For all planners are keep asking about S-Curve

the Artical has been written By: David Garland

Introduction

The first time most project managers become aware of the existence of S-curves is when they are
requested by the client or senior management to include one in their next progress report. The
following explains what the mysterious S-curve is, why it is an important project management
tool, and how to generate one.

Editor's Note:

The S-curve is a powerful project management control tool. Why it is the shape it is, how to use it
and "Max's Rule of Thumb" for drawing it as a part of the project planning activity are all
described in Chapter 10 of A Management Framework for Project, Program and Portfolio
Integration. You can also find more information on this web site by entering "S-curve" or
"Resource loading" into the site search engine field.

What is an S-curve?
An S-curve is defined as:

"A display of cumulative costs, labor hours or other quantities plotted against time. The name
derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the
middle, which is typical of most projects. The beginning represents a slow, deliberate but
accelerating start, while the end represents a deceleration as the work runs out."[1]
Types of S-curves
There are a variety of S-curves that are applicable to project management applications, including:

Man Hours versus Time S-curve


Costs versus Time S-curve
Baseline S-curve
Actual S-curve
Target S-curve
Value and Percentage S-curves

Each of these is described in the following pages.

Resource Consumption
Man Hours versus Time S-curve
The Man Hours versus Time S-curve is appropriate for projects that are labor intensive. It shows
cumulative man hours expended over time for the duration of the project. As man-hours are a
product of manpower and working hours, these may be adjusted together or individually in an
attempt to keep the project on schedule. Projects may require additional man-hours to finish on
time due to low productivity, delays and disruptions, rework, variations, etc.

By: David Garland

What is the S-Curve, and how do calculate the work progress..

Introduction
The first time most project managers become aware of the existence of S-curves is when they are
requested by the client or senior management to include one in their next progress report. The
following explains what the mysterious S-curve is, why it is an important project management
tool, and how to generate one.

Editor's Note:

The S-curve is a powerful project management control tool. Why it is the shape it is, how to use it
and "Max's Rule of Thumb" for drawing it as a part of the project planning activity are all
described in Chapter 10 of A Management Framework for Project, Program and Portfolio
Integration. You can also find more information on this web site by entering "S-curve" or
"Resource loading" into the site search engine field.

What is an S-curve?
An S-curve is defined as:

"A display of cumulative costs, labor hours or other quantities plotted against time. The name
derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the
middle, which is typical of most projects. The beginning represents a slow, deliberate but
accelerating start, while the end represents a deceleration as the work runs out."[1]
Types of S-curves
There are a variety of S-curves that are applicable to project management applications, including:

Man Hours versus Time S-curve


Costs versus Time S-curve
Baseline S-curve
Actual S-curve
Target S-curve
Value and Percentage S-curves

Each of these is described in the following pages.

Resource Consumption
Man Hours versus Time S-curve
The Man Hours versus Time S-curve is appropriate for projects that are labor intensive. It shows
cumulative man hours expended over time for the duration of the project. As man-hours are a
product of manpower and working hours, these may be adjusted together or individually in an
attempt to keep the project on schedule. Projects may require additional man-hours to finish on
time due to low productivity, delays and disruptions, rework, variations, etc.

Figure 1: Man Hours versus Time S-curve


Costs versus Time S-curve
The Costs versus Time S-curve is appropriate for projects that contain labor and non-labor (e.g.
material supply / hire / subcontract) tasks. It shows cumulative costs expended over time for the
duration of the project, and may be used to assist in the calculation of the project's cash flow,
and cost to complete.
Figure 2: Costs versus Time S-curve
Progress Tracking
Baseline S-curve
Prior to project commencement, a schedule is prepared outlining the proposed allocation of
resources and the timing of tasks necessary to complete the project within a set time frame and
budget. This schedule is referred to as the Baseline Schedule. From this schedule, a Baseline S-
curve is generated. This S-curve reflects the planned progress of the project. If the project
requirements change prior to commencement (e.g. change of scope, delayed start), the Baseline
Schedule may require revision to reflect the changed requirements.

Figure 3: Baseline S-curve


Target S-curve
Following project commencement, modification of the Baseline Schedule is usually required.
Changes are continually made to the Production Schedule (which is originally the same as the
Baseline Schedule). The production schedule reflects the actual progress of the project to date,
and any revisions made to tasks yet to commence or not yet completed. From this schedule, a
Target S-curve may be generated. This S-curve reflects the ideal progress of the project if all
tasks are completed as currently scheduled. In an ideal world, the Target S-curve will meet the
Baseline S-curve at the end of the project (On Time, On Budget) or finish below and to the left of
the Baseline S-curve (Early, Under Budget). In reality, it is not uncommon for the Target S-curve
to finish above and to the right of the Baseline S-curve (Late, Over Budget).

Figure 4: Target S-curve


Actual S-curve
The production schedule is updated on a regular basis throughout the duration of the project.
These updates include the revision of percentage complete for each task to date. Using this
information, an Actual S-curve may be generated. This S-curve reflects the actual progress of the
project to date, and may be compared with the Baseline and Target S-curves to determine how
the project is progressing. During the project, the Actual S-curve will terminate at the Cut Off
Date. This is the date the Production Schedule was last updated. At the completion of the project,
the Actual S-curve will meet the Target S-curve.

Figure 5: Actual S-curve


Value and Percentage S-curves
S-curves may be graphed as absolute values (i.e. Man Hours or Costs) versus Time, or as
percentage values versus Time. Value S-curves are useful for determining Man Hours or Costs
expended to date, and Man Hours or Costs to complete. Percentage S-curves are useful for
calculating the project's actual percentage complete against target and baseline percentage
complete, and for calculating the project's percentage growth (or contraction).

Using S-curves
Why Use an S-curve?
S-curves are an important project management tool. They allow the progress of a project to be
tracked visually over time, and form a historical record of what has happened to date. Analyses of
S-curves allow project managers to quickly identify project growth, slippage, and potential
problems that could adversely impact the project if no remedial action is taken.

Determining Growth
Comparison of the Baseline and Target S-curves quickly reveals if the project has grown (Target S-
curve finishes above Baseline S-curve) or contracted (Target S-curve finishes below Baseline S-
curve) in scope. A change in the project's scopes implies a re-allocation of resources (increase or
decrease), and the very possible requirement to raise contract variations. If the resources are
fixed, then the duration of the project will increase (finish later) or decrease (finish earlier),
possibly leading to the need to submit an extension of time claim.

Figure 6: Calculating Project Growth using S-curves


Determining Slippage
Slippage is defined as:

"The amount of time a task has been delayed from its original baseline schedule. The slippage is
the difference between the scheduled start or finish date for a task and the baseline start or finish
date. Slippage can occur when a baseline plan is set and the actual dates subsequently entered
for tasks are later than the baseline dates or the actual durations are longer than the baseline
schedule durations".[2]

Comparison of the Baseline S-curve and Target S-curve quickly reveals any project slippage (i.e.
the Target S-curve finishes to the right of the Baseline S-curve). Additional resources will need to
be allocated or additional hours worked in order to eliminate (or at least reduce) the slippage. An
extension of time claim may need to be submitted if the slippage cannot be eliminated or
reduced to an acceptable level.

Figure 7: Calculating Project Slippage using S-curves


Determining Progress
Comparison of the Target S-curve and Actual S-curve reveals the progress of the project over
time. In most cases, the Actual S-curve will sit below the Target S-curve for the majority of the
project (due to many factors, including delays in updating the production schedule). Only towards
the end of the project will the curves converge and finally meet. The Actual S-curve can never
finish above the Target S-curve. If the Actual S-curve sits above the Target S-curve at the Cut Off
Date, the Production Schedule should be examined to determine if the project is truly ahead of
schedule, or if the Production Schedule contains unrealistic percentage complete values for
ongoing tasks.

Figure 8: Calculating Project Progress using S-curves


Generating S-curves
Project Benchmarks
Percentage S-curves may be used to calculate important project benchmarks on an ongoing
basis, including:

Project percentage growth (Target and Baseline S-curves)


Project percentage slippage (Target and Baseline S-curves)
Actual percentage complete against Target percentage complete to date
Actual percentage complete against Baseline percentage complete to date

How is an S-curve Generated?


To generate a Baseline S-curve, a Baseline Schedule is required.
The Baseline Schedules should contain the following information for each task:

Baseline Start Date, Finish Date


Baseline Man Hours and/or Costs

To generate Actual and Target S-curves, a Production Schedule is required.


The Production Schedules should contain the following information for each task:

Actual Start Date, Finish Date


Actual Man Hours and/or Costs
Actual Percentage Complete

Worked Example
To better understand how S-curves are generated, consider a simple project comprising three
tasks.
A Baseline Schedule prepared using MS Project for this project is shown below.

Figure 9: Sample Baseline Schedule


Baseline Man Hours versus Time S-curve
To generate a Baseline Man Hours versus Time S-curve, two sets of calculations are performed.
The first set of calculations is performed for each task in the Baseline Schedule.

1. Calculate the duration in days for each task


i.e. Baseline Duration = Baseline Finish Date - Baseline Start Date + 1
2. Calculate Man Hours per day for each task
i.e. Baseline MHs per Day = Baseline Man Hours / Baseline Duration
These calculations are shown in the following table.

Figure 10: Baseline S-curve Calculation 1 of 2


The second set of calculations is performed for each day in the Baseline Schedule.

1. Calculate the total Man Hours per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours per Day for all tasks.

These calculations are shown in the following table.

Figure 11: Baseline S-curve Calculation 2 of 2


The S-curve is constructed by assigning the Dates to the X Axis, and the YTD values to the Y Axis.
The resulting Baseline Man Hours versus Time S-curve is shown below.

Figure 12: Baseline Man Hours versus Time S-curv


Actual versus Target
Target Man Hours versus Time S-curve
To generate the Actual and Target S-curves, a Production Schedule is required. A Production
Schedule for this project is shown below.

Figure 13: Production Schedule


To generate a Target Man Hours versus Time S-curve, two sets of calculations are necessary. The
first set of calculations is performed for each task in the Production Schedule.

1. Calculate the duration in days for each task


i.e. Duration = Finish Date - Start Date + 1
2. Calculate Man Hours per day for each task
i.e. MHs per Day = Man Hours / Duration

These calculations are shown in the following table.

Figure 14: Target S-curve Calculation 1 of 2


The second set of calculations is performed for each day in the Production Schedule.

1. Calculate the total Man Hours per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours per Day for all tasks.

These calculations are shown in the following table:


Figure 15: Target S-curve Calculation 2 of 2
The resulting Target Man Hours versus Time S-curve is shown below.

Figure 16: Target Man Hours versus Time S-curve


Actual Man Hours versus Time S-curve
To generate an Actual Man Hours versus Time S-curve, two sets of calculations are performed, but
before these calculations may be performed, the Cut Off Date needs to be defined. This is the
date the Production Schedule was last updated. For this example a Cut Off Date of 3rd November
2008 will be used.

The first set of calculations is performed for each task in the Production Schedule.

1. Determine the Task Status: Complete, Ongoing, Not Started.


Complete: Tasks that have a Finish Date prior to the Cut Off Date.
Ongoing: Tasks that have commenced and have a Finish Date on or after the Cut Off Date.
Not Started: Tasks that have a Start Date after the Cut Off Date.
2. Calculate the Duration to Date based on the Task Status.
Complete: Duration To Date = Finish Date - Start Date + 1
Ongoing: Duration To Date = Cut Off Date - Start Date + 1
Not Started: Duration To Date = 0.
3. Calculate Man Hours to Date for Complete and Ongoing Tasks.
i.e. Man Hours to Date = Man Hours x % Complete / Duration to Date.

These calculations are shown in the following table.

Figure 17: Actual S-curve Calculation 1 of 2


The second set of calculations is performed for each day in the Production Schedule up to the Cut
Off Date.

1. Calculate the total Man Hours to Date per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours to Date per Day for all tasks.

These calculations are shown in the following table.

Figure 18: Actual S-curve Calculation 2 of 2


The resulting Actual Man Hours versus Time S-curve is shown below.

Figure 19: Actual Man Hours versus Time S-curve


The Baseline, Actual, and Target S-curves are usually combined, as shown below.
Figure 20: Man Hours versus Time S-curves
Analysis

S-curve Analysis

Initial examination of the S-curves generated above reveal the following about the status of the
project.

The project has grown in scope. (The Target S-curve finishes above the Baseline S-curve)
The project has slipped. (The Target S-curve finishes to the right of the Baseline S-curve)
The project is behind schedule. (The Actual S-curve sits below the Target S-curve at the Cut
Off Date)

Project Growth

Analysis of the Baseline and Target S-curve data reveals the project has grown in scope by 12
man-hours, or 14.29%.

i.e. Growth = Target MHs - Baseline MHs = 96 - 84 = 12


i.e. Growth % = (Target MHs / Baseline MHs - 1) x 100% = (96 / 84 - 1) x 100% = 14.29%

Project Slippage

Analysis of the Baseline and Target S-curve data reveals the project has slipped by 1 day, or
20.00%.

i.e. Slippage = Target Duration - Baseline Duration = 6 - 5 = 1


i.e. Slippage % = (Target Duration / Baseline Duration - 1) x 100% = (6 / 5 - 1) x 100% =
20.00%

Project Progress

According to MS Project, based on the Production Schedule the project is 50% complete. MS
Project calculates percentage complete based on durations, and does not take into account man-
hours assigned to each task. Analysis of the Actual and Target S-curve data reveals the project is
53.13% complete as of the Cut Off Date, while the project should be 59.38% complete.

i.e. Actual % Complete = (Actual YTD Man Hours @ Cut Off Date / Target Man Hours) x
100% = (51 / 96) x 100% = 53.13%
i.e. Target % Complete = (Target YTD Man Hours @ Cut Off Date / Target Man Hours) x
100% = (57 / 96) x 100% = 59.38%

Conclusion
Project status
The project will finish late and over budget compared to the Baseline Schedule. Progress to date
(i.e. the Cut Off Date) is behind schedule compared to the Production Schedule. Detailed analysis
of the project is required to determine why the project will be completed late and over budget.
Project growth and/or slippage may be due to a number of factors, including underestimation of
effort in the Baseline Schedule, low productivity, rework, variations (approved or not), etc.

In this example, variations may need to be raised to account for the extra man hours expended,
and an extension of time claim raised for the later than planned completion. The Production
Schedule may need review to ensure tasks have been updated accurately (especially with respect
to true percentage complete values), and ongoing and future tasks may require revising.

Generating S-curves
Some software scheduling packages automatically generate S-curves. On the other hand, some
(including MS Project) do not. In this case, a third party software application is required to process
the Baseline and Production Schedule data to generate the required S-curves.

Midori Media's myPM SCG S-curve Generator is an MS Windows application that integrates with
MS Excel to generate the various types of S-curves discussed above. MS Project users will need to
export their schedule data to an MS Excel file (easily accomplished using MS Project's File Save As
option). myPM SCG processes the resulting export file, and creates an MS Excel Output file
containing the required S-curves. These may be copy-pasted to MS Word for inclusion in Project
Progress Reports.

The value of S-curves


The S-curve is an important but often overlooked and misunderstood project management tool. A
variety of S-curves exist, the most common being Man Hours versus Time, and Costs versus
Time. By creating a Baseline Schedule, a Baseline S-curve can be generated. Baseline S-curves
provide a basis on which to compare a project's actual status to its planned status. They may also
assist in the planning of manpower and financial resources required to complete the project.

A Production Schedule allows Actual and Target S-curves to be generated. These allow the
progress of a project to be monitored, and quickly reveal any divergence from the Baseline
Schedule. S-curves may also be used to determine project growth, slippage, and progress to date.

Figure 1: Man Hours versus Time S-curve


Costs versus Time S-curve
The Costs versus Time S-curve is appropriate for projects that contain labor and non-labor (e.g.
material supply / hire / subcontract) tasks. It shows cumulative costs expended over time for the
duration of the project, and may be used to assist in the calculation of the project's cash flow,
and cost to complete.

Figure 2: Costs versus Time S-curve


Progress Tracking
Baseline S-curve
Prior to project commencement, a schedule is prepared outlining the proposed allocation of
resources and the timing of tasks necessary to complete the project within a set time frame and
budget. This schedule is referred to as the Baseline Schedule. From this schedule, a Baseline S-
curve is generated. This S-curve reflects the planned progress of the project. If the project
requirements change prior to commencement (e.g. change of scope, delayed start), the Baseline
Schedule may require revision to reflect the changed requirements.
Figure 3: Baseline S-curve
Target S-curve
Following project commencement, modification of the Baseline Schedule is usually required.
Changes are continually made to the Production Schedule (which is originally the same as the
Baseline Schedule). The production schedule reflects the actual progress of the project to date,
and any revisions made to tasks yet to commence or not yet completed. From this schedule, a
Target S-curve may be generated. This S-curve reflects the ideal progress of the project if all
tasks are completed as currently scheduled. In an ideal world, the Target S-curve will meet the
Baseline S-curve at the end of the project (On Time, On Budget) or finish below and to the left of
the Baseline S-curve (Early, Under Budget). In reality, it is not uncommon for the Target S-curve
to finish above and to the right of the Baseline S-curve (Late, Over Budget).

Figure 4: Target S-curve


Actual S-curve
The production schedule is updated on a regular basis throughout the duration of the project.
These updates include the revision of percentage complete for each task to date. Using this
information, an Actual S-curve may be generated. This S-curve reflects the actual progress of the
project to date, and may be compared with the Baseline and Target S-curves to determine how
the project is progressing. During the project, the Actual S-curve will terminate at the Cut Off
Date. This is the date the Production Schedule was last updated. At the completion of the project,
the Actual S-curve will meet the Target S-curve.

Figure 5: Actual S-curve


Value and Percentage S-curves
S-curves may be graphed as absolute values (i.e. Man Hours or Costs) versus Time, or as
percentage values versus Time. Value S-curves are useful for determining Man Hours or Costs
expended to date, and Man Hours or Costs to complete. Percentage S-curves are useful for
calculating the project's actual percentage complete against target and baseline percentage
complete, and for calculating the project's percentage growth (or contraction).

Using S-curves
Why Use an S-curve?
S-curves are an important project management tool. They allow the progress of a project to be
tracked visually over time, and form a historical record of what has happened to date. Analyses of
S-curves allow project managers to quickly identify project growth, slippage, and potential
problems that could adversely impact the project if no remedial action is taken.

Determining Growth
Comparison of the Baseline and Target S-curves quickly reveals if the project has grown (Target S-
curve finishes above Baseline S-curve) or contracted (Target S-curve finishes below Baseline S-
curve) in scope. A change in the project's scopes implies a re-allocation of resources (increase or
decrease), and the very possible requirement to raise contract variations. If the resources are
fixed, then the duration of the project will increase (finish later) or decrease (finish earlier),
possibly leading to the need to submit an extension of time claim.

Figure 6: Calculating Project Growth using S-curves


Determining Slippage
Slippage is defined as:

"The amount of time a task has been delayed from its original baseline schedule. The slippage is
the difference between the scheduled start or finish date for a task and the baseline start or finish
date. Slippage can occur when a baseline plan is set and the actual dates subsequently entered
for tasks are later than the baseline dates or the actual durations are longer than the baseline
schedule durations".[2]

Comparison of the Baseline S-curve and Target S-curve quickly reveals any project slippage (i.e.
the Target S-curve finishes to the right of the Baseline S-curve). Additional resources will need to
be allocated or additional hours worked in order to eliminate (or at least reduce) the slippage. An
extension of time claim may need to be submitted if the slippage cannot be eliminated or
reduced to an acceptable level.

Figure 7: Calculating Project Slippage using S-curves


Determining Progress
Comparison of the Target S-curve and Actual S-curve reveals the progress of the project over
time. In most cases, the Actual S-curve will sit below the Target S-curve for the majority of the
project (due to many factors, including delays in updating the production schedule). Only towards
the end of the project will the curves converge and finally meet. The Actual S-curve can never
finish above the Target S-curve. If the Actual S-curve sits above the Target S-curve at the Cut Off
Date, the Production Schedule should be examined to determine if the project is truly ahead of
schedule, or if the Production Schedule contains unrealistic percentage complete values for
ongoing tasks.

Figure 8: Calculating Project Progress using S-curves


Generating S-curves
Project Benchmarks
Percentage S-curves may be used to calculate important project benchmarks on an ongoing
basis, including:
Project percentage growth (Target and Baseline S-curves)
Project percentage slippage (Target and Baseline S-curves)
Actual percentage complete against Target percentage complete to date
Actual percentage complete against Baseline percentage complete to date

How is an S-curve Generated?


To generate a Baseline S-curve, a Baseline Schedule is required.
The Baseline Schedules should contain the following information for each task:

Baseline Start Date, Finish Date


Baseline Man Hours and/or Costs

To generate Actual and Target S-curves, a Production Schedule is required.


The Production Schedules should contain the following information for each task:

Actual Start Date, Finish Date


Actual Man Hours and/or Costs
Actual Percentage Complete

Worked Example
To better understand how S-curves are generated, consider a simple project comprising three
tasks.
A Baseline Schedule prepared using MS Project for this project is shown below.

Figure 9: Sample Baseline Schedule


Baseline Man Hours versus Time S-curve
To generate a Baseline Man Hours versus Time S-curve, two sets of calculations are performed.
The first set of calculations is performed for each task in the Baseline Schedule.

1. Calculate the duration in days for each task


i.e. Baseline Duration = Baseline Finish Date - Baseline Start Date + 1
2. Calculate Man Hours per day for each task
i.e. Baseline MHs per Day = Baseline Man Hours / Baseline Duration

These calculations are shown in the following table.

Figure 10: Baseline S-curve Calculation 1 of 2


The second set of calculations is performed for each day in the Baseline Schedule.

1. Calculate the total Man Hours per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours per Day for all tasks.

These calculations are shown in the following table.

Figure 11: Baseline S-curve Calculation 2 of 2


The S-curve is constructed by assigning the Dates to the X Axis, and the YTD values to the Y Axis.
The resulting Baseline Man Hours versus Time S-curve is shown below.

Figure 12: Baseline Man Hours versus Time S-curv


Actual versus Target
Target Man Hours versus Time S-curve
To generate the Actual and Target S-curves, a Production Schedule is required. A Production
Schedule for this project is shown below.

Figure 13: Production Schedule


To generate a Target Man Hours versus Time S-curve, two sets of calculations are necessary. The
first set of calculations is performed for each task in the Production Schedule.

1. Calculate the duration in days for each task


i.e. Duration = Finish Date - Start Date + 1
2. Calculate Man Hours per day for each task
i.e. MHs per Day = Man Hours / Duration

These calculations are shown in the following table.

Figure 14: Target S-curve Calculation 1 of 2


The second set of calculations is performed for each day in the Production Schedule.

1. Calculate the total Man Hours per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours per Day for all tasks.

These calculations are shown in the following table:

Figure 15: Target S-curve Calculation 2 of 2


The resulting Target Man Hours versus Time S-curve is shown below.

Figure 16: Target Man Hours versus Time S-curve


Actual Man Hours versus Time S-curve
To generate an Actual Man Hours versus Time S-curve, two sets of calculations are performed, but
before these calculations may be performed, the Cut Off Date needs to be defined. This is the
date the Production Schedule was last updated. For this example a Cut Off Date of 3rd November
2008 will be used.
The first set of calculations is performed for each task in the Production Schedule.

1. Determine the Task Status: Complete, Ongoing, Not Started.


Complete: Tasks that have a Finish Date prior to the Cut Off Date.
Ongoing: Tasks that have commenced and have a Finish Date on or after the Cut Off Date.
Not Started: Tasks that have a Start Date after the Cut Off Date.
2. Calculate the Duration to Date based on the Task Status.
Complete: Duration To Date = Finish Date - Start Date + 1
Ongoing: Duration To Date = Cut Off Date - Start Date + 1
Not Started: Duration To Date = 0.
3. Calculate Man Hours to Date for Complete and Ongoing Tasks.
i.e. Man Hours to Date = Man Hours x % Complete / Duration to Date.

These calculations are shown in the following table.

Figure 17: Actual S-curve Calculation 1 of 2


The second set of calculations is performed for each day in the Production Schedule up to the Cut
Off Date.

1. Calculate the total Man Hours to Date per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours to Date per Day for all tasks.

These calculations are shown in the following table.

Figure 18: Actual S-curve Calculation 2 of 2


The resulting Actual Man Hours versus Time S-curve is shown below.

Figure 19: Actual Man Hours versus Time S-curve


The Baseline, Actual, and Target S-curves are usually combined, as shown below.

Figure 20: Man Hours versus Time S-curves


Analysis

S-curve Analysis

Initial examination of the S-curves generated above reveal the following about the status of the
project.

The project has grown in scope. (The Target S-curve finishes above the Baseline S-curve)
The project has slipped. (The Target S-curve finishes to the right of the Baseline S-curve)
The project is behind schedule. (The Actual S-curve sits below the Target S-curve at the Cut
Off Date)

Project Growth
Analysis of the Baseline and Target S-curve data reveals the project has grown in scope by 12
man-hours, or 14.29%.

i.e. Growth = Target MHs - Baseline MHs = 96 - 84 = 12


i.e. Growth % = (Target MHs / Baseline MHs - 1) x 100% = (96 / 84 - 1) x 100% = 14.29%

Project Slippage

Analysis of the Baseline and Target S-curve data reveals the project has slipped by 1 day, or
20.00%.

i.e. Slippage = Target Duration - Baseline Duration = 6 - 5 = 1


i.e. Slippage % = (Target Duration / Baseline Duration - 1) x 100% = (6 / 5 - 1) x 100% =
20.00%

Project Progress

According to MS Project, based on the Production Schedule the project is 50% complete. MS
Project calculates percentage complete based on durations, and does not take into account man-
hours assigned to each task. Analysis of the Actual and Target S-curve data reveals the project is
53.13% complete as of the Cut Off Date, while the project should be 59.38% complete.

i.e. Actual % Complete = (Actual YTD Man Hours @ Cut Off Date / Target Man Hours) x
100% = (51 / 96) x 100% = 53.13%
i.e. Target % Complete = (Target YTD Man Hours @ Cut Off Date / Target Man Hours) x
100% = (57 / 96) x 100% = 59.38%

Conclusion
Project status
The project will finish late and over budget compared to the Baseline Schedule. Progress to date
(i.e. the Cut Off Date) is behind schedule compared to the Production Schedule. Detailed analysis
of the project is required to determine why the project will be completed late and over budget.
Project growth and/or slippage may be due to a number of factors, including underestimation of
effort in the Baseline Schedule, low productivity, rework, variations (approved or not), etc.

In this example, variations may need to be raised to account for the extra man hours expended,
and an extension of time claim raised for the later than planned completion. The Production
Schedule may need review to ensure tasks have been updated accurately (especially with respect
to true percentage complete values), and ongoing and future tasks may require revising.

Generating S-curves
Some software scheduling packages automatically generate S-curves. On the other hand, some
(including MS Project) do not. In this case, a third party software application is required to process
the Baseline and Production Schedule data to generate the required S-curves.

Midori Media's myPM SCG S-curve Generator is an MS Windows application that integrates with
MS Excel to generate the various types of S-curves discussed above. MS Project users will need to
export their schedule data to an MS Excel file (easily accomplished using MS Project's File Save As
option). myPM SCG processes the resulting export file, and creates an MS Excel Output file
containing the required S-curves. These may be copy-pasted to MS Word for inclusion in Project
Progress Reports.

The value of S-curves


The S-curve is an important but often overlooked and misunderstood project management tool. A
variety of S-curves exist, the most common being Man Hours versus Time, and Costs versus
Time. By creating a Baseline Schedule, a Baseline S-curve can be generated. Baseline S-curves
provide a basis on which to compare a project's actual status to its planned status. They may also
assist in the planning of manpower and financial resources required to complete the project.

A Production Schedule allows Actual and Target S-curves to be generated. These allow the
progress of a project to be monitored, and quickly reveal any divergence from the Baseline
Schedule. S-curves may also be used to determine project growth, slippage, and progress to date.