Title Instrument Air Compressor charging

1. OBJECTIVE
To standardize the procedure for Instrument Air Compressor
failure in 1x76MW CDQ Power plant.

1.1 FUNCTION/PURPOSE

1.1.1To Produce Instrument Air for various equipments like


control valves, dm plant etc.

2. SCOPE

This explains the procedure for Instrument Air Compressor


Failure

3. RESPONSIBILITY

Shift in charge
Desk engineer
Field engineer

4. PROCEDURE

TECHNICAL DATA

Installed : 2 Nos.
Power : 30 kW;

Preparation - Review &


OPD Approval - HOD
JSW Techno Projects Management Limited, Vijayanagar Works, P.O
Vidyanagar, Toranagallu,, Dist. Bellary.
D.C.N ISO 9001 : 2008 (7.5.1) / ISO Issue / Effective
CDQ PP- 14001 : 2004 (4.4.7) / BS Rev. No. - Date
OP- SOP- OHSAS 18001 : 2007 (4.4.7) 1/1 16/09/201
10 4
Title Instrument Air Compressor charging

Full Load Current: 52Amps;


Motor Speed: :1465 RPM;

ANNEXURE 1

5. SAFETY MEASURES
5.1 Permit To Work system: Applicable
5.2 Confined Space Working system: Applicable
5.3 Lock Out & Tag Out (LOTO): Applicable
5.4 No maintenance or civil work is allowed without valid permit

6. REFERENCE DOCUMENTS

6.1 PID Name & No: General arrangement of Instrument Air


Compressor.

Preparation - Review &


OPD Approval - HOD
JSW Techno Projects Management Limited, Vijayanagar Works, P.O
Vidyanagar, Toranagallu,, Dist. Bellary.
D.C.N ISO 9001 : 2008 (7.5.1) / ISO Issue / Effective
CDQ PP- 14001 : 2004 (4.4.7) / BS Rev. No. - Date
OP- SOP- OHSAS 18001 : 2007 (4.4.7) 1/1 16/09/201
10 4
Title Instrument Air Compressor charging

6.2 Control room & Field engineer log book.

Preparation - Review &


OPD Approval - HOD