Professional Documents
Culture Documents
This project report of this task is comprised of the works related to the planning exercises
breakdown and resource planning. The works will also comprise of preparing a preliminary
construction sequence sketch and program of work for the construction of a three-bay ten-storey
concrete framed building for a given floor plan and cross section
Designer
The team for design (the "Designer") includes a designer, a structural engineer, a capacity
inspector and a structure facilities engineer. The architect must carry the following tasks:
Makes sure that constructions are intended to evade hazards to well-being and protection
Planning Supervisor
In the meantime, a Planning Supervisor has also been selected for this plan. The Planning
Supervisor is a high-ranking designer from the same section. The Planning Supervisor have to
co-ordinate the well-being and care features of the project design and early preparation and to
Contractor
The building is of flat slab construction and contains 32 columns per floor. Table forms
are to be used for the floor slab construction. A fixed tower crane is to be used for all lifting
operations, formwork, reinforcement and the column concrete pours. The larger floor pours are
to be concrete pumped.
Formwork resources are critical for the success of the project. Sufficient formwork is to
be available for 16 columns. These may be used two times on each floor level with some degree
of remaking taking place after the 2nd, 4th, 6th and 8th floor has been completed. Sufficient table
forms are to be made available for two complete half-floor slabs. These can be moved up the
Vertical column sides can be stripped overnight. However, horizontal slab soffits must be left in
Activities:
1.5 Assumptions
AON
A B E
Start
C D F
AOA
Earliest start (ES) = earliest time at which an activity can start, assuming all predecessors
have been completed
Latest start (LS) = latest time at which an activity can start so as to not delay the completion
time of the entire project
Latest finish (LF = latest time by which an activity has to be finished so as to not delay the
completion time of the entire project
ES/EF Network
LS/LF Times
Variability in Activity Times
Computing Variance
Linked Bar Chart
C
Site and structural civil engineers must understand that concrete suppliers execute a thorough
examination of existing formwork resolutions to aid select the finest arrangement for the
building development. For the reason that circumstances differ for each single project, there is no
Additional influences the contactor will assess when selecting a formwork system comprises of:
Is the compulsory material easily obtainable? Does the supplier make the material or do
reduce rental price, save labour requests, and diminish assembly area necessities.
Does the supplier offer on-site field service to train and decrease the knowledge curve of
ascended and are tie-off points built into the arrangement where compulsory?
What knowledge does the firm have with your sort of project?
Does the supplier offer engineering services? Will the supplier deliver general sketches of
the system or particular assembly sketches for the formwork for the project?
It is suggested that the horizontal slab formwork must be left in position for a minimum period of
7 days because for site planning and management it is very important to keep the formwork in
place till the cement material cultivates adequate power. Though, if the formwork is kept too
lengthy it will effect in additional price and therefore a stability has to be reached at between
E
It is not possible to reduce the duration of the project.
References
Zingoni, A. (2010). Advances and trends in structural engineering, mechanics, and computation.