RATE ANALYSIS FOR REINFORCED CEMENT CONCRETE


DOWNLOADED FROM THECONSTRUCTOR.ORG

RCC 1 :2 :4 Analysis for


Wet Volume 0.65
Dry Volume 1.00

MATERIAL Qty.
CEMENT BAGS 4.12
SAND 0.29
Aggregate 0.57
Reinforcement 127.56

LABOUR With
Mechanical Mixer & Vibrartor Days
MASON 2.00
LABOUR 2.00
WATER CARRIER 0.00
BAR BENDER 0.00
MIXER OPERTOR 2.000
MIXER VIBRATOR 0.000
0.00
PRIME COST (Rs.):

Water Charges 1.5%


Sundries (including mixer machine, transportation etc) 7.5 %
Contractor's Profit 20

Total Cost per m3 of RCC =

Cost of RCC for Given


ENT CONCRETE
NSTRUCTOR.ORG Steel % by volume of
Concrete
3 SLAB 1.00%
m 3
BEAM 2.00%
COULMN 2.50%
Road 0.60%
AMOUNT SUBTOTAL
Units Rs. / Unit (Rs.) (Rs.)
bags 7 29
m3 10 3
m3
35 20
Kg 0 0
51.73

2.4 4.80
0.85 1.70
1 0.00
200 0.00
1.2 2.40
200 0.00 8.90

61

1
5
% 12

otal Cost per m3 of RCC = 120

Cost of RCC for Given Data = Rs. 78