Polyethylene Sheets
1.00 1,950.00 1,950.00 d. Tie Wire
0.25 700.00 43.75
8.00 40.00 80.00
4.00 40.00 160.00
0.08 47.00 3.76
0.08 68.00 5.44
0.50 28.00 14.00
2.00 21.00 42.00

2,410.25 S
2,624.31 G. Direct Unit Cost (E + F)
9% of G 236.19 H. Overhead, Contingencies
8% of G 209.95 I. Contractor's Profit (CP)
5% of (G + H + I) 153.52 J. Value Added Tax (VAT)
(G + H + I + J) 3,223.97 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 77.94 c. Unskilled Labor

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

1.00 1,212.00 1,212.00 b. Cargo Truck/Delivery Tr


9.88 b. Applicator Machine
c. Kneading Machine
Minor Tools (10 % of Labo

1,221.88 S
1,419.42 C.
D. Output per hour = 25.0000
236.57 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 1,350.00 1,350.00 a. Thermoplastic Paint (W


b. Glass Beads
c. Primer
d. LPG (50 kg.)
e. LPG (12 kg.)
f. Calsumine
Miscellaneous (5% of Mat

1,350.00 S
1,586.57 G. Direct Unit Cost (E + F)
9% of G 142.79 H. Overhead, Contingencies
8% of G 126.93 I. Contractor's Profit (CP)
5% of (G + H + I) 92.81 J. Value Added Tax (VAT)
(G + H + I + J) 1,949.10 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 100.36 b. Skilled Labor
1.00 38.97 155.88 c. Unskilled Labor

325.66 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.50 1,212.00 606.00 b. Cargo Truck/Delivery Tr


32.57 b. Applicator Machine
c. Kneading Machine
Minor Tools (10 % of Labo

638.57 S
964.23 C.
D. Output per hour = 25.0000
192.85 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

14.67 90.00 1,320.30 a. Thermoplastic Paint (Ye


6.67 55.00 366.85 b. Glass Beads
1.60 350.00 560.00 c. Primer
112.36 d. LPG (50 kg.)
e. LPG (12 kg.)
f. Calsumine
Miscellaneous (5% of Mat

2,359.51 S
2,552.35 G. Direct Unit Cost (E + F)
9% of G 229.71 H. Overhead, Contingencies
8% of G 204.19 I. Contractor's Profit (CP)
5% of (G + H + I) 149.31 J. Value Added Tax (VAT)
(G + H + I + J) 3,135.57 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Unskilled Labor
1.00 38.97 77.94

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.10 371.00 37.10 a. Asphalt Kettle/Drum


19.75 Minor Tools (5% of Labor)

56.85 S
254.39 C.
D. Output per hour = 20.0000
14.13 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 15.00 15.00 a. Blown Asphalt


0.58 48.00 27.84 Miscellaneous (5% of Mat
0.39 81.15 31.65
1.49
75.98 S
90.11 G. Direct Unit Cost (E + F)
9% of G 8.11 H. Overhead, Contingencies
8% of G 7.21 I. Contractor's Profit (CP)
5% of (G + H + I) 5.27 J. Value Added Tax (VAT)
(G + H + I + J) 110.70 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Skilled Labor
1.00 38.97 77.94 c. Unskilled Labor

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.50 371.00 185.50 a. Cargo Truck (2 - 5 mt)


19.75 Minor Tools (10 % of Labo

205.25 S
402.79 C.
D. Output per hour = 1.00000
67.13 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

1.00 220.00 220.00 a. Portland Cement


9.25 850.00 7,862.50 b. Sand
0.005 650.00 3.01 c. Gravel
d. Form Lumber, Good - 4
e. 75mm G.I. Pipe
f. G.I. Flat Bar, 1 1/2"x1/8
g. G.I. Bolts w/ Nuts & Wa
h. G.I. Bolts w/ Nuts & Wa
i. Sign Face, 3mm thk. Alu
j. Assorted CWN (1 kg./10
Miscellaneous (0.3% of M

8,085.51 S
8,152.64 G. Direct Unit Cost (E + F)
9% of G 733.74 H. Overhead, Contingencies
8% of G 652.21 I. Contractor's Profit (CP)
5% of (G + H + I) 476.93 J. Value Added Tax (VAT)
(G + H + I + J) 10,015.52 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.50 69.42 104.13 a. Construction Foreman


1.50 50.18 150.54 b. Skilled Labor
1.50 38.97 116.91 c. Unskilled Labor

371.58 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.75 172.00 129.00 a. Cargo Truck (2 - 5 mt)


0.50 219.75 109.88 Minor Tools (10 % of Labo
0.50 351.50 175.75
0.05 2,450.00 122.50
37.16

574.28 S
945.86 C.
D. Output per hour = 1.00000
945.86 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

5.68 220.00 1,249.60 a. Portland Cement


0.30 850.00 255.00 b. Sand
0.60 650.00 390.00 c. Gravel
22.07 40.00 882.80 d. Form Lumber, Good - 4
0.441 47.00 20.73 e. 75mm G.I. Pipe
1.94 350.00 339.50 f. G.I. Flat Bar, 1 1/2"x1/8
28.67 20.00 286.70 g. G.I. Bolts w/ Nuts & Wa
0.29 68.00 19.72 h. G.I. Bolts w/ Nuts & Wa
i. Sign Face, 3mm thk. Alu
j. Assorted CWN (1 kg./10
Miscellaneous (0.2% of M

3,444.05 S
4,389.91 G. Direct Unit Cost (E + F)
9% of G 395.09 H. Overhead, Contingencies
8% of G 351.19 I. Contractor's Profit (CP)
5% of (G + H + I) 256.81 J. Value Added Tax (VAT)
(G + H + I + J) 5,393.00 K. Total Unit Cost
RICE ANALYSIS (DUPA)

ngth 4.24m.) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Unskilled Labor
1.00 38.97 77.94

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

2.00 371.00 742.00 c. Water Truck/Pump (160


19.75 Minor Tools (10% of Labor

761.75 S
959.29 C.
D. Output per hour = 50.0000
959.29 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

5.00 1,550.00 7,750.00 a. Erosion Control Net CG


4.24 3,300.00 13,992.00 (Price includes bamboo pe
3.37 40.00 134.80
656.30
22,533.10 S
23,492.40 G. Direct Unit Cost (E + F)
9% of G 2,114.32 H. Overhead, Contingencies
8% of G 1,879.39 I. Contractor's Profit (CP)
5% of (G + H + I) 1,374.31 J. Value Added Tax (VAT)
(G + H + I + J) 28,860.41 K. Total Unit Cost
RICE ANALYSIS (DUPA)

gle) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Unskilled Labor
1.00 38.97 77.94

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.25 783.00 195.75 c. Water Truck/Pump (160


19.75 Minor Tools (10% of Labor

215.50 S
413.04 C.
D. Output per hour = 50.0000
413.04 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.48 220.00 105.60 a. Erosion Control Net CG


0.025 850.00 21.25 (Price includes bamboo pe
0.050 650.00 32.50
8.00 40.00 80.00
3.10 530.00 1,643.00
2.00 48.00 96.00
12.00 10.00 120.00
1.00 2,800.00 2,800.00
0.08 68.00 5.44

4,903.79 S
5,316.83 G. Direct Unit Cost (E + F)
9% of G 478.52 H. Overhead, Contingencies
8% of G 425.35 I. Contractor's Profit (CP)
5% of (G + H + I) 311.03 J. Value Added Tax (VAT)
(G + H + I + J) 6,531.73 K. Total Unit Cost
RICE ANALYSIS (DUPA)

gle) Item No./Description


Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Unskilled Labor
1.00 38.97 77.94

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.25 783.00 195.75 Minor Tools (10% of Labor


19.75

215.50 S
413.04 C.
D. Output per hour = 15.0000
413.04 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.48 220.00 105.60 a. Coco Fiber Roll (CGR 2


0.025 850.00 21.25 (Price includes nylon rope
0.050 650.00 32.50
8.00 40.00 80.00
3.10 530.00 1,643.00
2.00 48.00 96.00
12.00 10.00 120.00
1.00 4,200.00 4,200.00
0.08 68.00 5.44

6,303.79 S
6,716.83 G. Direct Unit Cost (E + F)
9% of G 604.52 H. Overhead, Contingencies
8% of G 537.35 I. Contractor's Profit (CP)
5% of (G + H + I) 392.93 J. Value Added Tax (VAT)
(G + H + I + J) 8,251.63 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Unskilled Labor
1.00 38.97 77.94

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.25 783.00 195.75 Minor Tools (10% of Labor


19.75

215.50 S
413.04 C.
D. Output per hour = 15.0000
413.04 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.48 220.00 105.60 a. Coco Fiber Roll (CGR 3


0.025 850.00 21.25 (Price includes nylon rope
0.050 650.00 32.50
8.00 40.00 80.00
3.10 530.00 1,643.00
2.00 48.00 96.00
12.00 10.00 120.00
1.00 2,800.00 2,800.00
0.08 68.00 5.44

4,903.79 S
5,316.83 G. Direct Unit Cost (E + F)
9% of G 478.52 H. Overhead, Contingencies
8% of G 425.35 I. Contractor's Profit (CP)
5% of (G + H + I) 311.03 J. Value Added Tax (VAT)
(G + H + I + J) 6,531.73 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1.00 69.42 69.42 a. Construction Foreman


1.00 50.18 50.18 b. Unskilled Labor
1.00 38.97 77.94

197.54 S

No. of Hours Hourly Rate Amount Nam

B. Equipment

0.25 783.00 195.75 a. Hydroseeding Machine


19.75 b. Water Truck/Pump (160
(including maintenance tim

215.50 S
413.04 C.
D. Output per hour = 62.500
413.04 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

0.48 220.00 105.60 a. Grass Cover


0.025 850.00 21.25 (Price includes grass seed
0.050 650.00 32.50 & binding agent for hydros
8.00 40.00 80.00
3.10 530.00 1,643.00
2.00 48.00 96.00
12.00 10.00 120.00
1.00 4,200.00 4,200.00
0.08 68.00 5.44

6,303.79 S
6,716.83 G. Direct Unit Cost (E + F)
9% of G 604.52 H. Overhead, Contingencies
8% of G 537.35 I. Contractor's Profit (CP)
5% of (G + H + I) 392.93 J. Value Added Tax (VAT)
(G + H + I + J) 8,251.63 K. Total Unit Cost

Item No./Description
Unit of Measurement
Output per hour

A. Labor

a. Construction Foreman
b. Unskilled Labor

Nam

B. Equipment

a. Water Truck/Pump (160


Minor Tools (10% of Labor
S
C.
D. Output per hour = 35.0000
E. Direct Unit Cost (C D)

Name

F. Materials

a. Vetiver Grass System


(Price includes cocopeat f

S
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 605(2)c Regulatory Signs (60cm Octagon)


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 783.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

bag 0.48 220.00


cu.m. 0.025 850.00
cu.m. 0.050 650.00
Good - 4 uses bd.ft. 8.00 40.00
m. 3.10 530.00
kg. 2.00 70.78
pc. 12.00 10.00
m thk. Aluminum Sheet pc. 1.00 4,500.00
(1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 605(2)d Regulatory Signs (90cm Octagon)


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 783.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

bag 0.48 220.00


cu.m. 0.025 850.00
cu.m. 0.050 650.00
Good - 4 uses bd.ft. 8.00 40.00
m. 3.10 530.00
kg. 2.00 48.00
pc. 12.00 10.00
m thk. Aluminum Sheet pc. 1.00 7,500.00
(1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 605(3)a Informative Signs (12"x24")


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 783.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

bag 1.320 220.00


cu.m. 0.073 850.00
cu.m. 0.145 650.00
Good - 4 uses bd.ft. 8.00 40.00
m. 3.10 530.00
kg. 2.00 48.00
pc. 12.00 10.00
m thk. Aluminum Sheet pc. 1.00 2,750.00
(1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 605(3)b Informative Signs (12"x48")


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 783.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

bag 1.320 220.00


cu.m. 0.073 850.00
cu.m. 0.145 650.00
Good - 4 uses bd.ft. 8.00 40.00
m. 3.10 530.00
kg. 2.00 48.00
pc. 12.00 10.00
m thk. Aluminum Sheet pc. 1.00 5,450.00
(1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 605(3)c Informative Signs (18"x24")


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 783.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

bag 1.320 220.00


cu.m. 0.073 850.00
cu.m. 0.145 650.00
Good - 4 uses bd.ft. 8.00 40.00
m. 3.10 530.00
kg. 2.00 48.00
pc. 12.00 10.00
m thk. Aluminum Sheet pc. 1.00 3,750.00
(1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 605(3)d Informative Signs (18"x48")


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 783.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

bag 1.320 220.00


cu.m. 0.073 850.00
cu.m. 0.145 650.00
Good - 4 uses bd.ft. 8.00 40.00
m. 3.10 530.00
kg. 2.00 48.00
pc. 12.00 10.00
m thk. Aluminum Sheet pc. 1.00 8,200.00
(1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 606(1) Pavement Marking (Premix Reflectorized)


: sq.m.
: 10.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.05 783.00
of Labor)

Sub - Total for B


Total (A + B)
= 10.00000 sq.m

Name and Specification Unit Quantity Unit Cost

kings (White) L 1.00 450.00


% of above)
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 606(2)a Pavement Markings (Reflectorized Traffic Paint - White)


: sq.m.
: 10.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.05 783.00
0% of Labor)

Sub - Total for B


Total (A + B)
= 10.00000 sq.m

Name and Specification Unit Quantity Unit Cost

Traffic Paint (White) L 1.00 450.00


% of above)
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 606(2)b Pavement Markings (Reflectorized Traffic Paint - Yellow)


: sq.m.
: 10.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.05 783.00
0% of Labor)

Sub - Total for B


Total (A + B)
= 10.00000 sq.m

Name and Specification Unit Quantity Unit Cost

Traffic Paint (Yellow) L 1.00 475.00


% of above)
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 607(1) Reflective Pavement Studs


: ea.
: 10.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 3 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

CP-8 with attachment 1 1.00 201.25


1 0.25 783.00
r (15 - 35 cfm) 1 1.00 205.00
of Labor)

Sub - Total for B


Total (A + B)
= 10.00000 ea

Name and Specification Unit Quantity Unit Cost

d Catcheye Flush Surface pc. 1.00 3,465.00


mm (type depends on the req.)
L 0.012 1,200.00
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 607(2) Reflective Pavement Studs (4" RPM)


: ea.
: 10.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 3 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

CP-8 with attachment 1 1.00 201.25


1 0.25 783.00
r (15 - 35 cfm) 1 1.00 205.00
of Labor)

Sub - Total for B


Total (A + B)
= 10.00000 ea

Name and Specification Unit Quantity Unit Cost

d Catcheye Raised Surface pc. 1.00 3,465.00


mm (type depends on the req.)
L 0.012 1,200.00
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 608(1) Furnishing and Placing Topsoil


: cu.m.
: 1.25

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
2 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

or (5 hp) 1 1.00 123.00


% of Labor)

Sub - Total for B


Total (A + B)
= 1.25 cu.m

Name and Specification Unit Quantity Unit Cost

cu.m. 1.05 490.00


Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 608(2) Placing Topsoil


: cu.m.
: 1.25

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
2 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

or (5 hp) 1 1.00 123.00


% of Labor)

Sub - Total for B


Total (A + B)
= 1.25 cu.m

Name and Specification Unit Quantity Unit Cost


Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 609 Sprigging
: sq.m.
: 35.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
2 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

ump (16000L) 1 0.25 2,450.00


% of Labor)

Sub - Total for B


Total (A + B)
= 35.00000 sq.m

Name and Specification Unit Quantity Unit Cost

sq.m. 1.05 89.00


kg. 0.10 26.00
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 610 Sodding
: sq.m.
: 25.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 8 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

ump (16000L) 1 0.50 2,450.00


% of Labor)

Sub - Total for B


Total (A + B)
= 25.00000 sq.m

Name and Specification Unit Quantity Unit Cost

sq.m. 1.05 89.00


Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 611(1) Trees (Furnishing and Transplanting), 150mm dia. or less


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

9 - 10 mt) 1 1.00 1,212.00


1 1.00 1,537.00
ump (16000L) 1 0.50 2,450.00
% of Labor)

atering for three (3) months

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

ed at Site) pc. 1.00 400.00


kg. 3.00 26.00
pc. 3.00 50.00
sq.m. 3.00 10.00
kg. 0.25 46.67

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 611(2) Trees (Transplanting), 150mm dia. or less


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

9 - 10 mt) 1 1.00 1,212.00


1 1.00 1,537.00
ump (16000L) 1 0.50 2,450.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

kg. 3.00 26.00


pc. 3.00 50.00
sq.m. 3.00 10.00
kg. 0.25 46.67
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 612(1) Reflectorized Thermoplastic Pavement Markings (White)


: sq.m.
: 25.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
2 1.00 50.18
r 6 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

elivery Truck(2 - 5 mt) 1 1.00 783.00


1 1.00 93.75
1 1.00 187.50
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 25.00000 sq.m

Name and Specification Unit Quantity Unit Cost

Paint (White) bag 0.325 1,565.00


bag 0.033 650.00
L 0.120 160.00
cyl. 0.004 3,800.00
cyl. 0.002 735.00
kg. 0.125 3.00
% of Materials)

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)


: sq.m.
: 25.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
2 1.00 50.18
r 6 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

elivery Truck(2 - 5 mt) 1 1.00 783.00


1 1.00 93.75
1 1.00 187.50
% of Labor Cost)

Sub - Total for B


Total (A + B)
= 25.00000 sq.m

Name and Specification Unit Quantity Unit Cost

Paint (Yellow)) bag 0.325 1,780.00


bag 0.033 650.00
L 0.120 175.00
cyl. 0.004 3,800.00
cyl. 0.002 735.00
kg. 0.125 3.00
% of Materials)

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
: kg.
: 20.00
.

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 6 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 1.00 10.00
of Labor)

Sub - Total for B


Total (A + B)
= 20.0000 kg

Name and Specification Unit Quantity Unit Cost

kg. 1.05 250.00


% of Materials)
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 620(a) Chevron Signs (450mmx600mm)


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 783.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

bag 0.48 220.00


cu.m. 0.025 850.00
cu.m. 0.050 650.00
Good - 4 uses bd.ft. 8.00 40.00
m. 3.25 530.00
1/2"x1/8" kg. 5.00 48.00
uts & Washer, 5mm pc. 3.00 10.00
uts & Washer, 2mm pc. 12.00 10.00
m thk. Aluminum Sheet pc. 2.00 3,750.00
(1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00
.3% of Materials)

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 620(b) Chevron Signs (600mmx800mm)


: ea.
: 1.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
1 1.00 50.18
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 783.00
% of Labor)

Sub - Total for B


Total (A + B)
= 1.00000 ea

Name and Specification Unit Quantity Unit Cost

bag 0.48 220.00


cu.m. 0.025 850.00
cu.m. 0.050 650.00
Good - 4 uses bd.ft. 8.00 40.00
m. 3.45 530.00
1/2"x1/8" kg. 5.00 48.00
uts & Washer, 5mm pc. 3.00 10.00
uts & Washer, 2mm pc. 12.00 10.00
m thk. Aluminum Sheet pc. 2.00 7,500.00
(1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00
.2% of Materials)

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 622(1)a Bio-Engineering Solutions (Coco-net)


: sq.m.
: 50.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 8 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

ump (16000L) 1 0.25 2,450.00


% of Labor)

Sub - Total for B


Total (A + B)
= 50.0000 sq.m

Name and Specification Unit Quantity Unit Cost

ol Net CGN 400 w/ 5 % wastage sq.m. 1.05 110.00


amboo pegs)
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 622(1)b Bio-Engineering Solutions (Coco-net)


: sq.m.
: 50.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 8 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

ump (16000L) 1 0.25 2,450.00


% of Labor)

Sub - Total for B


Total (A + B)
= 50.0000 sq.m

Name and Specification Unit Quantity Unit Cost

ol Net CGN 700 w/ 5 % wastage sq.m. 1.05 156.00


amboo pegs)
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 622(2)a Bio-Engineering Solutions (Coco-logs/Fascine)


: m
: 15.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

% of Labor)

Sub - Total for B


Total (A + B)
= 15.0000 m

Name and Specification Unit Quantity Unit Cost

ll (CGR 200) m 1.05 388.00


ylon ropes and live stakes)
`

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 622(2)b Bio-Engineering Solutions (Coco-logs/Fascine)


: m
: 15.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 8 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

% of Labor)

Sub - Total for B


Total (A + B)
= 15.0000 m

Name and Specification Unit Quantity Unit Cost

ll (CGR 300) m 1.05 509.00


ylon ropes and live stakes)
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 622(3)a Bio-Engineering Solutions (Vegetation)


: sq.m.
: 62.50

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 2 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

Machine 1 1.00 952.00


ump (16000L) 1 1.00 2,450.00
nance time)

Sub - Total for B


Total (A + B)
= 62.500 sq.m

Name and Specification Unit Quantity Unit Cost

sq.m. 1.05 45.00


rass seeds, mulch, cocopeat
or hydroseeding)
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: 622(3)b Bio-Engineering Solutions (Vegetation)


: sq.m.
: 35.00

Designation No. of Person No. of Hours Hourly Rate

1 1.00 69.42
r 8 1.00 38.97

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

ump (16000L) 1 0.50 2,450.00


% of Labor)
Sub - Total for B
Total (A + B)
= 35.0000 sq.m

Name and Specification Unit Quantity Unit Cost

sq.m. 1.05 70.00


ocopeat fertilizer)

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
5% of (G + H + I)
(G + H + I + J)
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

195.75
19.75

215.50
413.04

413.04

Amount

105.60
21.25
32.50
80.00
1,643.00
141.56
120.00
4,500.00
5.44

6,649.35
7,062.39
635.62
564.99
413.15
8,676.15
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

195.75
19.75

215.50
413.04

413.04

Amount

105.60
21.25
32.50
80.00
1,643.00
96.00
120.00
7,500.00
5.44

9,603.79
10,016.83
901.52
801.35
585.98
12,305.68
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

195.75
19.75

215.50
413.04

413.04

Amount

290.40
62.05
94.25
80.00
1,643.00
96.00
120.00
2,750.00
5.44

5,141.14
5,554.18
499.88
444.33
324.92
6,823.32
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

195.75
19.75

215.50
413.04

413.04

Amount

290.40
62.05
94.25
80.00
1,643.00
96.00
120.00
5,450.00
5.44

7,841.14
8,254.18
742.88
660.33
482.87
10,140.27
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

195.75
19.75

215.50
413.04

413.04

Amount

290.40
62.05
94.25
80.00
1,643.00
96.00
120.00
3,750.00
5.44

6,141.14
6,554.18
589.88
524.33
383.42
8,051.82
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

195.75
19.75

215.50
413.04

413.04

Amount

290.40
62.05
94.25
80.00
1,643.00
96.00
120.00
8,200.00
5.44

10,591.14
11,004.18
990.38
880.33
643.74
13,518.64
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

39.15
9.88

49.03
246.57

24.66

Amount

450.00
22.50
472.50
497.16
44.74
39.77
29.08
610.76
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

39.15
19.75

58.90
256.44

25.64

Amount

450.00
22.50
472.50
498.14
44.83
39.85
29.14
611.97
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

39.15
19.75

58.90
256.44

25.64

Amount

475.00
23.75
498.75
524.39
47.20
41.95
30.68
644.22
ALYSIS (DUPA)

Amount

69.42
116.91

186.33

Amount

201.25
195.75
205.00
9.32

611.32
797.65

79.76

Amount

3,465.00

14.40
3,479.40
3,559.16
320.32
284.73
208.21
4,372.43
ALYSIS (DUPA)

Amount

69.42
116.91

186.33

Amount

201.25
195.75
205.00
9.32

611.32
797.65

79.76

Amount

3,465.00

14.40
3,479.40
3,559.16
320.32
284.73
208.21
4,372.43
ALYSIS (DUPA)

Amount

69.42
100.36
77.94

247.72

Amount

123.00
24.77

147.77
395.49

316.39

Amount

514.50
514.50
830.89
74.78
66.47
48.61
1,020.75
ALYSIS (DUPA)

Amount

69.42
100.36
77.94

247.72

Amount

123.00
24.77

147.77
395.49

316.39

Amount
0.00
316.39
28.48
25.31
18.51
388.69
ALYSIS (DUPA)

Amount

69.42
100.36
77.94

247.72

Amount

612.50
24.77

637.27
884.99

25.29

Amount

93.45
2.60
96.05
121.34
10.92
9.71
7.10
149.06
ALYSIS (DUPA)

Amount

69.42
311.76

381.18

Amount

1,225.00
38.12

1,263.12
1,644.30

65.77

Amount

93.45
93.45
159.22
14.33
12.74
9.31
195.60
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

1,212.00
1,537.00
1,225.00
19.75

3,993.75
4,191.29

4,191.29

Amount

400.00
78.00
150.00
30.00
11.67

669.67
4,860.96
437.49
388.88
284.37
5,971.69
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

1,212.00
1,537.00
1,225.00
19.75

3,993.75
4,191.29

4,191.29

Amount

78.00
150.00
30.00
11.67
269.67
4,460.96
401.49
356.88
260.97
5,480.29
ALYSIS (DUPA)

Amount

69.42
100.36
233.82

403.60

Amount

783.00
93.75
187.50
40.36

1,104.61
1,508.21

60.33

Amount

508.63
21.45
19.20
15.20
1.47
0.38
28.32

594.64
654.96
58.95
52.40
38.32
804.62
ALYSIS (DUPA)

Amount

69.42
100.36
233.82

403.60

Amount

783.00
93.75
187.50
40.36

1,104.61
1,508.21

60.33

Amount

578.50
21.45
21.00
15.20
1.47
0.38
31.90

669.89
730.22
65.72
58.42
42.72
897.08
ALYSIS (DUPA)

Amount

69.42
233.82

303.24

Amount

10.00
15.16

25.16
328.40

16.42

Amount

262.50
13.13
275.63
292.05
26.28
23.36
17.08
358.78
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

195.75
19.75

215.50
413.04

413.04

Amount

105.60
21.25
32.50
80.00
1,722.50
240.00
30.00
120.00
7,500.00
5.44
29.57

9,886.86
10,299.91
926.99
823.99
602.54
12,653.43
ALYSIS (DUPA)

Amount

69.42
50.18
77.94

197.54

Amount

195.75
19.75

215.50
413.04

413.04

Amount

105.60
21.25
32.50
80.00
1,828.50
240.00
30.00
120.00
15,000.00
5.44
34.93

17,498.22
17,911.26
1,612.01
1,432.90
1,047.81
22,003.98
ALYSIS (DUPA)

Amount

69.42
311.76

381.18

Amount

612.50
38.12

650.62
1,031.80

20.64

Amount

115.50
115.50
136.14
12.25
10.89
7.96
167.24
ALYSIS (DUPA)

Amount

69.42
311.76

381.18

Amount

612.50
38.12

650.62
1,031.80

20.64

Amount

163.80
163.80
184.44
16.60
14.75
10.79
226.58
ALYSIS (DUPA)

Amount

69.42
77.94

147.36

Amount

14.74

14.74
162.10

10.81

Amount

407.40
407.40
418.21
37.64
33.46
24.47
513.77
ALYSIS (DUPA)

Amount

69.42
311.76

381.18

Amount

38.12

38.12
419.30

27.95

Amount

534.45
534.45
562.40
50.62
44.99
32.90
690.91
ALYSIS (DUPA)

Amount

69.42
77.94

147.36

Amount

952.00
2,450.00

3,402.00
3,549.36

56.79

Amount

47.25
47.25
104.04
9.36
8.32
6.09
127.81
ALYSIS (DUPA)

Amount

69.42
311.76

381.18

Amount

1,225.00
38.12
1,263.12
1,644.30

46.98

Amount

73.50

73.50
120.48
10.84
9.64
7.05
148.01
ITEM NO.

PART C
100(1)
100(2)a
100(2)b
100(3)a
100(3)b
101(1)
101(2)
101(2)
101(2)
101(2)
101(2)a
101(2)b
101(2)c
101(2)d
101(2)e
101(2)f
101(2)g
101(3)a.1
101(3)a.2
101(3)b
101(3)c
101(4)a
101(4)b
102(1)
102(2)a
102(2)b
102(3)a
102(3)b
102(3)c
102(3)d
102(4)
103(1)a
103(1)b
103(1)c
103(2)a
103(2)b
103(2)c
103(3)
103(4)
103(5)a
ITEM NO.
103(5)b
103(6)
104(1)a
104(1)b
ITEM NO.
104(2)
104(3)
104(4)
105(1)
105(2)
105(3)
PART D
200
200(1)
201
201(1)
202
203
204
205
206
PART E
300(1)
300(2)
301(1)
301(2)
302(1)
302(2)
303(1)
303(2)
303(3)
303(4)
304(1)
304(2)
304(3)
304(4)
304(5)
305(1)
305(2)
305(3)
305(4)
306(a)
306(b)
306(1)
306(2)
307
308(a)
ITEM NO.
308(b)
309
310(a.1)
ITEM NO.
310(a.2)
310(a.3)
310(b.1)
310(b.2)
310(b.3)
311(1)a.1
311(1)a.2
311(1)a.3
311(1)a.4
311(1)a.5
311(1)a.6
311(1)b.1
311(1)b.2
311(1)b.3
311(1)b.4
311(1)c
311(2)
PART G
404
405
500(1)a
500(1)b
500(1)c
500(1)d
500(1)e
500(1)f
501(1)
501(2)
501(3)
502
502(4)
502(5)
502(6)
503(a)
503(b)
504(1)a
504(1)b
504(1)c
504(1)d
504(1)e
504(2)a
504(2)b
ITEM NO.
504(2)c
504(2)d
504(2)e
504(3)a
504(3)b
504(3)c
504(3)d
504(3)e
504(3)f
504(4)
505(1)
505(2)
505(3)
505(4)
505(5)
505(6)
505(7)
505(8)
505(9)
506
507
508
509(a)
509(b.1)
509(b.2)
509(c)
510(1)
510(2)
511(1)
511(2)
511(3)
PART H
600(1)
600(2)
600(3)
600(4)
600(5)
600(6)
601(a)
601(b)
602(1)a
ITEM NO.
602(1)b
602(2)a
602(2)b
602(3)a
602(3)b
602(4)
603(1)
603(3)a
603(3)b
603(4)
604(1)
604(2)
604(3)
604(4)
605(1)a
605(1)b
605(2)a
605(2)b
605(2)c
605(2)d
605(3)a
605(3)b
605(3)c
605(3)d
606(1)
606(2)a
606(2)b
607(1)
607(2)
608(1)
608(2)
609
610
611(1)
611(2)
612(1)
612(2)
613
620(a)
620(b)
622(1)a
ITEM NO.
622(1)b
622(2)a
622(2)b
622(3)a
622(3)b
PART J
SPL 2(a)
SPL 2(b)
SPL 3(a)
SPL 3(b)
DESCRIPTION

EARTHWORKS
Clearing and Grubbing (with Stripping)
Individual Removal of Trees (small a,150-300mm )
Individual Removal of Trees (small b, 301-500mm )
Individual Removal of Trees (large a, 501-750mm )
Individual Removal of Trees (large b, 751-900mm )
Removal of Structures and Obstruction (other than concrete)
Removal of Concrete Bridge Structures
Removal of Steel Bridge Structures
Removal of Stone Masonry Lined Drainage Structures
Removal of Concrete Drainage Structures
Removal of RCPC (24" dia.) - 610mm
Removal of RCPC (30" dia.) - 760mm
Removal of RCPC (36" dia.) - 910mm
Removal of RCPC (42" dia.) - 1070mm
Removal of RCPC (48" dia.) - 1220mm
Removal of RCPC (60" dia.) - 1520mm
Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm ), L = 10 ft.
Removal of Existing Concrete Pavement (0.23m thk.)
Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section))
Removal of Existing Asphalt Pavement (100mm thk.)
Removal of Sidewalk
Removal of Curb
Removal of Existing Curbs & Gutter
Roadway Excavation (Unsuitable)
Roadway Excavation (Surplus Common)
Roadway Excavation (Surplus Common) - w/ Backhoe
Roadway Excavation (Surplus Soft Rock) - w/ Backhoe
Roadway Excavation (Surplus Soft Rock)
Roadway Excavation (Surplus Hard Rock) - Blasting
Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation)
Roadway Excavation (Unclassified)
Structure Excavation (Common Soil)
Structure Excavation (Soft Rock)
Structure Excavation (Solid Rock)
Bridge Excavation (Common Soil)
Bridge Excavation (Soft Rock)
Bridge Excavation (Solid Rock)
Foundation Fill
Excavation ordered below Plan Elevation
Shoring
DESCRIPTION
Cribbing/Cofferdamming
Pipe Culvert and Drain Excavation
Embankment from Borrow
Embankment from Roadway Excavation
DESCRIPTION
Selected Borrow for topping, case 1
Selected Borrow for topping, case 2
Earth Berm
Subgrade Preparation (Common Material)
Subgrade Preparation (Existing Pavement)
Subgrade Preparation (Unsuitable Material)
SUBBASE AND BASE COURSE
Aggregate Subbase Course
Aggregate Subbase Course (for intermittent Reblocking)
Aggregate Base Course
Aggregate Base Course (for Reblocking)
Crushed Aggregate Base Course
Lime Stabilized Road Mix Base Course
Portland Cement Stabilized Road Mix Base Course
Asphalt Stabilized Road Mix Base Course
Portland Cement Treated Plant Mix Base Course
SURFACE COURSE
Gravel Surface Course (Uncrushed)
Crushed Aggregate Surface Course
Bituminous Prime Coat (MC Cut-back Asphalt)
Bituminous Prime Coat (RC Cut-back Asphalt)
Bituminous Tack Coat (RC Cut-back Asphalt)
Bituminous Tack Coat (Emulsified Asphalt)
Bituminous Seal Coat (Cover Aggregate)
Bituminous Seal Coat (MC Cut-back Asphalt)
Bituminous Seal Coat (RC Cut-back Asphalt)
Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
Bituminous Surface Treatment (Aggregate Grading)
Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
Bituminous Surface Treatment (MC Cut-back Asphalt)
Bituminous Surface Treatment (RC Cut-back Asphalt)
Bituminous Surface Treatment (Emulsified Asphalt)
Bituminous Penetration Macadam Pavement (Aggregates)
Bituminous Penetration Macadam Pavement (Asphalt Cement)
Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt)
Bituminous Penetration Macadam Pavement (Emulsified Asphalt)
Bituminous Road Mix Surface Course (MC Cut-back Asphalt)
Bituminous Road Mix Surface Course (Emulsified Asphalt)
Aggregate for Bituminous Road Mix Surface Course
Bituminous Material for Bituminous Road Mix Surface Course
Bituminous Plant Mix Surface Course-General - 50mm thk.
Cold Asphalt Plant Mix (Emulsified Asphalt) - 50mm thk.
DESCRIPTION
Cold Asphalt Plant Mix (Cut-back Asphalt) - 50mm thk.
Bituminous Plant Mix (Stockpile Maintenance Mixture)
Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Delivered)
DESCRIPTION
Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Delivered)
Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Delivered)
Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Batching Plant)
Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Batching Plant)
Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Batching Plant)
PCC Pavement (Plain) - Conventional Method, 150mm thk.
PCC Pavement (Plain) - Conventional Method, 200mm thk.
PCC Pavement (Plain) - Conventional Method, 230mm thk.
PCC Pavement (Plain) - Conventional Method, 250mm thk.
PCC Pavement (Plain) - Conventional Method, 280mm thk.
PCC Pavement (Plain) - Conventional Method, 300mm thk.
PCC Pavement (Plain) - Using Concrete Paver, 230mm thk.
PCC Pavement (Plain) - Using Concrete Paver, 250mm thk.
PCC Pavement (Plain) - Using Concrete Paver, 280mm thk.
PCC Pavement (Plain) - Using Concrete Paver, 300mm thk.
PCC Pavement (Plain) - Conventional Method, 150mm thk. (Using One Bagger Mixer)
PCC Pavement (Reinforced), 230mm thk.
DRAINAGE AND SLOPE PROTECTION STRUCTURES
Reinforcing Steel Bar, Grade 40 (Minor Structures)
Structural Concrete Class A (Minor Structures)
Pipe Culverts, 610mm dia. (24" )
Pipe Culverts, 760mm dia. (30" )
Pipe Culverts, 910mm dia. (36" )
Pipe Culverts, 1070mm dia. (42" )
Pipe Culverts, 1220mm dia. (48" )
Pipe Culverts, 1520mm dia. (60" )
Underdrain
Blind drain
Granular Backfill filter material for Underdrains
Manhole/Catch Basin/Inlet
Concrete Covers
Metal Frames and Gratings
Metal Frames and Covers (Circular)
Drainage Steel Grating w/ Frame (675mm x 975mm Sump Grating)
Drainage Steel Grating w/ Frame (715mm x 2000mm Trench Grating)
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia.) - 610mm
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm
Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm
Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm
Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm
DESCRIPTION
Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm
Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm
Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm
Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
Cleaning Culvert Pipe in place (760mm dia.) - Half Silted
Cleaning Culvert Pipe in place (910mm dia.) - Half Silted
Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted
Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted
Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted
Reconditioning Drainage Structures
Riprap, Class A
Riprap, Class B
Riprap, Class C
Riprap, Class D
Grouted Riprap, Class A
Grouted Riprap, Class B
Grouted Riprap, Class C
Grouted Riprap, Class D
Filter Layer of Granular Material
Stone Masonry
Rubble Concrete
Hand-Laid Rock Embankment
Sheet Piles (Timber)
Sheet Piles (Steel) - Slope Protection
Sheet Piles (Steel) - Cofferdamming
Sheet Piles (Concrete), furnished and driven
Bed Course Granular Material
Concrete Slope Protection
Gabions
Mattresses
Filter Cloth
MISCELLANEOUS STRUCTURES
Concrete Curb (Cast in place)
Concrete Gutter (Cast in place)
Concrete Curb and Gutter, Type A (Cast in place) - National Road
Concrete Curb (Precast)
Concrete Gutter (Precast)
Concrete Curb & Gutter (Precast)
Sidewalk (100mm thk.)
Sidewalk - Using One Bagger Mixer, (100mm thk.)
Right-of-Way Monuments (Cast in place)
DESCRIPTION
Right-of-Way Monuments (Precast)
Maintenance Marker Posts (Cast in place)
Maintenance Marker Posts (Precast)
Kilometer Post (Cast in Place)
Kilometer Post (Precast)
Guide Post
Cable Wire Guardrail
Metal Guardrail (Metal Beam) including Concrete Post
Metal Beam End Piece
Guardrail (Timber)
Fencing (Barbed Wire)
Fencing (Chain Link Fence Fabric)
Fencing (Posts)
Fencing (Gates) - (Height = 3m & length = 4.24m)
Danger/Warning Signs (60cm Triangle)
Danger/Warning Signs (90cm Triangle)
Regulatory Signs (60cm Triangle)
Regulatory Signs (90cm Triangle)
Regulatory Signs (60cm Octagon)
Regulatory Signs (90cm Octagon)
Informative Signs (12" x 24")
Informative Signs (12" x 48")
Informative Signs (18" x 24")
Informative Signs (18" x 48")
Pavement Markings (Premix Reflectorized)
Pavement Markings (Reflectorized Thermoplastic), White
Pavement Markings (Reflectorized Thermoplastic), Yellow
Reflectorized Pavement Studs (Flush Type)
Reflectorized Pavement Studs (Raised Profile Type)
Furnishing and Placing Topsoil
Placing Topsoil
Sprigging
Sodding
Trees (Furnishing and Transplanting), 150mm dia. or less
Trees (Transplanting), 150mm dia. or less
Reflectorized Thermoplastic Pavement Markings (White)
Reflectorized Thermoplastic Pavement Markings (Yellow)
Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
Chevron Signs (450mmx600mm)
Chevron Signs (600mmx800mm)
Bio-Engineering Solutions (Coco-net), CGN 400
DESCRIPTION
Bio-Engineering Solutions (Coco-net), CGN 700
Bio-Engineering Solutions (Coco-logs/Fascine), CGR 200
Bio-Engineering Solutions (Coco-logs/Fascine), CGR 300
Bio-Engineering Solutions (Vegetation), Hydroseeding
Bio-Engineering Solutions (Vegetation), Vetiver Grass System
SPECIAL ITEMS
Crack and Seat - Using Backhoe
Crack and Seat - Using Arrow Master
Tree Planting - With Tree Guard
Tree Planting
DETAILED UNIT PRICE ANALYSIS

Item No./Description : SPL 2(a) Crack and Seat


Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Laborer 1
c. Laborer 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1


b. Vibratory Roller (10 m.t.), SP56 1
c. Water Truck (1000 gal.) 1

Sub - Total for B


C. Total (A + B)
D. Output per hour = 35.0000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS

Item No./Description : SPL 2(b) Crack and Seat


Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person

A. Labor

a. Construction Foreman 1
b. Skilled Laborer 1
c. Laborer 2

Sub - Total for A

Name and Capacity No of Units

B. Equipment

a. Arrow Master D 500 1


(Additional 35% for Oil and Lubricants)
b. Vibratory Roller (10 m.t.), SP56 1
c. Water Truck (1000 gal.) 1
Sub - Total for B
C. Total (A + B)
D. Output per hour = 30.0000 sq.m
E. Direct Unit Cost (C D)

Name and Specification Unit

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM)
I. Contractor's Profit (CP)
J. Value Added Tax (VAT)
K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1 109.19 109.19 a. Construction Foreman


1 79.70 79.70 b. Laborer
1 61.44 122.88

311.77 S

No. of Hours Rental Rate Amount Nam

B. Equipment

1.00 2,074.95 2,074.95 a. Cargo Truck (5 T)


0.75 1,507.00 1,130.25 b. Water Truck (1000 gal.)
0.10 1,065.00 106.50 Minor Tools (10% of Labor

3,311.70 S
3,623.47 C.
D. Output per hour = 60.0000
103.53 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

a. Saplings
b. Coco Lumber
c. Assorted CWN (1 kg./10
d. Fertilizers
0.00 S
103.53 G. Direct Unit Cost (E + F)
9% of G 9.32 H. Overhead, Contingencies
8% of G 8.28 I. Contractor's Profit (CP)
12% of (G + H + I) 14.54 J. Value Added Tax (VAT)
(G + H + I + J) 135.66 K. Total Unit Cost
RICE ANALYSIS (DUPA)

Item No./Description
Unit of Measurement
Output per hour

No. of Hours Hourly Rate Amount

A. Labor

1 109.19 109.19 a. Construction Foreman


1 79.70 79.70 b. Laborer
1 61.44 122.88

311.77 S

No. of Hours Rental Rate Amount Nam

B. Equipment

1.00 1,485.84 1,485.84 a. Cargo Truck (5 T)


b. Water Truck (1000 gal.)
0.75 1,507.00 1,130.25 Minor Tools (10% of Labor
0.10 1,065.00 106.50
2,722.59 S
3,034.36 C.
D. Output per hour = 60.0000
101.15 E. Direct Unit Cost (C D)

Quantity Unit Cost Amount Name

F. Materials

a. Saplings
b. Fertilizers

0.00 S
101.15 G. Direct Unit Cost (E + F)
9% of G 9.10 H. Overhead, Contingencies
8% of G 8.09 I. Contractor's Profit (CP)
12% of (G + H + I) 14.20 J. Value Added Tax (VAT)
(G + H + I + J) 132.54 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

: SPL 3(a) Tree Planting


: pc.
: 60.00

Designation No. of Person No. of Hours Hourly Rate

1 1 109.19
10 1 61.44

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 712.00
1000 gal.) 1 0.25 1,065.00
% of Labor)

Sub - Total for B


Total (A + B)
= 60.0000 pc

Name and Specification Unit Quantity Unit Cost

pc. 1 50.00
bd.ft. 8 20.00
(1 kg./100 bd.ft.) kg. 0.08 68.00
kg. 0.10 50.00
Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
12% of (G + H + I)
(G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

: SPL 3(b) Tree Planting


: pc.
: 60.00

Designation No. of Person No. of Hours Hourly Rate

1 1 109.19
10 1 61.44

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

1 0.25 712.00
1000 gal.) 1 0.25 1,065.00
% of Labor)
Sub - Total for B
Total (A + B)
= 60.0000 pc

Name and Specification Unit Quantity Unit Cost

pc. 1 50.00
kg. 0.10 26.00

Sub - Total for F

ngencies & Miscellaneous (OCM) 9% of G


8% of G
12% of (G + H + I)
(G + H + I + J)
ALYSIS (DUPA)

Amount

109.19
614.40

723.59

Amount

178.00
266.25
72.36

516.61
1,240.20

20.67

Amount

50.00
160.00
5.44
5.00
220.44
241.11
21.70
19.29
33.85
315.95
ALYSIS (DUPA)

Amount

109.19
614.40

723.59

Amount

178.00
266.25
72.36
516.61
1,240.20

20.67

Amount

50.00
2.60

52.60
73.27
6.59
5.86
10.29
96.01

You might also like