Kusile Boiler 2- Mechanical Work Schedule_20160204 Classic Schedule Layout 20-Feb-17 08:41

Activity ID Activity Name Original Start Finish Activity % Comment December 2016 January 2017
Duration Complete
28 04 11 18

Kusile Boiler 2- Mechanical Work Schedule_20160204 178 26-Jul-16 A 03-Apr-17

Milestones 15 13-Feb-17 03-Mar-17

PA001 Completion 15 13-Feb-17 03-Mar-17


Ducting 15 13-Feb-17 03-Mar-17
PA Fan to Air heater (System 1.3) 0 13-Feb-17 13-Feb-17
A2450 PA001 Walkdown Comp 1,3 & 5 0 13-Feb-17 0%
A21510 PA001 Walkdown Comp 2,4 & 6 0 13-Feb-17 0%
133 - Mill Cold Air Lines - PA Fan to Mill (System1.4) 8 13-Feb-17 20-Feb-17
A21440 PA001 Walkdown Component 8 & 9 0 20-Feb-17* 0%
A21450 PA001 Walkdown Component 10 0 20-Feb-17* 0%
A21460 PA001 Walkdown Component 11 0 20-Feb-17* 0%
A21470 PA001 Walkdown Component 12 0 20-Feb-17* 0%
A21480 PA001 Walkdown Component 13 0 20-Feb-17* 0%
A21490 PA001 Walkdown Component 14 0 13-Feb-17 0%
A21500 PA001 Walkdown Component 15 0 13-Feb-17 0%
03 - Hot Air Distribution Lines (System 3) 7 16-Feb-17 23-Feb-17
A2470 PA001 Walkdown Components 12 / 14 0 16-Feb-17 0%
A21250 PA001 Walkdown Components 13 / 15 0 23-Feb-17 0%
02 - Hot Air Collection Lines (System 2) 0 13-Feb-17 13-Feb-17
A21520 PA001 Walkdown Comp 1, 2 & 6 0 13-Feb-17 0%
A21530 PA001 Walkdown Comp 3,4 & 5 0 13-Feb-17 0%
04 - Burner Air Lines (System 4) 6 13-Feb-17 18-Feb-17
Burner Air Lines (System 4.1) 4 13-Feb-17 16-Feb-17
A21740 Component 43, 44, 47, 48 & 51 PA001 0 13-Feb-17 0%
A21750 Component 42, 45, 46, 49 & 50 PA001 4 13-Feb-17 16-Feb-17 0%
Core Air Lines (System 4.2) 6 13-Feb-17 18-Feb-17
A2780 Bank 50 - PA001 Walkdown 0 13-Feb-17 0%
A2790 Bank 40 - PA001 Walkdown 0 13-Feb-17 0%
A2800 Bank 30 - PA001 Walkdown 0 18-Feb-17 0%
A2810 Bank 20 - PA001 Walkdown 0 13-Feb-17 0%
A2820 Bank 10 - PA001 Walkdown 0 13-Feb-17 0%
08 - Mill Air Lines (System 6) 0 14-Feb-17 14-Feb-17
130 - Mill Hot Air Lines - PA / Air heater to Mill ( 6.1 / 6.2) 0 14-Feb-17 14-Feb-17
System 6.2 0 14-Feb-17 14-Feb-17
A2590 PA001 Walkdown 0 14-Feb-17 0%
System6.1 0 14-Feb-17 14-Feb-17
A2600 PA001 Walkdown 0 14-Feb-17 0%
09 - Flue Gas lines (System 7) 15 13-Feb-17 03-Mar-17
152 - Filter to ID - Duct PJFF to ID Fan (System 7.4) 5 22-Feb-17 03-Mar-17
A2610 PA001 Walkdown - Comp 1 0 22-Feb-17 0%
A3010 PA001 Walkdown - Comp 2 0 03-Mar-17 0%
151 - RAH to Filter - Flue Gas Duct underneath RAH (System 7.2) 1 13-Feb-17 14-Feb-17
A2620 PA001 Walkdown - Component 14 0 13-Feb-17 0%
A3260 PA001 Walkdown - Component 15 0 13-Feb-17 0%
A3270 PA001 Walkdown - Component 16 0 13-Feb-17 0%
A3280 PA001 Walkdown - Component 17 0 14-Feb-17 0%
130 - Boiler to RAH - Flue Gas Duct from Boiler to RAH (System 7.1) 7 13-Feb-17 20-Feb-17
A21360 PA001 Walkdown Component 1 & 2 0 13-Feb-17 0%
Component 3 To 9 7 13-Feb-17 20-Feb-17
A21370 PA001 Walkdown Component 3 0 13-Feb-17 0%
A21380 PA001 Walkdown Component 5 0 13-Feb-17 0%
A21390 PA001 Walkdown Component 6/8 0 20-Feb-17 0%
A21400 PA001 Walkdown Component 7/9 0 15-Feb-17 0%
A21410 PA001 Walkdown Component 4.1 0 13-Feb-17 0%
A21420 PA001 Walkdown Component 4.5 0 13-Feb-17 0%
A21430 PA001 Walkdown Component 4.4 0 13-Feb-17 0%

Actual Work Critical Remaining Work Summary Page 1 of 8 TASK filters: Ducting, In Progress.
Remaining Work Milestone Oracle Corporation
Kusile Boiler 2- Mechanical Work Schedule_20160204 Classic Schedule Layout 20-Feb-17 08:41
Activity ID Activity Name Original Start Finish Activity % Comment December 2016 January 2017
Duration Complete
28 04 11 18
Construction Works 153 26-Jul-16 A 04-Mar-17

System 06 - Combustion Air & Flue Gas System 153 26-Jul-16 A 04-Mar-17
1.1 - Cold Air Suction 47 13-Dec-16 A 04-Mar-17
Cold Air Suction to FDF (1.1) Component 9.2, 9.3 & 9.4 18 13-Dec-16 A 04-Mar-17
A16890 Final Handover 2 16-Jan-17 A 04-Mar-17 65%
A16880 Clean Ducting 4 13-Dec-16 A 04-Mar-17 0%
Cold Air Suction to FDF (1.1) Component 9.1, 10.1 & 10.2 6 13-Feb-17 18-Feb-17
A27520 Scaffolding Dismmantled 0 18-Feb-17* 0%
A16680 Install Maintance Doors 3 Off 6 13-Feb-17 18-Feb-17 0%
1.3 - PA Fan to Air Heater 5 16-Jan-17 A 13-Feb-17
Installation 5 16-Jan-17 A 13-Feb-17
Component 1, 3 & 5 1 13-Feb-17 13-Feb-17
A18550 Handover Comp 1,3 & 5 1 13-Feb-17 13-Feb-17 0%
Component 2, 4 & 6 1 16-Jan-17 A 13-Feb-17
A18790 Clean Comp 2,4 & 6 1 16-Jan-17 A 13-Feb-17 50%
A18800 Handover Comp 2,4 & 6 1 18-Jan-17 A 13-Feb-17 50%
1.4 - PA Fan to Mill 57 27-Nov-16 A 18-Feb-17
Installation 57 27-Nov-16 A 18-Feb-17
Component 10 56 27-Nov-16 A 18-Feb-17
A17290 Fit Stub guides (8off) and do fit-up inspection (Insulation Scaffoldin) 1 27-Nov-16 A 13-Feb-17 10%
A17380 Cut access window to fit tensioner rods, Lift & feed tensioner rods through opening
1 13-Feb-17 13-Feb-17 0%
A17390 Fit-up of component 10 to 8 Tensioner rods & lugs (Dog, wedge and tack weld) and
2 do
13-Feb-17
fit-up inspection 15-Feb-17 0%
A17310 Weld Stub guides (8off) and NDT wel ding 3 12-Feb-17 A 13-Feb-17 50%
A17400 Weld out component 10 to 8 Tensioner rod lugs and NDT welding 3 15-Feb-17 18-Feb-17 0%
Component 13 - Modification Delay 3 02-Feb-17 A 13-Feb-17
A18070 Preliminary Survey (2 off) component 13 Expansion Bellows (Protocols) 1 02-Feb-17 A 13-Feb-17 0%
A18080 Cut (2 off) component 13 Expansion Bellows "Gags" 1 11-Feb-17 A 13-Feb-17 50%
A18050 Weld out component 13.1 to component 11 Joint and NDT welding 2 06-Feb-17 A 13-Feb-17 50%
A18060 Weld out component 13.2 to component 13.1 Joint and NDT welding 2 10-Feb-17 A 13-Feb-17 50%
Component 14 - Modification Delay 26 17-Jan-17 A 14-Feb-17
A18180 Weld out component 14.2 to component 14.1 Joint and NDT welding 2 17-Jan-17 A 14-Feb-17 50%
A18190 Preliminary Survey (2 off) component 14 Expansion Bellows (Protocols) 2 08-Feb-17 A 14-Feb-17 0%
Component 15 - Modification Delay 32 05-Jan-17 A 14-Feb-17
A18310 Preliminary Survey (2 off) component 15 Expansion Bellows (Protocols) 1 13-Feb-17 14-Feb-17 0%
A18290 Weld out component 15.1 to component 11 Joint and NDT welding 3 08-Feb-17 A 14-Feb-17 92.23%
A18300 Weld out component 15.2 to component 15.1 Joint and NDT welding 3 11-Feb-17 A 14-Feb-17 50%
A18340 Weld out component 15.2 to Item 6.2 (Mill Air Line) Joint and NDT welding 3 05-Jan-17 A 14-Feb-17 69.23%
Component 10 To 15 - Modification Delay 2 06-Feb-17 A 14-Feb-17
A18000 Final Handover of components 10 to 15 1 06-Feb-17 A 14-Feb-17 60%
A17990 Clean components 10 to 15 (Cleanliness Protocols) 2 13-Feb-17 14-Feb-17 0%
2.0 - Secondary Air Hot Collection 4 13-Feb-17 17-Feb-17
Component 3, 4 & 5 4 13-Feb-17 17-Feb-17
A20580 Clean After Dis mantling Sc affold 4 13-Feb-17 17-Feb-17 0%
Component 1, 2 & 6 4 13-Feb-17 17-Feb-17
A20570 Clean After Scaffold Dismatling 4 13-Feb-17 17-Feb-17 0%
3.0 - Secondary Air Hot Distribution 13 13-Feb-17 01-Mar-17
Install Secondary Hot Air Distribution duct Component 13 / 15 13 13-Feb-17 01-Mar-17
A9470 Position Inspection window door & bolt down (Impact) 1 22-Feb-17 23-Feb-17 0%
A9430 Final Handover of components 13 / 15 2 13-Feb-17 14-Feb-17 0%
A9440 Clean components 13 / 15 (Cleanliness Protocols) 2 18-Feb-17 21-Feb-17 0%
A9460 Re-fit Acc es s window at 16m level and do fit- up inspec tion 2 21-Feb-17 22-Feb-17 0%
A9450 Weld out Access window on 16m level and do NDT welding 3 22-Feb-17 01-Mar-17 0%
A16290 Break Down Scaffolding 4 14-Feb-17 18-Feb-17 0%
Install Secondary Hot Air Distribution duct Component 12 / 14 5 13-Feb-17 17-Feb-17
A9520 Position Inspection window door & bolt down (Impact) 1 16-Feb-17 16-Feb-17 0%
A9480 Final Handover of components 12 / 14 2 13-Feb-17 14-Feb-17 0%
A9490 Clean components 12 / 14 (Cleanliness Protocols) 2 15-Feb-17 16-Feb-17 0%

Actual Work Critical Remaining Work Summary Page 2 of 8 TASK filters: Ducting, In Progress.
Remaining Work Milestone Oracle Corporation
Kusile Boiler 2- Mechanical Work Schedule_20160204 Classic Schedule Layout 20-Feb-17 08:41
Activity ID Activity Name Original Start Finish Activity % Comment December 2016 January 2017
Duration Complete
28 04 11 18
A9510 Re-fit Acc es s window at 16m level and do fit- up inspec tion 2 15-Feb-17 16-Feb-17 0%
A9500 Weld out Access winow on 16m level and do NDT welding 3 15-Feb-17 17-Feb-17 0%
A16300 Break Down Scaffolding 4 13-Feb-17 16-Feb-17 0%
4.1 - Burner Air Lines 34 11-Dec-16 A 17-Feb-17
Install Components 43, 44, 47, 48 & 51 (1 to 8) 4 31-Jan-17 A 17-Feb-17
Component 43, 44, 47, 48 & 51 4 31-Jan-17 A 17-Feb-17
A7980 Final Handover of components 43, 44, 47, 48 & 51 1 31-Jan-17 A 13-Feb-17 95.77%
A7990 Final Handover of components 44 4 13-Feb-17 17-Feb-17 0%
Install Components 42, 45, 46, 49 & 50 (1 to 8) 4 11-Dec-16 A 16-Feb-17
Components 42, 45, 46, 49 & 50 4 11-Dec-16 A 16-Feb-17
A9390 Final Handover of Components 42, 45, 46, 49 & 50 4 11-Dec-16 A 16-Feb-17 25%
4.2 - Core Air Lines 73 08-Nov-16 A 18-Feb-17
Lift Core Air Ducting Bank 10-50 36 08-Nov-16 A 16-Feb-17
Lift Bank 40 7 12-Nov-16 A 16-Feb-17
A5450 Lift and Float to position box section components 4 12-Nov-16 A 16-Feb-17 90%
A5460 Lift and Float to position pipe section components 4 12-Nov-16 A 16-Feb-17 90%
Lift Bank 30 4 08-Nov-16 A 16-Feb-17
A5430 Lift and Float to position pipe section components 4 08-Nov-16 A 16-Feb-17 75%
Lift Bank 20 2 10-Dec-16 A 14-Feb-17
A5400 Lift and Float to position pipe section components 2 10-Dec-16 A 14-Feb-17 60%
Install Core Air Ducting Bank 10-50 71 12-Nov-16 A 18-Feb-17
Install Bank 40 4 12-Nov-16 A 14-Feb-17
A5760 Weld out ALL and NDT welding 4 12-Nov-16 A 14-Feb-17 90%
Install Bank 30 16 10-Feb-17 A 18-Feb-17
A5690 Weld out ALL and NDT welding 2 10-Feb-17 A 14-Feb-17 90%
A5700 Remove all Rigging gear 2 16-Feb-17 18-Feb-17 0%
A5660 Survey all components elevation & position 4 13-Feb-17 16-Feb-17 0%
Install Bank 20 14 30-Jan-17 A 14-Feb-17
A5620 Weld out ALL and NDT welding 2 30-Jan-17 A 14-Feb-17 90%
A5630 Remove all Rigging gear 2 13-Feb-17 14-Feb-17 0%
Install Bank 10 14 30-Jan-17 A 14-Feb-17
A5550 Weld out ALL and NDT welding 2 30-Jan-17 A 14-Feb-17 90%
A5560 Remove all Rigging gear 2 13-Feb-17 14-Feb-17 0%
6.1 - Hot Primary Air Duct 77 30-Oct-16 A 14-Feb-17
Components 16 To 24 77 30-Oct-16 A 14-Feb-17
A27540 No Ac cess MHPSA 0 13-Feb-17 0%
A4200 Final Handover of components 16 to 24 - Note 2 30-Oct-16 A 14-Feb-17 50%
6.2 - Hot Air to Mill 2 29-Nov-16 A 14-Feb-17
Installation 2 29-Nov-16 A 14-Feb-17
Sys6.1-3 Final Handover of components 27 to 46 2 29-Nov-16 A 14-Feb-17 95%
7.1 - Flue Gas 167 26-Jul-16 A 20-Feb-17
Install Flue Gas Duct Component 3 To 9 167 26-Jul-16 A 20-Feb-17
Component 6/8 44 17-Dec-16 A 20-Feb-17
A3660 Fit gaskets and bolt down Maintenance door 2 17-Feb-17 20-Feb-17 0%
A3650 Lift and float to position (1off) Maintenance door 7 17-Dec-16 A 17-Feb-17 88.89%
Component 7/9 163 26-Jul-16 A 15-Feb-17
A3680 Weld out component 7/9 to component 5 Joint and NDT welding 1 26-Jul-16 A 14-Feb-17 99%
A3790 Lift and float to position (1off) Maintenance door 1 13-Dec-16 A 14-Feb-17 50%
A3800 Fit gaskets and bolt down Maintenance door 1 14-Feb-17 15-Feb-17 0%
Component 4.5 3 05-Oct-16 A 15-Feb-17
A3910 Weld out component 4.5 to component 3 Joint and NDT welding 2 05-Oct-16 A 15-Feb-17 99%
7.2 - Flue Gas RAH 8 13-Feb-17 21-Feb-17
Component 14 1 13-Feb-17 13-Feb-17
A3070 Final handover component 1 13-Feb-17 13-Feb-17 0%
Component 15 1 13-Feb-17 13-Feb-17
A3130 Final handover component 1 13-Feb-17 13-Feb-17 0%
Component 16 5 13-Feb-17 17-Feb-17
A3190 Final handover component 1 13-Feb-17 13-Feb-17 0%

Actual Work Critical Remaining Work Summary Page 3 of 8 TASK filters: Ducting, In Progress.
Remaining Work Milestone Oracle Corporation
Kusile Boiler 2- Mechanical Work Schedule_20160204 Classic Schedule Layout 20-Feb-17 08:41
Activity ID Activity Name Original Start Finish Activity % Comment December 2016 January 2017
Duration Complete
28 04 11 18
A3150 Bolt down & torque bolts on Flexible Expansion Bellow 2 15-Feb-17 17-Feb-17 0%
A3140 Fit (1off) Flexible Bellow on component 16 and do fit-up inspection 3 13-Feb-17 15-Feb-17 0%
Component 17 8 13-Feb-17 21-Feb-17
A27560 Access PJFF 0 13-Feb-17 0%
A3250 Final handover component 1 13-Feb-17 14-Feb-17 0%
A3210 Bolt down & torque bolts on Flexible Expansion Bellow 2 18-Feb-17 21-Feb-17 0%
A3240 Clean components 2 13-Feb-17 14-Feb-17 0%
A3200 Fit (1off) Flexible Bellow on component 17 and do fit-up inspection 3 17-Feb-17 21-Feb-17 0%
7.4 - Flue Gas Duct to ID Fan 15 13-Feb-17 03-Mar-17
Install Flue Gas To ID Fan Comp 1 10 13-Feb-17 22-Feb-17
A27550 Access PJFF (MHPSA TO SUPPLY) 0 13-Feb-17 0%
A2970 Final Handover Component 1 1 22-Feb-17 22-Feb-17 0%
A2950 Bolt down & torque bolts on Flexible Expansion Bellow 2 17-Feb-17 20-Feb-17 0%
A2960 Clean component 1 (Cleanliness Protocols) 2 20-Feb-17 22-Feb-17 0%
A2930 Fit (1off) Flexible Bellow on component 1 and do fit-up inspection 5 13-Feb-17* 17-Feb-17 0%
Install Flue Gas To ID Fan Comp 2 10 17-Feb-17 03-Mar-17
A3000 Final Handover Component 2 1 02-Mar-17 03-Mar-17 0%
A2980 Bolt down & torque bolts on Flexible Expansion Bellow 2 22-Feb-17 28-Feb-17 0%
A2990 Clean component 2 (Cleanliness Protocols) 2 28-Feb-17 02-Mar-17 0%
A2940 Fit (1off) Flexible Bellow on component 2 and do fit-up inspection 5 17-Feb-17 22-Feb-17 0%

Extra Work 42 13-Feb-17 03-Apr-17

SI Instruction 0 13-Feb-17 13-Feb-17


SI Instructions Recieved 0 13-Feb-17 13-Feb-17
SI Document 0931 0 13-Feb-17 13-Feb-17
A27620 Recieved SI 0 13-Feb-17 0%
SI Document (Khumbulani 2) 0 13-Feb-17 13-Feb-17
A27650 Requested For SI 0 13-Feb-17* 0%
A27660 Recieved SI 0 13-Feb-17 0%
SI Document (Khumbulani 3) 0 13-Feb-17 13-Feb-17
A28270 Requested For SI 0 13-Feb-17* 0%
A28290 Recieved SI 0 13-Feb-17 0%
SI Work 42 13-Feb-17 03-Apr-17
SI 0904 Rewelding On Pin Rack 19 13-Feb-17 07-Mar-17
A27450 Inspection 0 04-Mar-17 0%
A27460 NDTs 0 06-Mar-17 0%
A27470 Replace Insulation 0 06-Mar-17 0%
A27480 Remove Scaffolding 0 07-Mar-17 0%
A27390 NDTs 1 14-Feb-17 15-Feb-17 0%
A27400 Remove covers on Leaf Seals and Housekeeping 1 15-Feb-17 16-Feb-17 0%
A27410 Preparations for window welds 1 16-Feb-17 17-Feb-17 0%
A27420 Rig Window into position 1 17-Feb-17 18-Feb-17 0%
A27380 Inspection 2 13-Feb-17 14-Feb-17 0%
A27430 Dogg and Tack window 4 18-Feb-17 23-Feb-17 0%
A27440 Weld Window 4 23-Feb-17 03-Mar-17 0%
SI 0931 4.1 Burner Erosion Modifications 40 13-Feb-17 03-Apr-17
16 Meter Level 28 13-Feb-17 16-Mar-17
Burner Bottom Section 28 13-Feb-17 16-Mar-17
A27760 Touch-up Painting all affected ares (by others) 0 16-Mar-17 0%
A27670 Obtain Permit to work / Lift all equipment to work area 3 13-Feb-17 15-Feb-17 0%
A27690 Mark out & cut bottom part of Burner casing as per Site Instruction drawing 3 15-Feb-17 18-Feb-17 0%
A27720 Weld out "new" erotion plates as per welding sequence & information then NDT the
3 welds
02-Mar-17
bottom 06-Mar-17 0%
A27730 Prep bottom part of Burner casing for re-fitment of access plate that was cut, prep3casing
06-Mar-17
plate 08-Mar-17 0%
A27740 Re-align, Fit & Tack weld casing plate i n original position 3 08-Mar-17 11-Mar-17 0%
A27700 Mark out installation are for "new" erotion plates. Prep, Fit & Tack weld "new" er otion
4 18-Feb-17
plates top- QC fi tup inspec
22-Feb-17
tion 0%
A27710 Weld out "new" erotion plates as per welding sequence & information then NDT the
4 welds
22-Feb-17
top 02-Mar-17 0%
A27750 Weld out casing plate as per welding sequence & information then NDT the welds5 11-Mar-17 16-Mar-17 0%

Actual Work Critical Remaining Work Summary Page 4 of 8 TASK filters: Ducting, In Progress.
Remaining Work Milestone Oracle Corporation
Kusile Boiler 2- Mechanical Work Schedule_20160204 Classic Schedule Layout 20-Feb-17 08:41
Activity ID Activity Name Original Start Finish Activity % Comment December 2016 January 2017
Duration Complete
28 04 11 18
Ducting 25 15-Feb-17 16-Mar-17
A27780 Erect access scaffold to area where Baffle plate is to be installed (by Others) 0 15-Feb-17 0%
A27860 Touch-up Painting all affected ares (by others) 0 16-Mar-17 0%
A27880 Dismantle scaffolds (by others) 0 16-Mar-17 0%
A27800 Mark out the profile of the "new" Baffle plate on boths sides (outside) Duct component,
1 22-Feb-17
and remove IPE stiffeners
23-Feb-17 0%
A27810 Cut slots in the Duct component casing on both sides as per profile marks 1 23-Feb-17 28-Feb-17 0%
A27820 Slide "new" Baffle plate from one side into slots, Align & Tack weld 2 28-Feb-17 02-Mar-17 0%
A27830 Weld out "new" Baffle plates as per welding sequence & information then NDT the2wel
02-Mar-17
ds ( Outside of duct only)
04-Mar-17 0%
A27840 Prep IPE stiffeners & Toungue plates, Prep Duct casing then Fit & Tack weld all - QC
2 04-Mar-17
fitup inspection 07-Mar-17 0%
A27850 Weld out IPE stiffeners & Toungue plates as per welding sequence & information then
2 07-Mar-17
NDT the welds 08-Mar-17 0%
24 Meter Level 26 15-Feb-17 18-Mar-17
Burner Bottom Section 26 15-Feb-17 18-Mar-17
A29010 Touch-up Painting all affected ares (by others) 0 18-Mar-17 0%
A28970 Weld out "new" erotion plates as per welding sequence & information then NDT the
2 welds
04-Mar-17
bottom 07-Mar-17 0%
A28930 Obtain Permit to work / Lift all equipment to work area 3 15-Feb-17 18-Feb-17 0%
A28940 Mark out & cut bottom part of Burner casing as per Site Instruction drawing 3 18-Feb-17 22-Feb-17 0%
A28950 Mark out installation are for "new" erotion plates. Prep, Fit & Tack weld "new" er otion
3 22-Feb-17
plates top- QC fi tup inspec
28-Feb-17
tion 0%
A28980 Prep bottom part of Burner casing for re-fitment of access plate that was cut, prep3casing
07-Mar-17
plate 10-Mar-17 0%
A28990 Re-align, Fit & Tack weld casing plate i n original position 3 10-Mar-17 13-Mar-17 0%
A28960 Weld out "new" erotion plates as per welding sequence & information then NDT the
4 welds
28-Feb-17
top 04-Mar-17 0%
A29000 Weld out casing plate as per welding sequence & information then NDT the welds5 13-Mar-17 18-Mar-17 0%
Ducting 23 18-Feb-17 18-Mar-17
A29020 Erect access scaffold to area where Baffle plate is to be installed (by Others) 0 18-Feb-17 0%
A29090 Touch-up Painting all affected ares (by others) 0 18-Mar-17 0%
A29100 Dismantle scaffolds (by others) 0 18-Mar-17 0%
A29030 Mark out the profile of the "new" Baffle plate on boths sides (outside) Duct component,
1 28-Feb-17
and remove IPE stiffeners
01-Mar-17 0%
A29040 Cut slots in the Duct component casing on both sides as per profile marks 1 01-Mar-17 02-Mar-17 0%
A29050 Slide "new" Baffle plate from one side into slots, Align & Tack weld 2 02-Mar-17 04-Mar-17 0%
A29060 Weld out "new" Baffle plates as per welding sequence & information then NDT the2wel
04-Mar-17
ds ( Outside of duct only)
07-Mar-17 0%
A29070 Prep IPE stiffeners & Toungue plates, Prep Duct casing then Fit & Tack weld all - QC
2 07-Mar-17
fitup inspection 08-Mar-17 0%
A29080 Weld out IPE stiffeners & Toungue plates as per welding sequence & information then
2 08-Mar-17
NDT the welds 10-Mar-17 0%
26 Meter Level 28 18-Feb-17 24-Mar-17
Burner Bottom Section 28 18-Feb-17 24-Mar-17
A29190 Touch-up Painting all affected ares (by others) 0 24-Mar-17 0%
A29110 Obtain Permit to work / Lift all equipment to work area 3 18-Feb-17 22-Feb-17 0%
A29120 Mark out & cut bottom part of Burner casing as per Site Instruction drawing 3 22-Feb-17 28-Feb-17 0%
A29130 Mark out installation are for "new" erotion plates. Prep, Fit & Tack weld "new" er otion
3 28-Feb-17
plates top- QC fi tup inspec
03-Mar-17
tion 0%
A29160 Prep bottom part of Burner casing for re-fitment of access plate that was cut, prep3casing
11-Mar-17
plate 15-Mar-17 0%
A29170 Re-align, Fit & Tack weld casing plate i n original position 3 15-Mar-17 18-Mar-17 0%
A29150 Weld out "new" erotion plates as per welding sequence & information then NDT the
4 welds
08-Mar-17
bottom 11-Mar-17 0%
A29140 Weld out "new" erotion plates as per welding sequence & information then NDT the
4 welds
03-Mar-17
top 08-Mar-17 0%
A29180 Weld out casing plate as per welding sequence & information then NDT the welds5 18-Mar-17 24-Mar-17 0%
Ducting 25 22-Feb-17 24-Mar-17
A29200 Erect access scaffold to area where Baffle plate is to be installed (by Others) 0 22-Feb-17 0%
A29270 Touch-up Painting all affected ares (by others) 0 24-Mar-17 0%
A29280 Dismantle scaffolds (by others) 0 24-Mar-17 0%
A29210 Mark out the profile of the "new" Baffle plate on boths sides (outside) Duct component,
1 03-Mar-17
and remove IPE stiffeners
04-Mar-17 0%
A29220 Cut slots in the Duct component casing on both sides as per profile marks 1 04-Mar-17 06-Mar-17 0%
A29230 Slide "new" Baffle plate from one side into slots, Align & Tack weld 2 06-Mar-17 07-Mar-17 0%
A29240 Weld out "new" Baffle plates as per welding sequence & information then NDT the2wel
07-Mar-17
ds ( Outside of duct only)
09-Mar-17 0%
A29250 Prep IPE stiffeners & Toungue plates, Prep Duct casing then Fit & Tack weld all - QC
2 09-Mar-17
fitup inspection 11-Mar-17 0%
A29260 Weld out IPE stiffeners & Toungue plates as per welding sequence & information then
2 11-Mar-17
NDT the welds 14-Mar-17 0%
28 Meter Level 28 22-Feb-17 28-Mar-17
Burner Bottom Section 28 22-Feb-17 28-Mar-17
A29370 Touch-up Painting all affected ares (by others) 0 28-Mar-17 0%
A29290 Obtain Permit to work / Lift all equipment to work area 3 22-Feb-17 28-Feb-17 0%

Actual Work Critical Remaining Work Summary Page 5 of 8 TASK filters: Ducting, In Progress.
Remaining Work Milestone Oracle Corporation
Kusile Boiler 2- Mechanical Work Schedule_20160204 Classic Schedule Layout 20-Feb-17 08:41
Activity ID Activity Name Original Start Finish Activity % Comment December 2016 January 2017
Duration Complete
28 04 11 18
A29300 Mark out & cut bottom part of Burner casing as per Site Instruction drawing 3 28-Feb-17 03-Mar-17 0%
A29310 Mark out installation are for "new" erotion plates. Prep, Fit & Tack weld "new" er otion
3 03-Mar-17
plates top- QC fi tup inspec
07-Mar-17
tion 0%
A29340 Prep bottom part of Burner casing for re-fitment of access plate that was cut, prep3casing
15-Mar-17
plate 18-Mar-17 0%
A29350 Re-align, Fit & Tack weld casing plate i n original position 3 18-Mar-17 22-Mar-17 0%
A29330 Weld out "new" erotion plates as per welding sequence & information then NDT the
4 welds
11-Mar-17
bottom 15-Mar-17 0%
A29320 Weld out "new" erotion plates as per welding sequence & information then NDT the
4 welds
07-Mar-17
top 10-Mar-17 0%
A29360 Weld out casing plate as per welding sequence & information then NDT the welds5 22-Mar-17 28-Mar-17 0%
Ducting 25 28-Feb-17 28-Mar-17
A29380 Erect access scaffold to area where Baffle plate is to be installed (by Others) 0 28-Feb-17 0%
A29450 Touch-up Painting all affected ares (by others) 0 28-Mar-17 0%
A29460 Dismantle scaffolds (by others) 0 28-Mar-17 0%
A29390 Mark out the profile of the "new" Baffle plate on boths sides (outside) Duct component,
1 07-Mar-17
and remove IPE stiffeners
07-Mar-17 0%
A29400 Cut slots in the Duct component casing on both sides as per profile marks 1 07-Mar-17 08-Mar-17 0%
A29410 Slide "new" Baffle plate from one side into slots, Align & Tack weld 2 08-Mar-17 10-Mar-17 0%
A29420 Weld out "new" Baffle plates as per welding sequence & information then NDT the2wel
10-Mar-17
ds ( Outside of duct only)
13-Mar-17 0%
A29430 Prep IPE stiffeners & Toungue plates, Prep Duct casing then Fit & Tack weld all - QC
2 13-Mar-17
fitup inspection 15-Mar-17 0%
A29440 Weld out IPE stiffeners & Toungue plates as per welding sequence & information then
2 15-Mar-17
NDT the welds 16-Mar-17 0%
33 Meter Level 28 28-Feb-17 03-Apr-17
Burner Bottom Section 28 28-Feb-17 03-Apr-17
A29550 Touch-up Painting all affected ares (by others) 0 03-Apr-17 0%
A29470 Obtain Permit to work / Lift all equipment to work area 3 28-Feb-17 03-Mar-17 0%
A29480 Mark out & cut bottom part of Burner casing as per Site Instruction drawing 3 03-Mar-17 07-Mar-17 0%
A29490 Mark out installation are for "new" erotion plates. Prep, Fit & Tack weld "new" er otion
3 07-Mar-17
plates top- QC fi tup inspec
09-Mar-17
tion 0%
A29520 Prep bottom part of Burner casing for re-fitment of access plate that was cut, prep3casing
18-Mar-17
plate 22-Mar-17 0%
A29530 Re-align, Fit & Tack weld casing plate i n original position 3 22-Mar-17 25-Mar-17 0%
A29510 Weld out "new" erotion plates as per welding sequence & information then NDT the
4 welds
14-Mar-17
bottom 18-Mar-17 0%
A29500 Weld out "new" erotion plates as per welding sequence & information then NDT the
4 welds
09-Mar-17
top 14-Mar-17 0%
A29540 Weld out casing plate as per welding sequence & information then NDT the welds5 25-Mar-17 03-Apr-17 0%
Ducting 25 03-Mar-17 03-Apr-17
A29560 Erect access scaffold to area where Baffle plate is to be installed (by Others) 0 03-Mar-17 0%
A29630 Touch-up Painting all affected ares (by others) 0 03-Apr-17 0%
A29640 Dismantle scaffolds (by others) 0 03-Apr-17 0%
A29570 Mark out the profile of the "new" Baffle plate on boths sides (outside) Duct component,
1 09-Mar-17
and remove IPE stiffeners
10-Mar-17 0%
A29580 Cut slots in the Duct component casing on both sides as per profile marks 1 10-Mar-17 11-Mar-17 0%
A29590 Slide "new" Baffle plate from one side into slots, Align & Tack weld 2 11-Mar-17 14-Mar-17 0%
A29600 Weld out "new" Baffle plates as per welding sequence & information then NDT the2wel
14-Mar-17
ds ( Outside of duct only)
16-Mar-17 0%
A29610 Prep IPE stiffeners & Toungue plates, Prep Duct casing then Fit & Tack weld all - QC
2 16-Mar-17
fitup inspection 17-Mar-17 0%
A29620 Weld out IPE stiffeners & Toungue plates as per welding sequence & information then
2 17-Mar-17
NDT the welds 20-Mar-17 0%
SI (Khumbulani 2) Installation Of Delta Wings 35 13-Feb-17 24-Mar-17
Installation on Right Hand Side Duct 35 13-Feb-17 24-Mar-17
A30080 Conduct MHPSA Inspection 1 21-Mar-17 21-Mar-17 0%
A30060 Housekeeping & MRPE Inspection 2 18-Mar-17 20-Mar-17 0%
A29960 Lift to position Top (4m OD) plate and supports, Fit & tack weld 3 13-Feb-17 15-Feb-17 0%
A29970 Weld out (2off) Delta plates & Supports, NDT as per requirement 3 18-Feb-17 22-Feb-17 0%
A29980 Lift to position 8off (2m OD) plate and supports and Fit & tack weld 3 28-Feb-17 02-Mar-17 0%
A29990 Lift to position 2off (3m OD) plate and supports, Fit & tack weld 3 11-Mar-17 15-Mar-17 0%
A30000 Weld out (8off) Delta plates & Supports, NDT as per requirement 3 02-Mar-17 06-Mar-17 0%
A30010 Erect scaffold inside 7.2 comp 15 (Access for 2.2m & 3m OD plates) 3 06-Mar-17 08-Mar-17 0%
A30020 Lift to position 2off (2.2m OD) plate and supports, Fit & tack weld 3 09-Mar-17 11-Mar-17 0%
A30040 Weld out (4off) Delta plates & Supports, NDT as per requirement 3 15-Mar-17 18-Mar-17 0%
A30090 Lift to position Bottom (4m OD) plate and supports, Fit & tack weld 3 15-Feb-17 18-Feb-17 0%
A30110 Dismantle Scaffold 3 22-Mar-17 24-Mar-17 0%
A30070 Erect scaffold inside 7.2 comp 13 (Access for 2m OD plates) 4 22-Feb-17 27-Feb-17 0%
Installation on Left Hand Side Duct 35 13-Feb-17 24-Mar-17
A30230 Conduct MHPSA Inspection 1 21-Mar-17 21-Mar-17 0%

Actual Work Critical Remaining Work Summary Page 6 of 8 TASK filters: Ducting, In Progress.
Remaining Work Milestone Oracle Corporation
Kusile Boiler 2- Mechanical Work Schedule_20160204 Classic Schedule Layout 20-Feb-17 08:41
Activity ID Activity Name Original Start Finish Activity % Comment December 2016 January 2017
Duration Complete
28 04 11 18
A30210 Housekeeping & MRPE Inspection 2 18-Mar-17 20-Mar-17 0%
A30120 Lift to position Top (4m OD) plate and supports, Fit & tack weld 3 13-Feb-17 15-Feb-17 0%
A30130 Weld out (2off) Delta plates & Supports, NDT as per requirement 3 18-Feb-17 22-Feb-17 0%
A30140 Lift to position 8off (2m OD) plate and supports and Fit & tack weld 3 28-Feb-17 02-Mar-17 0%
A30150 Lift to position 2off (3m OD) plate and supports, Fit & tack weld 3 11-Mar-17 15-Mar-17 0%
A30160 Weld out (8off) Delta plates & Supports, NDT as per requirement 3 02-Mar-17 06-Mar-17 0%
A30170 Erect scaffold inside 7.2 comp 15 (Access for 2.2m & 3m OD plates) 3 06-Mar-17 08-Mar-17 0%
A30180 Lift to position 2off (2.2m OD) plate and supports, Fit & tack weld 3 09-Mar-17 11-Mar-17 0%
A30200 Weld out (4off) Delta plates & Supports, NDT as per requirement 3 15-Mar-17 18-Mar-17 0%
A30240 Lift to position Bottom (4m OD) plate and supports, Fit & tack weld 3 15-Feb-17 18-Feb-17 0%
A30260 Dismantle Scaffold 3 22-Mar-17 24-Mar-17 0%
A30220 Erect scaffold inside 7.2 comp 13 (Access for 2m OD plates) 4 22-Feb-17 27-Feb-17 0%
SI (Khumbulani 3) 1.3 Evase Modifications 31 13-Feb-17 20-Mar-17
Evase LHS 27 13-Feb-17 15-Mar-17
A28280 Material take off according to the engineering drawings 0 13-Feb-17 0%
A28320 Request for scaffolding to access the ground situated on the ground 0 15-Feb-17 0%
A28330 Request for scaffolding to access inside of the PA fan 0 15-Feb-17 0%
A28370 Request QC inspection (fit up) 0 18-Feb-17 0%
A28390 NDT the plates 0 22-Feb-17 0%
A28400 Apply paint over weld joints 0 22-Feb-17 0%
A28430 Request QC inspection 0 25-Feb-17 0%
A28450 NDT the plates 0 02-Mar-17 0%
A28460 Apply paint over welded joints 0 02-Mar-17 0%
A28490 NDT part 4 0 06-Mar-17 0%
A28510 Request QC inspection 0 07-Mar-17 0%
A28530 NDT part 3 0 08-Mar-17 0%
A28570 NDT part 5.0 0 11-Mar-17 0%
A28300 Install rigging material (lugs and rigging gear) 1 13-Feb-17 13-Feb-17 0%
A28310 Top and tail the evase, rigging the evase to the ground, evase must lay on its side1 14-Feb-17 14-Feb-17 0%
A28340 Prep the plates for welding activities (stiffeners and vains) 1 15-Feb-17 15-Feb-17 0%
A28350 Measure and mark out areas for stiffeners 1 16-Feb-17 16-Feb-17 0%
A28410 Measure and mark out areas for veins 1 23-Feb-17 23-Feb-17 0%
A28470 Install Part 4 (discharge backing plate)inside the evase 1 03-Mar-17 03-Mar-17 0%
A28500 Fit and tack weld Part 3 (discharge backing plate)inside the PA fan 1 07-Mar-17 07-Mar-17 0%
A28520 Weld Part 3 (discharge backing plate)inside the PA fan ) 1 08-Mar-17 08-Mar-17 0%
A28540 Cut Item 5.0 as per engineering instruction 1 09-Mar-17 09-Mar-17 0%
A28550 Fit and tack Item 5.0 inside the evase (ground level) 1 10-Mar-17 10-Mar-17 0%
A28560 Weld Item 5.0 according to applicable procedure 1 11-Mar-17 11-Mar-17 0%
A28580 Rig the evase box back to position 1 13-Mar-17 13-Mar-17 0%
A28590 Align the evase with the PA fan and ducting i tem 1.3 1 14-Mar-17 14-Mar-17 0%
A28600 Install the flexible mebrane as per provided basing eng drawing 1 15-Mar-17 15-Mar-17 0%
A28360 Fit and tack weld the plates (Part 2 to 2.4) 2 17-Feb-17 18-Feb-17 0%
A28420 Fit and tack weld the veins (Item 1 to Item 5) 2 24-Feb-17 25-Feb-17 0%
A28480 Weld Part 4 (discharge backing plate)inside the evase 2 04-Mar-17 06-Mar-17 0%
A28380 Weld the stiffeners according applicable welding procedure (2 to 2.4) 3 20-Feb-17 22-Feb-17 0%
A28440 Weld the vein according to applicable welding procedure (Item 1 to Item 5.0) 4 27-Feb-17 02-Mar-17 0%
Evase RHS 31 13-Feb-17 20-Mar-17
A28610 Material take off according to the engineering drawings 0 13-Feb-17 0%
A28640 Request for scaffolding to access the ground situated on the ground 0 16-Feb-17 0%
A28650 Request for scaffolding to access inside of the PA fan 0 16-Feb-17 0%
A28690 Request QC inspection (fit up) 0 21-Feb-17 0%
A28710 NDT the plates 0 25-Feb-17 0%
A28720 Apply paint over weld joints 0 25-Feb-17 0%
A28750 Request QC inspection 0 01-Mar-17 0%
A28770 NDT the plates 0 07-Mar-17 0%

Actual Work Critical Remaining Work Summary Page 7 of 8 TASK filters: Ducting, In Progress.
Remaining Work Milestone Oracle Corporation
Kusile Boiler 2- Mechanical Work Schedule_20160204 Classic Schedule Layout 20-Feb-17 08:41
Activity ID Activity Name Original Start Finish Activity % Comment December 2016 January 2017
Duration Complete
28 04 11 18
A28780 Apply paint over welded joints 0 07-Mar-17 0%
A28810 NDT part 4 0 10-Mar-17 0%
A28830 Request QC inspection 0 11-Mar-17 0%
A28850 NDT part 3 0 13-Mar-17 0%
A28890 NDT part 5.0 0 16-Mar-17 0%
A28620 Install rigging material (lugs and rigging gear) 1 14-Feb-17 14-Feb-17 0%
A28630 Top and tail the evase, rigging the evase to the ground, evase must lay on its side1 15-Feb-17 15-Feb-17 0%
A28660 Prep the plates for welding activities (stiffeners and vains) 1 16-Feb-17 16-Feb-17 0%
A28670 Measure and mark out areas for stiffeners 1 17-Feb-17 17-Feb-17 0%
A28730 Measure and mark out areas for veins 1 27-Feb-17 27-Feb-17 0%
A28790 Install Part 4 (discharge backing plate)inside the evase 1 08-Mar-17 08-Mar-17 0%
A28820 Fit and tack weld Part 3 (discharge backing plate)inside the PA fan 1 11-Mar-17 11-Mar-17 0%
A28840 Weld Part 3 (discharge backing plate)inside the PA fan ) 1 13-Mar-17 13-Mar-17 0%
A28860 Cut Item 5.0 as per engineering instruction 1 14-Mar-17 14-Mar-17 0%
A28870 Fit and tack Item 5.0 inside the evase (ground level) 1 15-Mar-17 15-Mar-17 0%
A28880 Weld Item 5.0 according to applicable procedure 1 16-Mar-17 16-Mar-17 0%
A28900 Rig the evase box back to position 1 17-Mar-17 17-Mar-17 0%
A28910 Align the evase with the PA fan and ducting i tem 1.3 1 18-Mar-17 18-Mar-17 0%
A28920 Install the flexible mebrane as per provided basing eng drawing 1 20-Mar-17 20-Mar-17 0%
A28680 Fit and tack weld the plates (Part 2 to 2.4) 2 20-Feb-17 21-Feb-17 0%
A28740 Fit and tack weld the veins (Item 1 to Item 5) 2 28-Feb-17 01-Mar-17 0%
A28800 Weld Part 4 (discharge backing plate)inside the evase 2 09-Mar-17 10-Mar-17 0%
A28700 Weld the stiffeners according applicable welding procedure (2 to 2.4) 3 23-Feb-17 25-Feb-17 0%
A28760 Weld the vein according to applicable welding procedure (Item 1 to Item 5.0) 4 03-Mar-17 07-Mar-17 0%

Actual Work Critical Remaining Work Summary Page 8 of 8 TASK filters: Ducting, In Progress.